simulation based production planning, scheduling, and control johannes krauth sim-serv
TRANSCRIPT
Planning Steps
Production Programme Planning /
Plant or Process Design
(time horizon: years)
Production Planning (months / weeks)
Detailed Scheduling (days / hours)
Control
Overall Planning Objectives
Maximise Capacity Utilisation
Minimise Delays
Minimise Throughput Times
Minimise Work in Progress
Note: Conflicting Objectives!!
Facility Planning
Based on assumed demand
Searches “optimal” match of needed and available capacity
Planning horizon: years
Not an ongoing activity
Optimal Match
Needed per year:
10,400 h milling
______________
8,500 h welding
…
Available per year:
4 machines = 5376 h
(1 shift, 80% utilis.);
= 10752 h (2 shifts)
__________________
4 workers = 8400 h
5 workers = 10080 h
…
?
Limitations
no interdependencies taken into account
based on estimated / experienced degrees of capacity utilisation
adequate for strategic, long-term planning, when little information is available
Production Planning
Based on (expected) customer orders
Using fixed throughput times per step (based on experience or assumptions)
Accepts / rejects orders and fixes start and end dates
Example: Assumed and Real Durations
Department Estimated Throughput Time
Process Time
Lathing 20 days 1 hour
Machining 5 days 20 hours
Surface Treatm. 7 days 1.5 hours
Polishing 7 days 10 hours
Assembly 15 days 20 hours
Total 54 days 52.5 hours
Limitations
Capacity assumed available
Actual shop floor status not taken into account
Waiting times included and therefore fixed
Applicable only when long delivery times are acceptable
Production Scheduling
Planning Horizon: 1 week – 1 day
Based on confirmed orders and actually available resources
Must take into account technical restrictions
Finds exact sequence of operations per work station
Contribution of Simulation
Detailed models
Exact representation of all processes, all needed resources
Realistic transition times, based on current shop floor status
All kinds of rules and constraints can be taken into account
Ways to Use Simulation:
MRP /ERP
System
Simulation Modelcontrols
feeds
back
1. Offline, from outside
Ways to Use Simulation
2. Online, as part of planning toolbox
MRP / ERP System:
Long Term Planning Module_____________________
Medium Term Planning Module___________________
Scheduling Module:
Simulation Model
Shop Floor
Contribution of Optimisation
Can use a large variety of criteria for “optimal” solutions
Finds very good schedules quickly
Takes away hours of routine work from the planners
Allows them to focus on the essentials
Examples
2 Examples: Simulation helps optimise planning tool and process
4 Examples: Simulation and Optimisation modules as part of planning toolbox
Conclusion from Examples:
Broad range of industry sectors
Leitstand / APS tools can complement existing MRP / ERP tools or run stand-alone
Typical benefits include Higher capacity utilisation Less WiP Less delays, shorter throughput times Payback often within a few months!!