quarterly environment report › ... › 2016 › 01 › 2015-quarter-3.pdf · this quarterly...
TRANSCRIPT
1
Quarter 3: 2015
Environment and Community
Terramin Australia Ltd
July-September: 2015
Quarterly Environment Report
2
EXECUTIVE SUMMARY
This quarterly Environment Report (QER) for the Angas Zinc Mine (AZM) summarises the results of the
environmental monitoring program between July and September 2015, as required as part of the Mine’s
Program for Environmental Protection and Rehabilitation (PEPR).
Terramin Australia Ltd ceased mining operations at AZM on September 30th
, 2013, with the site placed into a
Care and Maintenance phase.
This QER reflects the environmental monitoring requirements outlined in the Mine Care and Maintenance Plan
(MCMP), which has been approved by the Department for State Development (DSD) on the 23rd
March 2015.
The Tailings Storage Facility surface area remains at approximately 11,000m2, with the RL of the TSF decant
pond at 68.23m, as of the 28th
September(Appendix I).
The water level in monitoring bore DH2 was at 25.95m below the surface (measured from the bore collar) on
the 28th
September and underground in the mine void has reached the entrance to the mine as planned,
submerging any potential PAF material in the decline, drives and stopes. The AZM mine void groundwater
model has been updated by Australian Groundwater Technologies and was provided to DSD with the updated
2014 Compliance Report, and the SCCC and wider public in the preceding Quarterly Environment Report (April
– June 2015).
Throughout the quarter, weed control has continued as part of the weed and pest management plan. A weed
and pest survey was undertaken in July and has been included in Appendix L.
Senior DSD Mining Regulators Antonia Scrase (Principal Officer of Mine Closure), Kyle Rice (Senior
Environmental Project Manager) and the Director of Mining Greg Marshall visited site on the 23rd
of
September and conducted a quarterly compliance visit.
DSD, Terramin and the SCCC continued to work on the Terms of Reference throughout the quarter, as well as
finalise the appointment of a new chairperson, Mr Kelvin Trimper.
Cover photo: Caterpillars on a Eucalypt on the western side of the TSF
3
TABLE OF CONTENTS
Executive Summary ................................................................................................................................................ 2
Background ............................................................................................................................................................. 5
1. Mining and Mine Void Acid and Metalliferous Drainage ............................................................................... 5
2. Surface Water .............................................................................................................................................. 10
3. Groundwater ................................................................................................................................................ 12
4. Noise ............................................................................................................................................................ 13
5. Public Health and Nuisance ......................................................................................................................... 13
Dust Deposition Gauges ................................................................................................................................... 13
High Volume Sampler ....................................................................................................................................... 16
6. Waste Disposal and Hazardous Substances ................................................................................................. 17
7. TSF Water / Acid Mine Drainage .................................................................................................................. 17
TSF Decant Pond .............................................................................................................................................. 17
TSF Seepage Drain Flows .................................................................................................................................. 17
TSF Surface Area ............................................................................................................................................... 18
TSF Groundwater Monitoring Bores ................................................................................................................ 18
TSF PAF testwork results .................................................................................................................................. 19
8. Weeds and Pests .......................................................................................................................................... 19
9. Community Engagement ............................................................................................................................. 19
Strathalbyn Community Consultation Committee (SCCC) ............................................................................... 19
Complaints Register ......................................................................................................................................... 20
10. Additional Information ............................................................................................................................ 20
11. Summary.................................................................................................................................................. 21
12. References ............................................................................................................................................... 21
13. Appendix A – Angas Zinc Mine – Filled and unfilled voids ...................................................................... 22
14. Appendix B – Water Monitoring Locations ............................................................................................. 23
15. Appendix C – Surface Water Monitoring Data ........................................................................................ 24
16. Appendix D – Groundwater Monitoring Data ......................................................................................... 25
Groundwater Quality Raw Data ....................................................................................................................... 29
4
17. Appendix E – Groundwater Standing Water Levels ................................................................................. 30
18. Appendix F – Dust Monitoring Locations ................................................................................................ 31
19. Appendix G – Dust Leading Indicator Data – Dust Deposition Gauges ................................................... 32
Total Insoluble Matter ...................................................................................................................................... 32
Offsite Lead Measurements ............................................................................................................................. 33
Onsite Lead Measurements ............................................................................................................................. 33
20. Appendix H - Dust Leading Indicator Data – HiVol .................................................................................. 35
Total SolId Particulate Measurements ............................................................................................................. 35
PM10 measurements ....................................................................................................................................... 36
Lead measurements ......................................................................................................................................... 37
21. Appendix I – TSF ...................................................................................................................................... 38
Decant Pond RL Over Time ............................................................................................................................... 38
Seepage Drain Flows ........................................................................................................................................ 39
22. Appendix J – TSF Monitoring Bores ......................................................................................................... 40
23. Appendix K – TSF Seepage Drains ............................................................................................................ 44
24. Appendix L – Weed and Pest Survey 2015 .............................................................................................. 45
5
BACKGROUND
This is the third QER for 2015 and represents the period from July to September 2015 (Quarter 3). This report
is prepared for the Strathalbyn Community Consultative Committee, the Department for State Development
and the Terramin Board of Directors. This document is a reports on Terramin’s status against the measurable
criteria outlined in the recently approved Mine Care and Maintenance Plan (23rd
March 2015) submitted as an
addendum to the PEPR in July 2014.
