Building the Future Current Activities this Week : Mass Excavation : Grading is ongoing in Area 3. Backfilling of on-grade is ongoing in Area 1 and Area 2. Site Utilities : Storm Sewer installation (Line 6000) is ongoing on east side of France Family Drive. Foundations : Area 2 Concourse Level – E-Line footing excavation has started and is currently to Column Line 18. Area 3 Field Level – Wall Form installation is ongoing on A-Line and is currently to Column Line 9. Area 3 Field Level – Installation of Drilled Piers are ongoing. Area 4 Mezzanine Level – D-Line grade beam excavation has begun. Structural Steel Erection : Area 1 – Steel Erection in sequence 1-4 is ongoing and Is currently to Column Line 31. Decking/Detailing/Studs/Edge Angle is ongoing in sequence 1-2 on Mezzanine, Concourse and Suite Levels. To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 5.26.2010 Re: Wizards Stadium Project Update – Week of 5.24.2010 France Family Drive – Storm Line 6000 installation is ongoing. Currently at station 4+00. Area 4 – Drilled Pier installation is ongoing near Column Line 1. Field Level Area 2 – South East Vomitory Wall installation is ongoing (Column Lines 11-12).

Upload: kansas-city-wizards

Post on 03-Jul-2015

552 views

Category:

Sports


2 download

DESCRIPTION

KC Soccer Stadium construction update from Turner Construction.

TRANSCRIPT

Page 1: Weekly Construction Update 06-06-2010

Building the Future

Current Activities this Week:

Mass Excavation:

Grading is ongoing in Area 3. Backfilling of on-grade

is ongoing in Area 1 and Area 2.

Site Utilities:

Storm Sewer installation (Line 6000) is ongoing on

east side of France Family Drive.

Foundations:

Area 2 Concourse Level – E-Line footing excavation has

started and is currently to Column Line 18.

Area 3 Field Level – Wall Form installation is ongoing

on A-Line and is currently to Column Line 9.

Area 3 Field Level – Installation of Drilled Piers

are ongoing.

Area 4 Mezzanine Level – D-Line grade beam excavation

has begun.

Structural Steel Erection:

Area 1 – Steel Erection in sequence 1-4 is ongoing and

Is currently to Column Line 31.

Decking/Detailing/Studs/Edge Angle is ongoing in

sequence 1-2 on Mezzanine, Concourse and Suite Levels.

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 5.26.2010

Re: Wizards Stadium Project

Update – Week of

5.24.2010

France Family Drive – Storm Line 6000

installation is ongoing. Currently at station

4+00.

Area 4 – Drilled Pier installation is ongoing

near Column Line 1.

Field Level Area 2 – South East Vomitory

Wall installation is ongoing (Column Lines

11-12).

Page 2: Weekly Construction Update 06-06-2010

Building the Future

Underground MEP:

Deep Sanitary installation has started in Area 2.

MEP Rough-in:

Plumbing and Electrical rough-in on Concourse Level has

started.

Projected Activities occurring next Week:

Mass Excavation:

Grading at Area 3 will continue.

Site Utilities:

Installation of the Storm Line 6000 on the East Side (France

Family Drive) of the site will continue. Storm Line 5000 and

4000 will begin.

Deep Underground Plumbing:

Deep Sanitary installation in Area 2 will continue.

Foundations:

Area 2 Concourse Level – Footing/Grade Beam installation

will begin.

Area 3 Field Level – A-Line wall placement will begin

Area 3 Mezzanine Level – Grade beam installation will

begin.

Structural Steel Erection:

Erection of Structural Steel in Sequence 1-4 will continue.

Decking/Detailing/Studs/Edge Plates will continue in

Sequence 1-2.

Area 1 – Structural Steel Erection at West

Building is ongoing in Sequence 1-4 (bays

28-31 shown).

Field Level Area 1 – Shot looking north from

Concourse Level.

Field Level Area 2 – Deep Sanitary Line

installation has started near Column Line 15.

Page 3: Weekly Construction Update 06-06-2010

Building the Future

Additional Photos:

Suite Level Area 1 – Edge plate being

installed between Column Lines 26 - 27.

Concourse Level Area 1 – Plumbing rough-in

has started at north end.

Mezzanine Level Area 4 – Grade Beam

installation has started at Column Line 33

(North Supporter’s Seating Area).

Press Level Area 1 – Steel being set in place

that holds the precast seating tubs.

Field Level Area 1 – Hydrotherapy Pit poured

and backfilled.

Field Level Area 1 – Column encasement and

backfilling ongoing.