weekly construction update 6-22-2010

4
Building the Future Current Activities this Week : Mass Excavation : Backfilling of on-grade seating is ongoing in Area 1, Area 2 and Area 3. Site Utilities : Storm Sewer installation (Line 6000) is ongoing on east side of France Family Drive. Sanitary Sewer Line E installation is ongoing on east side of France Family Dive. Foundations : Area 2 Concourse Level – E-Line footing installation is complete to column line 14. Area 3 Field Level – A-Line wall (to column line 1) is complete. Area 3 Field Level – Isolated footing installation is ongoing. Concrete Flatwork : Area 1 – Mezzanine slab-on deck is complete, Main Concourse structural slab is complete, Suite Level slab on deck is complete from column line 23-32. Area 1 – Underslab MEP rough-in is ongoing on Press Level. To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 6.16.2010 Re: Wizards Stadium Project Update – Week of 6.14.2010 Field Level Area 1 – Shallow Underground plumbing pipe installation ongoing at Aux Locker Rooms. Suite Level – Concrete Slab on Metal Deck is complete from Column Line 23 - 32. Field Level Area 3 – A-Line wall installation is complete to Column Line 1.

Upload: kansas-city-wizards

Post on 30-Jun-2015

1.260 views

Category:

Sports


2 download

DESCRIPTION

KC Soccer Stadium construction update from Turner Construction.

TRANSCRIPT

Page 1: Weekly Construction Update 6-22-2010

Building the Future

Current Activities this Week:

Mass Excavation:

Backfilling of on-grade seating is ongoing in Area 1,

Area 2 and Area 3.

Site Utilities:

Storm Sewer installation (Line 6000) is ongoing on

east side of France Family Drive.

Sanitary Sewer Line E installation is ongoing on east

side of France Family Dive.

Foundations:

Area 2 Concourse Level – E-Line footing installation is

complete to column line 14.

Area 3 Field Level – A-Line wall (to column line 1) is

complete.

Area 3 Field Level – Isolated footing installation is

ongoing.

Concrete Flatwork:

Area 1 – Mezzanine slab-on deck is complete, Main

Concourse structural slab is complete, Suite Level slab

on deck is complete from column line 23-32.

Area 1 – Underslab MEP rough-in is ongoing on Press

Level.

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 6.16.2010

Re: Wizards Stadium Project

Update – Week of

6.14.2010

Field Level Area 1 – Shallow Underground

plumbing pipe installation ongoing at Aux

Locker Rooms.

Suite Level – Concrete Slab on Metal Deck is

complete from Column Line 23 - 32.

Field Level Area 3 – A-Line wall installation is

complete to Column Line 1.

Page 2: Weekly Construction Update 6-22-2010

Building the Future

Structural Steel Erection:

Area 1 – Steel Erection in sequence 1-5 complete. Steel

Erection in sequence 1-3 is ongoing.

Decking/Detailing/Studs/Edge Angle is nearly complete in

Sequence 1-5.

Underground MEP:

Deep Sanitary installation is ongoing in Area 3.

Electrical Secondary is ongoing in Area 2.

MEP Rough-in:

Plumbing and Electrical rough-in for concrete decks are

ongoing at Press Level. Shallow plumbing rough-in is

ongoing at Area 1 Field Level.

Projected Activities occurring next Week:

Mass Excavation:

Backfilling of on-grade seating areas will continue in Area

3. Rough grading of field will continue.

Site Utilities:

Installation of the Storm Line 6000 on the East Side (France

Family Drive) of the site will continue. Storm Line 5000 and

4000 will begin. Installation of Sanitary Line E will continue.

Deep Underground Plumbing:

Deep Sanitary installation in Area 3 will continue.

Foundations:

Area 3 Field Level – Foundation installation will continue.

Area 4 Mezzanine Level – Foundation Wall installation will

begin.

Concrete Flatwork:

Area 1 Press Level – Concrete placement will begin.

Area 1 – Structural Steel Erection at West

Building is complete from Column Line 33 –

23. Decking is ongoing on the Press Level.

Concourse Level Area 2 – Backfill of E-Line

walls are ongoing. This area is where

southwest concourse restrooms and

concessions are located.

Area 1 – Structural Steel Erection Sequence

1-3 in underway (outdoor terrace area).

Page 3: Weekly Construction Update 6-22-2010

Building the Future

Structural Steel Erection:

Erection of Structural Steel in Sequence 1-3 will

continue.

Delivery of Roof Trusses for sequence 1-7 will begin to

arrive on site.

Structural Precast:

Erection of the precast risers and tubs will begin.

Underground MEP:

Deep Sanitary installation will continue in Area 3.

Electrical Secondary will continue in Area 2

MEP Rough-in:

Plumbing and Electrical rough-in for concrete decks will

continue at Press Level. Shallow plumbing rough-in will

continue at Area 1 Field Level. Shallow electrical will

begin at Area 1 Field Level.

Field Level Area 2 – Shot looking south (from

Suite Level Column Line 32) of south

foundation walls.

Suite Level Area 1 – Steel edge plate

installation ongoing at Roof Level.

Page 4: Weekly Construction Update 6-22-2010

Building the Future

Additional Photos:

Suite Level – Concrete placed at exterior

walkway outside of Lower Suite Lounge.

Area 1 – Shot looking at East Elevation of

the West Building.

Press Level – Underslab MEP rough-in

ongoing prior to reinforcing steel

installation.

Mezzanine Level Area 4 – Wall form

installation is ongoing.

Concourse Level Area 1 – Ironworkers

installing one of the numerous pieces of

steel in Sequence 1-3.

Field Level Area 1 – Electrical conduits

penetrating D-Line wall into electrical room

between Column Line 30 – 30.5.