1. MINING AND MINE VOID ACID AND METALLIFEROUS DRAINAGE
Production ceased at the Angas Zinc Mine (AZM) on the 30th
of September 2013. As part of the ongoing Acid
and Metalliferous Drainage management strategy the mine void has been allowed to refill with ground water
seep. In order to speed up the process of filling the void and mitigate potential oxidisation, additional water,
sourced from onsite bores has been pumped into the mine void at approximately 4 L/s. During this time the
water has been monitored for level and pH. The water level was at the 46.6m RL/51.8m AHD, with a measured
pH of 5.9 on the 22nd
September 2015 (Figure 2).
Water was detected in the monitoring bore DH2 in June 2014. This bore is utilised to monitor the mine void
cone of depression recovery, as well as monitor any occurrence of Acid and Metalliferous Drainage (AMD)
related to the mine void. A year on, DH2 had a standing water level of 25.95 m, measured from the bore collar,
on the 28th
of September (Figure 3).
As a result of the winter rains and stormwater caught onsite, the water level of the mine void has risen to
approximately 51.8m AHD and now can be seen at the portal entrance. Monitoring water levels of bores near
the mine void, DH2, DH3 and the Pastefill line (which targets the 140m RL decline void) continues. Figure 1
shows the location of DH2, DH3, LG2 and the Pastefill line which is also being monitored to assist with
updating the required groundwater/mine void recovery model. DH2, DH3 and the Pastefill 140 line will
continue to be sampled to determine if any AMD is occurring in the mine void. On September 2, 2015
Terramin were able to obtain a purged sample from DH2, which, when analysed by a NATA accredited
laboratory, revealed a pH of 7.27 and a sulphate concentration of 2650mg/L. Prior to mining, between 2006
and 2008, the sulphate concentrations of bores (AWE1, LG1, LG2, RG7 and RG8) near the ore bodies ranged
between 1400- 3900 mg/L, hence the results to date support a view that mitigation of AMD has been
successful. The laboratory results have been reviewed by Australian Groundwater Technology and
demonstrate that the contaminants are below the conservative modelled values (e.g. ͌7,500 mg/L for sulphate
within the first 100 days) for the mine void recharge model.
Overall, the results continue to demonstrate that groundwater reintroduction into the mine void has been
successful in mitigating the potential effects of AMD to date. Mine void recharge water level against recorded
pH has been included in Figure 2. Monitoring will continue throughout the Care and Maintenance phase, as
well as the Closure phase.
All groundwater modelling reports, including the most recent mine void recharge model recalibration, have
been submitted to DSD for review as part of the Care and Maintenance and Closure Plan requirements, and
the resubmitted AZM Annual Compliance Report.
Frequent groundwater monitoring of the mine void and nearby bores confirms a cone of depression remains,
Bore DH3 is ͌1.7m metre higher than the water level at the portal. A conceptual schematic of the standing
water level surrounding the mine void is shown in Figure 3. This aligns with the requirements outlined in
Australian Groundwater Technologies Groundwater Closure Plan (Appendix A, Care and Maintenance Plan).
6
Figure 1 Location of DH2, DH3, the 140 RL Pastefill line and the mine drives
7
Figure 2 Mine void level and pH
200
180 170
130
102 89 88 85
75 72 71 65
46.62
6.95
6.44
7.1
6.58 6.66 6.47
7.78 8.23
6.2
6.71 6.74
6.13
6.71 6.52
7.43
5.9
0
1
2
3
4
5
6
7
8
90
50
100
150
200
250
pH
RL
Mine Void level v pH
RL pH
8
Figure 3 Mine portal, void, pastefill 140 line and DH3 cross section (diagrams conceptual only, not to scale, aerial picture from 2009)
9
Figure 4 Plume migration - Oxidisation of mine void walls, Source SO4 conc. = 5500 mg/L
10
2. SURFACE WATER
Quarter 3 surface water testing was undertaken at the Angas River, upstream at Croser and Downstream at
Hogben (Appendix B). The t-test indicates whether the samples are significantly different from each other (that
is, the p-value is lower than the t-value, which results in a rejected hypothesis that there is an impact), the
results from this test indicate variation of mean values of the samples taken at Croser (downstream) compared
to the upstream sample area at Hogben. Metals which recorded results under detectable limits included
arsenic, cadmium and selenium, as well as total phosphorus. As there is no mining activity and no water flows
from operating areas on site, it would be prudent to recognise that these results indicate the natural variation
in the Angas river.
