shared services for efficiency – a progress report...shared services for efficiency – a progress...

80
Shared Services for Efficiency – A Progress Report REPORT BY THE COMPTROLLER AND AUDITOR GENERAL NIA 206/07- 08 24 July 2008

Upload: others

Post on 12-Jun-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency –A Progress Report

REPORT BY THE COMPTROLLER AND AUDITOR GENERALNIA 206/07-08 24 July 2008

Page 2: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing
Page 3: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Report by the Comptroller and Auditor General for Northern Ireland

Ordered by the Northern Ireland Assembly to be printed and publishedunder the authority of the Assembly, in accordance with its resolution of27 November 2007

Shared Services for Efficiency –A Progress Report

NIA 206/07-08 BELFAST: The Stationery Office £5.00

Page 4: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing
Page 5: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

This report has been prepared under Article 8 of the Audit (Northern Ireland) Order 1987 forpresentation to the Northern Ireland Assembly in accordance with Article 11 of that Order.

J M Dowdall CB Northern Ireland Audit OfficeComptroller and Auditor General 24 July 2008

The Comptroller and Auditor General is the head of the Northern Ireland Audit Officeemploying some 145 staff. He, and the Northern Ireland Audit Office are totally independentof Government. He certifies the accounts of all Government Departments and a wide range ofother public sector bodies; and he has statutory authority to report to the Assembly on theeconomy, efficiency and effectiveness with which departments and other bodies have used theirresources.

For further information about the Northern Ireland Audit Office please contact:

Northern Ireland Audit Office106 University StreetBELFASTBT7 1EU

Tel: 028 9025 1100email: [email protected]: www.niauditoffice.gov.uk

© Northern Ireland Audit Office 2008

Page 6: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Contents

Shared Services for Efficiency – A Progress Report

Page

Executive Summary 1

Part One 7The Northern Ireland Civil Service is seeking to make a step change in its quality, efficiency and effectiveness

Increasing public expectations have been a major driver of the reform agenda 8

The reform agenda is also about improving the efficiency and effectiveness of 8public services

By 2004 work on ambitious projects aimed at rationalising NICS frontline services 9had already been initiated

Many of the projects are now implementing new service provision and ways of working 10

NICS Reform projects now report on their progress to a Civil Service Reform 10Oversight Board

Scope of this Study 12

Part Two 13Projects were developed on the basis of a clear business need and different procurement options were chosen

All the projects meet a high priority business need but their scope has changed 14

There were changes in the overall costs between Outline Business Case and Full 16Business Case

There were differences in the appraisal processes for the projects and the procurement 17routes selected

The outsourcing of accounting services for NICS Departments was not fully explored 18

The procurement solution on the HR Connect project evolved, after the Outline Business 18Case, to a PPP strategic partnership agreement

DFP made efforts to involve and interest prospective contractors and this has had 19beneficial effects

The procurement and implementation phases have lasted longer than estimated in the 21Outline Business Cases

Page 7: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report

Page

Part Three 23Risks to delivery have been identified and are being managed

Managing the risks is integral to the delivery of projects 24

Early assumptions that accommodation for a data centre for the IT Assist project would 24be provided by Workplace 2010 proved to be incorrect

The collection of baseline data and work on benefits realisation was hindered by the 25absence of measurable data

Project Teams engaged stakeholders to get their support 26

Affordability and certainty over funding services are key to the progress of projects 28

Managing the delivery of these projects has been a major challenge for DFP with 28gaps in capacity and capability being filled with the assistance of the private sector

To the end of December 2007, procurement and implementation costs for the shared 30services projects total £44 million

A number of milestones were not achieved by the contractor resulting in changes to 30the HR Connect project agreement

Part Four 33Lessons are emerging for future procurements and projects

There are examples of a good approach to some of the main challenges to delivering projects 34• Contract and Negotiations• Governance and Partnerships• Preparing for Operational Phase

Projects have undertaken Gateway reviews and some have gone through a post 36procurement evaluation

The projects are now subject to new oversight arrangements 38

The work of the Project Management Office has included work to consolidate the 40approach to benefits realisation

In addition to regular oversight, DFP has developed business principles for the provision 41of shared services in the NICS

Page 8: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Contents

Shared Services for Efficiency – A Progress Report

Page

Appendix 1 “Fit for Purpose”: The reform agenda in the Northern Ireland 44Civil Service: Themes and Initiatives

Appendix 2 HR Connect: Project Summary and Progress 45

Appendix 3 Account NI: Project Summary and Progress 49

Appendix 4 Workplace 2010: Project Summary and Progress 52

Appendix 5 Records NI: Project Summary and Progress 54

Appendix 6 Centre for Applied Learning (CAL): Project Summary and Progress 56

Appendix 7 IT Assist: Project Summary and Progress 58

Appendix 8 Network NI: Project Summary and Progress 60

Appendix 9 Civil Service Human Resource Management System: Cancellation 62of the Payroll Project – NIAO Report (November 2004)

Appendix 10 Shared Services Projects: Main Options in Outline Business Case 63

Appendix 11 Shared Services Projects: Cost Summary 64

Appendix 12 Records NI Pilot – Top Ten Implementation Lessons Learned 65

Appendix 13 Summary of Business principles for Shared Services within the NICS 66

Page 9: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Abbreviations

Shared Services for Efficiency – A Progress Report

BAFO Best and Final OfferCAL Centre for Applied LearningCPD Central Procurement DirectorateDARD Department of Agriculture and Rural DevelopmentDCAL Department of Culture, Arts and LeisureDEL Department for Employment and LearningDETI Department of Enterprise, Trade and InvestmentDFP Department of Finance and PersonnelDHSSPS Department of Health, Social Services and Public SafetyDOE Department of the EnvironmentDRD Department for Regional DevelopmentDSD Department for Social DevelopmentEDRM Electronic Document & Record Management SystemFBC Full Business CaseHR Human ResourcesHRMS Human Resources Management SystemICT Information and Communications TechnologyISU Information Support UnitIT Information TechnologyITN Invitation to NegotiateNI Northern IrelandNIAO Northern Ireland Audit OfficeNICS Northern Ireland Civil ServiceNIO Northern Ireland OfficeOBC Outline Business CaseOFMDFM Office of the First Minister and Deputy First MinisterOGC Office of Government CommerceOJEU Official Journal of the European UnionPFI Private Finance InitiativePMO Programme Management OfficePPP Public Private PartnershipPSG Permanent Secretaries GroupSRO Senior Responsible OfficerSSC Shared Services Centre

Page 10: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing
Page 11: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Executive Summary

Page 12: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Executive Summary

2 Shared Services for Efficiency – A Progress Report

1. The Northern Ireland Civil Service (NICS)departments are currently undertaking amajor programme of reform. The NICS isseeking to improve its capacity andcapability by improving its processes andinfrastructure and developing its skills andpeople, so that they can better service thepublic. This reform programme waslaunched in October 2004 with thepublication of “Fit for Purpose: The reformagenda in the Northern Ireland CivilService”. Central to the current programmeof reform are seven key projects (theprojects) which have been taken forwardand developed as part of the Fit for Purposeinitiative (Figure 1). These projects providefor a service-wide consolidation and

redesign of business processes into stand-alone centres or ‘shared services’ projects.The value of these projects is estimated tobe in the region of £2.9 billion.

2. This study provides a progress report, to theend of December 2007, on the delivery ofthese projects. It includes an examination ofhow the Department of Finance andPersonnel (DFP) has assessed and managedthe main risks. Overall the projects arepivotal to the progress of the NI CivilService reform agenda and are, in somecases, already beginning to change theway the NICS operates. Although it is stilltoo early to reach a firm conclusion as towhether these new services are delivering

Figure 1: A major programme of reform across all NICS departments is currently in progress

}}

}NICS Reform

New WorkingMethods andSkilled People

New WorkingEnvironment

New TechnologyFoundation

Source: NIAO review of documentation supporting projects

Page 13: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 3

the efficiencies and benefits envisaged, DFPhas had successes in managing aspects ofthe procurement and implementationprocesses. It is also clear that, in someaspects, projects have encountereddifficulties which have produced challengesfor DFP. Since December 2007, significantprogress has been made in a number ofareas, particularly in the systematicidentification of benefits that will be derivedfrom the projects.

3. This review has not set out to make anassessment of the value for money for eachproject. But given their significance to theNICS programme of reforms, we willcontinue to monitor their implementation witha view to providing further assurance reportsto the Northern Ireland Assembly.

Main Findings

4. The Workplace 2010 project is currently atprocurement stage, therefore this study onlyexamines the decision making process up tothe development of the Outline BusinessCase (OBC). In the remaining six projects,new services are being implemented after aprocess of procurement and/or appraisal.These vary in complexity, scope, contractperiod and value and have different deliverysolutions.

5. The establishment of the Civil Service ReformOversight Board (as a sub-committee of theDFP Departmental Board) and a subsequentclarification of its role, has led to thedevelopment of more effective programmemanagement arrangements that align withgood practice. In addition to regular

oversight, DFP has developed businessprinciples for the provision of sharedservices in the NICS.

6. Outline Business Cases were prepared forthe key projects setting out thestrategic/policy context and defined theoperational need for the services beingprocured. We found clear reasons fordefining each of the Shared Servicesprojects as priority projects.

7. The developing nature of these projects hasled to significant changes in the overall cashcosts. In two of the projects (HR Connectand Account NI), following negotiation withthe preferred bidders, contract periods wereextended. DFP informed us that thesechanges were within the relevantprocurement rules and regulations. Thescope of Account NI was also enlargedwhich led to additional costs. In contrast, onthe Network NI project, there was asignificant reduction in cost, resulting mainlyfrom a change in the scope and thesuccessful bid being significantly lower thanexpected.

8. A number of suppliers indicated theirwillingness to provide accounting serviceson an outsourced basis, including a privatefinance route. However, this option was notinvestigated further by DFP as departmentsconsidered that outsourced provision ofaccounting services would not be “ascalable and flexible solution”.

9. In preparing the OBC in 2003, the HRConnect Programme Board concluded thatfull outsourcing was not a viable option atthat point. However, it supported the

Page 14: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Executive Summary

4 Shared Services for Efficiency – A Progress Report

exploration of two options, including partialPPP. Indeed in considering operationalneed, the outline business case recordedthat an independent improvement of specificHR functions could not guarantee commonstandards with consistent and accurateinformation. Initially a full Public PrivatePartnership (PPP), delivering all the requiredservices, was viewed by the Project Boardas representing too much change (businessand cultural) to ensure successful delivery.There was concern that it would make thecompetition for the procurement moredifficult and lead to potential delay in thenegotiation of a contract. However, in early2004, different levels of outsourcing wereexplored with the short-listed bidders in anextensive and extremely detailed consultationphase. Discussions with bidders and theresults of site visits indicated a ‘mixedeconomy’ solution (i.e. part outsourcing andpart in-house) might not deliver the requiredefficiency savings. In light of these findings,in April 2004 the Project Board agreed toinvite a full PPP bid from the three short-listedbidders.

10. Five of the seven projects went to anexternal procurement process. We foundthat all of the projects had attempted tointerest prospective contractors. All of thefive projects subjected to externalprocurement have attracted at least threedeveloped bids.

11. With the exception of the Centre for AppliedLearning (CAL), which was delivered on time(but is significantly smaller than the otherinitiatives), all other projects have takenlonger to procure and/or implement theirbusiness solution compared with what was

originally estimated. Contract signature hasbeen reached 9 to 18 months later thaninitially planned, with Workplace 2010experiencing a longer delay. The reasons fordelay include initial timetables based onoptimistic assumptions, changes at preferredbidder stage and unforeseen complexity.These types of delay are not unusual inprojects of this nature.

12. In the IT Assist project, the provision of datacentre accommodation is central to theproject: it was initially assumed that theresponsibility for accommodating this servicewould then be handed over to the successfulWorkplace 2010 bidder as part of thatcontract. However subsequently during themore detailed planning, it became clear thatthis option was not feasible so, followingdetailed evaluation of the options, theProject Team prepared a separate businesscase for its provision. The preferred optionwas procurement from a private sectorsupplier at a cost of £10 million. DFP toldus that it considered that there would havebeen significant up front costs no matterwhich option had been chosen.

13. Projects which, during the planning orprocurement phases, have gaps in baselineinformation on the current provision are likelyas a consequence to encounter difficulty indeveloping benefits realisation strategies.We noted several projects that had reachedcontract signature where the benefitsrealisation strategy was either underdevelopment, required more work in relationto their management, monitoring andreporting, or were not yet approved. Wedo, however, acknowledge the additionalwork on baselines for benefits realisation

Page 15: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 5

completed during the later part of 2007and presented to the DFP DepartmentalBoard in February 2008.

14. Project teams have involved stakeholders, tosecure their support. We have identifiedexamples of where this process has workedeffectively on a number of the projects.However, on several of the projects therewas resistance from departments to fundprojects and in Network NI, changes infunding commitments from departments thatdeveloped after approval of the OBCcreated uncertainty as to whether therewould be sufficient funding for the projectduring the initial implementation period.

15. Managing the delivery of these projects hasbeen a major challenge for DFP and insome cases gaps in capacity and capabilityhave been filled with assistance from theprivate sector. This has contributed toincreased procurement and implementationcosts.

16. There are examples of good approaches tosome of the main challenges in deliveringprojects. For example, the structure of theRecords NI contract reflects good practice:its terms and conditions include open bookaccounting and ‘gain sharing’ arrangementsand benchmarking during the lifetime of thecontract. A further example is HR Connect,where the contract allows for departments inGreat Britain to reuse, in certaincircumstances, the process and softwaresolution developed. Furthermore, DFPbelieves that the contract also reflects goodpractice in areas such as Intellectual PropertyRights, Data Protection and Confidentiality,Warranties and Disclaimers, Indemnities andLimit of Liability.

17. All projects (with the exception of the Centrefor Applied Learning) have undertakenGateway reviews and some have gonethrough a post procurement evaluation.Formal post procurement ‘lessons learned’reports have been completed for HRConnect, Records NI and Account NI. Thisis useful both to inform future projects and,because there can be a significant turnoverof key personnel on such projects(particularly at significant break points suchas contract signature), as a response to aneed for continuity and knowledge sharing.

Page 16: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing
Page 17: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Part One:The Northern Ireland Civil Service is seeking to make astep change in its quality, efficiency and effectiveness

Page 18: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Part One:The Northern Ireland Civil Service is seeking to make a step changein its quality, efficiency and effectiveness

8 Shared Services for Efficiency – A Progress Report

1.1 The NICS is currently undertaking a majorprogramme of reform as it seeks to improveits capacity and capability by improving itsprocesses and infrastructure and develop itsskills and people, so that they can betterservice the public. This reform programmewas launched in October 2004 with thepublication of “Fit for Purpose”1. This studyprovides a progress report to the end ofDecember 2007 on key projects(summarised in Figure 1) and examines howthe main risks have been assessed andmanaged.

Increasing public expectations have been amajor driver of the reform agenda

1.2 Research commissioned as part of theReview of Public Administration,2 andpublished in 2004, noted that “the publicare demanding, and expecting, higherquality service delivery from the publicsector in line with changes that have takenplace in recent years in the private sector”.This is endorsed in the ‘Fit for Purpose’document which recognises that services arebeing routinely delivered in shortertimeframes and in more accessible wayswhich people, as consumers, areincreasingly expecting as a matter of course.In this context, the public sector recognisesthat it needs to be aware of and able tomeet people’s rising expectations from publicservices.

