a look inside the commissioning process · a look inside the commissioning process ... final...
TRANSCRIPT
Garry Caldbeck, Principal
Randy Teed, PE, CEM
A Look Inside the Commissioning Process
Page 2
Commissioning
Commissioning is a quality assurance process that provides documented confirmation that building systems are planned, designed, installed, tested, operated and maintained in compliance with the owner’s project requirements.
Commissioning is highly successful when collaboration exists between the design professionals and the construction team.
Page 3
Who are the Shareholders?
Owner
Architect
Engineers / Design Team
Commissioning Firm
Building Automation System (BAS)
Building Trades Personnel
Commissioning is an investment in a successful project.
Page 4
Who are the Cx Team Members?
Engineer
Professional Engineer, Energy Engineer
Control Engineer and Control Technician
HVAC, Plumbing, Hydronic, Refrigeration Technicians
Testing, Adjusting and Balancing (TAB) Technician
Building Envelope Specialist
Infrared Level 1 Thermographer Specialist
Indoor Air Quality (IAQ) Specialist
Page 5
A Look Inside the Commissioning Process
Shareholder presence and involvement
How does Commissioning (Cx) affect construction?
Does it slow it down?
Does it improve the process?
Why Commission: Cost Vs. Investment
Overview of the Process
Today we will discuss:
Page 6
Why Commission?
Page 7
Why Commission?
Page 8
Why Commission?
Page 9
Why Commission?
Page 10
Why Commission?
Page 11
International Energy Conservation Code (IECC)
C402.4 Includes requirements for Air Barrier/Building Envelope
C403 Raises the bar for equipment minimum efficiency requirements
- Utility rebate programs align to these standards as well
C403.2.8 Minimum pipe insulation thickness based on fluid operating temperature, insulation conductivity, and pipe size
C403.2.4 Requires Automatic Start controls for each HVAC system
- Must be capable of adjusting start time to condition space prior to occupancy
C403.3.1 Requires air or water economizer on all cooling systems with fans
- Must be capable of integrating with BAS to modulate OA
International Energy Conservation Code, IECC -2012 (Commercial)
Page 12
Commissioning as a Code Requirement (IECC - 2012)
CDs clearly indicating provisions for commissioning
Commissioning Plan
- Narrative of commissioning activities at each phase
- List of systems and equipment to be commissioned
- Functions (calibrations and controls) to be tested
- Testing conditions and measurable critera for performance
Air and Hydronic Systems Testing and Balancing
Functional Performance Testing
Preliminary Report listing all deficiencies at that point
Final Commissioning Report
IECC – 2012, Section C408 Requires:
Page 13
Regional Adoption of IECC
State-wide adoption of IECC - 2012
State-wide adoption of IECC - 2009
Limited Statewide Adoption or Local Government Adoption
No adoption of IECC
IECC - 2012 pending adoption
Page 14
Benefits of the Energy Codes
Command higher rents & higher sale prices
Hold value longer
Produce better results for building owners/tenants
- Marketing
- Image
- Reduced Operating Costs
National Association of Realtors confirms, energy efficient buildings:
Page 15
Benefits of Commissioning
In a study of 60 commercial buildings
- Over half suffered from control problems
- 40% had problems with HVAC equipment
- 15% were missing specified equipment
$0.02-$0.19/ft2 in annual energy cost savings
$0.23-$6.96/ft2 in annual non-energy cost savings
- Reduced maintenance, extended equipment life
Intangible benefits
- Proper ventilation, light levels, temperature control
Pacific Northwest National Labs found:
Page 16
Systems to be Commissioned
MEP Systems
- Mechanical, Electrical, Plumbing
BAS (Building Automation System)
Building Envelope – All 6 Sides
Domestic Hot Water
The building systems to be commissioned may include:
Page 17
Systems to be Commissioned
Fire and Life Safety- Fire/Smoke Damper Testing
- Smoke Evac System Testing
- System Interlocks for Shutdown and Equipment Restarts
Renewable Energy Systems- Solar Hot Water
- Photovoltaics
Security/Access/IT Data
The building systems to be commissioned may also include:
Page 18
Types of Commissioning
Mission Critical Cx
- Data Centers
- Hospitals
- Central Plants
LEED (Leadership in Energy and Environmental Design)
- Fundamental Cx
- Enhanced Cx
- Existing Building Cx
Sustainable Cx
- Green – Sustainability
- Often High Performance
Multiple paths to obtain an efficient and functional building:
Page 19
More Types of Commissioning
Building Envelope Cx (BECx)
Continuous or “On-Going” Cx
- Measurement and Verification
Retro-Commissioning (RCx)
The amount of time required for Cx depends on:
- Project Size
- Complexity
- Number of Systems to Commission
- When Commissioning Begins (the earlier it starts, the better!)