Quarter 3 surface water monitoring results revealed no significant difference between the two sites.
Stormwater runoff was monitored over the quarter, with no opportunity to obtain any samples. Over the
quarter, Strathalbyn received 108.8mm of precipitation, while the average rainfall for the same period
obtained for the Bureau of Statistics is 177.3mm. There were no single events recording over 15mm of rainfall
over a 24 hour period. No rain events through the quarter generated water leaving site through the three
observation sites. Resultantly, Burnside Creek did not receive any overflow from the STEDS area, and thus
turbidity monitoring was not required at the Angas River.
Water was observed entering the main AZM driveway drains on the 12th
August 2015, but not at a deep
enough flow to gain a useful sample.
11
Table 1: Surface water assay results and t-test values
Site Units
Croser 1
Croser 2
Croser 3
Mean Croser
Hogben 1
Hogben 2
Hogben 3
Mean Hogben p-value t-value
pH pH 7.92 7.94 7.95 7.94 7.84 7.74 7.72 7.77 0.07 4.30
EC-L us/cm 3100 3050 3020 3057 3110 3100 3110 3107 0.16 4.30
TDS-180 mg/L 1630 1630 1660 1640 1660 1640 1690 1663 0.07 4.30
Turbidity NTU 4 3.6 3.1 3.6 32.8 120 5.1 52.6 0.29 4.30
SO4-D mg/L 78 82 80 80 81 79 81 80 0.87 4.30
As-T mg/L 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 Under detectable limits
Cd-T mg/L 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 Under detectable limits
Cu-T mg/L 0.002 0.015 0.001 0.006 0.002 0.002 0.001 0.002 0.42 4.30
Pb-T mg/L 0.005 0.008 0.001 0.005 0.001 0.002 0.001 0.001 0.20 4.30
Zn-T mg/L 0.048 0.145 0.01 0.068 0.012 0.025 0.007 0.015 0.27 4.30
Mn-T mg/L 0.019 0.012 0.02 0.017 0.031 0.02 0.022 0.024 0.13 4.30
Se-T mg/L 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 Under detectable limits
Fe-T mg/L 0.42 0.22 0.25 0.30 0.42 0.32 0.3 0.35 0.23 4.30
NOX-N mg/L 0.16 0.17 0.16 0.16 0.16 0.17 0.01 0.11 0.42 4.30
TKN-N mg/L 0.2 0.2 0.1 0.2 0.2 0.2 0.2 0.2 0.42 4.30
N-T mg/L 0.4 0.4 0.3 0.4 0.4 0.4 0.2 0.3 0.42 4.30
P-T mg/L 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 Under detectable limits
____ Under detection limits
12
3. GROUNDWATER
The environmental monitoring plan outlined in the Care and Maintenance Plan for Angas Zinc Mine requires,
where access is possible, quarterly monitoring of RG1, RG2, RG3, RG4 and RG8. The weekly water level
monitoring of DH2 for three months after water has been detected in the well has been completed, however,
regular monitoring of DH2, DH3 and the 140 RL Pastefill line has continued throughout the quarter.
Measurements undertaken in July for the quarter demonstrate a continuity of the patterns of most
parameters from previous quarters in RG1, RG4 and RG8, and are all significantly within leading indicator limits
and thus also PEPR compliance limits. RG5 and RG6 remain void of water.
All water levels remained within PEPR criteria and below the leading indicator levels. RG1, RG4 and RG8 did
not exceed the drawdown beyond a one-metre band of 2006 levels, which is shown in Figure 5 below. Land
access was not available for RG2 and RG3.
Since water was detected in DH2 in June 2014, the standing water level has risen in line with the mine void and
presently stands 25.95 m below surface, measured from the bore collar, on the 28th
of September (Figure 3).
The recently recalibrated groundwater model for the mine void recharge has been discussed above, in section
1: Mining and Mine Void Acid and Metalliferous Drainage.
As mentioned in section 1, the full suite of results has been reviewed by Australian Groundwater Technologies
to update the mine void groundwater model, and was submitted to DSD for review as part of the Care and
Maintenance and Closure Plan requirements, and the resubmitted AZM Annual Compliance Report.
