weekly construction update 07-07-2010
TRANSCRIPT
Building the Future
Current Activities this Week:
Mass Excavation:
Backfilling of on-grade seating is ongoing in Area 2
and Area 3.
Site Utilities:
Storm Sewer installation (Line 3000) is ongoing along
Village West Parkway.
Storm Line Installation (Line 6000 and Sanitary Sewer
Line E installation is ongoing on east side of France
Family Dive is ongoing.
Foundations:
Area 3 Field Level – Isolated footing installation is
ongoing and is currently to Column Line 3.5.
Concrete Flatwork:
Area 1 – Mezzanine slab-on deck is complete, Main
Concourse structural slab is complete, Suite Level slab
on deck is complete, Press Level slab on deck is
complete. Field Level Area 1 slab-on-grade is complete
from column line 32-29.
Structural Steel Erection:
Area 1 – Detailing and decking in sequence 1-3 is ongoing.
Erection of Steel Sequence 2-1 is ongoing.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 7.7.2010
Re: Wizards Stadium Project
Update – Week of
7.5.2010
Concourse Level Area 2 – Underground
plumbing and electrical rough-in for the
Concourse Buildings is ongoing.
Field Level Area 1 – Concrete placement for
slab-on-grade between column lines 32-29.
Field Level Area 1 – Cast-in-place concrete
riser installation has started.
Building the Future
Structural Steel Erection:
Area 1 – Detailing and decking in sequence 1-3 is ongoing.
Erection of Steel Sequence 2-1 is ongoing.
Underground MEP:
Electrical Secondary Distribution is ongoing in Area 3.
MEP Rough-in:
Area 1 – Shallow electrical and plumbing rough-in will
continue.
Metal Stud Framing:
Area 1 Suite Level – Metal stud framing for Suites is
ongoing.
Projected Activities occurring next Week:
Mass Excavation:
Backfilling of on-grade seating areas will continue in Area
3.
Site Utilities:
Installation of the Storm Line 6000 on the East Side (France
Family Drive) of the site will continue.
Deep Underground MEP:
Deep Sanitary and Electrical Distribution installation
in Area 3 will continue.
Foundations:
Area 3 Field Level – Foundation installation will continue.
Area 4 Mezzanine Level – Foundation Wall installation will
continue.
Area 1 – Shot of the West Building from the
south concourse area.
Suite Level Area 1 – Metal stud framing for
Suites are ongoing.
Area 2 –Steel erection in Sequence 2-1 is in
full swing.
Building the Future
Concrete Flatwork:
Area 1 Field Level – Prep for concrete placement for
slab-on-grade will continue.
Area 1 Field Level – Installation of on-grade seating risers
will continue.
Structural Steel Erection:
Erection of Structural Steel in Sequence 2-1 will
continue. Decking and detailing in Sequence 2-1 will begin.
Erection of the Canopy Trusses will begin.
Underground MEP:
Electrical Secondary will continue in Area 3.
MEP Rough-in:
Plumbing and Electrical rough-in for Area 1 Field Level slab
on grade will continue.
Metal Stud Framing:
Area 1 Suite Level – Metal stud framing for Suites will
continue.
Area 1 Press Level – Metal stud framing for Suites will
begin.
Area 1 – Shot from Roof Level showing
precast concrete and curvature of steel
structure.
Field Level Area 3 – Foundation installation
is ongoing.
Building the Future
Additional Photos:
Area 1 – Shot of the West Building from the
northeast.
Field Level Area 3 – Cauldron Club field wall
reinforcing in place.
Suite Level Area 1 – Precast tub being picked
by crane on its way to be installed.
Suite Level Area 1 – Metal Stud Framing
installation is ongoing.
Suite Level Area 1 – Ironworkers setting and
fastening precast seating tubs.
Mezzanine Level Area 4 – Shot of north
foundation wall installation.