soil and groundwater remediation at rr-72 former …this document presents the basis of design for...
TRANSCRIPT
FINAL
BASIS OF DESIGN
SOIL AND GROUNDWATER REMEDIATION AT RR-72 FORMER RIFLE RANGE
MCX SERVICE STATION MARINE CORPS BASE
CAMP LEJEUNE, NORTH CAROLINA
CONTRACT TASK ORDER 0284
MAY 23,1995
Prepared For:
DEPARTMENT OF THE NAVY ATLANTIC DIVISION NAVAL FACILITIES
ENGINEERING COMMAND No$olk, Virginia
Under:
LANTDIV CLEAN Program Contract N62470-89-D-4814
Prepared by:
BAKER ENVIRONMENTAL, INC. Coraopolis, Pennsylvania
TABLE OF CONTENTS
Section
INTRODUCTION .......................................................... 1
PURPOSE ................................................................. 2
BACKGROUND ............................................................ 2 Site Description ....................................................... 2 SiteHistory .......................................................... 2 Site Topography and Geology ............................................ 3 SiteHydrogeology ..................................................... 3
SITE REMEDIATION GOALS ............................................... 3
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
11.0
12.0
MOBILIZATION AND PREPARATORY WORK ......................... 4
MONITORING, SAMPLING, TESTING, AND ANALYSIS ................. 7
SITE WORK ....................................................... 10
SURFACE WATER COLLECTION AND CONTROL .................... 11
GROUNDWATER COLLECTION AND CONTROL ..................... 11 5.1 Groundwater Recovery Trench ................................... 12 5.2 Groundwater Treatment System ................................... 13 5.3 Infiltration Gallery ............................................. 14
AIR POLLUTION/GAS COLLECTION AND CONTROL ................. 15
SOLIDS COLLECTION AND CONTAINMENT ......................... 15
DECONTAMINATION WATER COLLECTION AND CONTAINMENT .... 15
DRUMS, TANKS, AND MISCELLANEOUS DEMOLITION AND DISPOSAL 15
OFF-SITE TREATMENT ............................................ 16
SITE RESTORATION ............................... ................ 16
DEMOBILIZATION ................................................ 16
ii
TABLES
Table 1 Groundwater Remediation Endpoints . . . . . . . . . . . . . . . . , . . . . . . . . . 5
APPENDICES
A Construction Schedule B Recovery Trench and Infiltration Gallery Design Calculations c Laboratory Data for W-6 and MW-13 D Groundwater Treatment System Equipment Information E Electrical Voltage Drop Calculations
. . . 111
BASIS OF DESIGN
SOIL AND GROUNDWATER REMEDIATION AT
RR-72 FORMER RIFLE RANGE, MCX SERVICE STATION
MARINE CORPS BASE,
CAMP LEJEUNE, NORTH CAROLINA
INTRODUCTION
This document presents the Basis of Design for soil and groundwater remediation at a former
underground storage tank (UST) site located at RR-72, Former Rifle Range, MCX Service Station,
Marine Corps Base (MCB), Camp Lejeune, North Carolina. It has been prepared by Baker
Environmental, Inc. (Baker) for presentation to the Department of the Navy (DON), Naval Facilities
Engineering Command, Atlantic Division (LANTDIV) under Navy Clean Contract Number N62470,
and in accordance with LANTDIV’s Scope of Work dated September 26,1994.
The DON is implementing a remedial action at RR-72, as part of the UST management program for
MCB Camp Lejeune. The goal of this action is to remediate groundwater contaminated by previous
releases of product from the USTs located at the site. It is the intent of the DON and of MCB Camp
Lejetme, to remediate the site as described in the Corrective Action Plan (CAP) for RR-72, which
was prepared by Baker (Baker, 1994). The CAP was prepared to meet the requirements of the North
Carolina Department of Environment, Health, and Natural Resources (DEHNR), “Groundwater
Section Guidelines for the Investigation and Remediation of Soils and Groundwater.” The CAP
identified the main components of the proposed groundwater collection and treatment system, and
presented a conceptual design of this system Using this conceptual design as a starting point, Baker
has developed a performance based design for the groundwater collection and treatment system.
LANTDIV intends to use a Remedial Action Contractor @AC) to implement this remedial action.
In this report the terms “RAC” and “Contractor” are used interchangeably.
PURPOSE
The purpose of the Basis of Design is to present LANTDIV with background data on the project,
describe the most important elements of the remedial design, and to present any assumptions used
in the design. This document is not intended to be part of plans and specifications to be utilized by
the Contractor for the execution of the remedial action. Baker assumes no responsibility for the use
of this report for any purposes other than the intended uses stated above.
BACKGROUND
MCB Camp Lejeune is a training base for the U.S. Marine Corps, located in Onslow County, North
Carolina The base covers approximately 236 square miles and includes 14 miles of coastline. MCB
Camp Lejeune is bounded to the southeast by the Atlantic Ocean to the northeast by State Route 24,
and to the west by U.S. Route 17. The town of Jacksonville, North Carolina is located north of the
base.
Site Descrintion
The Rifle Range Area is located in the southwest quadrant of MCB Camp Lejeune. The main
entrance to the Rifle Range is off State Route 2 10, approximately 1.5 miles southeast of the
intersection with U.S. Route 17 (See Drawing No. T-l).
The site consists of a service building (Building RR-72), that is located near the intersection of
Shelhock Drive and Powder Lane, the surrounding paved area where the fuel dispensing pumps were
located, and the area where three 4,000 gallon USTs were located (north of Building RR-72).
Site Historv
Based on information provided by Activity personnel, three USTs @R-72-1, RR-72-2, and RR-72-3)
were installed in 1956, and were used to store regular, unleaded, and premium gasoline. In May
199 1, UST RR-72-l was excavated and removed after a suspected product release. At this time,
product in USTs RR-72-2 and RR-72-3 was also removed. In December 1993, USTs RR-72-2 and
RR-72-3 were removed from the site.
2
Site TouograDhv and Geology
The surface topography at the site is generally flat to the north, east, and west of the ASTs. The
ground surface dips rapidly to the south towards a ravine. Surface water runoff flows toward the
same ravine (See Drawing No. C-l).
The Rifle Range area is underlain by undifferentiated layers of surficial, sedimentary clays and sands
of Pleistocene and Holocene age, extending to depths of 50 to 100 feet. Underlying the site,
. extending downward approximately 10 to 15 feet below ground surface (bgs), is a fine-grained sand
that contains some silty/clayey peat lenses. In addition, there is a sharp contact that separates sand
from the bluish-gray sandy clay which underlies the entire site.