Figure 5 Standing Water Levels
0
5
10
15
20
25
30
35
Jan
-13
Feb
-13
Mar
-13
Ap
r-1
3
May
-13
Jun
-13
Jul-
13
Oct
-13
Jan
-1
4
Ap
ril-
14
Au
g-1
4
Oct
-14
Jan
-15
Mar
-15
Ap
r-1
5
Jul-
15
met
res
bel
ow
gro
un
d le
vel
Standing Water Levels
RG1 RG1 PEPR criteria RG4 RG4 PEPR Criteria RG8 RG8 PEPR Criteria
13
4. NOISE
As outlined in the Care and Maintenance addendum to the PEPR (approved March 2015), noise monitoring has
ceased through the Care and Maintenance phase. There were no noise related complaints received
throughout the quarter.
5. PUBLIC HEALTH AND NUISANCE
Terramin installed a new High Volume Sampler (HVS) at the beginning of September 2014. The HVS measures
lead, TSP and PM10 levels over a 24 hour period every three days. In addition to the HVS, twelve Dust
Deposition Gauges (DDGs) remain installed both onsite and offsite and sampled monthly for Total Insoluble
Matter (TIM) and lead. Locations of all dust monitors can be seen in Appendix F. All leading indicators and
compliance limits remain as per the PEPR requirements.
DUST DEPOSITION GAUGES
Total Insoluble Matter remained under the NSW best practice guidelines of 4g/m2/month (leading indicator
criteria) for all gauges for the quarter, with the exception of DDG2 in September, and DDG12 in July and
August. DDG2 is located to the north-east of the ML in the adjoining landfill facility and as previously
identified, DDG12 is located in an agricultural field and routinely experiences higher dust levels due to
agricultural activities. As there were no mining activities undertaken throughout quarter 3, this dust deposition
has likely emanated from regional agricultural activities and not related to site.
Both off and on-site lead deposition gauges continued to be below the leading indicator limits at all DDGs
(Appendix G), with the exception of DDG3 in July. A slight increase can be observed in the majority of gauges,
as can be expected with the dryer weather. DDG3 is located offsite, to the west of the ML, adjacent to an
agricultural field and STEDS ponds. It frequently experiences higher dust levels, due to the agricultural
activities undertaken next to it. The soil contamination baseline study undertaken by Tonkin in 2005 showed
elevated metal levels at 23 sampling points of 58 in the region. Upon analysis of the report’s lead occurrences
map, frequent instances of elevated lead levels can be observed, north of the STEDS pond area, which is north-
east of DDG3, as can be seen in Figure 6. A more thorough metals analysis of the regional soil was undertaken
by Terramin geologists in 2009, with similar results obtained, shown by purple and red symbols, when
compared to 2005 levels (Figure 7).
As lead levels have remained at typical levels recorded throughout care and maintenance at all other DDGs
and with no mining, surface loading or crushing and processing activities occurring on ML6229 throughout the
quarter, it is unlikely the deposition at DDG3 is linked to AZM activities. As agricultural activities have been
undertaken in the fields to the north of the gauge throughout the quarter, it is possible the lead content found
in the dust is linked to these activities.
Supporting this hypothesis is the analysis of the average wind speed and direction from the onsite weather
station for the ML for July. Wind direction was most commonly observed as travelling in a south-south-
westerly direction for July, on average between 213 and 235 degrees, while wind speeds were on average
between 12 and 29km/hr for the month. Resultantly, lead dust is unlikely to have emanated from the TSF, as
there were no unusual instances of lead over the quarter observed at onsite DDGs 8, 6, 4, 5, 7 or 9, or
recorded by the high volume sampler.
14
Figure 6 Results of baseline soil investigation undertaken by Tonkin in 2005
15
Figure 7 Results of soil investigation undertaken by Terramin in 2009
16
HIGH VOLUME SAMPLER
Throughout the quarter there has been no instance of particulate lead, PM10 or TSP levels above the PEPR
criteria (Appendix H).
17
6. WASTE DISPOSAL AND HAZARDOUS SUBSTANCES
There was no waste removed from site throughout the quarter.
7. TSF WATER / ACID MINE DRAINAGE
TSF DECANT POND
The Reduced Level (RL) of the TSF decant pond was 68.23 m RL on the 30th
of September, details in Appendix I.
As the tailings dam has filled with tailings over time, the water level (RL) has ceased to be a relevant measure
of compliance. Terramin will focus on maintaining the TSF decant surface area below 15,000m2.
In 2012, the criteria was confirmed by DSD that “RL will be measured until the 15,000m2 area is reached and
from then, all monitoring will be based on water surface area”.
The criteria is described as below:
Reduced Level (RL) indicators on the external wall (Stair side) of the TSF decant chute is read monthly to
ensure that the TSF maintains adequate capacity to manage a 1:1000 year storm event. The TSF is
managed to ensure the following decant pond RL (m) are not exceeded if the surface area is less than
15,000m2:
74.8 as of Dec 2012
74.8 as of June 2013
74.7 as of Dec 2013
74.6 as of June 2014
74.5 as of Dec 2014
74.2 as of June 2015
Thus, the TSF decant pond RL of 68.23m remains within compliance limits.
