scottish sea farms ltd st margaret’s hope biomass … · contours and spot depths from admiralty...
TRANSCRIPT
-
SCOTTISH SEA FARMS LTDST MARGARET’ S HOPE BIOMASSAND TREATMENT MODELLING
TECHNICAL SUMMARY
Report To: Scottish Environment Protection Agency
Report No: 171016- 01
Our Ref: RS
Status: V1
Date: 17 October 2016
Scottish Sea Farms Ltd
South Shian
Connel
PA37 1SB
Tel: 01631 574203 Mob: 07825030003
Email: rachel.speirs@scottishseafarms. com
IAUsermailto:[email protected]
-
Page 2 of 18
1. Summary
Modelling was carried out by Scottish Sea Farms Ltd ( SSF) for a proposed new marine cage site St
Margaret’ s Hope ( SMH). Appropriate maximum biomass, chemical consent limits and sampling
stations have been calculated, consent limits achieved are detailed in the table below:
Treatment Recommended consent mass
Biomass A maximum consent biomass of 1247.1 t and stocking density 17
kg/ m³ is recommended for this site.
Salmosan ( Azamethiphos) The total quantity of Azamethiphos to be discharged should not
exceed 78.2 g in a 3-hour period or 152.8 g in a 24-hour period.
This can be used to treat one cage in 3 hours or two cages in 24
hours at a maximum treatment depth of 1.5 m.
Excis (Cypermethrin) The total quantity of chemical to be discharged in a 3h period
should not exceed 14.2 g. The equivalent treatment volume is
2840.0 m³
Alphamax ( Deltamethrin) The total quantity of chemical to be discharged in a 3h period
should not exceed 5.3 g. The equivalent treatment volume is 2650
m³
SLICE ( Emamectin Benzoate) A maximum treatment quantity ( MTQ) of 436.5 g and a total
allowable quantity ( TAQ) of 2182.4 g. This is enough chemical to
treat the maximum biomass 5 times.
Table 1: Consent limits for Biomass and treatment chemicals at SMH.
2. Introduction
This document is a technical summary of an assessment carried out for a proposed new marine cage
site located west of St Margaret’ s Hope, Scapa Flow. Scottish Sea Farms plan to develop a site with a
cage configuration of 12 x 80 m circumference cages arranged 2x6 in a 70 m grid. Modelling has
been carried out in order to identify appropriate biomass and lice treatment chemical limits for this
proposed cage configuration. Sampling transects and sampling stations have been identified and are
detailed in section 4 below.
This summary provides site-specific methods only and is supported by generic method statements
AMMR12v01 and AMMR12v02.
-
Page 3 of 18
Figure 1: Location of the proposed marine cage site SMH, Scapa Flow.
3. Input Data
3.1 Site Data
The input data, including the bathymetry and the current data, for this site was provided by SEPA
and is summarized below:
Site Name: St Margaret’ s Hope
Site NGR: 343360 994633
Receiving Water: Water Sound
Company: Scottish Sea Farms
Peak biomass ( tonnes): 1247.1
Medicines applied for: Excis, Salmosan, Alphamax, Slice
Current Meter NGR: 343423 994652
Distance to Shore( km): 0.27
Water Depth at Site(m): 11.4
of Cages: 12
Round/ Square?: Round
Diameter/ Circumference/ Width (m): 80 m circumference
Working Depth ( m): 12
Treatment shallowing depth ( range?) ( m): 1.5
Table 2: SMH site data
-
Page 4 of 18
3.2 Bathymetry
The model configuration has been modified from the model setup created by Xodus Ltd on behalf of
SSF for the modelling of a proposed new site, SMH. The bathymetry was created by digitizing
contours and spot depths from Admiralty Chart No. 35-0 and includes depths collected during the
hydrographic survey, as outlined in report A-30530- S12-REPT- 001. The data limited to a 1km² model
domain with the grid limits:
DataAreaXMin= 342920
DataAreaXMax= 343920
DataAreaYMin= 994290
DataAreaYMax= 995290
3.3 Cage set-up
The cage grid consists of 12 x 80 m circumference cages arranged in two groups laid out in a 6x2 70
m grid with a working depth of 12 m. The cage configuration can be seen in figure 2.
Figure 2: Screenshot of cage configuration taken from Hope- FFMTv3. 0
-
Page 5 of 18
3.3 Current data
Current meter data was collected by Xodus Aurora in April and May 2011 on behalf of Scottish Sea
Farms Ltd. The survey was carried out using a 600 kHz RDI Workhorse ADCP moored on the sea
floor.
Statistics for this dataset were derived using HGdata_ analysis_ v7.xls. All data was corrected to grid
north using a magnetic variation of 3.15° W. Summaries of the derived statistical data for the 3 bins
are available in Appendix 1.
The raw data was formatted into hourly averaged data for use in AUTODEPOMOD using the SEPA
tool temp-20min- HGv3. xls ( input data displayed in Table 2). The intermediate Spring tide (SNS) and
Neap tides (NSN) were identified as occurring at hours 256 and 82 respectively.
