stave assembly (module mounting and stave 250)

53
Stave Assembly (module mounting and stave 250) Ian Wilmut (RAL)

Upload: damian

Post on 23-Feb-2016

60 views

Category:

Documents


1 download

DESCRIPTION

Stave Assembly (module mounting and stave 250). Ian Wilmut (RAL). Martin Gibson. Martin has been developing the module mounting system at RAL for the last three years – everything we have so far comes from his input. Martin died on Tuesday 20 th August from Oesophageal cancer - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Stave Assembly (module mounting and stave 250)

Stave Assembly (module mounting and stave 250)

Ian Wilmut (RAL)

Page 2: Stave Assembly (module mounting and stave 250)

Martin Gibson• Martin has been developing the module mounting system at RAL

for the last three years – everything we have so far comes from his input.

• Martin died on Tuesday 20th August from Oesophageal cancer • Module mounting activities will continue at RAL picking up

where Martin left off.– We hope we can continue to do as good a job as he always did

• We are all very sad about this – and are only now really appreciating just how much he knew, and just what we have lost.

• We have all struggled to find words to express our sadness, all I can say is “Martin we miss you”

Page 3: Stave Assembly (module mounting and stave 250)

I will talk about• Recap on how the module mounting works

– Hopefully very quick• Stave 250

– Where we stand today – What we had to do to get here

• How module mounting is going without Martin– Glue patterns and cupped sensors changing shape

• Plans for stave 250 (in the context of module mountuing)• Plans for the longer term

– 130nm modules– Pixel disk module mounting

• Problems we have encountered

Page 4: Stave Assembly (module mounting and stave 250)

Module mounting system

Page 5: Stave Assembly (module mounting and stave 250)

Module mounting process

• I have discussed this lots of times before…– Last upgrade week (https://

indico.cern.ch/getFile.py/access?contribId=73&sessionId=12&resId=1&materialId=slides&confId=233533)

– Upgrade week before that (videos)(https://indico.cern.ch/conferenceDisplay.py?confId=158040) 10:10 on Wednesday

– Probably the week before that as well• Rather than re-cap the whole process in

minute detail here is a “cartoon” explanation of what is happening.

Page 6: Stave Assembly (module mounting and stave 250)

We have a stage with a camera that can move in x and y

X stage

Y stage

In plan view

Page 7: Stave Assembly (module mounting and stave 250)

LASER

As the X axis of the stage isn’t very straight we have laser line to correct things

X stage

Y stage

Page 8: Stave Assembly (module mounting and stave 250)

LASER

Into this we insert a stave in a frame (eachstave stays in the frame for the whole build)

X stage

Y stage

Page 9: Stave Assembly (module mounting and stave 250)

LASER

The frame has a series of fecucials that can be found and a co-ordinate system placed with

X stage

Y stage

Page 10: Stave Assembly (module mounting and stave 250)

LASER

We can now survey the stave and understand where it is in the frame using feducials or pads on the bus

X stage

Y stage

Note: we don’t yet know enough about bus tapes and accumulation of errors to understand what the criterion for QA of bus or bus to stave will be – so for now we will just collect as much data as we can.

Page 11: Stave Assembly (module mounting and stave 250)

LASER

We can then park the camera out of the way

X stage

Y stage

Page 12: Stave Assembly (module mounting and stave 250)

The module can then be picked up on to a vacuum chuck

Close up side view of 1 module

Page 13: Stave Assembly (module mounting and stave 250)

The chuck is rotationally compliant in the X and Y axis.

Close up side view of 1 module

Page 14: Stave Assembly (module mounting and stave 250)

The compliance is used to orientate the module to match the local stave shape with small feet

which reference the surface

Close up side view of 1 module

Page 15: Stave Assembly (module mounting and stave 250)

The chuck is part of a larger bridge which has lead screws to move the module in the X and Y

axis and provides rotation in Z

Page 16: Stave Assembly (module mounting and stave 250)

LASER

We can then place the bridge over the frame (key into the table)

X stage

Y stage

Page 17: Stave Assembly (module mounting and stave 250)

LASER

Move the camera to where the 1st corner of the sensor should be

X stage

Y stage

Page 18: Stave Assembly (module mounting and stave 250)

LASER

Move the module so the feducial is in the centre of the field of view (in the right place)

X stage Y stage

Page 19: Stave Assembly (module mounting and stave 250)

LASER

Move the camera to where the 2nd module feducial should be

X stage Y stage

Rotate the module into the correct place

Page 20: Stave Assembly (module mounting and stave 250)

LASER

Park the camera and remove the bridge

X stage

Y stage

Page 21: Stave Assembly (module mounting and stave 250)

LASER

Apply the glue to the stave & reinstate the bridge

X stage

Y stage

Page 22: Stave Assembly (module mounting and stave 250)

Stave 250

Page 23: Stave Assembly (module mounting and stave 250)

Stave 250 summary

• Received broken• Repaired• Retested• Installed in frame• Test connected to

infrastructure• Ready for mounting (just

as soon as we are happy with the glue)

• 5 flat test plates to “flat” stave

• 3 psudo bowed modules to “flat” stave

• 2 real bowed sensors to stave

• Lots of “removed” test pieces where we didn’t let the glue set.