TSF SEEPAGE DRAIN FLOWS
The seepage drain flows in the TSF have remained significantly lower when compared to the mine being
operational. This pattern can be expected to continue while AZM remains in Care and Maintenance and the
TSF water volumes are low. Figure 8 presents the seepage drain flows through the Care and Maintenance
phase to date, significantly lower than throughout the operational phase (Appendix I). The highest seepage
flow rate for the quarter was approximately 2.3L/min, observed in August 2015, while drains 3, 4 and 5
continue to have no flow.
18
Figure 8 Seepage drain flows through Care and Maintenance
TSF SURFACE AREA
Visual estimation of the TSF surface area was undertaken on the 30th
September with use of set sight lines and
is calculated to be approximately 11,000m2. The surface area of the TSF decant pond remains below the
compliance limit of 15,000m2. The surface area has increased throughout the winter period due to rainfall,
however, is expected to decrease as the seasons move through to spring and summer. The surveyed TSF plan
has been included in Appendix M.
TSF GROUNDWATER MONITORING BORES
TSF bores were sampled and analysed monthly through quarter 3.
All parameters were within ranges typically recorded since operations began and remain significantly within
Leading Indicator limits.
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
10
/10
/13
10
/11
/13
10
/12
/13
10
/01
/14
10
/02
/14
10
/03
/14
10
/04
/14
10
/05
/14
10
/06
/14
10
/07
/14
10
/08
/14
10
/09
/14
10
/10
/14
10
/11
/14
10
/12
/14
10
/01
/15
10
/02
/15
10
/03
/15
10
/04
/15
10
/05
/15
10
/06
/15
10
/07
/15
10
/08
/15
10
/09
/15
Drain 1 Drain 2 Drain 3 Drain 4 Drain 5 Total Flow (L/min)
19
TSF PAF TESTWORK RESULTS
The acid testwork on the tailings dam surface advised by O’Kane Consultants (Review of Terramin’s AZM
MCMP, 2013) was undertaken on the 19th
June 2015. The methodology requires a 2:1 paste to be made from
the tailings with either distilled water (pH(field)) or hydrogen peroxide (pH(fox)) and a pH reading taken after
any reactions have taken place. Specifically, the procedure provides:
A core of tailings material to be taken from settled tailings;
Samples required from the top 100mm and bottom 700mm of the core;
Any rainfall in the days prior to sampling to be recorded;
Monitor the locations every quarter for the first year post operations and every six months
thereafter;
Provide all data in a spreadsheet to DSD upon completion of each monitoring round.
The testwork is covered by an Occupational Health and Safety risk assessment and an approved Job Hazard
Analysis is in place to ensure sampling is conducted safely. Only locations which can safely be accessed are
included in each monitoring round.
O’Kane advised quarterly testwork for the initial 12 months, and on the basis of the results have now revised
the testwork regularity to be completed biannually, thus no PAF testwork was undertaken this quarter. The
testwork will be undertaken again in December 2015.
8. WEEDS AND PESTS
A weed and pest survey was undertaken in July and demonstrated an overall continued decrease in the
occurrence of declared weeds onsite. The report has been included in Appendix L.
Fuel load reduction works continued to be undertaken to reduce the risk of bushfire during summer. Weed
spraying has been undertaken as weather conditions permit, as well as slashing and brush-cutting where
required.
9. COMMUNITY ENGAGEMENT
STRATHALBYN COMMUNITY CONSULTATION COMMITTEE (SCCC)
Terms of Reference
Terramin have continued to work with the SCCC and the DSD to tailor and finalise the Terms of Reference for
the SCCC. This was completed at a workshop at Angas Zinc Mine in September with the agreed sub-committee,
Terramin Chief Executive Officer Martin Janes, DSD Director of Mining Regulation Greg Marshall and SCCC
members Anne Woolford and Mike Farrier. The Terms of Reference have been finalised and approved by the
SCCC. A copy can be found on Terramin’s website at: http://www.terramin.com.au/community/angas-zinc-
mine-community/.
Chairperson
The same committee have met on numerous occasions over the quarter to finalise a new chairperson for the
SCCC. We are pleased to welcome Kelvin Trimper to the position. Kelvin has been involved in developing and
implementing some of South Australia’s most complex community development projects, which have required
building relationships between both local and state governments and the private sector. The sub-committee is
20
confident that Kelvin has the skills, experience and knowledge to chair the SCCC and look forward to his
involvement in the coming years.
COMPLAINTS REGISTER
There were no complaints received through Terramin’s hotline or lodged with the Environmental and
Community Superintendent throughout Q3 of 2015.
