019100-1 VER:10/10 COMMISSIONING PROGRAM SECTION 019100 COMMISSIONING PROGRAM PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. SRP’s Scope of Work Document or the Owner’s Project Requirements (OPR) B. Basis of Design (BOD) document from the AE. C. Roles and Responsibilities Matrix (found in the Bid documents) 1.2 SUMMARY A. Why SRP Commissions Commissioning is part of SRP’s Quality Assurance process that ensures a building or project’s complex range of systems is designed, installed, tested, and performs to SRP’s intent and operational needs. B. What SRP Expects From Commissioning. Depending on size and complexity of the project, expectations for Commissioning range from completing the manufacturer’s installation and startup checklists followed by a functional performance test to a fully integrated commission process that begins early in the design phase and ends when the warranty period is over. C. The Roles and Responsibilities SRP, AE Team, and Construction Team have on this project. SRP has a Roles and Responsibilities Matrix (see Paragraph 1.4 Responsibilities) that defines the responsibilities of each organization in the Design Phase, Pre-Construction Phase, Construction Phase, Acceptance Phase, and Post Occupancy Phase. D. This Section excludes Retro-Commissioning. 1.3 RELATED WORK 013300 Submittals Covers content and format of all submittals. 017700 Closeout Defines Substantial Completion and Functional Completion 017823 O&M Manuals Defines O&M documentation 015995 Mechanical Cx Describes details of testing to meet the Cx requirements. 016995 Electrical Cx Describes details of testing to meet the Cx requirements. 1.4 RESPONSIBILITIES & MATRIX The Roles and Responsibilities Matrix will be completed by SRP and included in the Bid packages for the AE and the Construction Team. Here is an example of a completed matrix.

Upload: hoangnhan

Post on 12-May-2018

255 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: SECTION 019100 - COMMISSIONING PROGRAM - SRP: … ·  · 2011-05-03SECTION 019100 COMMISSIONING PROGRAM PART 1 ... Commissioning Plan ... Microsoft Word - SECTION 019100 - COMMISSIONING

019100-1 VER:10/10 COMMISSIONING PROGRAM

SECTION 019100 COMMISSIONING PROGRAM PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. SRP’s Scope of Work Document or the Owner’s Project Requirements (OPR)

B. Basis of Design (BOD) document from the AE.

C. Roles and Responsibilities Matrix (found in the Bid documents)

1.2 SUMMARY

A. Why SRP Commissions

Commissioning is part of SRP’s Quality Assurance process that ensures a building or project’s complex range of systems is designed, installed, tested, and performs to SRP’s intent and operational needs.

B. What SRP Expects From Commissioning.

Depending on size and complexity of the project, expectations for Commissioning range from completing the manufacturer’s installation and startup checklists followed by a functional performance test to a fully integrated commission process that begins early in the design phase and ends when the warranty period is over.

C. The Roles and Responsibilities SRP, AE Team, and Construction Team have on this project.

SRP has a Roles and Responsibilities Matrix (see Paragraph 1.4 Responsibilities) that defines the responsibilities of each organization in the Design Phase, Pre-Construction Phase, Construction Phase, Acceptance Phase, and Post Occupancy Phase.

D. This Section excludes Retro-Commissioning.

1.3 RELATED WORK 013300 Submittals Covers content and format of all submittals. 017700 Closeout Defines Substantial Completion and Functional Completion 017823 O&M Manuals Defines O&M documentation 015995 Mechanical Cx Describes details of testing to meet the Cx requirements. 016995 Electrical Cx Describes details of testing to meet the Cx requirements.

1.4 RESPONSIBILITIES & MATRIX

The Roles and Responsibilities Matrix will be completed by SRP and included in the Bid packages for the AE and the Construction Team. Here is an example of a completed matrix.

Page 2: SECTION 019100 - COMMISSIONING PROGRAM - SRP: … ·  · 2011-05-03SECTION 019100 COMMISSIONING PROGRAM PART 1 ... Commissioning Plan ... Microsoft Word - SECTION 019100 - COMMISSIONING

019100-2 VER:10/10 COMMISSIONING PROGRAM

Page 3: SECTION 019100 - COMMISSIONING PROGRAM - SRP: … ·  · 2011-05-03SECTION 019100 COMMISSIONING PROGRAM PART 1 ... Commissioning Plan ... Microsoft Word - SECTION 019100 - COMMISSIONING

019100-3 VER:10/10 COMMISSIONING PROGRAM

1.4 DEFINITIONS AND DELIVERABLES

A. Design Phase Owners Project Requirements (OPR) - A document written by the Owner’s Representative, which details the functional requirements of Project and expectations of how it will be used and operated. This document may include project and design goals, measurable performance criteria, budgets, schedules, success criteria, and supporting information dynamic document that provides the explanation of the ideas, concepts and criteria that are considered very important to SRP. SRP may furnish a detailed Scope Document that is equivalent to the OPR. Deliverable: Written Document

Basis of Design (BOD) - The A/E team’s written record of the primary thought processes and assumptions behind design decisions. It records concepts, calculations, decisions, and product selections used to meet the OPR/Scope Document and to satisfy applicable regulatory requirements. Deliverable: A written document or written in the drawings.

Commissioning Specification - A specific set of requirements that must be satisfied to insure that the equipment and systems installed meet all the Owners Project Requirements.