1 “Fit for Purpose” – The reform agenda for the Northern Ireland Civil Service, October 20042 The Review of Public Administration was commissioned in June 2002 with the objective of reviewing the arrangements for

the accountability, development, administration and delivery of public services in Northern Ireland3 Northern Ireland Executive: ‘Programme for Government: making a difference’, December 20014 ‘Releasing Resources to the Front Line – Independent Review of Public Sector Efficiency’ (The Gershon Review), July 2004

The reform agenda is also about improvingthe efficiency and effectiveness of publicservices

1.3 The previous Northern Ireland Executive inits last Programme for Government3 made aclear commitment to improving the efficiencyand effectiveness of the administration anddelivery of public services in NorthernIreland. In Great Britain, an efficiencyreview4 of the Home Civil Service (led bySir Peter Gershon) highlighted the scope forefficiencies through greater sharing ofsupport functions such as finance andhuman resources. ‘Fit for Purpose’summarised the challenge to the NICS asdelivering reforms through practicalmeasures. These measures aimed tomaintain the traditional values of the publicservice; support the more modern values ofcustomer focus, professionalism, flexibility,and diversity; and in doing so, enable theNICS to perform more capably andefficiently.

1.4 The practical measures proposed andenvisaged in ‘Fit for Purpose’ comprisedthree fundamental themes that wereoverlapping and complementary (thegeneric measures within each of the themesare noted at Appendix 1):

• Putting the front line first - maximisingthe potential to get energy and resourcesfocused on providing the public functionsthat define the NICS, whether it be thedirect delivery of public services,supporting those who do so orsupporting Ministers in developing publicpolicy and legislation;

Page 19: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 9

• Building capability - enhancing theleadership, expertise, professionalismand general capabilities of the NICS tomeet the current and future challenges indelivering public services; and

• Embracing diversity - better realising thefull potential of society here, both throughimproving services and increasing publicconfidence. This includes being open toworking in new ways and in newstructures including partnership with theprivate and voluntary sectors.

By 2004 work on ambitious projects aimedat rationalising NICS frontline services hadalready been initiated

1.5 The Gershon Review identified ‘back office’support functions as one of the main areasfor potential savings and efficiencies throughsharing arrangements. In ‘Fit for Purpose’, aspart of the ‘putting the front line first’ theme,four projects (HR Connect; Account NI;Workplace 2010; and Records NI) wereindividually and collectively viewed ashelping to ensure that, through the resulting

Figure 2: Seven key projects are driving the NICS Reform Agenda

HR Connect Aims to modernise and transform NICS and Northern Ireland Office (NIO) personnel (Appendix 2) function, replacing out-of-date systems with modern payroll and personnel processes.

Centralised administrative personnel services will be provided from a shared service centre in Belfast. This is viewed as a pathfinder project for HR services provided by government departments in the UK.

Account NI Modernising NICS accounting processes. A shared services centre based in Belfast (Appendix 3) aims to deliver centralised transaction processing services, such as payments

processing, to all departments.

Workplace 2010 Aims to introduce a modern, flexible working environment that is predominantly open (Appendix 4) plan, that will support a modern civil service and new ways of working, and enable

the civil service to transform the way it delivers public services; providing accommodation that is fit for purpose.

Records NI Aims to provide a common storage facility for all of the NICS known as an Electronic (Appendix 5) Document & Record Management System (EDRMS).

Centre for Applied Is aiming, through a reorganisation of existing provision, to provide quality generic Learning (CAL) training services mainly to NICS departments and agencies, including members of (Appendix 6) the Senior Civil Service.

IT Assist A new information and communications technology shared service centre. Its aim is (Appendix 7) to ensure value for money and a more flexible and reliable service.

Network NI Providing a single, dedicated, high-speed, network service connecting all NICS (Appendix 8) locations, to deliver voice, video and data communication in support of a modern

public sector.

Source: NIAO

Page 20: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Part One:The Northern Ireland Civil Service is seeking to make a step changein its quality, efficiency and effectiveness

10 Shared Services for Efficiency – A Progress Report

efficiencies, increases in public spendingwas focused on frontline services forcitizens. Harnessing technology was alsopart of putting the front line first, throughdeveloping initiatives based on Informationand Communications Technology (ICT).These initiatives included the planning of asingle shared ICT service (IT Assist) for arange of generic functions and a newproject (Network NI) to co-ordinate therequirement for new broadband technologyacross the NICS and the wider publicsector.

1.6 Developing talent and professionalism was aninitiative within the building capability theme.Overhauling training was one of the specificmeasures within that initiative. For example,there was a commitment to a comprehensivereview of the delivery of generic trainingacross the NICS with the aim of devising anew model. This review took place andultimately resulted in the creation of the Centrefor Applied Learning. A summary of these keyreform programmes is outlined in Figure 2.Further analysis of the current status of each ofthese projects is provided in Appendices 2 to8, examining the history and progress of theprojects to date.

Many of the projects are now implementingnew service provision and ways of working

1.7 The Workplace 2010 project is currently atprocurement stage, therefore this study canonly examine the decision making processup to the development of the OutlineBusiness Case. In the remaining six projectsnew services are being implemented after aprocess of procurement and/or appraisal.

5 Projects also differ in their definitions of implementation. For HR Connect, it consists of the design, test and build phase,continuing until the date of when the last service goes live. For Account NI, it is the design, test and build phase followedby a migration to departments in a series of five waves. For IT Assist, it is the building of a physical system followed by astaged migration of departments onto the new service.

6 Managing Successful Programmes – Office of Government Commerce

These projects vary in complexity, scope,contract period and value and deliverysolutions. These factors have influencedplanned and/or actual implementation5

periods for each of the projects, which havevaried from the 6 months achieved for theCAL project to an estimated implementationof 32 months for the HR Connect project(Figure 3).

The NICS Reform projects now report ontheir progress to a Civil Service ReformOversight Board

1.8 As outlined in Figure 3, five of the keycontracts were signed during 2006. Therehave been improvements to the governancestructures, starting with the establishment ofan Oversight Board which met formally forthe first time in September 2006. TheOversight Board is chaired by a non-Executive member of the DFP Board andincludes members from other NICSDepartments. In December 2006, the roleof the Oversight Board was clarified,defining the programme as covering thewhole of the civil service reform programme,including the supporting infrastructure. Thisled to the development of more effectiveprogramme management arrangements thatalign with good practice issued by theOffice of Government Commerce (OGC)6.These included improved planning co-ordination of project delivery, riskmanagement, communications and benefitsassessment planning. These processes weresubjected to an external review in July2007, commissioned by the Department.The review endorsed the general approachadopted, but recommended a number of

Page 21: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 11

Figure 3: Progress of Shared Service Projects as at 31 December 2007

Project / 2006 2007 2008 2009

OBC Approval Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Date

Jan Sept

CALJuly 2005

Mar Nov

HR ConnectJune 2003

June Apr

Account NIOctober 2003

July Mar

Records NIApril 2004

Dec Mar

IT Assist March 2006

Sept Oct

Network NIMarch 2005

Workplace2010Oct 2005

Contract Signature (or equivalent) Implementation Phase

NOTESCAL: The approval of a shared service approach by the Permanent Secretaries Group (PSG), which comprises the 11Departmental Permanent Secretaries and is chaired by the Head of the NI Civil Service, was taken as equivalent to theapproval of the Outline Business Case. CAL was established in April 2006 and there was no commercial procurement. Theproject was closed at the end of September 2006 when CAL assumed responsibility for all NICS generic training.IT Assist: OBC recommended an in-house solution, so there was no single major procurement.

Source: NIAO and Civil Service Reform Oversight Board

Page 22: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Part One:The Northern Ireland Civil Service is seeking to make a step changein its quality, efficiency and effectiveness

12 Shared Services for Efficiency – A Progress Report

changes to its operation. The OversightBoard accepted all of the review’srecommendations in principle and inresponse have developed an action plan fortaking these forward in 2008 and beyond.

Scope of this Study

1.9 Given the importance of these sharedservices projects to the delivery of reform inNorthern Ireland and the current cost andfuture expenditure commitments that willensue, we felt it appropriate at this point totake stock of the main issues that haveemerged during the procurement andimplementation processes to date. Thisincludes the governance arrangements put inplace for this portfolio of projects. Thisreview has not set out to make anassessment of value for money for eachproject. But given their significance to theNICS programme of reforms, we willcontinue to monitor their implementation witha view to providing further assurance reportsto the Northern Ireland Assembly. Thefollowing chapters examine the projectsconsidering;

• Were the projects developed on thebasis of a clear business need and wereappropriate procurement optionsexplored? (Part Two)

• Have risks to delivery been identified andwell managed? (Part Three)

• Are there lessons emerging for futureprocurements and projects? (Part Four)

Page 23: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Part Two:Projects were developed on the basis of a clear businessneed and different procurement options were chosen

Page 24: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Part Two:Projects were developed on the basis of a clear business need anddifferent procurement options were chosen

14 Shared Services for Efficiency – A Progress Report

All the projects met a high priority businessneed but their scope has changed

2.1 For any project, the public sector should firstestablish a clear need and priority for theservices being procured. This should befollowed by consideration of appropriateprocurement options such as: thereorganisation or reconfiguration of existingservices; the assessment of potential in-housesolutions; outsourcing; or a long-termstrategic partnership with the private sector.

Outline Business Cases were prepared forsix of the projects, setting out thestrategic/policy context and defining theoperational need for the services beingprocured. We found clear reasons for eachof the projects being defined as priorityprojects. Figures 4 and 5 provide ananalysis of the strategic context andoperational need identified for two of themajor projects - HR Connect and Workplace2010. The HR Connect project included thereplacement of a payroll system, for which

Strategic/Policy Context

NICS HR Strategy: This strategy, which sought tomodernise HR in the NICS, had been endorsed by theprevious Northern Ireland Executive.

The government reform agenda: A key priority of theagenda is the modernisation of government to ensure thedelivery to all customers of efficient, integrated serviceswhich maximise the potential of technology.

Human Resource Management Information (HRMI)Strategy: The HRMI strategy underpins the NICS HRstrategy. At its heart is the vision of a commoninformation source and common practice. Streamlining ofprocesses will release HR staff from low-leveladministrative tasks and overall the HR function will bemore responsive to business needs.

e-Government targets: The Modernising GovernmentWhite Paper in GB (1999) emphasised the need tochange and improve by exploiting ICT and setting targetsfor delivering Government services by electronic means.The transformation of HR services would be a key enablerin supporting departments to achieve targets in the e-Government strategy set by the previous NI Executive.

Operational Need

Customer Expectations: Departments, particularlytheir HR Divisions, were under increasing pressureto meet customer expectations of up to dateinformation that could be accessed quickly.

Quality of Existing Systems: The technologywithin the current systems was dated and costly tomaintain.

Skills Gap: There was a lack of skills indepartments in the use of the Human ResourceManagement System (HRMS), one of the two mainsystems.

Changing business environment: The two mainsystems, payroll and HRMS, were due to expire in2006 and 2008 respectively. Both systems wereperforming poorly and would not support achanging business environment.

The OBC noted that if these operational issueswere not addressed in a cohesive and structuredway, the improvement in HR could becomefragmented with the potential for duplication,greatly increased costs and a reduction in thelikely benefits.

Figure 4: The HR Connect Outline Business Case identified strategic and operational needs

Source: HR Connect Outline Business Case (approved June 2003)

Page 25: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 15

7 The achievement or otherwise of these targets is beyond the scope of this report

an earlier procurement had been cancelledin 2001. This cancellation was the subjectof an NIAO report, a summary of which isat Appendix 9. The Department told us that,as it was a reorganisation of existingprovision, an OBC was not required for the

Centre for Applied Learning (CAL) project.The business need was, neverthelessdemonstrated in a series of reviews,including one involving officials from theCabinet Office. In addition, CAL prepareda document, after its establishment, setting

Strategic/Policy Context

Gershon: The Gershon review identified the releasing ofresources out of back office activities into high priorityfrontline services as a major source of efficiencies. Theproject’s outcome - a more streamlined and efficient estateable to realise monetary benefits - was seen as beingconsistent with Gershon.

NICS Reform and Efficiency Programmes: The likelychanges in the delivery of NICS Corporate Servicesthrough the adoption of large ‘shared service’ centres,and what was a pilot phase for Records NI, wouldreduce space requirements.

DFP Public Service Agreement and Strategic Plan(2003-2005): Modernising the provision of governmentoffice accommodation was a key area of reform for DFP.Along with the Strategic Investment Board, DFPcommissioned the Strategic Development Plan for theNICS office estate to reform, rationalise and modernisethe way in which the NICS procures, manages andutilises its office estate.

Fit for Purpose (October 2004): The specific targets7

included programmes to rationalise support services inhuman resources, financial and accounting services andoffice accommodation, and also to reduce the number ofCivil Service buildings in the Greater Belfast area by 50per cent by 2010.

Revised NICS Government Office Specification Policy:The remit of the Strategic Development Plan included thedevelopment of a standard specification based onexperience of best practice in UK government, with thepurpose of defining the operational policies to be pursuedin relation to the NICS estate.

Operational Need

Backlog maintenance: Condition assessment workconfirmed a backlog covering both building fabricand services. It was concluded that it would beunreasonable to expect efficient and productivework to be performed in some offices.

Modernise the working environment: Theworkspace available was not fully utilised becauseof cellular offices allocated by grade. In someinstances, cellular offices led to others working invery cramped conditions. It means that thestructure of the building dictates the culture of thebusiness, rather than supports it.

Meet operational requirements: Interviews withall of the departments indicated support formoving to as few buildings as possible, supportfor the principles of new ways of working andagreement of the need to use assets efficiently andeffectively.

Figure 5: The Workplace 2010 Outline Business Case identified strategic and operational needs

Source: Workplace 2010 Outline Business Case (approved October 2005)

Page 26: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Part Two:Projects were developed on the basis of a clear business need anddifferent procurement options were chosen

16 Shared Services for Efficiency – A Progress Report

out the rationale for its creation and tosupport its action plan to ensure that thebenefits of the project are achieved (benefitsrealisation).

There were changes in the overall costsbetween Outline Business Case and FullBusiness Case

2.2 Our examination of documentationsupporting the seven projects noted that, todate, a Full Business Case (FBC) has beenproduced for four projects (Figure 6). Thedeveloping nature of these projects has led tosignificant changes in the overall cost

Project OBC FBC Reasons for Changes£m £m

Workplace 2010 1,968.1 N/A Project still at Outline Business Case stage at 31 December 2007.

HR Connect 328.5 465.1 1. Change in contract term from 10 to 15 years.2. Capital cost increased from £5.5m to £37.8m.

Account NI 113.6 169.4 1. Change in contract term from 10 to 12 years. 2. Scope changes and costs for services not in OBC, but in a separate OBC.3. Costs for procurement and implementation greater than planned for at OBC.4. Increased IT cost after benchmarking exercise.Note: The preferred bid was £105.9m.