Site Hvdroseolow
Based on data collected by Baker during site assessment activities conducted in February 1993,
shallow groundwater appears to flow southwest across the site toward the ravine. The top of
groundwater is encountered approximately 3 to 5 feet below the ground surface across the flat
portion of the site and at lesser depths as the surface topography falls toward the ravine.
Aquifer characterization tests were conducted by Baker during site assessment activities. During a
pump test at Recovery Well No. 1 (RW-l), the maximum flow rate that could be maintained without
the well being dewatered was 0.5 gallons per minute (gpm). At this rate, a maximum drawdown of
6.58 feet was recorded in RW-1. Based on these test results, a groundwater flow velocity of 248
feet/year was calculated.
SITE REMEDIATION GOALS
A determination of the extent of soil and groundwater contamination at RR-72 was the focus of a Site
Assessment Report prepared by Baker in May 1994. Subsequently, Baker prepared a CAP in July
1994, that presented remediation objectives and endpoints for the site. Based on the site assessment
activities completed at the site, remediation of the groundwater at the site is necessary. The CAP
concluded that, in general, the site cleanup goals are:
3
0 Contain migration of the groundwater contamination plume.
0 Reduce contaminant concentrations in the groundwater plume to North Carolina
Water Quality Standards (WQS).
In addition, the CAP also recommended remediation endpoints to address dissolved phase petroleum
contamination in the groundwater, and to meet accepted State guidelines for USTs. The remediation
endpoints for petroleum contamination in groundwater at the site are the State WQSs, which are
listed in Table 1 for the following contaminants detected at the site: Benzene, ethylbenzene, ethylene
dibromide (EDB), 1,4dichlorobenzene, and total xylenes.
It should be noted that the analytical results from soil sampling indicted that remediation of soil at
the site is not necessary. Total Petroleum Hydrocarbons (TPH.) concentrations in the soil do not
exceed 10 parts per million (ppm), the State of North Carolina action limit, or the site-specific
cleanup goal of 120 ppm developed by a Site Sensitivity Evaluation (SSE) completed as part of the
Final Site Assessment Report. However, conf%rnation soil sampling should be performed by the
Contractor in areas where soil is excavated, to verify that these soils do not exceed the site cleanup
goal for soil.
The following sections of this Basis of Design present the elements of the remedial action by
Hazardous, Toxic, and Radiological Waste (HTRW) account as defmed in the Remedial Action
Contracts Delivery Order Requirements Package Guide, NEESA 20.2-062, June 1992. Specific
HTRW Account Numbers are provided for reference with each section. A proposed construction
schedule, which lists project tasks by the HTRW account, is provided in Appendix A. A project
construction cost estimate is provided under a separate cover.
1.0 MOBILIZATION AND PREPARATORY WORK (HTRW Account No. 33.01)
Mobilization involves the acquisition, delivery, and setup of the necessary construction equipment,
material, and temporary facilities at the site. This task also includes the mobilization of the necessary
personnel to perform the work. In addition, during the mobilization period, the Contractor will
prepare all necessary pre-construction submittals, as described in Section 010 10,
4
TABLE 1
GROUNDWATER REMEDIATION ENDPOINTS RIFLE RANGE MCX SERVICE STATION,
MCB CAMP LEJEUNE, NORTH CAROLINA CONTRACT TASK ORDER 0284
I-
Parameter
Benzene
Ethylbenzene
EDB @)
1 ,CDichlorobenzene
Total Xylenes
Sampling Number of North Maximum Point with Sampling
Carolina Concentration Highest Points Above WQS (” Detected Concentration the WQS
1.0 357 MW-3 6
29 1090 M-W-3 6
0.005 100 RW- 1 1
1.8 110 RW-1 1
400 1900 HP-4 4
Notes: (‘) Water quality standard (‘) Ethylene dibromide
5
“General Paragraphs”, of the contract specifications. These specifications allow the Contractor up
to sixty days to prepare and submit the necessary pre-construction submittals.
The Contractor shall provide temporary facilities, including a Contractor staging/decontamination
area, a stockpile area, and temporary utilities, as necessary to complete the work.
Permits (33.01.01.05)
1 To meet State of North Carolina, Department of Environment, Health, and Natural Resources
(DEHNR), Division of Environmental Management @EM) regulatory requirements for remediation
of petroleum contaminated sites, a Non-Discharge Permit will be required for disposal of the treated
groundwater via an infiltration gallery. The permit application must address the requirements of
DEHNR regulations, as contained in 15A NCAC 2H.0200 (Waste Not Discharged To Surface
Waters). This permit application will be completed by Baker and submitted by the DON, with
assistance from the Base. In addition, because the groundwater treatment system will use an air
stripper which will produce an air discharge, the State requires that the treatment system be
registered with the State.
If it becomes necessary to consider discharge of the treated groundwater to a surface water, such as
via a storm sewer, a State of North Carolina NPDES General permit will be required, in accordance
with 15A NCAC 2B.0 100 (Wastewater Discharged to Surface Water).
.
In addition, the proposed work will require the abandonment of certain monitoring wells located at
the site. The Contractor shall be required to meet the requirements of 15A NCAC 2K.0214, which
specifies monitoring well abandonment procedures.
The Contractor will also have to arrange for any required Base permits, which would include any
temporary utilities, and an excavation permit.
2.0 MONITORING, SAMPLING, TESTING, AND ANALYSIS (HTRW Account No.
33.02)
The Contractor shall be required to submit to LANTDIV for approval, a Sampling and Analysis Plan
(SAP) describing the proposed sampling, analytical, and quality control procedures for the data
collected during the performance of work (See Section 0 10 10, “General Paragraphs” of the contract
specifications). The SAP shall ensure that all chemical data generated are scientifically accurate and
legally defensible. The SAP shall describe the quantity, frequency, and location of soil and water
samples to be collected and analyses to be performed.
The type and quantity of testing shall be based on the requirements set forth in the specifications (and
the Contractor’s health and safety plan and air monitoring plan) and as required during the project.
All required testing, documentation, and submittal of test results will be the responsibility of the
Contractor.
Air Monitoriw (33.02.03)
The Contractor shall develop and implement an air monitoring plan to characterize site air with
regard to personnel safety and off-site (perimeter of the active work area) migration of contaminants
as a result of site activities. The Contractor shall perform real-time monitoring for organic vapors
with a PID- or FID-type volatile organic detector and for explosive atmospheres with an
explosimeter. Action levels shall be identified in the Contractor’s Health and Safety Plan and Air
Monitoring Plan subject to the approval of the NTR.