Site name: St Margaret’ s Hope
Depth at mooring: 18.5
Height of surface meter from bottom ( m): 11.56
Height of middle meter from bottom ( m): 8.56
Height of bottom meter from bottom ( m): 2.06
Number of hourly record at which springs commence: 256
Number of hourly record at which neaps commence: 82
Identify current speed units (m/ s or cm/ s): m/ s
Mean Sea Level ( mCD): 1.93
Compass variation ( deg E/ W): 0 (correct using HGdata_ analysis)
Table2: Input parameters for the SEPA tool Hope- 20min- HGv3
Mean Sea Level (defined as the average of MHWS, MHWN, MLWS and MLWN for St Mary’ s (Scapa
Flow) was derived from Admiralty Total Tide software.
The current velocities at this site were found to be low indicating a quiescent to weakly flushed site.
3.4 Model set-up
Defaults values were used as described in SEPA guidelines Regulation and Monitoring of Marine
Cage Fish Farming in Scotland Annex H, Methods for Modelling In-feed Anti-parasitics and Benthic
Effects ( issue No. 2.3, 18 May 2005).
Initial runs were carried out using a constant feed input, auto- distribute set to on and an initial
stocking density of 17 kg/ m³. All runs used 1 particle initially and were then refined using 10
particles. MAX runs with an ITI of 10.5 were initially achieved; these were then followed by single
runs of 10 particles to limit the site to a maximum biomass of 17 kg/ m³.
3.5 Results
A passing run (Run 10) was achieved resulting in a maximum consent biomass of 1247. 1 tonnes with
a stocking density of 17 kg/ m³. Table 3 shows the flux, ITI and area results for this run while a
diagram of the flux contours and deposition footprint can be found in figure 3. A full summary of
results can be found in the marine sum spreadsheet in Appendix 2. The shape and size of the
deposition footprint is consistent with the local bathymetry and current profile at this site.
-
Page 6 of 18
Flux ( g/ m²/ y) ITI Area ( m²)
80% solids 1410 10.9 61842.7Cage Area Equivalent 11186 4 35845
Benthic Sampling Area 191.8 30 81556.7Table 3: Flux, ITI and Area results for run 10
Figure 3: Diagram of model output for run 10.
Transects have been aligned with the major axis of the deposition footprint (Fig. 3 & 4). The primary
transect has been placed at the point where the 30ITI contour is furthest from the cage group. While
a secondary transect has been included to offer a backup position if required in the field. Profiles of
each transect have been included below in Figure 5.
Sampling stations have been placed along each transect at the 30 ITI boundary and at 10m on either
side.
-
Page 7 of 18
Figure 4: Extract from Hope_Marine_Sum indicating position of transects and sampling stations.
Transect 1
Transect 2
Figure 5: Profile of sampling transects for run 10.
-
Page 8 of 18
4. Bath Treatments
4.1 Input
The input data for this model is summarised in table 4 below. The hydrographic statistics for this site
were generated using the SEPA tool HGdata_ analysis_ v7.xls. Distance from shore was measured
from Admiralty Chart No. 35-0 using ArcGIS v10.1.
Loch Data
Loch/ Strait/ Open water : Loch
Loch area (km2) : 9.2
Loch length (km) : 6.5
Distance to head (km) : 4.7
Distance to shore (km) : 0.27
Width of Strait (km) : ( only required for Strait)
Average water depth (m) : 11.4
Flushing time (days) :
Cage Data
of cages : 12
Cage shape : Round
Diameter/ Width (m) : 25.5
Working depth (m) : 12
Stocking density (kg/ m3) :
Treatment
No. of cages possible to treat in 3
hours :
1.00
Initial Treatment Depth ( m) : 1.5
Treatment Depth Reduction Increment
m) :
0.1
Hydrographic data analysis
Mean current speed ( m/ s) : 0.035
Residual Parallel Component U (m/ s) : 0.011
Residual Normal Component V (m/ s) : 0.002
Tidal Amplitude Parallel Component U
m/ s) :
0.051
Tidal Amplitude Normal Component U
m/ s) :
0.021
Table 4: Bath Treatment inputs for SMH.
-
Page 9 of 18
4.2 Results
The consent limits for all Bath treatment chemicals applied for are summarized in the marine sum
spreadsheet which can be found in Appendix 2.
Azamethiphos
Recommended consent mass (3h) – 78.2 g
Recommended consent mass (24h) – 152.8 g
Treatment Depth – 1.5 m
No. of cages per treatment – 1.0 in 3hrs, 2.0 in 24hrs
The TS plot for Azamethiphos is shown in figure 6 below:
Figure 6: Azamethiphos TS plot
Cypermethrin
Recommended consent mass (3h) – 14.2 g
No. of cages per treatment – 3.7
Deltamethrin
Recommended consent mass (3h) – 5.3 g
No. of cages per treatment – 3.5
-
Page 10 of 18
5. Infeed Treatments
5.1 Model Set-up
The model was setup using the method described in SSF’ s generic method report Bath and In-Feed
Method Statement and follows the guidelines and model defaults described in SEPA guidelines
Regulation and Monitoring of Marine Cage Fish Farming in Scotland Annex H, Methods for
Modelling In-feed Anti-parasitics and Benthic Effects ( issue No. 2.3, 18 May 2005) unless stated
otherwise below.