Records NI 21.2 17.5 The successful bidder will manage the service at an annual cost of over 50 per cent less than in the OBC, with a £2 million refresh after 5 years.

Network NI 48.7 29.3 1. The non-NICS bodies, including the Health Service, were withdrawn from the project in September 2006 to ensure competition in the network services market through separate procurement exercises for other major segments of the Northern Ireland public sector. 2. The OBC included £1.4m for capital and £5.7m for changes in the contract period.3. The successful bid was significantly less (in cash terms) than DFP had estimated in the OBC.

Source: NIAO review of documentation supporting projects

Figure 6: There were increases and decreases in estimated costs from Outline Business Case to Full BusinessCase in a number of the Projects

Page 27: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 17

8 “Economic Appraisal guidance: Step by Step Appraisal Guidance”, DFP 20039 These are usually considered as baseline type options. The do nothing option (also known as the status quo option) is the

genuine minimum input necessary to maintain services at, or as close as possible to, their current level. The do minimum canbe regarded as the status quo option in certain circumstances, but is a separate option where there is a new legalimperative or a policy commitment to develop services.

estimates included in their respective OBCsand FBCs. In two of the projects (HR Connectand Account NI), the contract periods wereextended, and the scope of the Account NIproject was also expanded (Figure 6). In bothprojects, the Outline Business Case wasbased on a 10 year period. In HR Connect,the period was extended to 15 years whenDFP issued the Invitation to Negotiate to theshort-listed bidders. In Account NI, the periodwas extended to 12 years followingnegotiation with the preferred bidder. InRecords NI, the reduction in the overall costwas due to the successful bidder pricing theannual running costs at significantly less thanthe estimate in the OBC. The original projectproposal for Network NI was theaggregation of the Northern Ireland publicsector demand so that the best possiblecommercial deal could be agreed withproviders. But the number of bodiesparticipating was reduced due to concernsabout the impact of aggregation on thecompetitive environment in Northern Ireland.

There were differences in the appraisalprocesses for the projects and theprocurement routes selected

2.3 A long-standing requirement of economicappraisal guidance is to identify anddescribe the procurement options. CurrentDFP guidance emphasises that it is only bycomparing alternative courses of action thatthe real merits of any particular course ofaction is exposed8. The options that aremost frequently considered in appraisals are:

• do nothing/do minimum9;

• ‘in-house’ public sector provision;

• a hybrid option of in-house and privatesector provision;

• private sector competitive tendering forservices using existing assets; and

• private sector provision and operation ofnew assets (Public Private Partnership(PPP) or Private Finance Initiative (PFI)solutions).

2.4 Appendix 10 provides an overview of theprocurement options considered for each ofthe Shared Services projects and thepreferred option chosen. Workplace 2010,currently in procurement, is being takenforward on the basis of a ‘total property’ PFIroute for most of the NICS office estate. Theprocurement options selected at OBC for theother projects (excluding CAL) were:

Project Option SelectedHR Connect In-house provision of HR

services (such as recruitment and absence management) with the payroll and support services outsourced to external provider

Account NI An in-house NICS shared service centre developed by an external provider

Records NI Partnership with single external provider

IT Assist A single in-house Shared Services Centre with the contracts rationalised into asmall number of strategic contracts

Network NI Fully outsourced to an external provider.

Page 28: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Part Two:Projects were developed on the basis of a clear business need anddifferent procurement options were chosen

18 Shared Services for Efficiency – A Progress Report

2.5 The IT enabled projects (IT Assist, RecordsNI and Network NI) did not adopt aPFI/PPP approach. A key reason behind thisdecision was the revised guidance10 issuedby Treasury in July 2003, which advisedthat there should be a presumption againstthe use of PFI for delivering IT enabledprojects. This was based on experience ofsignificant problems with PFI contracts in theIT sector.

2.6 Advisors were appointed in 2005 by the ITAssist Project Board to examine the potentialfor outsourcing options. Based on theinformation they had gathered, theyconcluded that the NICS “was not yet readyto consider the outsourcing option seriously”.They recommended that outsourcing shouldbe one of the options to be appraised in theOBC. An outsourcing option wasconsidered in the OBC. However, theappraisal of benefits did not contain adetailed analysis of the potential costsavings or redeployment of resources thatmay have resulted from that option.

The outsourcing of accounting services forNICS Departments was not fully explored

2.7 The previous Northern Ireland Executiveagreed the policy of providing accountingservices across Departments on a commonbasis in November 2001. Although it wasa move to a central database system, thenature of the procurement was NICS-wide,with the approach being to design andspecify the requirements in consultation withdepartments. In formally registering theirinterest in the Account NI project in the earlymonths of 2003, a number of suppliers

10 PFI: Meeting the Investment Challenge, HM Treasury, July 2003

indicated their willingness to provide thetransaction processing service on anoutsourced basis, including a private financeroute. These options were included in theinitial ‘long’ list of options. The Account NIProject Team asked departments for theirviews on all the options on the basis of pre-set criteria determined by DFP. Overall, theinformation received from departmentsindicated that their view was that therewould be a lack of flexibility with all formsof outsourced provision. They alsoconsidered that outsourced provision ofaccounting services would not be “ascalable and flexible solution”.

The procurement solution on the HR Connectproject evolved, after the Outline BusinessCase, to a PPP strategic partnershipagreement

2.8 The OBC approved in June 2003concluded that, although a full PPP was notconsidered a viable option, two optionswere proposed for further investigationthrough the procurement stage. This includedprovision for partial PPP. A full PPP deliveringall the required services was viewed in theOBC as representing too much change(business and cultural) to ensure successfuldelivery. The Project Board felt that the riskassociated with this could not be transferredto the contractor. It also concluded that itwould make the competition for theprocurement more difficult and lead topotential delay in the negotiation of acontract.

2.9 At a workshop in October 2003,Departmental Human Resource Directors (the

Page 29: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 19

11 OGC Gateway Process Review 1: Business Justification 12 “Improving the PFI tendering process”, National Audit Office, March 2007 (HC149, Session 2006-07)13 “HM Treasury: Tendering and benchmarking in PFI”, Committee of Public Accounts, November 2007 (HC 754, 63rd

Report of Session 2006-07)

project board members) discussed proposalsfor a future service delivery model. Theyagreed that the option to contract for awholly managed payroll service wasemerging as a preference. From January toMarch 2004, different levels of outsourcingwere explored with the three short-listedbidders in an extensive and extremelydetailed consultation phase. Each biddersubmitted blueprints and outline costsdetailing their views and approach toproviding HR services. This information wasused to further refine the service deliverymodel. Discussions with bidders and theresults of site visits indicated that a ‘mixedeconomy’ solution (i.e. part outsourcing andpart in-house) might not deliver the requiredefficiency savings. In light of these findings,in April 2004 the Project Board agreed toinvite a full PPP bid from the three short-listedbidders. We noted that DFP approval wasnot sought for this change in procurementapproach. The Department told us that, as achange in procurement approach wasprovided for in the OBC, DFP Supplyapproval was not required. The procurementresulted in a PPP, the contract for which wassigned in March 2006.

DFP made efforts to involve and interestprospective contractors and this has hadbeneficial effects

2.10 OGC procurement evaluation guidance11

recommends that the preparatory work onany project should establish potential marketinterest in a project. This can includeexamining recent similar procurements,evidence of competitive interest and marketcapability in that sector, and sounding out

the market to have some evidence as towhether the private sector is capable ofdelivering the particular project.

2.11 Five of the seven projects went through anexternal procurement process. We foundthat the five projects made an effort togenerate interest from prospectivecontractors. This was done through the useof methods such as Prior Indicative Notices(HR Connect and Account NI), which arepublished in the Official Journal of theEuropean Union (OJEU) and enable publicsector Authorities to provide advance noticeof potential procurement activity. We alsofound evidence of similar efforts in RecordsNI and Network NI, where some of the costinformation used in the Business Cases forthe projects was based on informationderived from prospective suppliers.

2.12 A National Audit Office census of PFIprojects signed between 2004 and 200612

found that only 67 per cent of those projectsreceived three or more developed bids.There were also regional variations - outsideof London, the North West and North Eastof England, it was more difficult to interestthe market because regional sub-contractorswere either not acceptable tobidders/capable of taking on the work orthere were no existing links with majorcontractors. In a project with only two bidsthere is a risk of no competition if onebidder is weak or withdraws from thecompetition13.

2.13 All the five projects subjected to externalprocurement in Northern Ireland haveattracted at least three developed bids, andthe process has had wider benefits for the

Page 30: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Part Two:Projects were developed on the basis of a clear business need anddifferent procurement options were chosen

20 Shared Services for Efficiency – A Progress Report

Proj

ect(N

ote

1)O

JEU

Not

ice

Cont

ract

Sign

atur

eIm

plem

enta

tion

Perio

d

Plan

ned

Act

ual

Plan

ned

Act

ual

Plan

ned

Act

ual

HRCo

nnec

tSe

ptemb

er20

03Se

ptemb

er20

03Se

ptemb

er20

04M

arch

2006

Septe

mber

2004

toAp

ril20

06to

(App

endi

x2)

Septe

mer2

008

Nov

embe

r200

8

Acco

untN

IO

ctobe

r200

3Ja

nuar

y20

04M

arch

2005

June

2006

April

2005

toJul

y20

06to

(App

endi

x3)

Mar

ch20

08Ap

ril20

09

Wor

kpla

ce20

10(N

ote2)

Nov

embe

r200

5N

ovem

ber2

005

Dece

mber

2006

Not

Know

nN

otKn

own

Not

Know

n(A

ppen

dix

4)

Reco

rdsN

ISe

ptemb

er20

04Jun

e20

05Se

ptemb

er20

05Jul

y20

06M

arch

2006

toJul

y20

06to

(App

endi

x5)

June

2007

Mar

ch20

08

CAL(N

ote3)

N/A

N/A

April

2006

April

2006

April

2006

toAp

ril20

06to

(App

endi

x6)

Octo

ber2

006

Octo

ber2

006

ITAs

sist(N

ote4)

N/A

N/A

Mar

ch20

06De

cemb

er20

06Se

ptemb

er20

06to

April

2007

to(A

ppen

dix

7)De

cemb

er20

08M

arch

2009

Netw

ork

NIJun

e20

05Ja

nuar

y20

06Se

ptemb

er20

06Se

ptemb

er20

07Se

ptemb

er20

06to

Septe

mber

2007

to(A

ppen

dix

8)De

cemb

er20

06O

ctobe

r200

9

NO

TES

1.Pl

anne

dda

tes

are

the

mile

stone

sin

clud

edin

the

Out

line

Busin

ess

Cas

e,ex

cept

forW

orkp

lace

2010

whi

chis

OJE

Uan

dC

ALw

hich

isba

sed

onth

ePe

rman

entS

ecre

tarie

sG

roup

.2.

Wor

kpla

ce20

10:T

heO

BCdi

dno

tspe

cify

atim

etab

le.

3.CA

L:Th

eDe

partm

entt

old

usan

OBC

was

notr

equi

red.

How

ever

,are

view

byth

eC

abin

etO

ffice

reco

mm

ende

dth

ecr

eatio

nof

ash

ared

serv

ice

cent

refo

rgen

eric

train

ing.

Subs

eque

ntly,

the

Perm

anen

tSec

reta

ries

Gro

upw

ithin

the

NIC

Sco

mm

issio

ned

atw

osta

gere

view

tobr

ing

forw

ard

prop

osal

sfo

rthe

esta

blish

men

tand

oper

atio

nalp

hasin

gin

ofC

AL.

4.IT

Ass

ist:

The

OBC

reco

mm

ende

dan

in-h

ouse

solu

tion

and

ther

ew

asno

maj

orpr

ocur

emen

t.

Sour

ce:N

IAO

revi

ewof

docu

men

tatio

nsu

ppor

ting

proj

ect

Figu

re7:

Shar

edSe

rvic

ePr

ojec

ts–

plan

ned

and

actu

alm

ilest

one

date

s(O

JEU

Not

ice

and

Cont

ract

Sign

atur

e)

Page 31: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 21

14 PRIME (DWP), Newcastle Estate Development, STEPS (Inland Revenue), MoDEL (Defence)15 Details of the Gateway process and its development are at paragraphs 4.6 and 4.7

local market with the entry of a newprovider.

The procurement and implementationphases have lasted longer than estimated inthe Outline Business Cases

2.14 The estimated and actual timescales forprocuring and delivering the projects are setout at Figure 7. Delays are not unusual inprojects of this nature. With the exception ofCAL, which was delivered on time but issignificantly smaller than the other initiatives,all other projects have taken longer toprocure and/or implement their businesssolution compared with what was originallyestimated. To date on the other projects,contract signature has been reached 9 to18 months later than initially planned.Workplace 2010 will take longer to reachcontract signature.

2.15 From our review of documentation anddiscussions with officials, the reasons fortime delays varied from project to projectand could be for multiple reasons. Anexample of those reasons (for HR Connect)is set out in Figure 8. Other reasons for timedelays included:

• Plans based on optimistic timescales: Inthe OJEU notice for Workplace 2010,the Department set an indicativeprocurement timescale of 13 months. Thiswas an optimistic commitment given theexisting experience of time taken onsmaller scale PFI procurements inNorthern Ireland and the larger estate-based PFI procurements in GreatBritain14; and

• Changes at preferred bidder stage: Inthe Account NI project, 18 monthselapsed between the appointment of asingle preferred bidder and contractsignature. A Gateway15 review by OGCpersonnel in March 2006 concluded thatthe length of the procurement may havebeen due to either the NICS having toofew skilled resources available at criticaltimes or delays in receiving financialmodels from the bidder, alongside theextension in the contract term. Also, theservice requirement was amended on 14occasions and the preferred biddersubmitted revised prices twice.

2.16 The Department told us that the Account NIproject board agreed to move quickly toawarding preferred bidder status because ofthe financial gap, £57 million in cash terms,between the first and second bidders.However the board recognised that, bydoing so, it removed the competitive tensionand therefore it was very important that thenegotiations with the preferred bidder wererobust around timetable and scope. Thelong time from appointment of the preferredbidder to contract award reflected this. Aspart of the clarification process through thebidding phase, there were amendments andclarifications provided to meet the projectrequirements. The Department advised thatthis is a normal part of major complexnegotiations.

Page 32: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Part Two:Projects were developed on the basis of a clear business need anddifferent procurement options were chosen

22 Shared Services for Efficiency – A Progress Report

Factors in time delays in procurement

The procurement period for the project was 30 months compared with the original assumption of 12 in thebusiness case. Apart from the change in the procurement approach to a full PPP (paragraphs 2.8 and 2.9), theprocurement was extended because of:

1) proceeding with three shortlisted bidders instead of two as planned. This did have the effect of increasingcompetition between the bidders, mitigating the impact of bidder withdrawal on the procurement process;

2) the bidders had to support their proposals with ‘reference’ sites where they were providing services. In somecases, the sites were not able to meet DFP’s procurement timetable, with the result that the visits took placelater and over a longer timescale;

3) the time taken to develop the detailed service levels and key performance indicators;

4) unexpected additional due diligence requests by the bidders. (Due diligence is the work carried out by theparties (including funders) in a procurement to clarify the nature and extent of risks in a project and thenprice accordingly); and

5) the complexity of contract negotiations.