Air Samding
High-volume air sampling shall be used to quantify any release of toxic particulates associated with
remedial work at the project site in accordance with OSHA requirements for worker health and
safety.
Water Samnlin~ (33.02.05)
The Contractor shall collect water samples for chemical analysis from the water generated as part
of the remedial action including, but not limited to, spent decontamination fluids, groundwater and/or
surface water collected from dewatering activities, and groundwater collected during remediation
and treated via the on-site groundwater treatment system. Water sampling shall occur at the
following locations and frequencies, depending on the source:
Suent decontamination fluids and liauid collected from dewaterinp activities
Collect one composite sample per tanker or one composite sample per 10 drums.
Groundwater from the on-site rzroundwater treatment system
Samples shall be collected from four locations to monitor and determine the performance of the
groundwater treatment system: at the recovery trench, the infhtent to the air stripper, the effluent
from the air stripper, and the effluent from the carbon adsorbers.
Samples shall be collected in accordance with the following schedule:
0 During the first 30 days of operation collect one sample fkom each of the four
locations at system startup, and ever 10 days thereafter (i.e., day 0, 10,20,30).
0 During day 3 1 through 90 collect one sample from each of four locations every 15
days (i.e., day 45,60,75,90).
0 During day 9 1 through 180 collect one sample from each of four locations every 30
days (i.e., day 120, 150, 180).
Soil Samuliw (33.02.06)
Soils at the site are not expected to be contaminated at levels above the remediation goals for the site
(120 ppm TPH). However, the Contractor shall collect samples from excavated soils to verify that
- 8
the soils do not contain TPH contamination at concentrations greater than 120 ppm (See Drawing
No. C-2). One (1) soil sample shall be collected for every 400 square feet of surface area to be
excavated. The Contractor shall follow the sampling procedures presented in the Contractor’s SAP.
Testinp and Analvsis (33.02.09)
The Contractor shall adhere to EPA &am-of-custody procedures during the collection, transport, and
analyses of all samples. The Contractor shall perform in-field testing and shall arrange laboratory
analyses of all samples to conform with NEESA Level C Quality Assurance Requirements. Samples
shall be analyzed as follows:
Water Testing
Potentially contaminated water generated during the remedial action including, but not limited to,
water from decontamination of personnel and equipment, shall be analyzed for the following
parameters:
0 TCLP Metals - EPA Methods 7060,7080,7130,7190,7420,7470,7741,7760
0 TCLP VOAs - EPA Method 8240
0 TCLP SVOAs - EPA Method 8270
Untreated (mfluent) and treated groundwater (effluent) from the on-site groundwater treatment
system shall be analyzed for the following:
0 VOAs - EPA Method 602
0 TAL Metals - EPA Method 6010
0 Total Suspended Solids (TSS)
0 Total Dissolved Solids (TDS)
Soil Testing
Soil samples collected at the site shall first be analyzed in the field using the following procedure:
9
1. Field screen a composite sample of the excavated soil using rapid immunoassay in-field
screening tests for petroleum fuels (EPA Proposed Method 4030).
2. If the in-field screen test results are below 10 ppm, the soil shall be considered as
uncontaminated and shall be disposed of off-site at an appropriate facility (possibly the Base
landfill), or used on-site as backfill.
3. If the in-field screen test results are at or above 10 ppm, place the sample in an appropriate
sample container for shipment to a laboratory for waste characterization analyses to verify
contamination and notify the Government. Characterization analyses for soils shall include:
0 TPH - EPA Method 5030/8015 I
0 TCLP Metals - EPA Methods 7060,7080,7130,7190,7420,7470,7741,
7760
0 TCLP VOAs - EPA Method 8240
0 TCLP SVOAs - EPA Method 8270
0 Total Organic Halogens (TOX) - EPA Method 9020
In addition, the potentially contaminated soil shall contain no free liquid as demonstrated by
EPA SW-846 Method 9095, Paint Filter Liquids Test.
The results of the characterization analyses shall be used for documenting and/or manifesting the
soils prior to transport to an off-site soil recycling facility.
3.0 SITE WORK @ITRW Account No. 33.03)
Site work includes all clearing and grubbing, and construction of temporary roadways, staging areas,
and fencing. Clearing and grubbing will be limited to an area of less than one acre where access and
excavation is required and a staging area will be located. The Contractor shall propose disposal
options for all vegetation and, in particular, for trees greater than six inches in stump diameter which
shall be subject to approval by LANTDIV and/or the Activity.
10
The Contractor shall be required to install safety and erosion control (silt) fencing as indicated and
specified.
The Contractor shall be required to place excavated soil directly into dump trucks or roll-off boxes,
or provide an excavated soil staging area. The Contractor shall also provide a decontamination pad
for use during the remedial action.
4.0 SURFACE WATER COLLECTION AND CONTROL @TRW Account No. 33.05)
The Contractor shall be required to provide devices or facilities as necessary to prevent surface water
from contacting contaminated materials (i.e., soil, equipment, etc.) during construction activities, and
flowing off-site. The Contractor shall be required to keep all excavated areas dewatered during
construction and to collect, sample, analyze, and dispose of any water accumulated in the excavation
and staging areas.
5.0 GROUNDWATER COLLECTION AND CONTROL (HTRW Account No. 33.06)
The focus of this remedial action is the collection and treatment of contaminated groundwater from
the site. The CAP identified the main components of the proposed groundwater collection and
treatment system, and presented a conceptual design of this system. Using this conceptual design
as a starting point, Baker has developed a performance based design for the groundwater collection
and treatment system. The main components of the system include a groundwater recovery trench,
a groundwater treatment system, and an infiltration gallery. The proposed remediation alternative
will provide a closed loop treatment system, which is consistent with the State of North Carolina’s
policy of implementing the most efficient and cost-effective remediation system for UST sites,
provided the system does not degrade groundwater quality.
A description of each of the main components of the remediation system are presented in the
following subsections, which are referenced to the applicable HTRW Work Breakdown Structure
(WBS) tasks.
11
5.1 Groundwater Recoverv Trench (HTRW Account No. 33.06.02)
Based on a review of site hydrogeological data, and the results of the pump test conducted at the site,
the CAP recommended the construction of a groundwater interceptor, or recovery, trench
downgradient of the contaminant plume. The recovery trench will create an area of higher
permeability, which will be used to collect groundwater.
Baker used hydrogeological data from the Site Characterization Report to estimate the rate that
groundwater will be recovered. Hydraulic conductivity (K) values from three nearby monitoring
wells, as determined from drawdown tests, were used to determine an average K for the site. Darcy’s
Law (Q=KiA) was used to estimate a groundwater flow rate into the recovery trench of
approximately 3 gallons per minute. Baker’s design calculations are provided in Appendix B.