The Slice run parameters were set to 5 x maximum biomass ( 6235. 4 t) using an annual feed load of
3186. 3 tonnes.
All other options were set to default.
5.2 Results
The passing run ( run 2) for Slice results in a TAQ of emamectin benzoate of 2182. 4 g, this has an
equivalent treatable biomass of 6235. 4 t which is 5 x peak biomass. The MTQ is 436.5 g, this is
enough to treat the maximum consented biomass of 1247. 1 t in one treatment. This scenario results
in a mass balance is 1575 g and a mean near- field concentration of 222 gkg¹. The near- field
concentration levels exceed the EQS trigger value with a difference in concentration between
predicted near field residue concentrations and EQS values of 214.4 gkg¹.
Figure 7: Diagram of model output from Slice Run 2.
-
Page 11 of 18
6. Discussion
The footprint of deposition produced by the model is consistent with the bathymetry and current
data recorded at this site. This is also reflected by the volume of mass retained within the model
100 % of the mass released).
There is little to no export from the model grid with dispersion of material almost completely within
the deposition footprint.
SMH is characterized by a flat, relatively shallow bathymetry with no unusual features and a
comparatively simple hydrography. This implies that the short term and MLA bath treatment
models adequately simulate the behaviour of bath treatment chemicals released at this site.
The maximum consent mass for Slice at SMH has been calculated as 2182. 4 g, this is enough to treat
a biomass of 6235. 4 t. The MTQ is 436.5 g which is sufficient to treat 1247. 1 t.
The EMBZ mass balance for the passing run (118 days) is 1575 g, this is the mass of medicine residue
which is left in the model grid at the end of this run. In order to calculate the amount of medicine
lost from the model due to export the following equation is used:
2182.4 x 0.74) - 1575
39.98 g
Therefore around 1.8 % of the medicine released is exported from the model grid. This is consistent
with the low current speeds found at this site. The model shows that the vast majority of the Slice
residue is retained within the model grid.
Using the SEPA tool marine_ sum. v3.1 we can see that the overall affected area is likely to cover an
area of 0.4 km². This is around 6 % of the available receiving area of 6.5 km². Inspection of the bed
record indicates that any medicine exported from the grid is likely to be in the direction of Hunda
Island and into the wider receiving area of Scapa Flow.
-
Page 12 of 18
7. Conclusion
The recommended consent limit for this site is a maximum biomass of 1247.1 tonnes at a stocking
density of 17 kg/ m³.
The model output for this site is representative of a quiescent site with a deposition footprint
consistent with the relatively weak vector averaged residual current and bathymetry of the site.
The recommended chemical consent limits for this site are:
Azamethiphos - 3h hour recommended consent limit of 78.20 g and a 24h limit of 152.8 g. This
quantity is sufficient to treat one whole cage with a treatment depth of 1.5 m in 3hrs and two cages
in 24hrs. In order to treat the whole site six treatments of two cages over six days would be
required.
Cypermethrin – 3h recommended consent limit of 14.2 g; this is sufficient to treat a volume of 2840
m³, or 3 whole cages at a shallowing depth 1.5 m.
Deltamethrin - 3h recommended consent limit of 5.3 g, this is sufficient to treat a volume of 2650. 0
m³ or 3 whole cages at a shallowing depth of 1.5 m.
Slice – A recommended consent limit of 436.5 g (MTQ) and a TAQ of 6235.4 g. This is enough
chemical to treat the maximum biomass 5 times.
-
Page 13 of 18
8. References
SEPA ( 2006) In-Feed consent limits at dispersive sites – v3. Available online:
http:// www.sepa.org.uk/ water/ water_regulation/ regimes/ aquaculture/ marine_aquaculture/ modell
ing/ technical_ guidance_ notes.aspx# limits
SEPA ( 2005) Regulation and Monitoring of Marine Cage Fish Farming in Scotland Annex H, Methods
for Modelling In-feed Anti-parasitics and Benthic Effects ( issue No. 2.3, 18 May 2005). Available
online:
http:// www.sepa.org.uk/ water/ water_regulation/ regimes/ aquaculture/ marine_aquaculture/ modell
ing.aspx
IAUserhttp://www.sepa.org.uk/water/water_regulation/regimes/aquaculture/marine_aquaculture/modelling/technical_guidance_notes.aspx#limits
IAUserhttp://www.sepa.org.uk/water/water_regulation/regimes/aquaculture/marine_aquaculture/modelling/technical_guidance_notes.aspx#limits
IAUserhttp://www.sepa.org.uk/water/water_regulation/regimes/aquaculture/marine_aquaculture/modelling.aspx
IAUserhttp://www.sepa.org.uk/water/water_regulation/regimes/aquaculture/marine_aquaculture/modelling.aspx
-
Page 14 of 18
Appendix 1 – Current Meter Data Summaries
Sub- Surface
-
Page 15 of 18
Cage Bottom
-
Page 16 of 18
Near Bed
-
Page 17 of 18
Appendix 2 - Marine Sum Spreadsheet
-
Page 18 of 18