During the procurement, there was the possibility of a judicial review. DFP told us that the impact of this wasmanaged in such a way that it ran in parallel with the procurement process and did not impact on thetimescales. There was an impact, noted in the Lessons Learned Report (June 2006), of a diversion of resourcesand core negotiating management team time from critical procurement tasks.

Source: NIAO review of documentation supporting project

Figure 8: Case Study (HR Connect)

Page 33: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Part Three:Risks to delivery have been identified and are beingmanaged

Page 34: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Part Three:Risks to delivery have been identified and are being managed

24 Shared Services for Efficiency – A Progress Report

Managing the risks is integral to thedelivery of projects3.1 There will be risks (both potential and actual)

in proceeding with any project. Theidentification of risks should commence atthe start of a project and be addressed byputting in place realistic procedures formitigating them if they occur. Riskmanagement is one of the main activities inmanaging projects. There needs to be activerisk management during a project, becausenew risks will emerge and the significanceof some of the existing risks may change.This section indicates how the sharedservices initiatives have managed some ofthe major risks.

Early assumptions that accommodation for adata centre for the IT Assist project would beprovided by Workplace 2010 proved to beincorrect

3.2 The business case for the IT Assist projectwas developed on the basis that the datacentre could be accommodated in theStormont Estate “for the foreseeable future”(defined by the project Steering Group inJanuary 2006 as two to five years). TheOBC (March 2006) for the IT Assist projectassumed that the responsibility foraccommodating this service would then behanded over to the successful Workplace2010 bidder as part of that contract. Ourreview of IT Assist papers noted that,following an intervention by the Workplace2010 Senior Responsible Officer16 (SRO)during the summer of 2006, anaccommodation options exercise for IT Assistwas commissioned. The outcome of this

16 The Senior Responsible Officer (SRO) is personally responsible and accountable for the success of a project or programme.The OGC advises that this includes ensuring that the project meets its objectives and delivers the projected benefits. TheSRO must be senior and recognized as the owner of the project/programme throughout the organisation. The SROresponsibility for the seven projects being reported on was covered by four officials, with one official having responsibilityfor four of the projects (Workplace 2010, Records NI, IT Assist and Network NI).

review was a recommendation, in July2006, for a short-term data centre solutionoperating outside the Workplace 2010deal. However as the OBC for IT Assistconsidered accommodation to be costneutral, it was agreed to continue to treatdata centre accommodation in the sameway within the OBC, but to commission aseparate business case to deal with theissue. This separate business caserecommended a seven year commitmentwith procurement from a private sectorsupplier. The business case showed a savingof £1.1m over that period by moving theNICS servers from their current locations inseveral places to a single fit for purposecomputer room. The accommodation projectfor the data centre was publicly advertisedin November 2006 and a preferred bidderidentified in April 2007. However, DFPSupply approval of the business case wasnot obtained until May 2007. A seven yearcontract, valued at £10 million, was signedin July 2007.

3.3 The IT Assist OBC option appraisal details aplanned cost saving, from selecting thesingle in-house Shared Service Centre option(paragraph 2.4), of £3.6 million on existingcontracts costing £27.4 million, over a 10year period. The data centre contract nowrepresents an additional commitment of £10million over a seven year period. DFP toldus that it considered that there would havebeen significant up front costs no matterwhich option had been chosen.

Page 35: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 25

17 OGC Gateway Review 1 (Business Justification)

The collection of baseline data and work onbenefits realisation was hindered by theabsence of measurable data

3.4 At the OBC stage, the basis for proceedingwith a project (by whatever procurementroute) should include a description of thebenefits that will accrue as a result of theinvestment. Current OGC guidance17 onreviewing the business justification for aproject expects reviewers to probe if thecritical success factors can be quantified ormeasured. The evidence expected includesexplanation of how the factors will bemeasured, with identification of baselinemeasures where appropriate.

3.5 A recurrent theme from our review ofdocumentation and discussions with staffwas that the development of these projectswas complicated and prolonged, due to theabsence of data, available in a uniformbasis, on the historic cost and theperformance of the services being provided.An example is Workplace 2010 (Figure 9).On CAL, the reviews of service provisionthat led to its creation (see paragraph 2.1)also cited problems with baseline measures,as historic data was incomplete or createdon a basis which was not comparable. The

Department informed us that its approach, inthe absence of a precise baselinemeasurement, is to use a ‘best estimate’figure agreed with the relevant stakeholders.DFP also advised that the IT Assist projectboard commissioned consultants to reviewthe options using (their own collated)baseline data and this facilitated thedevelopment of the OBC, using ‘reasonablyrobust’ figure work drawn from organisationsworldwide providing services to similarnumbers of users.

3.6 Projects which during the planning orprocurement phases have gaps in baselineinformation on the current provision arelikely, as a consequence, to encounterdifficulty in developing benefits realisationstrategies. We noted several projects thathad reached contract signature where thebenefits realisation strategy was either underdevelopment (Network NI); required morework in relation to their management,measurement, monitoring and reporting(Account NI); or were not yet approved(Records NI).

3.7 Anticipated benefits identified should belinked to specific key performanceindicators. For example, on Records NI, the

Availability of Baseline Data - Running Costs

“The direct running costs of the estate are around £88 million a year……………To put together a cost base-linefor the in-scope estate took the study team over three months. This is because the costs are managed by avariety of different organisations within NICS in a variety of different ways. This in itself is a fundamental issuefor NICS in that it cannot currently measure the performance of the estate on a cost basis, and therefore cannotsatisfy itself that it is managing these costs effectively.”

Source: Workplace 2010 Outline Business Case September 2005 (extract)

Figure 9: Case Study (Workplace 2010)

Page 36: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Part Three:Risks to delivery have been identified and are being managed

26 Shared Services for Efficiency – A Progress Report

benefits from the creation of electronicaccess to documents from multiple locationsacross the NICS will lead to improvedaccess and a reduced volume of registrystorage for documents. Whilst HR Connectand Account NI are significant projects, theearly benefits models that were developed(with input from external consultancy advice)were very elaborate. For example, HRConnect approached this on the basis ofkey performance indicators linked to thecontract. Through a process of refinementthere are now 45 top level benefit outcomesexpected from Departmental HR andCorporate HR. While it is important toidentify benefits that are likely to bedelivered, identifying such a large number ofkey indicators may result in a dilution of thesignificance of what is being measured.Work begun by DFP across Reform projectsin 2007 proceeded on the basis that thenumber of operational benefits on a projectshould be kept to 25 as an absolutemaximum.

Project Teams engaged stakeholders to gettheir support

3.8 It is a vital part of the management of aproject that stakeholders are identified andengaged at all stages of a project’sdevelopment. The stakeholder community isa diverse body with different interests androles in relation to a project, e.g. potentialstakeholder groups can include the relevantMinister, the Department procuring theproject, DFP supply, other public bodiesexpected to fund or use the services, seniorand middle managers, staff, non-staff usersof the service and potential contractors. The

likely internal and external stakeholders andtheir roles and responsibilities, including theirpotential influence on the project, should beidentified and agreed at an early stage ofthe project. Where the strategy or processidentifies major stakeholder related issues forthe procurement process or the eventualcontract, these need to be addressed assoon as possible. We have identifiedexamples of where this process appears tohave worked effectively:

• On the Network NI project, astakeholder analysis was completedidentifying all potential stakeholders atthe start of the project. This included theirstake in the project, potential impact,their expected contribution and attitude tothe project, perceived risks and astakeholder management strategy.

• On Workplace 2010, over 500 postswere identified as likely to be surplus torequirements as a result of implementingthe preferred solution. The Project Teamhas sought to minimise the impact onindividual staff likely to be affected bythe change. Trade Union representativeswere involved through the long standingarrangements in NICS used fornegotiation and consultation. This wascomplemented by work with the largestgroup of staff - support grades - affectedby the likely changes. This included one-to-one dialogue with all staff affected, todiscuss development opportunities andthe introduction of a new lateral transferprocess to allow application for transferto the NICS administrative grade. Overthree quarters of the support grade staffaffected have successfully applied and a

Page 37: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 27

18 A ‘healthcheck’ is not a formal Gateway review as prescribed by the Office of Government Commerce. The scope of thehealthcheck for the HR Connect project was the same as that for a Gate 3 Review.

comprehensive training programme hasbeen developed specifically for thisgroup, which includes interview andadministrative skills.

• On HR Connect, an external‘healthcheck’ at Gate 318, completed

towards the end of the procurement,noted that there had been extensiveconsultation with positive impacts andthere is evidence that this has continuedinto the implementation phase. Furtheranalysis is set out in the Case Study atFigure 10.

Figure 10: Case Study (HR Connect) – Stakeholder Relationships

Engagement

A ‘healthcheck’ completed in February 2006, a month before contract signature, found that stakeholders hadbeen fully engaged throughout, and individual stakeholders displayed a high level of support, not just inensuring that the new services would fully meet their business need but also in confirming their commitment toreleasing good quality staff. Post contract signature, the departments have released significant numbers of goodquality staff to work on the project, in their own Department, as well as centrally in DFP. Prior to contract signature, communications had generally been seen as good though there had been alimitation on communications with staff in the NICS as a whole. There were also communications plans andwork in progress on the creation of a website to go live after contract signature.

Funding of retained services

The numbers and budget for retained HR staff were agreed in August 2007, 17 months after the contract wassigned and over three years after the initial estimates, during which time those estimates changed significantly:

Date Retained staff Annual Cost (£m)

April 2004 230 11.4

September 2004 326 7.5

March 2005 380 10.5

May 2005 430 14.4

July 2007 413 14.3

August 2007 416 14.3

The overall annual budget for HR Connect (including retained services) was fixed and agreed at £26.5 millionat 2005/06 prices, at Best and Final Offer (BAFO) stage in July 2005. This was reaffirmed in March 2006prior to contract signature. DFP informed us that departments had agreed to the concept of living within theoverall range of what was affordable. The subsequent refinement of exact staffing figures and grade mix tookaccount of early contractual activity around business process design and final definition of the retainedorganisational structure. This in effect was the development of the new, radically different HR service model.

Source: NIAO review of documentation supporting project

Page 38: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Part Three:Risks to delivery have been identified and are being managed

28 Shared Services for Efficiency – A Progress Report

• On IT Assist, the development of theOBC was led by an E-GovernmentBoard sub-group comprising thedepartments most affected by theproposed intervention. Moreover, theSRO and Programme Director met withTrade Union representatives on severaloccasions.

Affordability and certainty over funding arekey to the progress of projects

3.9 While the business case for a project has todemonstrate that a preferred solution isaffordable as well as value for money,stakeholder engagement is particularlycrucial where specific stakeholders will befunding the project from their own budgets.On several of the Shared Services projects,outstanding funding issues remained despitethe approval of business cases and projectsbeing implemented. These includedresistance from departments to fund projects.In addition, in Network NI, changes infunding commitments from departments thatdeveloped after approval of the OBCcreated uncertainty as to whether therewould be sufficient funding for the projectduring the initial implementation period.

Managing the delivery of these projects hasbeen a major challenge for DFP with gaps incapacity and capability being filled with theassistance of the private sector

3.10 The effective delivery of projects is importantfor the achievement of wider governmentobjectives (see paragraph 1.3). Therefore, itis essential that project teams have the

19 “Reinvestment and Reform: Improving Northern Ireland’s Public Infrastructure”, HC79, Session 2006-07, December 2006

necessary resources and skills. Our 2006position report on the Reinvestment andReform Initiative19 noted that a StrategicInvestment Board and DFP review of staffresources and skills was in the process ofquantifying and specifying all existingdelivery resources (staff by type) across thepublic sector, including the mix of the skillsavailable. The aim was to formulate optionsto address the identified skills and resourcegaps in delivering the Investment Strategyand other key projects/programmes. Theparticular skills include Senior ResponsibleOfficer (SRO), investment decision making,programme management, projectmanagement, contract management,procurement, commercial, legal, technical,advisory, communication and relationshipmanagement.

3.11 The results of this review were not publishedbut a summary of the findings was madeavailable to the Construction Industry Forumand circulated to Achieving ExcellenceChampions, the Procurement PractitionersGroup and the Advisory Council onInfrastructure Investment. The interestscovered by these groups, in addition to theNICS, include the private sector, communityand voluntary groups, the constructionindustry, procurement specialists in the publicsector and trade unions. The reviewrecognised the substantial skills andexperience of the NICS in procurement andproject management. However, it alsoidentified additional pressures that theincreased pace and scale of delivery wouldplace on staff with these skills. DFP decidedthat capability and capacity demands wouldbe addressed by requiring departments toprovide delivery plans against the financial

Page 39: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 29

allocations under the current InvestmentStrategy for Northern Ireland (ISNI 2).OFMDFM, DFP and the Strategic InvestmentBoard have also implemented a range ofstrategies including:

• CAL delivering additional training coursesin programme and project management;

• the creation of Programme DeliverySupport Units in the Department ofEducation and the Department of theEnvironment. These are staffed by civilservants, Strategic Investment Board staffand specialist staff on short termcontracts;

• the establishment of a dedicated unitwithin the Central Procurement Directorate(CPD) in DFP. Its responsibility is tomanage contracts let in support of theInvestment Strategy for Northern Ireland;

• the development of Centres ofProcurement Expertise; and

• the creation of a Centre for Excellencefor Delivery within CPD. This unit hasresponsibility for improving departments’capacity and capabilities to successfullydeliver and manage major programmesand projects.

3.12 The Shared Service projects were already inprogress when this review wascommissioned. We found that, with theexception of CAL, all projects involvedexternal consultancy assistance. This wasparticularly the case with Account NI (Figure11). Other circumstances and reasons thatnecessitated the use of consultants were:

• Workplace 2010: the StrategicDevelopment Plan (2004) and theresultant OBC (2005) were prepared byconsultants with extensive input from DFPofficials. At that time there was noprogramme management office and thefirst full time project director was notappointed until February 2005;

The need for private sector assistance to fill resource gaps

Up to contract signature in June 2006, consultants provided advisory support and also some programmemanagement support to meet gaps in both resources and skills. The reasons advanced for the need forconsultancy input included:

1) there was a strain on staff resources due to a number of projects being carried out during the same period,at a time when total NICS staff numbers were being reduced;

2) the NICS lacks the specialist skills that are required on this type of work, particularly commercialnegotiations, as these are ‘one off’ projects and any skills developed are unlikely to be requiredsubsequently;

3) career progression paths in the NICS tend to favour those who have experience in a number of areas ratherthan expertise in a particular area; and

4) departments having a different priority from DFP on the release of staff to work on the project.

Source: NIAO review of documentation supporting project

Figure 11: Case Study (Account NI)

Page 40: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Part Three:Risks to delivery have been identified and are being managed

30 Shared Services for Efficiency – A Progress Report

• IT Assist: the transition programme for anumber of distinct project phases wasrevised in September 2006 into a seriesof projects using a framework to ensurethat the individual parts interfaced witheach other and with other reformprojects;

• HR Connect: the Department considersthat the legal consultants have delivereda high quality service on a complexprocurement and they are being retainedon a scaled down basis in theimplementation phase; and

• Records NI: during implementation thecontractor discovered that, contrary toassurances at contract award in July2006, the preparatory work in somedepartments was incomplete. Stoppingthe rollout to complete this work was notconsidered a viable option, so additionaldevelopment by the contractor wasrequired at a cost of £0.4 million.

