weekly construction update 06-06-2010
DESCRIPTION
KC Soccer Stadium construction update from Turner Construction.TRANSCRIPT
Building the Future
Current Activities this Week:
Mass Excavation:
Grading is ongoing in Area 3. Backfilling of on-grade
is ongoing in Area 1 and Area 2.
Site Utilities:
Storm Sewer installation (Line 6000) is ongoing on
east side of France Family Drive.
Foundations:
Area 2 Concourse Level – E-Line footing excavation has
started and is currently to Column Line 18.
Area 3 Field Level – Wall Form installation is ongoing
on A-Line and is currently to Column Line 9.
Area 3 Field Level – Installation of Drilled Piers
are ongoing.
Area 4 Mezzanine Level – D-Line grade beam excavation
has begun.
Structural Steel Erection:
Area 1 – Steel Erection in sequence 1-4 is ongoing and
Is currently to Column Line 31.
Decking/Detailing/Studs/Edge Angle is ongoing in
sequence 1-2 on Mezzanine, Concourse and Suite Levels.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 5.26.2010
Re: Wizards Stadium Project
Update – Week of
5.24.2010
France Family Drive – Storm Line 6000
installation is ongoing. Currently at station
4+00.
Area 4 – Drilled Pier installation is ongoing
near Column Line 1.
Field Level Area 2 – South East Vomitory
Wall installation is ongoing (Column Lines
11-12).
Building the Future
Underground MEP:
Deep Sanitary installation has started in Area 2.
MEP Rough-in:
Plumbing and Electrical rough-in on Concourse Level has
started.
Projected Activities occurring next Week:
Mass Excavation:
Grading at Area 3 will continue.
Site Utilities:
Installation of the Storm Line 6000 on the East Side (France
Family Drive) of the site will continue. Storm Line 5000 and
4000 will begin.
Deep Underground Plumbing:
Deep Sanitary installation in Area 2 will continue.
Foundations:
Area 2 Concourse Level – Footing/Grade Beam installation
will begin.
Area 3 Field Level – A-Line wall placement will begin
Area 3 Mezzanine Level – Grade beam installation will
begin.
Structural Steel Erection:
Erection of Structural Steel in Sequence 1-4 will continue.
Decking/Detailing/Studs/Edge Plates will continue in
Sequence 1-2.
Area 1 – Structural Steel Erection at West
Building is ongoing in Sequence 1-4 (bays
28-31 shown).
Field Level Area 1 – Shot looking north from
Concourse Level.
Field Level Area 2 – Deep Sanitary Line
installation has started near Column Line 15.
Building the Future
Additional Photos:
Suite Level Area 1 – Edge plate being
installed between Column Lines 26 - 27.
Concourse Level Area 1 – Plumbing rough-in
has started at north end.
Mezzanine Level Area 4 – Grade Beam
installation has started at Column Line 33
(North Supporter’s Seating Area).
Press Level Area 1 – Steel being set in place
that holds the precast seating tubs.
Field Level Area 1 – Hydrotherapy Pit poured
and backfilled.
Field Level Area 1 – Column encasement and
backfilling ongoing.