10. ADDITIONAL INFORMATION
The Environment and Geology teams at Terramin have been hosting an Environmental Policy and
Management student from the University of Adelaide and five geology students from TAFE SA over the
preceding quarter.
Environment and Community Superintendent Matt Daniel with University of Adelaide student Dylan Edwards sampling soils in the
Boxcut at AZM
Dylan Edwards from the University of Adelaide has been competing his final year studies on the long-term
erodibility of the soils located in the Boxcut at AZM, which will form part of the fill once the Boxcut has been
re-contoured in the rehabilitation phase pre-closure. This work was requested as part of the DSD’s feedback
presented on the Mine Closure Plan (MCP) submitted in December 2014. Dylan has almost finished his time
with us and we wish him well in the future.
Terramin continue to work on the Mine Closure Plan, specifically to address the feedback received in May
2015 from the DSD and DEWNR. A second workshop with government regulators, their consultants, Terramin
and Terramin’s consultants to review the Failure Mode Effect Analysis (FMEA) risk assessment was undertaken
21
in October 2015. The original FMEA workshop was undertaken in June 2012. This second workshop addressed
the outstanding issues in the Closure Plan, and re-risked identified hazards against the work Terramin has
completed in the preceding three years.
11. SUMMARY
Angas Zinc Mine continued to be maintained through the Care and Maintenance period:
The process plant, including crusher, mill and floatation areas, received regular maintenance;
Hillgrove staff remained onsite 1-2 days per week to load lime;
Onsite water management of the TSF and mine void continued;
Onsite surveying of weeds, visual amenity, seed collection;
The continuation of the Environmental Monitoring Plan;
Terramin continue to work with the DSD to progress the Mine Closure Plan in line with the most recent FMEA
workshop, towards its next submission.
12. REFERENCES
AECOM. Dust Deposition Limit Determination: PEPR Compliance Report. Adelaide, Australia. September 2012.
ATC Williams. Tailings Storage Facility Angas Zinc Mine, Operation and Maintenance Manual: Version 2.
Melbourne, Australia. May 2010.
Australian Groundwater Technologies. Groundwater Model Recalibration for the Angas Zinc Mine Closure and
Completion Plan. Adelaide, South Australia. May 2015.
22
13. APPENDIX A – ANGAS ZINC MINE – FILLED AND UNFILLED VOIDS
23
14. APPENDIX B – WATER MONITORING LOCATIONS
DH3
24
15. APPENDIX C – SURFACE WATER MONITORING DATA
Site Units
Croser 1
Croser 2
Croser 3
Mean Croser
Hogben 1
Hogben 2
Hogben 3
Mean Hogben p-value t-value
pH pH 7.92 7.94 7.95 7.94 7.84 7.74 7.72 7.77 0.065595493 4.30265273
EC-L us/cm 3100 3050 3020 3057 3110 3100 3110 3107 0.162781642 4.30265273
TDS-180 mg/L 1630 1630 1660 1640 1660 1640 1690 1663 0.07282735 4.30265273
Turbidity NTU 4 3.6 3.1 3.6 32.8 120 5.1 52.6 0.291350474 4.30265273
SO4-D mg/L 78 82 80 80 81 79 81 80 0.867546764 4.30265273
As-T mg/L 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 Under detectable limits