To the end of December 2007, procurementand implementation costs for the sharedservices projects total £44 million

3.13 Previous NIAO reports have identified therisks associated with engaging externalassistance on major projects. For example in2003 NIAO reported on the Education andLibrary Boards PFI contract for a newcomputerised accounting system introducedin 199920. The report noted that, threeyears after contract signature, the cost ofconsultancy support for that project stood at£2.2 million compared with an originalforecast of £0.6 million. These costs

20 ‘The PFI Contract for the Education and Library Boards’ New Computerised Accounting System’, HC498, March 2003,NIA 99/02 and ‘Departmental Responses to Recommendations in NIAO Reports’, October 2004, NIA 124/03

included the almost full time engagement ofone senior consultant from January 1997 toOctober 2001.

3.14 The total cost of external assistance onshared services projects up to the end ofDecember 2007 was £20.3 million (Figure12). Three of the projects – HR Connect,Account NI, Workplace 2010 – accountedfor 84 per cent of this expenditure. The totalamount spent up to December 2007 on theprocurement and implementation of eachproject, both in-house and consultancy costs,was £44 million and is outlined in Figure12. A summary of the total costs of the newservices is detailed further at Appendix 11.

A number of milestones were not achievedby the contractor resulting in changes to theHR Connect project agreement

3.15 On three of the projects there have been aseries of milestone payments (i.e. stagedpayments made for tangible assets deliveredby the contractor) during the implementationphase. For example, on HR Connectmilestone payments through to 2009-10 willtotal £37.8 million, i.e. the capital cost ofthe project (see Figure 6). During 2007,there were extensive commercialnegotiations with the Contractor (see Figure13) after they were notified that they hadmissed a number of milestone events by theplanned completion dates. This resulted inan amendment to the Strategic PartneringAgreement (the contract), following detailedanalysis by the project’s legal and financialadvisers.

Page 41: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 31

Project Internal(1) External(2) Total Milestone andCapital(3)

£m £m £m £m

HR Connect 8.0 5.3 13.3 19.3

Account NI 9.4 6.0 15.4 16.5

Workplace 2010 4.3 5.7 10.0 8.2

Records NI 0.6 1.6 2.2 10.6

CAL 0.1 - 0.1 0.0

IT Assist 0.9 1.1 2.0 0.0

Network NI 0.5 0.6 1.1 0.0

Totals 23.8 20.3 44.1 54.6

Notes1. Internal Costs are all other Administrative Resource costs falling to the projects.2. External costs include costs of consultancy support and other externally sourced support, such as staff substitution and

Strategic Investment Board support. Workplace 2010 external support costs relates to payments for services after August2005 and do not include the development and submission of the Strategic Development Plan and the OBC (paragraph3.12).

3. Milestone payments on HR Connect, Account NI and Records NI are staged payments made for tangible assetsdelivered by the contractor. The £8.2m on Workplace 2010 are capital payments for pilot projects (including ClareHouse). These costs are not regarded as directly associated with the delivery of the procurement, but as having beenincurred by the NICS to test technical accommodation specifications.

Source: NIAO/DFP

Figure12: Project Procurement and Implementation Costs

Page 42: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Part Three:Risks to delivery have been identified and are being managed

32 Shared Services for Efficiency – A Progress Report

Amendment to Strategic Partnering Agreement (November 2007)

In February/March 2007 the Department notified the Contractor that they had missed a number of milestoneevents by the planned completion dates. The Department revised the payments in respect of the missedmilestones and withheld a proportion of the payments. The Contractor was requested to provide draft actionplans detailing the arrangements for delivering the outstanding parts of the project.

The Department and the Contractor agreed to take forward two key issues in parallel:

• the Milestone payments due for the financial year ending 31 March 2007; and• addressing the consequence of proposed changes to the implementation and transistion plan, including the

potential introduction of services on a “release” basis.

With the benefit of significant assistance from the Department’s project team, the Contractor submitted a refineddeployment timetable in September 2007 (see Appendix 2).

In the commercial settlement, milestone payments were deferred and consequently were smaller in 2007-08.While the overall total of £37.8 million for milestone payments remains, these have been rescheduled. TheContractor received £3.4 million less in 2006-07 and £2.0 million less in 2007-08, with an additional £1.7million in 2008-09 and £3.7 million set aside for 2009-10.

As a result of delay in implementation, the consequential need to retain existing HR staff for longer, as well asongoing costs in the system to be phased out and contingency costs, there were additional staff costs and lostbenefits of £5.7 million. The Department negotiated a final recovery settlement of £5.2 million made up of£4.0 million in reduced fees due to the contractor during 2007-08 and 2008-09 under the contract and afunding/“contingency” of £1.2 million representing the continuation of the previous HR and Payroll systems foran additional period. The Department viewed this deal as affordable, not requiring any bids for additionalresources. There was, however, a funding gap of £452,000.

The Department also secured new warranties and protections in respect of the implementation period.

Source: NIAO review of documentation supporting project

Figure 13: Case Study (HR Connect)

Page 43: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Part Four:Lessons are emerging for future procurements andprojects

Page 44: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Part Four:Lessons are emerging for future procurements and projects

34 Shared Services for Efficiency – A Progress Report

4.1 This section examines how lessons emergingfrom the experience on the shared servicesprojects to date are being learnt andoutlines examples on how these are beingaddressed by the Department.

There are examples of a good approach tosome of the main challenges to deliveringprojects

Contract and Negotiations

4.2 During the negotiation phase with thepreferred bidder, the HR Connect andRecords NI projects benefited from externalassistance. The HR Connect contract wasdeveloped with advice from the CentralProcurement Directorate in DFP, the StrategicInvestment Board and legal advisors. HRConnect also received advice from theCabinet Office on the structure of theretained HR organisation. This contractallows for departments in Great Britain toreuse, in certain circumstances, the processand software solution developed. DFPbelieves that the contract also reflects goodpractice in areas such as Intellectual PropertyRights, Data Protection and Confidentiality,Warranties and Disclaimers, Indemnities andLimit of Liability. Records NI were assistedby OGC personnel with experience ofnegotiations. The structure of the contractreflects good practice, complying with thecurrent OGC guidance on terms andconditions models for ICT projects. Theseinclude:

• the equal sharing of efficiency savings onan annual basis;

• the opportunity for ‘gain sharing’ at fourpoints during the contract period, whereany profits by the contractor above athreshold profit margin of 7.5 per cent isshared;

• the equal sharing of gains from anyrefinancing by the private sector;

• arrangements for a benchmarkingexercise during the lifetime of thecontract; and

• open book accounting arrangements,including requests for changes.

Governance and Partnerships

4.3 The main approach on projects wherecontracts have been signed, has been acommitment to partnership and workingtogether, demonstrated in a variety ofapproaches:

• Records NI: The Executive GovernanceBoard has a Non-Executive Chair andincludes senior representatives from theprivate sector organisations involved inproviding the service;

• CAL: While there is no private sectorpartner, the governance Board includes aTrade Union nominee, an external non-executive member and senior nomineesfrom stakeholder departments includingHeads of Profession and, currently, threePermanent Secretaries;

• IT Assist: The governance structure wasdeveloped with the E-Government Boardand signed off by all departments, who

Page 45: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 35

21 The composition of the Board was expanded to include an independent external member in March 2008.

are also involved in the governance. TheGovernance Board is chaired by arepresentative from a user Department21;and

• HR Connect: The formal governancearrangements have been fullyimplemented in line with the contract.These arrangements include a StrategicPartnership Board, Business ManagementBoard and Service Delivery Board, eachof which are made up of Authority andContractor representatives, with theStrategic Partnership Board having a roleto ensure that the general aims andprinciples (those principles being set outin the HR Connect contract) of thepartnership relationship are achieved.

Preparing for Operational Phase

4.4 On the Workplace 2010 Project, DFPappointed a senior manager (who iscurrently the project director) to head thecontract management function after the dealis signed, with an interim role to prepare apublic sector team ready to manage thecontract. Workplace 2010 and Records NIpiloted new working practices. Workplace2010 introduced pathfinder projects throughrefurbishment work at Royston House, Belfastand a new building at Clare House,Holywood, in December 2006. There wasan independent healthcheck of the newpremises at Clare House in February 2007and a full post-occupancy evaluationundertaken by the Northern Ireland Statisticsand Research Agency duringOctober/November 2007. The laterevaluation noted that most respondents weresatisfied or very satisfied with aspects such

as improved teamworking and interaction,the contemporary working environment andthe image that the building portrayed tovisitors. The evaluation also noted areas ofconcern, with fewer than 50 per cent ofrespondents being satisfied or very satisfiedwith other aspects including noise,distraction, location, car parking,temperature, privacy, confidentiality and ICTprovision, though the report acknowledgedimprovements in IT related issues since theinitial healthcheck. DFP views the NorthernIreland Statistics and Research Agency(NISRA) report as providing valuable lessonswhich will contribute to shaping andinforming the final Workplace 2010contract, with those lessons beingincorporated into an action plan. At a locallevel, the Clare House Board is developinga specific action plan to address local issuesbased on the recommendations within thereport.

4.5 In Records NI, lead implementation projectswere initiated in February 2005 withinselected branches in three Departments(DETI, DCAL and OFMDFM). Two reportswere produced. The first, in June 2005,focused mainly on the experiences ofpreparation and implementation, andhelped to define the requirements of themain Records NI project. The key messagewas the need for extensive preparation inadvance of implementation, including theneed for staff to feel comfortable with thechange in operating methods. A secondreport in November 2006 detailed theoperational experiences. As a way ofmaximising the investment made in RecordsNI, the implementation project managersproduced a summarised list of ten

Page 46: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Part Four:Lessons are emerging for future procurements and projects

36 Shared Services for Efficiency – A Progress Report

recommendations as a way of continuallyreinforcing good management and bestpractice (Appendix 12). These are relevantto any similar projects that are atdevelopment phase.

Projects have undertaken Gateway reviewsand some have gone through a postprocurement evaluation

4.6 In 2001, the government established OGCGateway reviews to ensure all major centralcivil government projects and programmesare subject to rigorous tests and passthrough a series of critical points in theproject lifecycle. This guidance wasextended to Northern Ireland in 2003 and200422. Projects are independentlyassessed on their readiness to move onto thenext stage on the basis of a Red, Amber orGreen (RAG) status rating (Figure 14).Results of the review are reported directly tothe SRO of the project, who is also theowner of the report. The Gateway processencourages the promotion of openness andhonesty about the state of a project betweenthe project and review teams. In the UK,these arrangements have been refined toencourage procurement Centres ofExcellence in departments to get access toGateway reports as part of their monitoringof all departmental projects23.

4.7 Six of the projects have been subject toelements of the Gateway process (Figure14). CAL did not conduct a GatewayReview nor a formal written risk potentialassessment. Reasons cited by CAL for thisdecision are that the nature, duration, scale

22 This was introduced for IT-enabled projects in DAO(DFP) 33/03 and for all acquisition based programmes in DAO(DFP)17/04.

23 HM Treasury: Minute on the Nineteenth and Twenty-Seventh Reports from the Committee of Public Accounts 2004-2005,Cm 6682, November 2005.

and cost of the project (circa £0.1 million)meant that CAL was not a “major project”within the context of the OGC’s guidanceand therefore a formal Gateway processwas neither appropriate nor required. In themain, the reviews have been beneficial inthat, where projects have had a Gatewayred rating, they have actively responded tothe issues raised by the review, with animprovement in subsequent reviews. A redstatus rating does not mean that projectsshould be stopped as a result, though twoconsecutive red reviews in the UK doesresult in a letter from the Chief Executive ofthe OGC to the Permanent Secretary of thedepartment responsible. The Comptroller &Auditor General is also notified and mayinclude the project in a report to the PublicAccounts Committee.

4.8 In addition to the Gateway reviews, formalpost procurement ‘lessons learned’ reportshave been completed for HR Connect,Records NI and Account NI. This is useful inthat in addition to informing future projects,there can be a significant turnover of keypersonnel on projects (particularly atsignificant break points such as contractsignature) and there is a need for continuityand knowledge sharing. The review of themanagement processes for co-ordinatingReform programmes and projects noted thatprogramme, project and gateway skills werestill in short supply in Northern Ireland,particularly in the context of a growingdemand for such skills. It recommended thecontinuing use of, and improving theimplementation of, best practice forprogrammes/projects, and to continue towiden the Gateway disciplines.

Page 47: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 37

Figure 14: Status of Gateway reviews of Shared Services projects to 31 December 2007

Shared Gate 0 Gate 1 Gate 2 Gate 3 Gate 4 Gate 54

Services Strategic Business Procurement Investment Readiness BenefitsProject Assessment Justification Strategy Decision for Service Realisation

Workplace 2010

HR Connect1

Account NI2

Records NI

IT Assist 3 a b

CAL

Network NI

RED To achieve success the project team should take action immediately.

AMBER The project should go forward with actions on recommendations to be carried out before the next OGC Gateway Review of the project.

GREEN The project is on target to succeed but may benefit from the uptake of recommendations.

Notes1. On HR Connect, there were Gate 2, 2a and 2b reviews, all amber. At Gate 3, there was an OGC led ‘healthcheck’ but

not a formal Gate 3 review prior to the signing of the HR Connect deal. The ‘healthcheck’ took account of Gatewayguidance and was led by a consultant from the Strategic Assignment Consultants Service which acts in support of theOGC’s consultancy service. The scope of the ‘healthcheck’ was the same as that for a Gate 3 review.

2. Account NI had a Gate 1 peer review, as the Gateway Review process had not at that stage been formally adopted inNorthern Ireland, but this was not conducted by the OGC and there was no status rating. In the light of the findings of theGate 2 review and the time being taken for the procurement, the SRO requested that an independent mid gate review becarried out by OGC between the formal Gate 2 and Gate 3 reviews.

3. There have been two Gate 0 reviews on IT Assist in June 2006 and June 2007. 4. To date no Gate 5 reviews have been conducted as projects are not sufficiently advanced.

Source: NIAO/DFP

Page 48: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Part Four:Lessons are emerging for future procurements and projects

38 Shared Services for Efficiency – A Progress Report

The projects are now subject to newoversight arrangements

4.9 The Programme Support Office was set upin May 2005 to monitor and coordinateCommon Regional Infrastructure (whichincluded shared services) and assist thePermanent Secretaries Group (PSG) tounderstand the collective risk and impact of

the projects/programmes involved. TheProgramme Support Office developed intothe Programme Management Office (PMO)from April 2006. Its role was to monitor andco-ordinate the implementation of the Reformprogramme, reporting to the PSG. Thesearrangements evolved during 2006 and thePMO is now the operational arm of the CivilService Reform Oversight Board, a sub

Figure 15 Shared Services Oversight Arrangements

Department of Finance & PersonnelDepartmental Board

NICS ReformOversight Board

Programme Management

Office

PermanentSecretaries Group

Projects

Source: NIAO

Page 49: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 39

group of the DFP Departmental Board(Figure 15). The Oversight Board is chairedby a non-Executive member of the DFPBoard and includes members from otherNICS departments. It does not haveexecutive responsibility, but exists to giveassurance to the DFP Board that oversight ofthe entire infrastructure programme is beingaddressed, along with obtainingappropriate input from stakeholders,customers and technical advisers.