Baker’s design calls for a recovery trench approximately 75 feet long, 3 feet wide, with a nominal
depth of 8 feet. The trench will be backfilled with a gravel suitable for the application, and a
geotextile liner will be installed on the downgradient side of the trench to prevent groundwater from
migrating through the recovery trench.
Baker has incorporated a collection sump, or well, into the trench design. A pneumatic pump
capable of recovering groundwater and free product will be mounted in the sump (versus the electric
pump noted in the CAP). A pneumatic pump is better suited to the low flowrates and the need for
variable pump control.
Recovered groundwater, and any free product, will be pumped to the treatment system through a
small diameter (1 or 1.5inch) pipe or tubing, which will be installed within a casing pipe. This
arrangement provides secondary containment, and a more secure piping configuration. The piping
will be placed underground in a shallow trench, along with an air supply line to the pump.
In order to determine if the groundwater plume had migrated since the last sampling event, Baker
collected groundwater samples on December 2, 1994 from Monitoring Wells MW-6 and MW-13.
Samples were analyzed for BTEX components via EPA Method 602. While no BTEX components
were detected, the gasoline additive Methyl Tertiary Butyl Ether (MTBE) was detected in both wells,
12
possibly indicating that the leading edge of the plume is approaching these wells. Sampling data
from MW-6 and MW-13 is provided in Appendix C.
Based on the additional analytical data collected at the site, the recovery trench will be installed
between Monitoring Wells MW- 6 and MW-13. This location is approximately 50 feet south of the
location shown in the CAR, and is located in an area that is more accessible. This location also
reduces the overall trench depth approximately 4 feet, as the ground elevation at the proposed
location is approximately 5 feet lower than that shown in the CAR.
The Contractor shall be required to provide devices or facilities as necessary to collect and remove
groundwater encountered during the recovery trench construction activities. The Contractor shall
be required to keep all excavated areas dewatered during construction and to collect, sample, analyze,
and dispose of any water accumulated in the excavation and staging areas.
5.2 Groundwater Treatment System O!XTRW Account No. 33.13)
The CAP recommended that the grotmdwater treatment system be a preassembled unit, mounted to
an equipment platform at the factory, in order to minimize on site construction time, and provide a
system that has been assembled and tested prior to shipment to the site. There are a number of
equipment manufacturers who have developed and currently manufacture this type of equipment.
Baker has specified a completely preassembled, containerized and enclosed treatment system,
mounted on a steel I-beam platform, capable of being shipped and off-loaded at the site by a fork lift
or crane without damaging the equipment, inter-connecting piping, or electrical conduit. The
enclosure will include an access door, and/or removable wall panels for access to the equipment.
The wall and ceiling panels shall be insulated, and the enclosure will have an explosion-proof heater,
interior light, and exhaust fan. All electrical components within the enclosure shall conform to the
National Electrical Code’s requirements for Class I, Division I, Group D (explosion proof). All
electrical components mounted outside the enclosure shall be furnished in NEMA 3R panel(s).
The treatment system is designed to remove the volatile organic contaminants in the groundwater
down to concentrations below State Water Quality Standards, as listed in Table 1. The primary
treatment components to be used to treat the contaminated groundwater at the site are:
13
0 Oil/water separator
0 -Air stripper with effluent sump
0 Suspended solids bag filter
0 Two liquid phase carbon adsorbers (approximately 350 pounds of activated carbon
in each adsorber)
0 Compressed air system
0 Total fluids pumping system for recovery trench
All this equipment, with the exception of the total fluids pump, will be preassembled in the platform
enclosure, and will be furnished with all the necessary interconnecting piping, controls, and power
supply conduit. Baker specified a treatment system capable of treating up to 10 gallons per minute.
The process flow diagram of the treatment system is shown on Drawing No. C-4, and additional
information on the equipment is included in Appendix D.
5.3 Infiltration Gallem CHTRW Account No. 33.18)
After the recovered groundwater is treated via the on-site treatment system, the effluent will be
pumped to an infiltration gallery for recharge into the shallow aquifer. The gallery has been
designed much the same as a septic tank tile field, and incorporates a distribution header, and
individual laterals. The size of the infiltration gallery was based on an infiltration rate of 1.5 gallons
per square foot of draiige area per day (as recommended by 15A NCAC 02H.O400), and a design
flow rate of approximately 3 gallons per minute, or 4,300 gallons per day. The gallery has been
located over the area where the USTs were removed, which is upgradient of the recovery trench.
Baker’s preliminary design calculations for the infiltration gallery, and supporting documents, are
provided in Appendix A. The Contractor shall use these preliminary calculations to develop specific
construction plans and details for the infiltration gallery.
14
6.0 AIR POLLUTION/GAS COLLECTION AND CONTROL @TRW Account No. 33.07)
The excavation and loading activities during installation of the recovery trench and infiltration
gallery will most likely generate some dust emissions. Soil, haul roads, and other areas disturbed
by operations shall be treated with dust suppressants such as water to minimize emissions.
7.0 SOLIDS COLLECTION AND CONTAINMENT (HTRW Account No. 33.08)
In order to install the groundwater collection trench and infiltration gallery approximately 3 15 cubic
yards of soil will be excavated. If the soil sampling and analysis required by Section 2.0 determines
that any of this soil is contaminated, the Contractor shall prepare a staging area for stockpiling the
soil, or shall make arrangements for the soil the be loaded directly into dump trucks or roll-off boxes,
prior to removal for off-site disposal by the Contractor.
If the soil sampling and analysis determine that the soil to be excavated is not contaminated, the
Contractor shall make all necessary arrangements for the off-site disposal of the excavated soils.
8.0 DECONTAMINATION WATER COLLECTION AND CONTAINMENT (HTRW
Account No. 33.09)
The Contractor shall provide a decontamination pad to collect liquids from the decontamination of
personnel, earth-moving equipment, transportation trucks, and sampling equipment. The fluids will
be collected in tanker trucks, drums, or other appropriate containers for off-site disposal at an
appropriately permitted facility subject to LANTDIV and MCB Camp Lejeune approval.
9.0 DRUMS, TANKS, AND MISCELLANEOUS DEMOLITION AND DISPOSAL
@TRW Account No. 33.10)
No drums, tanks, or miscellaneous demolition and disposal are anticipated in this project except for
spent personal protective equipment (PPE) and other nonhazardous solid waste which shall be
disposed of in accordance with EPA Guidance (EPA Publication 9345.3-03FS).