Stave 250 (DC-DC) Module mounting

Page 24: Stave Assembly (module mounting and stave 250)

Stave 250 repair

• Stave 250 was built in the US between Brookhaven and LBL

• It was packed and shipped from LBL • When it was received at RAL it had been

“smashed” on one end• We have instigated a repair by flooding the core

with epoxy (West G-flex 650)• The core was then thermally imaged and cycled

top see if any damage was evident.

Page 25: Stave Assembly (module mounting and stave 250)

We had some quite big holes to fill!

Page 26: Stave Assembly (module mounting and stave 250)

We drilled holes along the end…

1 2 3 4 5 6 7 8 9 10 11 12

Page 27: Stave Assembly (module mounting and stave 250)

11 12

Which looked a bit like this

Page 28: Stave Assembly (module mounting and stave 250)

We then injected glue through the holes

11 12

Page 29: Stave Assembly (module mounting and stave 250)

Filling of extra holes

Small amount of surface flue where the masking allowed a little build up Smaller crack on rear completely filled

Page 30: Stave Assembly (module mounting and stave 250)

30

It was set up at QMUL and thermally imaged with warm water

Graham Beck, QMUL 1st August 2013

Page 31: Stave Assembly (module mounting and stave 250)

Graham Beck, QMUL for WP3/5, 29 April 2013

31

Thermal Cycling (first 5 cycles – next 5 are similar): - about 45 mins/cycle- Red line is thermocouple taped to End of Stave region (CFRP)

Then thermally cycled

Page 32: Stave Assembly (module mounting and stave 250)

32

10cm interval IR - 3D images (damaged side, before cycling)

Graham Beck, QMUL 1st August 2013

Page 33: Stave Assembly (module mounting and stave 250)

33

Before/After IR of damaged end

Graham Beck, QMUL 1st August 2013

Water bath and ambient are slightly different temperature before and after (try harder in future!)Maximum T rise of surface above ambient ~ 10 degrees (above pipe) - This is constant within a degree along stave length (0.5C asymmetry due to water cooling along length) and wrt before/after cycling.

Page 34: Stave Assembly (module mounting and stave 250)

Stave 250• We concluded it was well enough repaired to consider attaching modules. • We can’t be certain that its thermal performance has been reduced, but

we consider its performance to be adequate for real modules• We also found a number of faults with the stave that were addressed

through this process, – some have been fixed

• Holes• “shorts”

– some have been accommodated• Non straight closeout• Offset HV lines

– some we think we can live with • Non flat core• Non flat EOS

Page 35: Stave Assembly (module mounting and stave 250)

Lessons learned on stave production

• The edges are not straight – If this is always going to be the

case we need to change the handling tooling

• Glue filets are a problem (see image)

• We need to pack more robustly• Glue used to attach power bus

seems to have fibres in it that lower open circuit resistances.

• We still have off shaped we don’t understand

Good Bad

Page 36: Stave Assembly (module mounting and stave 250)

Gluing down modules

Page 37: Stave Assembly (module mounting and stave 250)

Challenges

• Up until 2 months ago only Martin had ever glued modules at RAL

• We thought what we needed to do was to extend Martins work mounting hogged modules to mounting cupped ones…

• In doing this we have learned a lot about 4445 and glue patterns.

• Most unexpectedly we have discovered that modules made with dramatically bowed sensors change shape when attached to the module mounting tooling.

Page 38: Stave Assembly (module mounting and stave 250)

Original glue pattern

• Glue pattern intended to push air towards perimeter of module

• Used to date with film of 75 or 150 microns

• Stavelet modules all use this pattern with glue layers of ~100µm

Page 39: Stave Assembly (module mounting and stave 250)

Flat “sensor” to flat stave

• Pattern was altered to allow for more space in the middle to allow for cupped sensor

• Worked well with flat plate

• This is a 50µm glue layer

Page 40: Stave Assembly (module mounting and stave 250)

With psudo bowed sensors it also seemed to work OK

• 2 layers of film stacked to simulate module surface

• 2 layers of film for this test

Page 41: Stave Assembly (module mounting and stave 250)

But it isn’t consistent

Page 42: Stave Assembly (module mounting and stave 250)

And…

Page 43: Stave Assembly (module mounting and stave 250)

And a failed electrical• Seen through a clear stave (sheet

of plexiglass/Perspex)• Looks quite good here• But this was

– Placed with vacuum & left for 1 hour

– Vac released and inspected – Looked very bad– Jig replaced with no vac for 1 hour– Re-inspected and looked like this

• So we are now wondering what effect the vaccum has on the module shape

Page 44: Stave Assembly (module mounting and stave 250)

The pick up chuck

Page 45: Stave Assembly (module mounting and stave 250)

Sensor shape• One specific challenge is that the module change shape when attached to the vac chuck.