4.10 The Oversight Board has met monthly and inaddition to receiving the progress reports onindividual projects, covered key issues forthe programme as a whole. The Boardconsidered a recommendation by the 2007review that it should meet quarterly andagreed to change the frequency of meetingsto every other month, but with individualprojects continuing to report on a monthlybasis. This was to allow a report on theportfolio of projects, thus providingmonitoring information between meetings.The issues considered on a programmebasis have included:

• risk management: particular attention isgiven to new risks reported and the morecritical risks that are likely to crystallise;

• financial reporting;

• costs and benefits planning;

• the schedule for rolling out new servicesto departments;

• communications; and

• current status of projects: there is a briefnote on the current issues in each of theprojects, along with a ‘traffic light’ rating(similar to that used in the Gatewayprocess). Projects that report either a ‘red’or ‘amber’ rating or have changed theirrating in the previous month are disclosedin the executive summary.

4.11 The risks and issues associated with each ofthe projects are reviewed on a monthlybasis and therefore the ratings may oftenchange. In the report for December 2007,the status of Network NI and Records NIwas green, while Account NI, HR Connect,IT Assist and Workplace 2010 reportedamber status. The reasons for amber statusby project were:

• Account NI: there were some technicalconcerns which needed to be workedthrough before departments who hadmoved over to Account NI could fully usethe Account NI system. The project teamwas also seeking clarity on systemtechnical issues with DSD and DHSSPS(both due to move over to Account NI in2008) who operate on a different ITsystem;

• HR Connect: complex design activity forpayroll and resourcing led to someslippage in the timetable;

• IT Assist: the current concern related toWorkplace 2010 decanting IT Assistfrom the Stormont Estate, and the risk toservice levels and the remainder of themigration plan;

Page 50: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Part Four:Lessons are emerging for future procurements and projects

40 Shared Services for Efficiency – A Progress Report

• Workplace 2010: the project movedfrom red to amber status after agreementwas reached following legal challenge,which allowed the procurement to moveto Best and Final Offers. Other significantrisks remained, such as the moving of ICTequipment during decant/recant of NICSbuildings, the impact of a new build onthe Stormont Estate, the timing of pre-contract refurbishments and the loss ofknowledge from the loss of a keymember on the Programme team.

The work of the Project Management Officehas included work to consolidate theapproach to benefits realisation

4.12 Through the development of a benefitsmodel and a benefits management lifecycle(Figure 16), the PMO has launched work tobring consistency to benefits realisation(paragraph 3.7). This was initially appliedto Records NI and then rolled out to theother projects. The result of this work waspresented to the DFP Departmental Board inFebruary 2008, which agreed to develop a

24 The number of intermediate benefits on the individual shared services projects range from 8 to 25. For HR Connect therewere 14 intermediate measurable benefits for Departmental accountability purposes, though HR Connect have 45 benefitsfor their own contract management functions (paragraph 3.7).

register of civil service reform benefits acrossDFP. The three elements of the modeldeveloped within the PMO are:

• Enablers: these are new tangiblecapabilities directly attributable to theinvestment in the project or programme;

• Intermediate Benefits: these are thefunctional or operational benefits that aremeasured in the model. There should beat least one key performance indicatorbehind each benefit. The optimumnumber of benefits should be 15 to 20with an absolute maximum of 2524. Thisrequires projects to identify and prioritisethe key benefits. Sometimes projects havesignificant costs or disbenefits and theseshould be measured. In Records NI, thecreation of a central electronic repositoryof documents and records leads toadditional bandwidth across the NICS,for which the impact and cost needs tobe managed and minimised; and

• End Benefits: the strategic end benefits tothe NICS. DFP has identified the benefits

Figure 16: Benefits Management Lifecycle Stages

Lifecycle Stage Activity

Identifying and Structuring The modelling and profiling of benefits.

Planning the Realisation The benefits management strategy and realisation plan, with baseline measurements, should be in place when the Full Business Case is approved.

Realising and Tracking The target measurements should be in place by the start of implementing the project. When these measurements are ready, this is the optimum time to factor in any associated governance arrangements.

Review and Evaluation Continuous management and measurement of benefits.

Page 51: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 41

25 Business Principles for Shared Services within the NICS, DFP, May 2007

in Records NI as being greater riskassurance for records management,improved staff morale for administrationstaff and efficiency savings.

In addition to regular oversight, DFP hasdeveloped business principles for theprovision of shared services in the NICS

4.13 In May 2007, DFP issued a paper25 on thebusiness principles (Appendix 13) tounderpin shared services within the NICS.These were developed through discussionswith key stakeholders across the reformprojects and the NICS, drawing on goodpractice. Departments were requested tonote these principles and communicate themto the relevant staff. SROs/ProgrammeDirectors on existing projects were asked toensure that both their current and futureplans for shared services were in line withthe principles. The principles representemergent thinking and will be reviewedduring 2008-09 as the shared servicesmature.

Page 52: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing
Page 53: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Appendices

Page 54: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Appendix 1 (Paragraph 1.4)

44 Shared Services for Efficiency – A Progress Report

“Fit for Purpose” The reform agenda in the Northern Ireland Civil Service: Themes and Initiatives

Putting the Front Line First Building Capability Embracing Diversity

1) Improving efficiency 1) Developing talent and 1) Recruiting across the boardprofessionalism

2) Improvements in purchasing goods 2) Recruiting at senior levelsand services 2) Managing professionalism

3) Exchanging experience3) Rationalising support services 3) Planning for delivery

4) Reaching out4) Tackling absenteeism 4) Modernising employee

relations 5) Tracking progress5) Planning the workforce and the payroll

6) Building relationships6) Business-led grading

7) Harnessing technology

Page 55: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Appendix 2 (Paragraph 1.6 and Figure 2)

Shared Services for Efficiency – A Progress Report 45

HR Connect

Project Summary

1. HR Connect (the service resulting from theeHR Programme) aims to provide anelectronic solution capable of modernising,harmonising and supporting business needsin the areas of industrial and non-industrialpayroll, personnel and recruitment throughchanges to the systems and processes withinand across Departmental boundaries. Theoverall business objectives as outlined in theFBC were:

• to ensure the continued delivery of currentpayroll services through theimplementation of a replacement solutionprior to the expiry of the existingcontracts in 2008 – Continuation ofpayroll services;

• to ensure, as a minimum, the continueddelivery of current HR services throughthe implementation of an eHR solutionprior to the expiry of the existing HRMScontract in 2008 – Continuation of HRservices;

• to increase, by the end of 2008/2009the efficiency of HR service delivery by 5per cent through implementation ofmodern HR support facilities, businessprocess improvement and the phasedintroduction of employee and managerself-service supporting the NICS Reformagenda – Increase efficiency of HRservice delivery;

• to meet business requirements to improveHR decision making through the provisionof detailed, specific, timely, accurate and

accessible personnel information by2008 – Improve HR decision making;

• to enable the delivery of consistent HRservices through the implementation ofcommon processes, systems, andstandards where sensible andeconomically viable to do so, by 2008– Deliver consistent HR services;

• to improve the delivery of HR services byensuring that all transactions are capableof being provided electronically by 2008– Improve electronic HR capability; and

• to exploit e-technology to reduce futurereliance on HR paper files by 70 percent by 2008 – Reduce reliance on HRpaper files.

Project Progress

2. DFP signed a PPP Strategic PartnershipAgreement in March 2006. The contractvalue is £37.8 million in capital fees and,after implementation, an annual cost of£26.5 million (£12.2 million ServiceCharge and £14.3 million Retained HR).The contract is for up to 15 years with anoption for DFP to terminate at any time afterthe 10th year. The agreement includes aperformance monitoring process for on-going service delivery and a benchmarkingprocess to ensure the service continues toprovide value for money and reflects bestpractice. The eHR programme moved intothe testing and implementation phase withmodules now planned to go live betweenOctober 2007 and November 2008, withthe final integration milestone payment duein June 2009. This payment is regarded byDFP as an example of the contract being

Page 56: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Appendix 2 (Paragraph 1.6 and Figure 2)

46 Shared Services for Efficiency – A Progress Report

structured to ensure satisfaction with theservice.

3. The implementation programme has movedaway from the stage/departmental clusterbased approach for the deployment ofservices. The deployment of services, asdocumented in the Amendment Agreementsigned in November 2007, will now be ona release basis as follows:

4. In the testing and implementation phase,there has been slippage and delays with theproposed go-live dates, for example theindustrial payroll module (release 2.0) wasoriginally scheduled for September 2007and the non-industrial payroll (release 3.0)scheduled for December 2007, but theexternal recruitment module (release 1.0)was brought forward from April 2008 toOctober 2007. The project team isconfident that full operation will be achievedduring 2008.

5. During February and March 2007, DFPissued letters to the contractor informing themthey had failed to meet some key milestoneplanned completion dates and requestedthem to provide draft action plans detailing

the arrangements for the delivery of theoutstanding deliverables. DFP formallyreserved its right to claim in respect ofdelays and breaches, a right which theyexercised in June 2007 and September2007. In March 2007, DFP revised thepayments in respect of the missed milestonesand withheld a proportion of the payments.The Contractor lodged a compensationclaim in respect of the non-industrial payroll.

DFP continues to robustly refute thecompensation claim.

6. There were extensive commercialnegotiations which resulted in anamendment to the strategic partneringagreement. The amended agreementconfirmed the action taken by DFP inwithholding payments. The contractor stillreceives the same total amount of milestonepayments, but these will be paid over fourfinancial years (the final payment being in2009-10) instead of three. DFP sought torecover costs relating to retained HR staff,additional provision of existing NICSindustrial and non-industrial payroll andadditional contingency (existing HRMS,UNIPAY industrial payroll and non-industrial

Release Function Go-live Date

1.0 External Recruitment October 2007

1.1 Employee Relations, Exit and HR Data Management December 2007

1.2 Internal Resourcing April 2008

3.0 Non-Industrial Payroll and Absence Management April 2008

4.0 Performance Management and Learning Development April 2008

2.0 Industrial Payroll and Absence Management June 2008

Page 57: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 47

payroll costs) amounting to £5.7 million. Thecommercial negotiations were completedwith DFP negotiating a final recoverysettlement of £5.2 million and securingadditional warranties and protectionsrelating to the implementation period. Theresulting funding gap of £452,000 equatesto eight per cent of the total claim. Thisposition was reached without the need toinvoke the dispute resolution process which,in DFP’s estimation would have been costlyfor both the Contractor and themselves. Thedeal reached does not compromise theaffordability of the programme or requireany bids for additional resources.

7. All data for release 1.0 (Recruitment) wasmigrated to the new system in earlyNovember 2007. The same month, HRdata for DFP and OFMDFM was successfullymigrated. By the end of 2007, HR datahad been migrated for NIO, DARD, DRD,DOE, DCAL, DETI and DHSSPS. Theremaining HR Connect participants (DSDand DEL) were migrated in January 2008,with all data migration from existing systemsdue to be completed by mid-August 2008.

Key Project Dates

8. The key dates for the project aresummarised in the table overleaf

Page 58: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Appendix 2 (Paragraph 1.6 and Figure 2)

48 Shared Services for Efficiency – A Progress Report

Date EventNovember 2002 Gateway Review 0 – the strategic assessment.January 2003 Prior Information Notice in the Official Journal of the European Union (OJEU).February 2003 Gateway Review 1 – the business justification.May 2003 Gateway Review 2 – procurement strategy.June 2003 Approval of OBC which recommended a partial PPP solution.September 2003 OJEU notice seeking expressions of interest.October 2003 Pre-qualification questionnaire responses. December 2003 1. 3 bidders selected to bid for contract.

2. Interim Gateway Review 2a.April 2004 Change in project solution from partial PPP to full PPP after external and

internal consultation.May 2004 Invitation to Negotiate (ITN) issued to bidders.June 2004 Interim Gateway Review 2b.July 2004 ITN responses received.September 2004 All three bidders selected to negotiate.October 2004 Negotiations commence with bidders.January 2005 One bidder withdraws.July 2005 Invitation of Best and Final Offer (BAFO).September 2005 BAFO responses received.October 2005 One bidder selected for further discussions.December 2005 Preferred Bidder appointed.February 2006 Gate 3 Healthcheck.March 2006 1. DFP Supply grants conditional approval of the FBC.

2. Award of Contract.3. DFP Supply grants formal approval of the FBC.

April 2006 Implementation work commences.August 2007 Gateway Review 4 – readiness for service.October 2007 External Recruitment service live.November 2007 Exit Management and Employee Relations early release live.December 2007 Exit Management and Employee Relations available to all NICS Departments

(except DSD and DEL).

Source: NIAO based on departmental papers

Page 59: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Appendix 3 (Paragraph 1.6 and Figure 2)

Shared Services for Efficiency – A Progress Report 49

Account NI

Project Summary

1. Account NI (formerly the AccountingServices Programme) will provide a newintegrated Resource Accounting andBudgeting System for all NICS Departments.A new Financial Shared Services Centre(SSC) will be responsible for the transactionprocessing needs of NI departments andtheir agencies. In addition, the SSC willperform other value added services such ashelp desk facilities, systems administration,report development & support, end-usertraining, contract & performancemanagement and development of serviceenhancements. These services will beprovided on a customer – supplier basis.

2. Account NI is an in-house NICS SharedService Centre, staffed by NI Civil Servantswho will be part of DFP and located inGoodwood House, Belfast. It is anticipatedthat, by April 2009, the SSC will have 206staff across the various NICS grades. Thecontract for the Accounting ServicesProgramme was signed in June 2006 withthe main contractor and their sub-contractors.The contract is for a period of 12 years andis worth approximately £48.5 million (realterms). The project will be funded asfollows:

• £10 million in milestone payments in theperiod between contract signature andservice commencement date; and

• £38.5 million payable by departmentsover the life of the contract.

3. Of the £48.5 million, the total capitalelement of the project represents £27million. This will be funded through the £10million of milestone payments, £13 millionusing a finance lease and £4 million ofunitary charges. The finance lease amountsand the unitary charges are included withinthe £38.5 million of amounts payable byDepartments noted above.

Progress to date

4. The procurement phase has been completedand the implementation phase hascommenced. The Account NI Projectimplementation and roll-out schedule wasoriginally set for June 2007 but due todelays this was revised to December 2007for the first Departments concerned – DFPand OFMDFM. DFP have experiencedproblems in implementing Account NI whichhas contributed to delays in the planneddelivery of outputs such as the submission ofthe main 2007-08 accounts of DFP andOFMDFM for audit. DFP’s decision to delaysubmitting the Departmental resourceaccount was also influenced by problemsexperienced in meeting the faster closingdeadline in the previous year. The delayswill prevent those accounts being certifiedby the Comptroller and Auditor Generalprior to the Assembly’s summer recess. Thecurrent implementation and roll-out planoutlines the approach that is being taken tomigrate the “waves” of departments andagencies against the proposed “Go-live”dates. A summary of the “waves” is asfollows

Page 60: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Appendix 3 (Paragraph 1.6 and Figure 2)

50 Shared Services for Efficiency – A Progress Report

Roll-out Department Go-live Dates at December 2007

Wave 1 DFP / OFMDFM December 2007

Wave 2 DETI / DEL April 2008

Wave 3 DSD / DHSSPS July 2008

Wave 4 DARD / DOE / DCAL November 2008

Wave 5 DRD / DE / Roads April 2009

Page 61: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 51

Key Project Dates

5. The key project dates are summarised in thetable below.

Date EventNovember 2000 Accounting Services Review commissioned.March 2001 Accounting Services Review Business Case finalised.November 2001 Accounting Services Review findings approved by the Executive.April 2002 Consultant advisers appointed.September 2002 Gateway 1 (Peer Review).October 2002 Prior Information Notice in OJEU issued.November 2002 Gateway 2 – procurement strategy.October 2003 Outline Business Case approved.January 2004 Formal Programme Notice in OJEU issued.March 2004 Invitation to Submit Outline Proposals Methodology approved.April 2004 Four of the five bidders invited to submit outline proposals.June 2004 Two OGC reviewers commence mid-Gate procurement progress review.July 2004 1. ITN methodology approved.