Cd-T mg/L 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 Under detectable limits
Cu-T mg/L 0.002 0.015 0.001 0.006 0.002 0.002 0.001 0.002 0.422649731 4.30265273
Pb-T mg/L 0.005 0.008 0.001 0.005 0.001 0.002 0.001 0.001 0.199359231 4.30265273
Zn-T mg/L 0.048 0.145 0.01 0.068 0.012 0.025 0.007 0.015 0.267483306 4.30265273
Mn-T mg/L 0.019 0.012 0.02 0.017 0.031 0.02 0.022 0.024 0.127643256 4.30265273
Se-T mg/L 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 Under detectable limits
Fe-T mg/L 0.42 0.22 0.25 0.30 0.42 0.32 0.3 0.35 0.225403331 4.30265273
NOX-N mg/L 0.16 0.17 0.16 0.16 0.16 0.17 0.01 0.11 0.422649731 4.30265273
TKN-N mg/L 0.2 0.2 0.1 0.2 0.2 0.2 0.2 0.2 0.422649731 4.30265273
N-T mg/L 0.4 0.4 0.3 0.4 0.4 0.4 0.2 0.3 0.422649731 4.30265273
P-T mg/L 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 Under detectable limits
____ Under detection limits
25
16. APPENDIX D – GROUNDWATER MONITORING DATA
5.50
6.00
6.50
7.00
7.50
8.00
8.50
9.00Ja
n-1
4
Feb
-14
Mar
-14
Ap
r-1
4
May
-14
Jun
-14
Jul-
14
Au
g-1
4
Sep
-14
Oct
-14
No
v-1
4
Dec
-14
Jan
-15
Feb
-15
Mar
-15
Ap
r-1
5
May
-15
Jun
-15
Jul-
15
pH
RG1 RG4 RG8 PEPR Criteria Leading indicator
pH
0
10000
20000
30000
40000
50000
60000
70000
80000
Jan
-14
Ap
r-1
4
Au
g-1
4
Oct
-14
Jan
-15
Ap
r-1
5
Jul-
15
EC (
us/
cm)
EC
RG1 RG4 RG8 PEPR Criteria Leading Indicator
26
0
0.01
0.02
0.03
0.04
0.05
0.06
0.07
0.08
0.09
0.1
Jan
-14
Ap
r-1
4
Au
g-1
4
Oct
-14
Jan
-15
Ap
r-1
5
Jul-
15
Arsenic
RG1 RG4 RG8 PEPR Criteria Leading Indicator
As
(m
g/L)
0.0000
0.0020
0.0040
0.0060
0.0080
0.0100
0.0120
Jan
-14
Ap
r-1
4
Au
g-1
4
Oct
-14
Jan
-15
Ap
r-1
5
Jul-
15
Cadmium
RG1 RG4 RG8 PEPR Criteria Leading Indicator
Cd
(m
g/L)
27
0
0.2
0.4
0.6
0.8
1
1.2
1.4
Jan
-14
Feb
-14
Mar
-14
Ap
r-1
4
May
-14
Jun
-14
Jul-
14
Au
g-1
4
Sep
-14
Oct
-14
No
v-1
4
De
c-1
4
Jan
-15
Feb
-15
Mar
-15
Ap
r-1
5
May
-15
Jun
-15
Jul-
15
Pb
(m
g/L)
Lead
RG1 RG4 RG8 PEPR Criteria Leading Indicator
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
5.00
Jan
-14
Feb
-14
Mar
-14
Ap
r-1
4
May
-14
Jun
-14
Jul-
14
Au
g-1
4
Sep
-14
Oct
-14
No
v-1
4
De
c-1
4
Jan
-15
Feb
-15
Mar
-15
Ap
r-1
5
May
-15
Jun
-15
Jul-
15
Zinc
RG1 RG4 RG8 PEPR Criteria Leading indictor
Zin
c (m
g/L)
28
0
0.02
0.04
0.06
0.08
0.1
0.12
0.14
Jan
-14
Ap
r-1
4
Au
g-1
4
Oct
-14
Jan
-15
Ap
r-1
5
Jul-
15
Se (
mg/
L)
Se
RG1 RG4 RG8 Leading Indicator PEPR Criteria
0
50
100
150
200
250
Jan
-14
Ap
r-1
4
Au
g-1
4
Oct
-14
Jan
-15
Ap
r-1
5
Jul-
15
Iron
RG1 RG4 RG8 PEPR Criteria Leading Indicator
Fe (
mg/
L)
29
GROUNDWATER QUALITY RAW DATA
Date Criteria Leading
Indicator
Jul-15
Site Units RG1 RG4 RG8
pH pH 8.70 8.15 7.43 7.45 7.17
EC-L uS/cm 68500 53670 12100 11100 32100
TDS mg/L 25000 24843 6430 6070 19300
As-T mg/L 0.090 0.038 0.002 0.002 0.005
Cd-T mg/L 0.0100 0.004 0.0001 0.0002 0.0004
Pb-T mg/L 0.820 0.262 0.006 0.002 0.046
Zn-T mg/L 4.400 1.704 0.018 0.005 0.248
Se-T mg/L 0.130 0.088 0.03 0.03 0.01
Fe-T mg/L 232.00 69.02 3.1 0.05 59.9
30
17. APPENDIX E – GROUNDWATER STANDING WATER LEVELS
0
5
10
15
20
25
30
35
Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Oct-13 Jan -14 April-14 Aug-14 Oct-14 Jan-15 Mar-15 Apr-15 Jul-15