1 2 3 4 5 6 7 8 9 10

00.020.040.060.08

0.10.120.140.160.18

Series1Series3

Series5Series7

Series9

Free sensor

1 2 3 4 5 6 7 8 9 10

-0.2

-0.15

-0.1

-0.05

0

0.05

0.1

0.15

Series1Series4

Series7Series10

Vac on 1 cup

1 2 3 4 5 6 7 8 9 10-0.04

-0.02

0

0.02

0.04

0.06

0.08

0.1

0.12

0.14

Series1Series3

Series5Series7

Series9

Vac on 3 cups (installed with tooling)

1 2 3 4 5 6 7 8 9 10-0.04-0.02

00.020.040.060.08

0.10.120.140.16

Series1Series3

Series5Series7

Series9

Vac on 3 cups (installed by hand)

1 2 3 4 5 6 7 8 9 10

-0.08-0.06-0.04-0.02

00.020.040.060.08

0.10.12

Series1Series4

Series7Series10

Vac on 3 cups through paper shim (installed with tooling)

Page 46: Stave Assembly (module mounting and stave 250)

250 Plans

• We will not mount any electrical modules until we have placed 3 failed electricals in a row with good coverage

• We will ten place one “mechanical grade” module with a FZ1 sensor to a stavelet

• Only then start with modules on stave 250

Page 47: Stave Assembly (module mounting and stave 250)

Longer term plans• Stave 250 & module mounting

– Use stave 250 as a proving ground for the process & collect data on method of all modules

– At the end of 250 formulate improvements to system– Iterate design for 130 stave (4 module bridges)– Post 130 stavelets build enough bridges for full stave

• Pixels– We are starting to look at extending this system for pixel disks –

very provisional• We are starting to produce full drawing sets for the kit we

presently have, and also the future iterations

Page 48: Stave Assembly (module mounting and stave 250)

Extras

Page 49: Stave Assembly (module mounting and stave 250)

Detector epoxy

S Canfer, STFC 12/9/13

Page 50: Stave Assembly (module mounting and stave 250)

Status

• A low modulus adhesive is required to bond detectors

• An epoxy has been formulated at RAL– Low viscosity– Very low Tg (approx -40°C)– Very low stiffness at ambient temperature– Low tear strength above Tg (potential for reworking)

• Cure currently 50°C for 24 hrs, should be possible to reduce this temperature

Page 51: Stave Assembly (module mounting and stave 250)

Compared to SE4445…

• This is an adhesive• Lower viscosity so a thinner joint should be

achievableso less materialand potentially the lack of any filler is an

advantage

Page 52: Stave Assembly (module mounting and stave 250)

Properties in compression by DMA

Created with NETZSCH Proteus software

Identity :Date/time :Laboratory :Operator :Project :Sample/shape :

555509/08/2013 11:56:41STFCSJCatlas5555/Cylindrical

Sample dim. :Deform. mode :Amplitude :DF/CSF :PF :Material :

1.6000x3.00009 mm/mm^2Penetration3.00...4.00 um3.00 N / 0.10 N 1.10 EPOXY

Temp. range :Segments :Frequency :Atmosphere :Flow rate :Smoothing :

30.0°C/3.0(K/min)/-100.0°C1/30.5Hz;1Hz;5HzHE40 ml/min1e-005/1 - 0

Calibration :Calibration :Calibration :Calibration :Temp.calib. :

130513.mm2230513-3mm-pen.em2sysstiff080813.cm8rotation_tuning.rm2130520-SJC.tm2

Instrument : NETZSCH DMA 242 File : C:\NETZSCH\Proteus61\data\130809 atlas-pene-3mm-5555-poststiffnesscal-3.ngb-dm2 Remark : 5555 EPOXY CHECK

-50 -40 -30 -20 -10 0 10 20 30Temperature /°C

0

500

1000

1500

2000

2500

E' /MPa

0.0

0.2

0.4

0.6

0.8

1.0

tan d

Main 2013-08-29 10:39 User: sjc95 130809 atlas-pene-3mm-5555-poststiffnesscal-3-1.ngb-taa

[1.1] 130809 atlas-pene-3mm-5555-poststiffnesscal-3.ngb-dm2E' (1.000 Hz)

tan d (1.000 Hz)

Value: -50.1 °C, 1854 MPa

Value: -0.2 °C, 4 MPa [1.1][1.1]STO

RAGE

MO

DULU

S M

Pa

Page 53: Stave Assembly (module mounting and stave 250)

Plans

• Irradiation at Birmingham syncrotron, hopefully October

• Make mockups of detector on CFRP and thermally cycle

• Try to reduce cure temperature (by catalyst choice and concentration)

• Further formulation development options:– Thixotropic modifiers– Silane bond promoter– Filler to increase K (but I prefer to aim for a thin joint)