Deliverable: Approved Commissioning Specifications

B. Pre-Construction Phase

Commissioning Plan (Cx Plan) – the overall plan, drafted before and developed after bidding that provides the structure, schedule and coordination planning for the commissioning process. There is a design phase plan and a construction phase plan. Deliverable: Project specific written plan.

Pre-functional Checklists – Checklist(s) of items to verify proper installation of equipment and startup of equipment. The manufacturer’s installation and startup checklists are the normal source documents. The Cx Agent may approve the manufacturer’s checklists or furnish more comprehensive checklists for use by the installing subcontractor. Pre-functional checklists are primarily static inspections and procedures to prepare the equipment for initial operation. Deliverable: Installation Checklist and Startup Checklist for each type of equipment installed. Functional Performance Testing Procedures (FPT) - Functional testing is the dynamic operation and testing of systems (rather than just components) under full operation. Systems are tested under various modes, various loads, simulated component failures, unoccupied, varying outside air temperatures, fire alarm, power failure, etc. The systems are run through all the control system’s sequences of operation and components are verified to be responding as the sequences state. The Cx Agent develops the functional test procedures in a sequential written form, oversees and documents the actual testing. FPTs are performed after pre-functional checklists, startup, and TAB are complete. Deliverable: Written Functional Performance Test plan.

C. Construction Phase

Installation Verification – The completion of the Installation Checklists by the Subcontractors, with overview by the Cx Agent. This activity is complete when the Cx Agent has reviewed and approves the checklists for each discrete piece of equipment and any discrepancies or deviations are noted on the Issues Log (maintained by the Cx Agent). Deliverables: Completed Installation Checklists and Issues Log

Page 4: SECTION 019100 - COMMISSIONING PROGRAM - SRP: … ·  · 2011-05-03SECTION 019100 COMMISSIONING PROGRAM PART 1 ... Commissioning Plan ... Microsoft Word - SECTION 019100 - COMMISSIONING

019100-4 VER:10/10 COMMISSIONING PROGRAM

Equipment Startup - It is the initial energizing of dynamic equipment, including executing the approved startup checklist by installing contractor. Startup may be witnessed by the Cx Agent. It is part of the Pre-functional Tests. Deliverables: Completed Startup Checklists and Issues Log

Test and Balance (TAB) - Traditional air or water test and balancing to set up the system flows and pressures as specified. Deliverable: TAB report.

System Verification – Verification of resolution of items on Issues Log prior to start of Acceptance Phase (and functional performance testing). Deliverables: Completed Issues Log with resolutions and indication equipment is ready for FPT.

D. Acceptance Phase

Functional Performance Testing – The completion of the Functional Performance Test by the Subcontractors under the direction of the Cx Agent. Deliverables: Completed FPT and updated Issues Log. Operator Training –Training using an approved training outline on the operations and maintenance of eth equipment to the Owners’ personnel as outlined in the specifications. Deliverables: Training outline, attendance rosters.

E. Post Occupancy Phase

Closeout Documentation – Required documentation from the Cx Agent and Contracting team after Substantial Completion. SRP requires this documentation to achieve Final Completion. Deliverables: Commissioning Report, O&M Manuals, Warranty information. Systems Manual – For LEED and non-LEED projects, the additional BOD, as-built, testing, sequence of operations etc information that supplements the O&M Manuals to provide Operations & Maintenance teams additional information on what was installed, why, how it was tested, and controls information. Deliverables: Completed Systems Manual Warranty Follow-Up /Deferred Testing – When required, a test plan and test results for seasonal testing and the notes/action items from the meeting to review all trouble calls & problems 90 days prior to the expiration of the warranty. Deliverable: Document showing Warranty Follow-up meeting was conducted and resolution of issues identified.

PART 2 – PRODUCTS 2.1 EQUIPMENT/SYSTEMS TO BE COMMISSIONED

A. The following equipment is typically commissioned.

Page 5: SECTION 019100 - COMMISSIONING PROGRAM - SRP: … ·  · 2011-05-03SECTION 019100 COMMISSIONING PROGRAM PART 1 ... Commissioning Plan ... Microsoft Word - SECTION 019100 - COMMISSIONING

019100-5 VER:10/10 COMMISSIONING PROGRAM

Equipment and System

Equipment and System HVAC System

Electrical System

__ Chillers __ Sweep or scheduled lighting controls __ Pumps __ Daylight dimming controls __ Cooling tower __ Lighting occupancy sensors __ Boilers __ Power quality __ Piping systems __ Security system __ Ductwork __ Emergency power system __ Variable frequency drives __ UPS systems __ Air handlers __ Fire and smoke alarm __ Packaged units (AC and

HP) __ Fire suppression / protection

systems __ Terminal units (air) __ Communications system __ Unit heaters __ Public address/paging __ Heat exchangers Plumbing __ Computer room units __ Service water heaters __ Fume hoods __ Service water booster pumps __ Lab room pressures Other __ Specialty fans __ Refrigeration systems __ Testing, Adjusting and

Balancing work __ BAS (controls) __ Building envelope

__ Chemical treatment systems

__ HVAC control system __ Fire and smoke dampers __ Indoor air quality1

__ Equipment sound control __ Equipment vibration

control __ Egress pressurization

__ Automatic Doors __ Seal of sweeps __ Seal at windows and

penetrations __ Elevator __ Kitchen Exhaust equipment __ Sun Shades (passive or active)

PART 3 – EXECUTION (N/A)

END OF SPECIFICATION SECTION