15
10.0 OFF-SITE TREATMENT (HTRW Account No. 33.18)
Any contaminated soil encountered at the site that has been placed in an on-site staging area shall
be loaded onto trucks or roll-of boxes and transported to an off-site soil recycling facility.
Manifesting is not required if the contaminated soil does not meet the characteristics of a hazardous
waste, as defined in 40 CFR 261. Miscellaneous non-contaminated waste (i.e., refuse and spent PPE)
shall be loaded onto trucks or roll-off containers and transported to a North Carolina-permitted solid
waste landfill or other appropriate facility subject to LANTDIV and MCB Camp Lejeune approval.
11.0 SITE RESTORATION @TRW Account No. 33.20)
The excavated areas shall be backfilled with non-contaminated, previously excavated soil or off-site
borrow material and regraded to the contours shown on the reference drawings. Fill material
provided from off-site will be placed and compacted in accordance with the contract specifications.
12.0 DEMOBILIZATION (HTRW Account No. 33.21)
All temporary facilities, equipment, and supplies acquired for this contract shall be removed from
the site upon completion of the remedial action.
Post-construction submittals shall include (1) a punch list showing correction of all listed items; (2)
a letter from the Contractor certifying completion of all contracted work in accordance with the
contract conditions, applicable regulations, and standards of practice; (3) a completed project current
condition with “as-built” drawings or survey for the entire site; (4) submittals, in one collated
document, of all quality control daily reports, samples, results of the analysis of samples, corrective
actions (if required, taken to correct deviations from the plans and specifications that were pre-
approved by LANTDIV), and results of corrective actions; and, (5) submittal in one collated
document of all quality assurance samples, and corrective actions (if required, taken to correct
unacceptable deviations from required quality standards).
The Contractor shall submit to LANTDIV a detailed report summarizing the remedial action, lessons
learned, and recommendations for inclusion in future similar contracts.
16
APPENDIX A CONSTRUCTION SCHEDULE
:
APPENDIX B RECOVERY TRENCH AND INFILTRATION -
GALLERY DESIGN CALCULATIONS
S,O.No. &?470- c2?34-iooo -05000 Subject: IflFILTRATIObJ GAu-ER’f @ RR.72
MC0 CAIJlP LEJEUFJE , NBC, Sheet No. A--Of3
Drawing No.
Computed by m Checked By Tx Date z-16 -44
S.O. No. bZ470 - as4 d 1000 - 05om
Subjectf 1MFIL’RAVW G&L&S’f’ Q RR 72 MC@ CAMi l-tzEUtd& . flJc Sheet No. ___ 2 of 5.
Drawing No.
Computed by J3)c Checked By x Date 12-16-44
s.o.No. 6;7470- 284 -loo0 - 05000
Subject: ItiFlLtiil7~~ 6Am t% f8?72 Ma3 w4PGs?mJE , rJJ* Sheet No. .-.?$- of ~ 3
Drawing No.
Computed by m CheckedBy w Date i-4-95
APPENDIX C LABORATORY DATA FOR MW-6 AND MW-13 -
- CEIMIC
CORPORATION “Analytical Chemistry for Environmental Management”
BTEX ANALYSIS VOLATILE ORGANICS ANALYSIS
SW846 METHOD 8240
Client: Baker Environmental
Client Sample ID: RR72-MW6-W-03
Date Sampled: 12/02/94
Date Sample Received: 12/05/94
Matrix: Aqueous
Laboratory ID: 941050-04
Date Sample Analyzed: 12/08/94
Associated Method Blank: V61208-B2
Dilution Factor: 1
Concentration in: PglL (ppb)
Target Analyte Sample Quantitation Concentration Limit
Methyl t-Butyl Ether 74 1 Benzene ND 1 Toluene ND 1 Ethylbenzene ND 1 Total Xylenes ND 1
ND = Not detected
Surrogate Spike Recovery
Surrogate Compound Recovery( %) QC Limits( %)
1 ,ZDichloroethaned4 102 76 - 114 Toluened8 99 88 - 110 Bromofluorobenzene 97 86 - 115
Reported by: Approved by:
10 Dean Knauss Drive, Narragansett, R.I. 02882 l (401) 782-8900 l FAX (401) 782-8905 BTEX Page 6
BTEX ANALYSIS VOLATILE ORGANICS ANALYSIS
SW846 METHOD 8240
Client: Baker Environmental
Client Sample ID: RR72-MW13-W-03
Date Sampled: 12/02/94
Date Sample Received: 12/05/94
Matrix: Aqueous
Laboratory ID: 94 105045
Date Sample Analyzed: 12/08/94.
