weekly construction update 6-22-2010
DESCRIPTION
KC Soccer Stadium construction update from Turner Construction.TRANSCRIPT
Building the Future
Current Activities this Week:
Mass Excavation:
Backfilling of on-grade seating is ongoing in Area 1,
Area 2 and Area 3.
Site Utilities:
Storm Sewer installation (Line 6000) is ongoing on
east side of France Family Drive.
Sanitary Sewer Line E installation is ongoing on east
side of France Family Dive.
Foundations:
Area 2 Concourse Level – E-Line footing installation is
complete to column line 14.
Area 3 Field Level – A-Line wall (to column line 1) is
complete.
Area 3 Field Level – Isolated footing installation is
ongoing.
Concrete Flatwork:
Area 1 – Mezzanine slab-on deck is complete, Main
Concourse structural slab is complete, Suite Level slab
on deck is complete from column line 23-32.
Area 1 – Underslab MEP rough-in is ongoing on Press
Level.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 6.16.2010
Re: Wizards Stadium Project
Update – Week of
6.14.2010
Field Level Area 1 – Shallow Underground
plumbing pipe installation ongoing at Aux
Locker Rooms.
Suite Level – Concrete Slab on Metal Deck is
complete from Column Line 23 - 32.
Field Level Area 3 – A-Line wall installation is
complete to Column Line 1.
Building the Future
Structural Steel Erection:
Area 1 – Steel Erection in sequence 1-5 complete. Steel
Erection in sequence 1-3 is ongoing.
Decking/Detailing/Studs/Edge Angle is nearly complete in
Sequence 1-5.
Underground MEP:
Deep Sanitary installation is ongoing in Area 3.
Electrical Secondary is ongoing in Area 2.
MEP Rough-in:
Plumbing and Electrical rough-in for concrete decks are
ongoing at Press Level. Shallow plumbing rough-in is
ongoing at Area 1 Field Level.
Projected Activities occurring next Week:
Mass Excavation:
Backfilling of on-grade seating areas will continue in Area
3. Rough grading of field will continue.
Site Utilities:
Installation of the Storm Line 6000 on the East Side (France
Family Drive) of the site will continue. Storm Line 5000 and
4000 will begin. Installation of Sanitary Line E will continue.
Deep Underground Plumbing:
Deep Sanitary installation in Area 3 will continue.
Foundations:
Area 3 Field Level – Foundation installation will continue.
Area 4 Mezzanine Level – Foundation Wall installation will
begin.
Concrete Flatwork:
Area 1 Press Level – Concrete placement will begin.
Area 1 – Structural Steel Erection at West
Building is complete from Column Line 33 –
23. Decking is ongoing on the Press Level.
Concourse Level Area 2 – Backfill of E-Line
walls are ongoing. This area is where
southwest concourse restrooms and
concessions are located.
Area 1 – Structural Steel Erection Sequence
1-3 in underway (outdoor terrace area).
Building the Future
Structural Steel Erection:
Erection of Structural Steel in Sequence 1-3 will
continue.
Delivery of Roof Trusses for sequence 1-7 will begin to
arrive on site.
Structural Precast:
Erection of the precast risers and tubs will begin.
Underground MEP:
Deep Sanitary installation will continue in Area 3.
Electrical Secondary will continue in Area 2
MEP Rough-in:
Plumbing and Electrical rough-in for concrete decks will
continue at Press Level. Shallow plumbing rough-in will
continue at Area 1 Field Level. Shallow electrical will
begin at Area 1 Field Level.
Field Level Area 2 – Shot looking south (from
Suite Level Column Line 32) of south
foundation walls.
Suite Level Area 1 – Steel edge plate
installation ongoing at Roof Level.
Building the Future
Additional Photos:
Suite Level – Concrete placed at exterior
walkway outside of Lower Suite Lounge.
Area 1 – Shot looking at East Elevation of
the West Building.
Press Level – Underslab MEP rough-in
ongoing prior to reinforcing steel
installation.
Mezzanine Level Area 4 – Wall form
installation is ongoing.
Concourse Level Area 1 – Ironworkers
installing one of the numerous pieces of
steel in Sequence 1-3.
Field Level Area 1 – Electrical conduits
penetrating D-Line wall into electrical room
between Column Line 30 – 30.5.