Page 20
Nine steps to a successful commissioning project
Early involvement at design stage
Cx Plan and Cx Kick-Off meeting
Building Automation System Controls Meeting
Site visits during construction
Functional performance testing
1
2
3
4
5
Issue log and corrective action reports
Owner training
Lessons learned - Building turn over
6
7
8
10 month review during warranty period9
Page 21
Nine steps to a successful commissioning project
Early involvement at design stage1
Allows the commissioning provider to work with the design team
Assists with articulating the Owner’s Project Requirements (OPR)
Reviews the engineer’s Basis of Design (BOD)
Reviews 50% and 95% Construction Documents, with Back-Checks
The BOD and OPR are LEED requirements, but they are valuable on any project
The goal is to discover problems early,
allowing changes to be made while still a pencil stroke.
Page 22
Why Commission Early?
Page 23
Example – Design Review
Review By: SystemWorks
Project Architect: . Architect Associates
Project M/E Engineers: Engineering Group Back Check Review
Date of Review: July 30, 2012 Date of Review: 10-26-12
Date of Response: October 25, 2012 Review By: SystemWorks
Date of Back Check : October 26, 2012 Document Status: 95% CD
The following are comments based on review of the 95% CD plans & specifications dated October 25, 2012.
Item System Document Review Comment Response / Action Back Check Review
1Air Cooled
ChillerM2
Review the refrigerant proposed for the air
cooled chiller. R-22 freon is being
discontinued. Consider using one of the
newer refrigerants.
R-22 freon is deleted. It was an oversight.
New chiller will be selected with the proper
refrigerant.
SW back checked 10/26/12. OK
2 Controls 230993
Recommend including BAS graphics
requirements in specification, (ex. link to
sequence of operations, floor plans, flashing
alarms, etc.)
Updated SW back checked 10/26/12. OK
3 Controls
Current drawings need additional information
shown i.e... thermostat type (adjustable, flat
plate, caged, insulated) placement, height,
mounting location (wall, ceiling, column)
override button, display.
Included SW back checked 10/26/12. OK
4
PipingAdd pipe flushing requirements. Updated SW back checked 10/26/12. OK
Page 24
Example – Design Review
Heating Water Steam Valves
Pump
Page 25
Nine steps to a successful commissioning project
Cx Plan and Cx Kick-Off Meeting2
Commissioning Plan
Project Milestones
Roles and Responsibilities of the design team and contractors
Commissioning Kick-Off Meeting
Explains Cx to the design team and contractors
Opportunity to explain Construction Checklists (specific to each trade)
Opportunity to explain the Commissioning Authority’s (CxA) role
Open door for Communication and Collaboration
Accountability and Deliverables
Page 26
Nine steps to a successful commissioning project
Building Automation System (BAS) Controls Meeting3
Reviews the controls sequences for functionality and comformance with the engineer’s Basis of Design
Meeting is held with Owner, Design Team, BAS field programmer and commissioning provider to discuss and clarify the engineer’s design intent.
The Owner’s input is essential in order to have a fully functional final product.
Equipment operation scheduling
Daily hours of operation
Hard-wired Safeties – Critical Alarms
Then functional performance test (FPTs) are prepared based on the engineer’s Basis of Design and control sequences.