Associated Method Blank: V61208-B2
Dilution Factor: 1
Concentration in: PglL (ppb)
Target Analyte Sample Quantitation Concentration Limit
Methyl t-Butyl Ether 23 1 Benzene 3 1 Toluene ND 1 Ethylbenzene ND 1 Total Xylems ND 1
ND = Not detected
Surrogate Spike Recovery
Surrogate Compound Recovery( %) QC Limits(%)
1 ,ZDichloroethanedL 101 76 - 114 Toluened8 95 88 - 110 Bromofluorobenzene 99 86 - 115
Reported by: Approved by:
BTEX Page 7
- CEIMIC CORPORATION
“Analytical Chemistry for Environmental Management”
TARGET COMPOUND LIST (TCL) VOLATILE ORGANICS ANALYSIS
SW846 METHOD 8240
Client: Baker Environmental
Client Sample ID: RR72-DRM
Date Sampled: 12/02/94
Date Sample Received: 12/05/94
Matrix: Aqueous
Laboratory ID: 941050-03
Date Sample Analyzed: 12/08/94
Associated Method Blank: V61208-B2
Dilution Factor: 1
Concentration in: pg/L (ppb)
Target Analyte Sample Quantitation Concentration Limit
Chloromethaue Bromomethane Vinyl Chloride Chloroethane Methylene Chloride Acetone Carbon Disulfide 1.1 -Dichloroethene 1,l -Dichloroethane 1 ,ZDichloroethene (total) Chloroform 2-Butauone 1,2-Dichloroethane 1 , 1,l -Trichloroethane Carbon Tetrachloride Bromodichloromethane 1 ,ZDichloropropane cis-1,3-Dichloropropene Trichloroethene Dibromochloromethane 1.1 ,ZTrichloroethane Benzene trans- 1,3-Dichloropropene Bromoform 4-Methyl-2-Pentanone 2-Hexanone 1,1,2,2-Tetrachloroethane Tetrachloroethene
ND ND ND ND ND ND ND ND ND ND ND ND ND ND ND ND ND ND ND ND ND ND ND ND ND ND ND ND
10 10 10 10 5
10 5 5 5 5 5
10 5 . 5 5 5 5 5 5 5 5 5 5 5
10 10 5 5
10 Dean Knauss Drive, Narragansett, R-I.02882 l (401) 782-8900 l FAX (401) 782-8905 Volatile Page 5
CEIMIC CORPORATION
“Analytical Chemistry for Environmental Management”
TARGET COMPOUND LIST (TCL) VOLATILE ORGANICS ANALYSIS
SW846 METHOD 8240
Client: Baker Environmental
Client Sample ID: RR72-DRM
Date Sampled: 12/02/94
Date Sample Received: 12105194
Matrix: Aqueous
Laboratory ID: 94105043
Date Sample Analyzed: 12/08/94
Associated Method Blank: V61208-B2
Dilution Factor: 1
Concentration in: pg/L (ppb)
Target Analyte Sample Quantitation Concentration Limit
Toluene Chlorobenzene Ethylbenzene Styrene Total Xylenes
ND 5 ND 5 ND 5 ND 5 ND 5
ND = Not detected
Surrogate Spike Recovery
Surrogate Compound Recovery( %) QC Limits(%)
1 ,ZDichloroethaned4 103 76 - 114 Toluened8 98 88-110 Bromofluorobenzene 98 86 - 115
Reported by: Approved by:
1oDean P!n auss Drive, Narragansett, R.I. 02882 l (401) 782-8900 l FAX (401) 782-8905 Volatile Page 6
CEIMIC CORPORATION
“Analytical Chemistry for Environmental Management”
TARGET COMPOUND LIST (TCL) SEMIVOLATILE ORGANICS ANALYSIS
SW846 METHOD 8270
Client: Baker Environmental
Client Sample ID: RR72-DRM
Date Sampled: 12/02/94
Date Sample Received: 12/05/94
Matrix: Aqueous
Surrogate Spike Recovery
Laboratory ID: 941050-03
Date Sample Extracted: 12/07/94
Date Sample Analyzed: 12109194
Associated Method Blank: S1207-B2
Dilution Factor: 1
Concentration in: pg/L (ppb)
Surrogate Compound Recovery( %) QC Liits(%)
2-Fluorophenol 46 2Xhlorophenold4 54 Phenol-d5 39 1,2-Dichlorobenzened4 46 Nitrobenzened5 53 2-Fluorobiphenyl 51 2,4,6-Tribromophenol 47 Terphenyld14 12 **
2i - 110 33-110 * 10 - 110 16-110 * 35 - 114 43 - 116 10 - 123 33 -141
* These limits are provided for advisory purposes. ** Surrogate recovery is out of the QC limits.
Reported by: Approved by:
10 Dean Knauss Drive, Narragansett, R.I. 02882 l (401) 782-8900 l FAX (401) 782-8905
Semivolatile Paee 8
.
CEIMIC CORPORATION
“Analytical Chemistry for Environmental Management”
TARGET ANALYTE LIST (TAL) TOTAL METALS
SW846 METHOD 6010
Client: Baker Environmental
Client Sample ID: RR72-DRM
Date Sampled: 12/02/94
Date Sample Received: 12/05/94
Matrix: Aqueous
Laboratory ID: 941050-03
Date Analysis Completed: 12/09/94
Dilution Factor: 1
Concentration in: mg/L @pm)
Target Analyte Preparation Sample
Batch Concentration Quantitation
Limit
Aluminum 1208 Antimony 1208 Arsenic 1208 Barium 1208 Beryllium 1208 Cadmium 1208 Calcium 1208 Chromium 1208 Cobalt 1208 Copper 1208 Iron 1208 Lead 1208 Magnesium 1208 Manganese 1208 Nickel 1208 Potassium 1208 Selenium 1208 Silver 1208 Sodium 1208 Thallium 1208 Vanadium 1208 Zinc 1208
5.4 ND ND
0.05 ND ND
21.3 ND ND ND 7.0
0.006 1.6
0.05 ND 1.2 ND ND 6.3 ND
0.02 0.02
0.2 0.2 0.01 0.01 0.01 0.01 0.5
0.02 0.04 0.04 0.1
0.005 0.5
0.02 0.04 0.5
0.01 0.01 0.5
0.01 0.02 0.02
ND = Not Detected
Reported by: Approved by:
10 Dean Knauss Drive, Narragansett, R.I. 02882 l (401) 782-8900 l FAX (401) 782-8905 Metals Page 2
CEIMIC CORPORATION
“Analytical Chemistry for Environmental Management”
TOTAL MERCURY
SW846 METOD 7470
Client: Baker Environmental
Project No.: 941050
Date Samples Received: 12/05/94
Date Analysis Completed: 12/07/94
Concentration in: mg/L (ppm)
Client ID Sample Method
Laboratory ID Concentration Reporting Limit
RR72-DRM 941050-03 ND 0.0003
CSFF-DRM 941050-07 ND 0.0003
Method Blank 1207PBW ND
% Recoverv
0.0003
Control Limit
Laboratory Control 1207ICV 112 75-125% Sample
ND = Not detected
Reported by: -.
Y I
Approved by: &
10 Dean Knauss Drive, Narragansett, R.I. 02882 l (401) 782-8900 l FAX (401) 782-8905
CEIMIC CORPORATION
“Analytical Chemistry for Environmental Management”
QUALITY CONTROL
LABORATORY CONTROL SAMPLE
Client: Baker Environmental
Client Sample ID: Laboratory Control Sample
Project No.: 941050
Laboratory ID: QC
Matrix: Aqueous
Target Analyte Date Control
Analyzed % Recovery Limits
Reactive Cyanide
Reactive Sulfide
12/07/94 74 50-125% ,
12/07/94 78 50-125
Reported by: Approved by: w
10 Dean Knauss Drive, Narragansett, R.I. 62882 l (401) 782-8900 l FAX(401) 782-8905
* CEIMIC CORPORATION
“Analytical Chemistry for Environmental Management”
INORGANIC ANALYTES
Client: Baker Environmental
Client ID: RR72-DRM
Laboratory ID: 941050-03
Date Sample Received: 12/05/94
Date Sampled: 12/02/94
Target Analyte
Method Reporting Date
Result Units Limit Analyzed
Flashpoint NC OF 200 12/08/94
PB 6.03 S.U. --- 12/07/94
Reactive Cyanide ND w/W 0.5 12/07/94
Reactive Sulfide ND w/W 1.3 12/07/94
NC = No Combustion ND = Not Detected
Reported by: Approved by:
10 Dean Knauss Drive, Narragansett, R.I. 02882 l (401) 782-8900 l FAX (401) 782-8905
CHAIN OF CUSTODY
CHAIN OF CUSTODY WC& 2ZSOI Original Chain of Custody goes to Laboratory Page I of /
Analyses t!?