2. ITN issued to three companies.October 2004 Companies submit formal proposals.December 2004 Preferred Bidder selected.March 2006 1. Gateway 3 – investment decision.

2. Minister approves submission on potential affordability gap of £12 million over project life.

3. Final Business Case.June 2006 12 year contract signed. Project to be rolled out June 2007 to October 2008.October 2006 Permanent Secretaries Group to be informed that project is at risk.December 2006 Contractor gives Notice that the June 2007 ‘go live’ date is unachievable.October 2007 Gateway 4 – readiness for service.

Source: NIAO based on departmental papers

Page 62: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Appendix 4 (Paragraph 1.6 and Figure 2)

52 Shared Services for Efficiency – A Progress Report

Workplace 2010

Project Summary

1. Workplace 2010 aims to develop astrategic and affordable solution to theurgent accommodation problems facing theNorthern Ireland Civil Service office estate.It is co-sponsored by the Department ofFinance and Personnel and the StrategicInvestment Board. The project’s strategicobjectives are:

• to enable the NICS to transform the wayit delivers public services;

• to provide accommodation in which staffare proud to work; and

• to safeguard funding for priority frontlineservices.

2. It is currently being procured through aPrivate Finance Initiative route with a totalestimated value of £1.5 billion over 20years. The key feature of the procurement isthe transfer of 65 buildings (previously 77,the number in the approved Outline BusinessCase) to a private sector partner. Thesebuildings comprise approximately 70 percent of the area of the NICS office estateand have a current occupancy of 16,700.Over half of the buildings in the plannedprocurement are in the Greater Belfast area.

3. The present intention of the sponsors is thatthe private sector partner will:

• make an upfront capital payment for thetransferred assets (the amount to be

determined) which will be reinvested inpriority frontline services;

• invest approximately £100 million in theestate across 20 key properties through acombination of new build andrefurbishment;

• manage the transfer of approximately13,000 staff into the newly refurbishedaccommodation; and

• maintain and service the whole of theNICS office estate throughout the life ofthe contract.

Progress to date

4. The project is in procurement. At the end ofthe Invitation to Negotiate (ITN) phase, twoof the four participating bidders were short-listed with a view to being asked to submitbest and final offers (BAFO) if required. Oneof the unsuccessful bidders challenged thisdecision through the Courts. This resulted inan injunction on the project until the casewas heard by the Commercial Court. InJanuary 2008, this challenge was settledout of court. Following the restoration ofdevolution, the Executive was presented witha paper in July 2007, seeking ministerialviews on Workplace 2010, with a view toobtaining Ministerial approval to proceed toBAFO. The Executive’s endorsement of theproject was secured in September 2007.

Key Project Dates

5. The key dates for the project to date aresummarised in the table opposite.

Page 63: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 53

Assuming that the project proceeds as a PFI procurement, then the current expectation is that a contract will be signed in March 2009.

Date EventApril 2004 DFP/Strategic Investment Board commission consultants to prepare a Strategic

Development Plan for the NICS office estate.September 2004 Strategic Development Plan completed. DFP/Strategic Investment Board commission

consultants to prepare an Outline Business Case.March 2005 Gateway Review 1 (the business justification) completed by OGC.April 2005 OBC recommends a PFI solution. October 2005 OBC approved by DFP supply.November 2005 Gateway Review 2 (procurement strategy) completed by OGC.November 2005 Notice in the Official Journal of the European Union seeking expressions of interest.January 2006 Six consortia declare an interest in the project by submitting Pre Qualification

Questionnaires.June 2006 Four consortia invited to submit proposals on the ITN.November 2006 Consortia submit bids.May 2007 The two preferred bidders from ITN stage announced.

Page 64: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Appendix 5 (Paragraph 1.6 and Figure 2)

54 Shared Services for Efficiency – A Progress Report

Records NI

Project Summary

1. DFP awarded a seven year contract in July2006 at a net present cost of £15.9million. The primary objective is to improveinformation and records management in theNorthern Ireland Civil Service byimplementing a single corporate NICSElectronic Document Records Management(EDRM) service that complies with recordsmanagement polices and procedures and isused by all 17,000 staff identified as withinthe scope of the project by the end of2007. As set out in ‘Fit for Purpose’ (2004),the EDRM systems will facilitate workingacross traditional NICS boundaries,enabling teams to work effectively withshared documents, which represents asignificant change in the NICS’smanagement of information.

Project Progress

2. The short to medium term objective of theproject in 2003 was to establish aframework and so permit NICS departmentsto approach EDRM in their own time andindependently but within a defined scopewhere systems are able to communicate witheach other. To further assist departments,there would be three lead implementations(in DETI, the Public Record Office ofNorthern Ireland (an agency within DCAL)and OFMDFM) which would enable theproduction of a lessons learned report.Under this approach, the OBC would thenassess the feasibility of establishing a

corporate EDRM shared application serviceto meet the medium to long term EDRMrequirements of all departments.

3. The OBC approved by DFP in 2005represented a strategic shift in delivery byrecommending a partnership with a singleexternal provider to deliver a singlemanaged service to the NICS. Theprocurement framework which had beendeveloped separately also took account ofthe OBC recommendation, in that the leadimplementers ran a joint secondarycompetition using the established frameworkcontract and procured Tower Software’sTRIM Context 5.2.2.

4. A series of milestone payments totalling£11.6 million are being paid during theimplementation phase while payments in theoperational phase reflect a service chargebased on the number of full users. Servicepayments are directly related to availabilityand system performance and can be abatedfor poor performance. Some 12,000 usershad been trained by December 2007.Revised governance structures andoperational management arrangements arebeing progressed to cater for the migrationfrom the implementation phase to the on-going operational phase of the Records NIservice.

Key Project Dates

5. The key dates for the project to date aresummarised in the table opposite.

Page 65: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 55

Date Event2001 The NICS Electronic Document and Records Management (EDRM) Working Party

recommended a corporate EDRM systems project.January 2003 1. Electronic Document and Records Management Systems Infrastructure

project established.2. Gateway ‘0’ review – strategic assessment.

April 2004 Outline Business Case produced by consultants and approved by Electronic Documents and Records Management Systems Infrastructure project board. Further work was undertaken to address potential issues of governance and funding around the preferred option of a cross departmental project.

October 2004 ‘Fit for Purpose’ .February 2005 1. Electronic Documents and Records Management Implementation project

initiated. 2. Prior Information Notice issued to OJEU (16 responses received).3. Project Board approve OBC plus Update report.

March 2005 Gateway 2 review – procurement strategy.April 2005 DFP approves Final OBC plus Update report.June 2005 OJEU contract notice issued.September 2005 Three responses to the Invitation to Submit an Outline Proposal.December 2005 Three responses to the Invite to Propose against the final Statement of Operational

Requirements.February 2006 ITN letter sent to three bidders.June 2006 1. BAFO received from three bidders.

2. Gateway 3 review – investment decision.3. Preferred Bidder appointed.

July 2006 1. DFP Supply approves Full Business Case.2. Contract signed.

October 2006 EDRM project re-branded as Records NI. January 2007 Gateway 4 - Readiness for Service.

Page 66: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Appendix 6 (Paragraph 1.6 and Figure 2)

56 Shared Services for Efficiency – A Progress Report

Centre for AppliedLearning (CAL)

Project Summary

1. The Centre for Applied Learning (CAL) is areorganisation of existing provision, andwas established in April 2006. CAL isresponsible for high quality generic trainingservices mainly to NICS departments andagencies, including the Senior Civil Service.CAL also provides training to a range ofnon-departmental public bodies and to NIObusiness units operating in NI. This service iscurrently being delivered by 57 staff.

2. The NICS reform agenda ‘Fit for Purpose’sought to build capability and develop talentand professionalism within the NICS throughthe provision of excellent training. CAL isdirectly linked to a Public Service Agreement(PSA) target, ‘to develop and sustain theNICS as an organisation which serves boththe institutions of government and the peopleof Northern Ireland through the provision ofhigh quality, cost effective services’. CAL’scurrent customer related strategic objectivesare:

• to deliver a range of high quality servicesstrategically aligned to the businessneeds of its clients and public servicereform;

• to develop long term high level strategicpartnerships to consistently offer valuedhigh quality service delivery; and

• to establish a business case for anappropriate location andaccommodation for CAL which willfacilitate effective delivery of NICSgeneric training services.

Project Progress

3. CAL operates on a shared service basis asrecommended in a series of internal reviewsin 2005 and 2006. After its establishment,its operations were phased in until itassumed responsibility in October 2006 forall NICS generic training. The costs for staffworking on the establishment of CAL were£0.1 million. There were no capital orprocurement costs. CAL received fundingfrom NICS departments in 2006-07 and2007-08 of £3.7 million and £3.2 millionrespectively. CAL will be moving to hardcharging from April 2008.

Key Project Dates

4. The key dates for the project to date aresummarised in the table opposite.

Page 67: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 57

Date Event2000 The ‘Review of Training and Development in NICS’ recommends a more strategic

approach to delivering generic training.July 2004 HM Treasury: ‘Releasing Resources to the Front Line’ (The Gershon Report).October 2004 1. DFP: ‘Fit for Purpose’.

2. Cabinet Office: ‘Professional Skills for Government’.March 2005 1. DFP: ‘Review of BDS Products and Services’.

2. DFP/CMPS: ‘Review of Training in the NICS’ recommends a shared service centre.July 2005 Permanent Secretaries Group endorses a shared service approach and commissions a

two stage review to bring forward detailed proposals.January 2006 1. Based on the two stage review. PSG unanimously endorses the phased creation of a

Shared Service Centre, subject to refinement of funding arrangements. 2. Chief Executive appointed by DFP Accounting Officer.

February 2006 PSG agrees funding transition arrangements.March 2006 Project Initiation Document.April 2006 1. Centre for Applied Learning (CAL) established.

2. 63 staff transferred from NI Departments.June 2006 CAL Governance arrangements agreed and Board Members formally appointed by DFP

Accounting Officer. The Board Members include an independent external member and a Trade Union nominee.

October 2006 1. CAL becomes responsible for all NICS generic training.2. Project phase closed and operational delivery phase commenced.

December 2006 PSG endorses CAL’s Business and Funding Model and directs CAL to move to hard charging.

December 2007 1. PSG agrees CAL’s movement to hard charging from April 2008.2. Northern Ireland Office Board agrees strategy to adopt CAL for all generic training

required for NIO Business Units that will transfer into the NICS as a result of devolution (detailed timing and arrangements to be agreed).

Page 68: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Appendix 7 (Paragraph 1.6 and Figure 2)

58 Shared Services for Efficiency – A Progress Report

IT Assist

Project Summary

1. The Information and CommunicationsTechnology Shared Service Centre (ICTSSC) is an outworking of the ReformAgenda Programme as outlined in ‘Fit forPurpose’ (2004). It aims to improveefficiency, modernize existing IT systems andensure improved business processes areenabled, utilizing standard IT infrastructureand operational systems across the NICS.The SSC is part of the Delivery andInnovation Division in DFP.

2. IT Assist was not subject to a procurementprocess as the Business Case recommendedan in-house solution (with some servicesbeing delivered by partnership-style contractswith the private sector) at a cash cost of£218 million over 10 years. The SSC iscurrently in the process of taking ownershipof IT assets and responsibility for their day today support, maintenance and replacement.Line of Business software applicationservices specific to individual departmentswill remain the responsibility of departmentalInformation Support Units (ISUs).

Project Progress

3. The SSC became operational in April 2007with the first two departments transferringtheir ISU staff and resources used for ITCommon Services where they were joinedby the Delivery and Innovation Division’sTelecommunications and IS Services teamsfrom DFP in the new delivery unit. Acommon helpdesk went live during May2007 servicing five departments (DFP,

OFMDFM, DRD, DOE and DCAL). A sixthdepartment (DETI) joined in October 2007and the remaining departments will bebrought on board on a phased basisthrough to the end of March 2009, whenall existing contracts have expired. To datethree new contracts have been signed forsecure messaging and storage, data centreaccommodation and service desk services.

4. The Transition Programme originally had anumber of distinct phases leading toproposed full implementation by June 2008.This was revised in October 2006 into aseries of candidate projects incorporatingfinance, personnel, accommodation andsecurity issues, as well as technical tasksand a ‘Reference Architecture’ to ensure thatprojects interface together and with otherreform programmes, with the finaldeliverable now planned for March 2009.

Key Project Dates

5. The key dates for the project to date aresummarised in the table opposite.

Page 69: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 59

Date EventMay 2004 OGC Review of alternative arrangements for ICT service provision in NI.October 2004 ‘Fit for Purpose’.March 2005 Strategic Outline Case endorsed by the Permanent Secretaries Group (E) – the group

charged with looking at shared service delivery. The Strategic Outline Case concluded that common ICT services should be provided to all departments and agencies across a single NICS infrastructure and that changes in service provision should be taken forward as a programme.

June 2005 Gateway 0 review – strategic assessment.March 2006 Outline Business Case (OBC) recommends an in-house solution.July 2006 DFP Supply approves the OBC on condition that certain updates are provided.December 2006 DFP Supply provided with updates to the OBC April 2007 Shared Service Centre becomes operationalJune 2007 Second Gateway 0 review – strategic assessment.

ICT Shared Services: Timetable for migration of data from old systems to new systems

Department Apr 07 Jul 07 Oct 07 Jan 08 Apr 08 Jul 08 Oct 08 Jan 09 Apr 09

DRD

DOE

DCAL

DFP

OFMDFM

DETI

DE

DHSSPS

DSD

DARD

DEL

Page 70: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

26 The e-Government Fund was established in 2004 to encourage and develop innovative electronic Government projectsacross the public sector in Northern Ireland, particularly in order to deliver improved services by NI Departments andAgencies. The fund, which closed in March 2008, has therefore supported projects aligned with public sector reform andcitizen-centred initiatives, including investment in public service infrastructure and digital inclusion.

