safeguards training kiev, ukraine may 13, 2011
DESCRIPTION
Safeguards Training Kiev, Ukraine May 13, 2011. Simplified Checklist EMP for Small Scale Civil Works – Introduction and Exercise. Checklist EMP: Rationale and Beginnings. 2007 review of SG implementation in health & education sectors indicated: Most of the projects Category “low B” - PowerPoint PPT PresentationTRANSCRIPT
Safeguards Training
Kiev, UkraineMay 13, 2011
Simplified Checklist EMP for Small Scale Civil Works –
Introduction and Exercise
Checklist EMP: Rationale and Beginnings
• 2007 review of SG implementation in health & education sectors indicated: – Most of the projects Category “low B”– Environmental impacts usually related only to small scale construction
/ building rehabilitation– EMPs existed on paper but were long, complex, impractical – and
mostly ignored… in most cases, no environmental site management at all
• Recognition that issues for small scale construction/rehabilitation are fairly standard… no need to continually “re-invent the wheel”
• Conclusion: need a streamlined, practical instrument, which would be standardized, easy to prepare, implement and monitor, specifically tailored to small scale infrastructure
Checklist EMP: Eligibility Criteria
• Category “low B” Project
• Environmental issues known and limited to small scale construction/rehabilitation works*
• Area of impact clearly defined & limited: either within an existing “footprint” or relatively small new areas known not to have major environmental or social issues
* We’re thinking of developing one for rehabilitation of irrigation & drainage … ideas for other potential applications?
Checklist EMP: Structure and Function
• components
•Basic information on project activities•Environmental baseline information
Part 1: Datasheet
•Grouped according to various themes or impact types
•Themes / types to be checked as applicable
2: Screening: potential impacts
•Each checked item from Part 2 triggers specific mitigation measures / parameters and specific, concrete activities to be implemented on site3: Mitigation
measures for each potential impact
•Focuses on reasonable, meaningful, practical monitoring parameters for key mitigation measures and impacts
4: Monitoring plan
5
• Parts 1 & 2: description of sub-project and identification of potential impacts: for use by screener/approver
• Part 3: identifies issues and associated mitigation measures: becomes part of construction contract
• Part 4: monitoring/supervision plan to verify effective mitigation: for use by construction site supervisor and PMU
How EMP Checklist is used
6
Typically a project financing small scale works will include multiple sub-projects
Project level (prior to Appraisal): a brief EMF, describing scope of sub-projects and potential issues
Sub-project level (during implementation): an Checklist EMP completed for each sub-project
Note: Checklist EMP approach can also be applied to one project component, with regular EMP or EA applied to others
Example: Country X Real Estate & Cadastre Project (XRECP)
Introductory information (to be filled in prior to Appraisal):
• Project will finance rehabilitation of 15 Cadastre office buildings, all currently in use (sub-projects)
• No new construction or extension of facilities – all works within existing footprint
• All buildings located in urban areas on commercial streets with moderate to heavy traffic.
• Some may be registered historical buildings
• Rehabilitation will be interior and exterior and may include: repair or replacement of roofs & windows, rewiring, removal/replacement of insulation, masonry repairs, repair/replacement of floors, repair/replacement of plumbing, painting
• A site-specific Checklist EMP form will be completed for each sub-project and will be attached to the construction works contract
8
Sub-project Example: Cadastre office construction in Town A
Part 1 (Site Description Section )
9
Part 2: Screening/ identification of issues (minor issues only)
Question: what kind of issues might lead to decision that Checklist EMP is not appropriate?
Part 2 completed for Town A Cadastre Office sub-project
Part 3: Mitigation Measures (delete any which do not apply)
12
Part 4: Monitoring Plan for selected potential impacts and mitigation measures