Samplers (Please print) L(D pPA: ‘Vo 0 .ja; v, c r
g.?s .E 2 --ikm~ce\o; \co&
E+J E< *‘r rn a3
Comp. 5 DATE Time Grab. Sample Identification
‘“9;” 17~ G R@,7&- ~wi-\d-o3 L 2 )( 7Av ‘$j2 @A (7 (ZR72-N\L3\3-‘vJ-O3 1, 2 x 7-i&
“9;: WI5 b RR7J - T) RrA L 5 % x x K Ro,tl,l ‘?$,3 be b c5FF - /v~.&,-bJ-03 I- 2 X 7-,\q \, I “9;: 123 6 CSF:F- (‘+,LdZZ-W -03 L Z )( 7- dq y
‘qi(3 (3% 6
I
zs5-m3 -01 L3 x F (L+L-F
Date/Time Received by (Signature) Datefime Remarks: (3-3-4Y
(4.30 -se< ReplG& L- 5atmpie tCICr)GC3yll Datemme Received by (Signature) Date/Time - p;(&;‘,\ xk!c y3002Wi/,ci‘-( J
Relinquished by (Signature) Da mrne ,/=,!,c.:TF c P
CEIMIC Corporation dean K&&i Drive, N$$ansett, RI 02882 (401) 782-8900 FAX (401) 782-8905 \ :
APPENDIX D GROUNDWATER TREATMENT SYSTEM -
EQUIPMENT INFORMATION
I Ejector Systems Incorporated
910 National Avenue, Addison, IL 60101-9612 QUOTATION
708-543-2214
l-$00.OIL-LEAK
Fax 708-543-2014
Baker Environmental Airport Office Park,
Quote # 942001-00
420 Rouser Road Bldg. 3 Date: 02/07/95
Coraopolis,‘ PA 15108 Terms: 30/20/5On30
Attn: Don Joiner Freight: prepaid and added
FOB Addison Phone: 412-269-6000 FAX: 4 12-269-2002
Quotation is valid for 60 days
Quote Specifications:
REF: Rifle Range Bldg. 72
SYSTEM ELECTRICAL: 3/60/208 service, brought to NEMA 3R exterior panel
Interior Electrical will be Class 1, Division 1, Group D.
Qtu PUMPING SYSTEM DESIGN CRITERIA:
Diameter Well Depth GTS Flow ---me -----_---_ ---_---__--- ---me ----em
1 6 inch 12 feet 3 ft. 3 9pm
TOTAL FLOW: 10 gpm @ 60 F LNAPL: PRESENT
WATER TREATMENT DESIGN CRITERIA: Dissolved Product: Di&&ge After ESI
Contaminant Concentration .
Air Stripper ----------------------------------------------------------
Benzene Ethylbenzene
357 ppb
zPes
1,090 ppb 1.0 ppb
19;;; I$ 29.0 ppb
-c 1 PPb
400.0 ppb < 1 PPb
.005 ppb < 1 PPb
1,4 DCB 110 ppb 1.8 ppb 3 PPb
1.7 ppb
We offer the following:
1 ON SITE Platform, enclosed 12'x8'. INCLUDING:
* INSULATED ENCLOSURE: 8'W x 12'L x 8.5'H with LIGHT, HEATER and THERMOSTAT
Equipment is mounted on a 8'W x 12'L steel platform with coated plywood deck. The enclosure consists of structural steel members and pre-assembled panels with aluminum skin. The enclosure incorporates one locking hinged door.
The side panels will be easily removable for additional access to the equipment for easier maintenance.
The breaker panel and control panel will be mounted on a vertical steel bracket attached to platform end. The bracket, panels and all conduits will allow for the removal of the enclosure side panels by one person. All electrical components located inside the enclosure
will be Class 1, Division 1, Group D explosion-proof. ;A;;;!le power connection (3/60/208) will be provided by
.
* ES1 STRIPPERATOR O-15 GPM Inte;;$ed process unit
* (2) Effluent Transfer Pump - l-1/2 HP with: (2) Transfer Pump Controls
44,857.44
Ejector Systems Incorporated
910 National Avenue, Addison, IL 60101-9812
STEMS
708-543-2214
l-800.OIL-LEAK
Fax 708-543-2014
Baker Environmental Quote # 94:001-00 Page #
with: Influent Totalizing Flowmeter with: with:
High/Low Air Supply Switch High Sump Level Switch
with: Interga 1 Product Storage Tank 100 ga.llon working capacity High Tank Level Switch
Standard Unit Includes: Oil/Water Separator
* 106 gallon operating capacity * adjustable product effluent weir
Air Stripper (1 tray) * cast aluminum blower * air pressure gauge * 6 removable nylon aeration tubes per tray
flexible wall, dual- 5/16" hole pattern Integral Effluent Sump
* 60 gallon capacity- * inspection/clean out hatch
Carbon Steel Construction * latched and gasketed lid * epoxy coated & lined
* COMPRESSED AIR SYSTEM 3 HP 11.0 CFM 8 150 PSI * pressure lubricated, cast iron block & heads * 80 gallon vertical receiver tank with relief
valve, auto drain valve, pressure switches and pressure gauge.