Appendix 8 (Paragraph 1.6 and Figure 2)

60 Shared Services for Efficiency – A Progress Report

Network NI

Project Summary

1. Network NI (formerly known as theBroadband Aggregation Project) is aninfrastructural project that covers theprocurement of an enhanced wide-areanetwork (WAN) service for the NICS, withan option to procure additional servicesincluding Internet Portal Telephony andClassroom 2000 (C2K) requirements. Theproject plans to procure demand in such away that best delivers value for money forthe public sector, increases the availability ofbroadband and supports the NITelecommunications Policy. The project wasprogressed to contract signature around theobjectives of:

• to provide bandwidth ranging from 0.5Megabytes per second to 2.5 Gigabytesper second to meet current specific userrequirements anywhere within the NICSportfolio of buildings, in a way thatmaximises value for money by 2008-09;

• to provide resilience and availability ofnetwork services giving a target 99.7per cent availability per site across theentire network once roll out is complete,with 99.99 per cent availability for keylocations e.g. data centres;

• to provide the potential for networkbandwidth to be varied in line withindividual organisational requirements.Specifically, the networks should providethe capacity to cater for peaks andtroughs in the business cycle;

• to provide a network that is flexible andeasily facilitates major changes toaccommodation, structures and workingpractices within the NICS; and

• to provide opportunities for the NICS toenhance existing networks to facilitate theintroduction of new business processesand IT systems undertaken as part of theReview of Public Administration.

Progress to date

2. The Department signed a six year contract inSeptember 2007, with an option to extendup to a maximum of ten years based on anannual review. The project will be rolled outacross 275 sites in eight phases with asteady state service expected fromSeptember 2009. The total cost is expectedto be £29.3 million over ten years,comprising initial connection, WANmaintenance and rental circuit charges(£8.7 million); service availability payments(£17.9 million); and network managementstaff costs (£2.7 million). The Contractor isexpected to absorb inflation for years one tosix, but will be allowed to include a GDPdeflator rate from year seven onwards. It isexpected the charges from year six willreduce to reflect the continual progressiontowards faster and cheaper broadbandprovision in the private sector.

3. The project has been allocated a budget forthe financial year ending March 2008,sourced from ‘e-gov’26 funding and a bididentified in the September monitoringround. From April 2008 it is expected thatthe service charges for the contract will befunded from the current departmental

Page 71: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 61

budgets for the wide area network andcentral funding until a system of hardcharging is in place.

Key Project Dates

4. The key dates for the project to date aresummarised in the table below.

Date EventApril 2002 PPS 10 Telecommunications sets out departmental planning policies for

telecommunications development.2002-03 Programme for Government: one of the five key priority areas is a commitment

to continue to implement the telecommunications strategy and to ensure all of Northern Ireland has world class infrastructure in terms of broadband capacity, access and cost.

2003 The ‘Feasibility Study into Aggregation of Public Sector Demand for Broadband communications’ recommends an aggregate body for NI to manage aggregation akin to Adits, the regional aggregation bodies, established by DTI in England.

January 2004 Gateway 1 Review – Business Justification.September 2004 Prior Information Notice in the Official Journal of the European Union.September 2005 The OBC recommends fully outsourced services.October 2005 Gateway 2 Review - Procurement Strategy.January 2006 Contract Notice issued in the Official Journal of the European Union and other

media seeking expressions of interest.February 2006 11 valid prequalification questionnaires received. Seven companies invited to submit

an outline proposal, four subsequently withdrew. July 2007 1. OBC updated with an addendum to the original, reducing scope to fulfill NICS and

C2K requirements rather than total public sector demand.2. Preferred bidder selected.

August 2007 1. Gateway 3 Review – Investment Decision. 2. Final Draft Business Case.

Page 72: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Appendix 9 (Paragraph 2.1)

62 Shared Services for Efficiency – A Progress Report

Civil Service Human Resource ManagementSystem: Cancellation of the Payroll Project –NIAO Report (November 2004)

1. This report examined the cancellation of aplanned new computerised payroll systemfor the NICS. The contract for the payrollsystem was signed between DFP andMcDonnell Douglas Information Systems inDecember 1991. However, the projectexperienced problems and delays over aperiod of nine years caused by deficienciesin the software and a range of contractualand management issues. It was finallycancelled in May 2001, without havingproduced a workable system, that is, wherethe payroll was part of a wider integratedhuman resource management system whichwould include all the main NICS personnelfunctions.

2. The NICS spent £3.3 million in developingthe project. In addition, planned savingsamounting to £6.1 million were notachieved. These savings were not realisedbecause NICS had to continue with theexisting inefficient payroll system, which hasbeen operational since 1986, and was notable to achieve planned staff reductions.

Main Recommendations

a. Procurement - The Department should havecommissioned an appraisal of all availableoptions, including a proper assessment ofthe risks involved in continuing withMcDonnell Douglas Information Systems, inorder to establish whether continuation withthe project was the most appropriate courseof action. It underlines how important it is toget the contract right in such projects. The

project must not only be unambiguous but italso needs to address the financialconsequences if the supplier fails to deliver.

b. System Development - Although economicappraisals were carried out by the ProjectManager in 1995, 1997 and 1999,NIAO considered that an independentappraisal would have provided anopportunity for a fundamental examinationof the objectives of the project and mighthave helped to ensure that better decisionswere made as to the way forward.

c. Project Management - The payroll projectwould have benefited from the appointmentof a senior manager with sufficient authorityto assume personal responsibility for theproject throughout its life. Such anappointment is essential for all future NICSprojects of this scale and complexity. Amore thorough evaluation of some of the keyrisks, such as is now accepted goodpractice, could have significantly improveddecision-making at crucial stages in theproject. It is important that such projects areproperly planned, resourced and managedin line with the guidance now available [in2004].

Page 73: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 63

Appendix 10 (Paragraph 2.4)

Shared Service Projects: Main Options in Outline Business Case

Project Preferred Option Other Options

HR Connect In - house provision of 1. Base CaseHR services with the 2. In-house provision of HR Services with a Single Primepayroll and support Contract covering Payroll Bureau and the HR Support services outsourced Services

3. In-house provision of HR Services with a Single Prime Contract covering a Payroll Fully Managed Facility and the HR Support Services

Account NI Shared Service Centre 1.. Base CasePhased Migration 2. Re-implementation but no shared services

3. Single Shared Service Centre4. Shared Service Centres organized on a functional

basis5. Shared Service Centres organized on a

departmental basis

Workplace 2010 Total Property PFI 1. Baseline ‘do nothing’2. Traditional Procurement (whole estate)3. Mixed Procurement (PFI – Greater Belfast,

Traditional – Regional estate)

Records NI Partnership with single 1. Independent records solutions deployed by each external provider department

2. Departments select from external providers within a framework agreement

3. Procure a single external shared application service provider to deliver a single service to the NICS

IT Assist A single SSC with the 1. Enhanced status quocontracts rationalised into 2. A single SSC with the existing range of contractsa small number of strategic 3. Several SSCs based on the ISUs with rationalisedcontracts contracts

4. Outsourcing of all common ICT services

Network NI Full outsourcing 1. Do nothing2. Managed service –the public sector designs network

and owns the assets

Page 74: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Appendix 11 (Paragraph 3.14)

64 Shared Services for Efficiency – A Progress Report

Shared Service Projects – Cost Summary

Outline Full Cash CostsAppendix Project Business Case Business CaseReference

NPV Cash NPV Cash To date ContractEnd

£’m £’m £’m £’m £’m £’m

4 Workplace 2010 925.6 1,968.1 * * * *

2 HR Connect 285.5 328.5 368.9 465.1 29.0 486.6

7 IT Assist 188.3 217.6 n/a n/a 31.6 217.6

3 Account NI 99.1 113.6 138.2 169.4 31.9 169.4

8 Network NI 41.9 48.7 24.9 29.3 1.8 29.3

5 Records NI 19.7 21.2 16.0 17.5 12.5 17.5

6 CAL n/a n/a n/a n/a n/a n/a

NOTES:Workplace 2010: The project is still in the procurement phase.HR Connect: The OBC costs were calculated over a 10 year period, while the FBC was based on the contract period of 15 years.IT Assist: The OBC recommended an in-house solution and there was no major procurement and no FBC.Account NI: The OBC costs were calculated over a 10 year period, while the FBC was based on the contract period of 12 years. Network NI: There was a major reduction in scope between OBC and FBC due to excluding non-NICS bodies and theHealth Service from the arrangements. DHSSPS remains in scope.CAL: There was no OBC or FBC as this was a reorganisation of existing provision into a SSC.

Source: NIAO/DFP

Page 75: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Appendix 12 (Paragraph 4.5)

Shared Services for Efficiency – A Progress Report 65

Records NI Pilot – Top Ten Implementation Lessons Learned

1. All the benefits initially perceived will not be realised unless the full functionality of the system is utilized; therecords management culture change will not be embedded and staff use of the system will decrease ifrelevant training and full functionality are not developed; ongoing resources are needed to undertake thisprocess.

2. Senior management must lead by example and mandate the use of TRIM (the standard software) andsupport the business and cultural change by acknowledging TRIM as the single repository for electronicinformation.

3. Frequent reviewing of staff training needs, management processes and monitoring the uptake is requiredi.e. refresher, advanced or more specific training for staff who may require it.

4. Adequate resources need to be in place to undertake the interim management tasks associated withmaintaining a quality records management system.

5. Adequate resources in both staff and time need to be available to develop and review the File Plan (thepreparatory work by each department to allow the contractor to deliver the business solution) on anongoing basis.

6. Delayed development of the File Plan will have an adverse impact on implementation.

7. The corporate decision on deletion of documents and associated data is recommended as the three leadimplementation departments have all approached this functionality in different ways.

8. It is necessary to review the TRIM configuration to meet business needs.

9. It is important to promote good practice in information management by monitoring the use of namingconventions.

10. To maximise the full potential of the TRIM solution staff must understand their specific role and responsibilityin managing information.

Page 76: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Appendix13 (Paragraph 4.13)

66 Shared Services for Efficiency – A Progress Report

Summary of Business Principles for SharedServices within the NICS

1. NICS managers and staff have anobligation to citizens to ensure that publicservices are delivered in the most effectiveand efficient manner possible.

2. Senior management will demonstrate strongand consistent leadership and commitmentin support of shared services.

3. Sharing is not an end in itself – sharedservices must provide benefits in terms of thecost and quality of the services provided.

4. All shared service providers should share acommon set of values, encompassingintegrity, responsibility, accountability,respect and continuous improvement.

5. There will be a presumption in favour ofimplementing standardised solutions. Wherenecessary, specific customization of services,and the associated costs will be negotiatedbetween the service provider and the userbut should never undermine the ability of theshared service centre to deliver its coreservices.

6. All NICS organizations should avail of allthe shared services provided.

7. All shared services should establish effectivecustomer-inclusive governance regimeswhich clearly articulate authorities,accountabilities and decision-makingresponsibilities.

8. Governance Board members will bemandated to act for the NICS corporategood and will be committed to the successof the shared service and providingassurance to the Accounting Officer for theshared service organization.

9. Service Level Agreements will beimplemented through discussion betweenprovider and customer to create a commonunderstanding about service priorities andobligations, clearly defining responsibilitiesfor both provider and customer. ServiceLevel Agreements will be kept as clear andsimple as possible and for in-sourcedsolutions will not link service levels tofinancial penalties or incentives.

10. Shared services will work to continuouslyimprove processes, policies, procedures,technology and staff development to achievecontinuous improvement.

11. Departments will work constructively togetherto ensure adequate funding for sharedservices will be secured at the outset.

12. In line with Government accounting rulesand guidance, shared services should moveto an appropriate hard charging regime atthe earliest practical opportunity in a clearand transparent way.

13. The charging mechanism must be agreedbetween provider and customer anddocumented in the Service Level Agreementto ensure clarity about the respective rolesand responsibilities. The chargingmechanism must be simple, fair, predictableand controllable.

Page 77: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Shared Services for Efficiency – A Progress Report 67

14. Each shared service will produce a concise,accessible, annual report setting outprogress and performance in relation togovernance, performance (including ServiceLevel Agreements), funding and charging.

Page 78: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

68 Shared Services for Efficiency – A Progress Report

NIAO Reports 2007-08

Title HC/NIA No. Date Published

2007Internal Fraud in Ordnance Survey of Northern Ireland HC 187 15 March 2007The Upgrade of the Belfast to Bangor Railway Line HC 343 22 March 2007Absenteeism in Northern Ireland Councils 2005-06 - 30 March 2007Outpatients: Missed Appointments and Cancelled Clinics HC 404 19 April 2007Good Governance – Effective Relationships between HC 469 4 May 2007Departments and their Arms Length BodiesJob Evaluation in the Education and Library Boards NIA 60 29 June 2007The Exercise by Local Government Auditors of their Functions - 29 June 2007Financial Auditing and Reporting - Health Sector: NIA 66 6 July 20072003-04 and 2004-05Financial Auditing and Reporting: 2005-06 NIA 65 6 July 2007Northern Ireland’s Road Safety Strategy NIA 1/07-08 4 September 2007Transfer of Surplus Land in the PFI Education NIA 21/07-08 11 September 2007Pathfinder ProjectsOlder People and Domiciliary Care NIA 45/07-08 31 October 2007

2008Social Security Benefit Fraud and Error NIA 73/07-08 23 January 2008Absenteeism in Northern Ireland Councils 2006-07 - 30 January 2008Electronic Service Delivery within NI Government Departments NIA 97/07-08 5 March 2008Northern Ireland Tourist Board – Contract to Manage the NIA 113/07-08 28 March 2008Trading Activities of Rural Cottage Holidays LimitedHospitality Association of Northern Ireland: A Case Study NIA 117/07-08 15 April 2008in Financial Management and the Public Appointment ProcessTransforming Emergency Care in Northern Ireland NIA 126/07-08 23 April 2008Management of Sickness Absence in the Northern NIA 132/07-08 22 May 2008Ireland Civil ServiceThe Exercise by Local Government Auditors of their Functions - 12 June 2008Transforming Land Registers: The LandWeb Project NIA 168/07-08 18 June 2008Warm Homes: Tackling Fuel Poverty NIA 178/07-08 23 June 2008Financial Auditing and Reporting: 2006-07 NIA 193/07-08 2 July 2008General Report by the Comptroller and Auditor General for Northern IrelandBrangam Bagnall & Co: Legal Practitioner Fraud NIA 195/07-08 4 July 2008perpetrated against the Health and Personal Social Services

Printed in the UK for the Stationery Office on behalf of the Northern Ireland Audit OfficePC2304 07/08

Page 79: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing
Page 80: Shared Services for Efficiency – A Progress Report...Shared Services for Efficiency – A Progress Report 3 the efficiencies and benefits envisaged, DFP has had successes in managing

Published by TSO (The Stationery Office) and available from:

Onlinewww.tso.co.uk/bookshop

Mail, Telephone, Fax & E-mailTSOPO Box 29, Norwich, NR3 1GNTelephone orders/General enquiries: 0870 600 5522Fax orders: 0870 600 5533Order through the Parliamentary Hotline Lo-Call 0845 7 023474E-mail [email protected] 0870 240 3701

TSO Shops16 Arthur Street, Belfast BT1 4GD028 9023 8451 Fax 028 9023 540171 Lothian Road, Edinburgh EH3 9AZ0870 606 5566 Fax 0870 606 5588

The Parliamentary Bookshop12 Bridge Street, Parliament SquareLondon SW1A 2JXTelephone orders/General enquiries 020 7219 3890Fax orders 020 7219 3866Email [email protected] bookshop.parliament.uk

TSO@Blackwell and other Accredited Agents