Page 27
Nine steps to a successful commissioning project
“Site Visits” during construction4
“A picture is worth a thousand words.” During Site Visits, the commissioning provider notes details that may affect equipment performance and serviceability.
Site Visits during construction identify problems and allows resolution to be done before concealment.
Site Visit pictures also document activites being performed correctly per the contract specification.
During Site Visits the commissioning provider interfaces with the design team and building trades to fill in the GAPS.
What’s wrong with just commissioning at the end of the project, during the post-construction phase?
Page 28
Example – Site Visit Pictures
Improper storage – Drywall is sitting directly on wet floor
Proper Storage – Drywall is covered and off the floor
Page 29
Example – Site Visit Pictures
Improper Storage – Ductwork open and sitting on floor in standing water
Proper Storage – Ductwork covered and on pallets off the floor
Page 30
Example – Site Visit Pictures
Installation/Serviceability – Strainer installed too close to floor; cannot be removed for service
Installation – Sleeves installed at hanger joints to protect insulation
Page 31
Example – Site Visit Pictures
Contract Specification – Geothermal differential pressure sensors are installed per specification
Contract Specification – Pump is correctly piped and installed per specification
Page 32
Example – Site Visit Pictures
Serviceability – Cable tray in front of service door for fan powered box
Serviceability – Proper installation of equipment for serviceability
Page 33
Example – Site Visit Pictures
Safety – Fire-rated wall integrity compromised by conduit
Safety – One hour fire-rated wall with fire caulk at decking
Page 34
Example – Site Visit Pictures
Circuit setter and two isolation valves are not installed where they should be, per the drawings
Safety – Manual ball valve vents and drains are not capped
Page 35
Example – Site Visit Pictures
The outside air exhaust louver to AHU-1 and ERV-1, located in tunnel, is not flashed or sealed
This wrench was preventing the dampers from closing 100%
Page 36
Example – Site Visit Pictures
The air filters are 100% plugged and collapsed inward
Hydronic fittings are not insulated
Page 37
Example – Site Visit Pictures
Pipe labeling does not indicate correct flow Per manufacturer’s recommendations, the suction diffusers should be supported.
Page 38
Example – Site Visit Pictures
Boiler is positioned very tight in the corner, the side panel and front panel are not accessible
Wiring for flow meter in boiler room is not in conduit
Page 39
Example – Site Visit Pictures
Dielectric fittings between chiller and heat exchanger piping may not be appropriate
Flex fitting should not be tightly stretched, to allow for movement
Page 40
Example – Site Visit Pictures
Penetrations to the outdoors are not properly sealed
Supply fan’s canvas connections need to be repaired in order to achieve design flow
Page 41
Example – Site Visit Pictures
Chilled water supply and return lines are properly capped
Supply grilles are being kept covered to keep ductwork clean
Page 42
Nine steps to a successful commissioning project
Functional performance testing5
Writes a functional performance test for each system and piece of equipment involved in the commissioning process.
Performs hands-on testing to verify installation and performance
Hands-on performance testing occurs after Testing, Adjusting and Balancing (TAB) work is completed. Random sample of TAB work will be verified.
Requires assistance of design team and control technicians to resolve minor concerns as they arise.
Makes sure all concerns are addressed by the appropriate individual.
Backchecks are used to validate completion of these items.
An issue log is used to track each of the items through to completion.
Page 43
Functional Performance Testing
Page 44
Trend Data Analysis
Trending System Using the Building Automation System
Quantify Savings
Identify any ‘Off-season’ issues
Tuning the PID loops
Before Cx After Cx
Daily Energy Usage Over Similar Weeks
Page 45
Functional Performance Testing Equipment
NIST Traceable Equipment
HOBO Onset Data Loggers
TeleAire CO2 Sensor with Data Logger
Vaisala HM34 Humidity and Temperature
Gray Wolf Multi Mode Monitor IAQ, Direct Sense Environmental Tester
Shortridge HydroData and AirData Mulit-meters
Bacharach Test Monitor Analyzer
Fluke Remote Read Electrical Multi-meter, Electrical Clamp Meter
Simpson Sound Measuring System
Page 46
Nine steps to a successful commissioning project
Issue logs and corrective action reports6
An issue log is created to track concerns or deficiencies found during functional performance testing.