* SUSPENDED SOLIDS BAG FILTER * 2.1 sq. ft. surface area * 65 gpm flow ca acity * 100 psi coate B pressure tank * 25 micron filtration * 3 replacement bags included * quick opening clamp cover
* LIQUID PHASE CARBON ADSORBERS * 2 drums connected in series * 300 pounds carbon in each drum * 150 psi pressure rating * inlet and outlet pressure gauges * inlet and outlet sample ports * cam-lock hose connections
* TOTAL FLUIDS PUMPING SYSTEM FOR 1 WELL:
* 3"~ 36"L Utility Ejector * S2 single well controller * winch support with well mount * down well hoses and support * all addititonal straps, clamps and fittings
* HIGH LEVEL SHUT OFF SYSTEM * latching pump shut-off relay w/manual reset
and 3 dry contacts * compressor-mounted air shut off valve
.,,\ R
STEMS
708-543-2214
l-800.OIL-LEAK
Fax 708-543-20 14
Ejector Systems Incorporated
910 National Avenue, Addison, IL 60101-9812 . Baker Environmental jhi;;eg# 94:001-00
* NEMA 3R EXTERIOR MOUNTED CONTROLS * breaker panel with individual branch
breakers for all major components * control panel with magnetic starters, high
level shut off system controls, and all additional control circuits required for the system
* ALARM SYSTEM AUTO-DIALER * monitors up to (4) dry contacts input
channels * dials up to (4) phone numbers with message
acknowledgement * battery back-up with condition monitor * voice synthesized’ output
NET TOTAL: Start up cost is $70/hour plus expenses
David Ogilvie Sales Engineer
~PIPPP~~P~
44,857.44
Wl1V
~3ddI?US
O
&V
'
1
c
OUTSIDE
1IR :XHAU
I-
INSIDE
AIR CDMPR, - RCVR
SOLENOID
/---A I TOTAL FLUIDS
-
SHUT FF I I
AIR STRIPPER
FILTER CARBON
STRIPPERATIIR
FILTER REGULATOR
-
PUMP
UNLESS OTHEW!CE DATE
SPECLFED DIN. ARE IN INCI-ES mm,, ED TUNG 11/17/93 m, c-DA&b-- I F,JF(?TnR CYCTFMS INC.
PLATFORM P, & 1, Dm PACKp$gE,D TREi 4TMENT SYSTEM
I\lr LL DAI\IT: ,\n,uiE BLDG, 72 1 StzE JDRAVING NLUPER
-A CAMPBR72 PART tw!Bm
FINISH1 USED Ml
SCALE NONE WEIGHT SHEET 1 OF 1’
L
APPENDIX E ELECTRICAL VOLTAGE DROP CALCULATIONS -
THE AC RESISTANCE AND REACTANCE OF CABLES IN THESE CALULATIONS IS BASED- ON THE 1993 NATIONAL ELECTRIC CODE ( CHAPTER 9 ) INSTALLED IN STEEL CONDUIT.
:IRClJIT VOLTAGE _.. .-_.. .--.. .--. ‘#SE(S) : (ior 3) :fRCUIT WATTAGE : :IRCUIT AMPERES : :IRCUIT BREAKER SIZE : ‘MIN.” SIZE FEEDER(S) REQD FOR COMBINATION LOADS ON
208 VOLTS -.. .--.- 3 PHASE
25000 WATTS 69.4 AMPERES X 1.25 = 66.7 AMPERES 100 AMPERES
(1)NO. 3 WIRE or - KCMIL 1 (2)NO. - KCMIL r
l EXAMPLE WIRE SIZE INPUT = ( 12 = 12 AWG ) , ( “3/O = 3/O AWG ) 8 ( 400 = 400 KCMll l l PARALLEL “MIMIMUM” WIRE SIZE IS NO. ” l/O” AS PER THE N.E.C.
“REQUIRED” FEEDER WIRE SIZ * (I )NO l/O WireJKCMIL lG56OO C. M. “REQUIRED” FEEDER WIRE SIZ ** (2 ) NO Wiren<CMIL - CM. “REQUIRED” FEEDER WIRE SIZ l l ( 3) NO WirdKCMIL - CM. “REQUIRED” FEEDER(S) : ONE TWO THREE VOLTAGE DROP : (ACTUAL) 2.75 0.W 0.00 VOLTS VOLTAGE DROP : (ACTUAL) % 1.3 0.0 0.0 %
CIRCUIT IMPEDENCE : 0.039592 0 0 OHMS SINGLE FEEDER REACTANCE : 0.016500 - - OHMS SINGLE FEEDER RESISTANCE : 0.036 - - OHMS
VOLTAGE DROP : (DESIGN) 6.2 VOLTS VOLTAGE DROP : (DESIGN) % (M .03=% 3.0% DROP
( NOT FOR MOTOR ONLY LOADS ). i 3 j NO. - KCMIL (
YRCUITS TOTAL FEEDER LENGTH : 150 FEET LONG
‘MINIMUM” FEEDER WIRE SIZE - KCMIL - C.M. “MINIMUM” FEEDER WIRE SIZE - KCMIL - C.M. “MINIMUM’ FEEDER WIRE SIZE i3jNo. - KCMIL - C.M. VOLTAGE DROP : (ACTUAL) 5.22 0.00 0.00 VOLTS VOLTAGE DROP: (ACTUAL) 16 2.5 0.0 0.0 K CIRCUIT IMPEDENCE : 0.075215 0 0 OHMS SINGLE FEEDER REACTANCE : 0.0177w - - OHMS SINGLE FEEDER RESISTANCE : 0.075 - - OHMS
“MINIMUM” NUMBER OF FEEDER(S) : / ONE TWO THREE
N
SIZE INPUT = ( 12 = 12 AWG ) , (“3/O = 3/O AWG ) 8 ( 400 = 400 KCMIL MUM” WIRE SIZE IS NO. * irn”~s PER THE N.E.C.
IRCUIT WATTAGE: ’ 25000 WATTS IRCUIT AMPERES : 69.4 AMPERES X 1.25 = 66.7 AMPERES
CIRCUIT BREAKER SIZE: I[ -M AMPERES MIN.” SIZE FEEDER(S) REQ’D ----I ( 1 ) NO. 3 WIRE or -
k FOR COMBINATION LOADS ONLY I KCMIL 1
- MOTOR ONLY LOADS )’
I I
( 2 1 NO. i 3 j ~0.
- KCMIL - KCMIL 1 ~‘(NCTFOR
IRCUITS TOTAL FEEDER LENGTH : 70 FEET LONG
“REQUIRED” FEEDER WIRE SIZ l ( 1) NO 2 Wire/KCMIL 66360 C.M. “REQUIRED” FEEDER WIRE SIZ l * ( 2 ) NO WiraKCMIL - C.M. “REQUIRED” FEEDER WIRE SIZ l l ( 3 ) NO WireiKCMlL - c. M. “REQUIRED” FEEDER(S) : ONE TWO THREE
VOLTAGE DROP : (ACTUAL) 1.99 0.00 0.00 VOLTS VOLTAGE DROP : (ACTUAL) % 1.0 0.0 0.0 %
CIRCUIT IMPEDENCE : 0.026676 0 0 OHMS SINGLE FEEDER REACTANCE : 0.007960 - - OHMS SINGLE FEEDER RESISTANCE : 0.026 - - OHMS
VOLTAGE DROP : (DESIGN) 6.2 VOLTS VOLTAGE DROP : (DESIGN) % (EX.O3=% 3.0% DROP
a.75 4 /* 3% 1-w v I.0720
- - - -5
4.79 -2.3%