Minor deficiencies corrected during testing are noted on the issue log and simply documented to show its final resolution.
A corrective action report may be utilized to track concerns or deficiencies that were not resolved during functional performance testing.
Retesting will be scheduled, as required, to ensure that the corrected issues meets the design documents … trust but verify.
Page 47
Example – Issue Log
ITEM #
Complete Y/N DATE DATE REVIEWED
System SystemWorks Reviews / Observations LISTED CO MPLETE WITH Resolution / Status
1 Y OAHUWhen a low limit trips a "Fire/Smoke" alarm is generated along with
the low limit alarm. Fire/Smoke shutdown is not tripped.06/12/12 09/05/12 GC
7/12/12- Re-Tested - No Change. 8/2/12 - Re-Tested, No Change,
8/10/12 - Re-Tested, No Change. 9/5/12 - SW Re-Tested
Complete.
2 R OAHU
Upon tripping a saftey device (low limit, static) the AHU (supply
fan + exhaust fan) will not restart after resetting the saftey device.
The fault on each VFD must manually be reset in addition to the
saftey device. All other Conditioning Unit VFD's have been
programmed to automatically restart after a fault.
06/12/12 GC 7/12/12- Re-Tested - No Change.
3 N Hangers
Some piping hangers have isolators and some do not. Specification
15245-8 (3.2, A) states that all piping within 15m (50') of vibrating
equipment in mech rms need isolation hangers. (3.2, B ) Outside
mech rms isolation hangers shall be used on piping greater than
100mm (4")
01/15/12 GC
2/20/12 - SW verified isolators are now installed in AHU-2B
mechanical room. 3/8/12 - Isolators are still missing in the following
mechanical rooms
4 Y CHW
Large amount of air in the chilled water system. Need to review
the methods used to purge as a group. Should automatic air vents
be installed temporarily or permanently?
01/15/12 3/19/12 GC
2/20/12 - Contractor has installed temporary air vents, has 12 more
on order to install at each AHU coil. GC plans to write an RFI to
identify and ask if the air vents should be removed or left after the air is
out of the system. 3/19/12 - Air vents will remain in system and be
piped to floor drain.
Green items are for SystemWorks backcheck when ready
Red items were noted complete but found incomplete
Yellow items for BG response or not complete yet
Page 48
Nine steps to a successful commissioning project
Owner training7
Verifies facility personnel have been trained by the installation contractors, designers and manufacturers’ representatives in the operation and maintenance of the building.
Examples: Control contractor demonstrates how the critical alarms will report to facility personnel. Vendors demonstrate proper operation of the equipment and recommended maintenance schedule.
Videotaping the training sessions provides a permanent record of operation and maintenance of the equipment and can also be used to train new staff when hired.
Page 49
The Scope of Owner Training
Page 50
The Scope of Owner Training
Page 51
The Scope of Owner Training
Page 52
Nine steps to a successful commissioning project
Lessons learned - Building turn over8
A lessons learned narrative is a summary of the knowledge and experience gained during the functional testing of the building systems.
This knowledge is unique to that building.
The benefits of building commissioning results in a smooth building turn over. Owners have confirmation that building systems are installed and operating per the OPR, BOD, control sequences, and contract specifications.
Page 53
Nine steps to a successful commissioning project
10 month review during warranty period9
Return visit to review current operation and identify any potential warranty related problems before the typical 12 month warranty expiration
Talk with building operating staff to identify their concerns
Final opportunity to fine tune the control loops and to look at building pressure changes during opposite season conditions.
Many times these conditions are simulated, but best practice is to return in the opposite season for actual testing.
Page 54
Trend Data Analysis
Energy Consumption Trends
Page 55
Summary
Changes made during the design phase are the most cost-effective
Owner input is essential
Commissioning touches all trades
To deliver a fully-functional building, all trades must be successful
Commissioning is an investment; invest early and reap the rewards throughout the life of the building.
Page 56
Do You Have Any Questions?