met
res
bel
ow
gro
un
d le
vel
Standing Water Levels
RG1 RG1 PEPR criteria RG4 RG4 PEPR Criteria RG8 RG8 PEPR Criteria
31
18. APPENDIX F – DUST MONITORING LOCATIONS
32
19. APPENDIX G – DUST LEADING INDICATOR DATA – DUST DEPOSITION GAUGES
TOTAL INSOLUBLE MATTER
0
5
10
15
20
25
30
35
7 5 4 2 8 1 6 9 11 3 12 10
g/m
2.m
on
th
Gauge number
Total Insoluable Matter
Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 *Leading Indictor
33
OFFSITE LEAD MEASUREMENTS
ONSITE LEAD MEASUREMENTS
0
50
100
150
200
250
Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15
Lead
de
po
siti
on
(m
g/kg
)
Offsite Lead Measurements
Leading Indicator 2 3 10 11 12
34
0
100
200
300
400
500
600
700
800
Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15
Lead
de
po
siti
on
(m
g/kg
Onsite Lead Measurements
Leading Indicator 1 4 5 6 7 8 9
35
20. APPENDIX H - DUST LEADING INDICATOR DATA – HIVOL
TOTAL SOLID PARTICULATE MEASUREMENTS
0
20
40
60
80
100
120
140
6/0
1/2
01
5
13
/01
/20
15
20
/01
/20
15
27
/01
/20
15
3/0
2/2
01
5
10
/02
/20
15
17
/02
/20
15
24
/02
/20
15
3/0
3/2
01
5
10
/03
/20
15
17
/03
/20
15
24
/03
/20
15
31
/03
/20
15
7/0
4/2
01
5
14
/04
/20
15
21
/04
/20
15
28
/04
/20
15
5/0
5/2
01
5
12
/05
/20
15
19
/05
/20
15
26
/05
/20
15
2/0
6/2
01
5
9/0
6/2
01
5
16
/06
/20
15
23
/06
/20
15
30
/06
/20
15
7/0
7/2
01
5
14
/07
/20
15
21
/07
/20
15
28
/07
/20
15
4/0
8/2
01
5
11
/08
/20
15
18
/08
/20
15
25
/08
/20
15
1/0
9/2
01
5
8/0
9/2
01
5
15
/09
/20
15
22
/09
/20
15
Total Solid Particulates (Hi-Vol)
PEPR Criteria Northern Unit
36
PM10 MEASUREMENTS
0
10
20
30
40
50
60
1/3
/20
15
1/1
0/2
015
1/1
6/2
015
1/2
2/2
015
1/2
8/2
015
2/3
/20
15
2/9
/20
15
2/1
5/2
015
2/2
4/2
015
3/2
/20
15
3/5
/20
15
3/1
1/2
015
3/1
7/2
015
3/2
3/2
015
3/2
9/2
015
4/4
/20
15
4/1
0/2
015
4/1
6/2
015
4/2
2/2
015
4/2
8/2
015
5/4
/20
15
5/1
0/2
015
5/1
6/2
015
5/2
2/2
015
5/2
8/2
015
6/3
/20
15
6/9
/20
15
6/1
5/2
015
6/2
1/2
015
6/2
7/2
015
7/3
/20
15
7/9
/20
15
7/1
5/2
015
7/2
1/2
015
7/2
7/2
015
8/2
/20
15
8/8
/20
15
8/1
4/2
015
8/2
0/2
015
8/2
6/2
015
9/1
/20
15
9/7
/20
15
9/1
3/2
015
9/1
9/2
015
9/2
5/2
015
10
/1/2
015
PM
10 (
ug
/m3)
PM10(Hi-Vol)
PEPR Criteria Pm10 ug/m3
37
LEAD MEASUREMENTS
0
0.1
0.2
0.3
0.4
0.5
0.6
3/0
1/2
01
5
10
/01
/20
15
17
/01
/20
15
24
/01
/20
15
31
/01
/20
15
7/0
2/2
01
5
14
/02
/20
15
21
/02
/20
15
28
/02
/20
15
7/0
3/2
01
5
14
/03
/20
15
21
/03
/20
15
28
/03
/20
15
4/0
4/2
01
5
11
/04
/20
15
18
/04
/20
15
25
/04
/20
15
2/0
5/2
01
5
9/0
5/2
01
5
16
/05
/20
15
23
/05
/20
15
30
/05
/20
15
6/0
6/2
01
5
13
/06
/20
15
20
/06
/20
15
27
/06
/20
15
4/0
7/2
01
5
11
/07
/20
15
18
/07
/20
15
25
/07
/20
15
1/0
8/2
01
5
8/0
8/2
01
5
15
/08
/20
15
22
/08
/20
15
29
/08
/20
15
5/0
9/2
01
5
12
/09
/20
15
19
/09
/20
15
26
/09
/20
15
Lead
de
po
siti
on
(u
g/m
3)
Lead (Hi-Vol)
EPA Early Indicator Report Limit PEPR criteria Northern Unit
38
21. APPENDIX I – TSF
DECANT POND RL OVER TIME
66.00
67.00
68.00
69.00
70.00
71.00
72.00
73.00
74.00
75.00
76.00
10.0
20.0
30.0
40.0
50.0
60.0
3/0
2/2
010
3/0
3/2
010
3/0
4/2
010
3/0
5/2
010
3/0
6/2
010
3/0
7/2
010
3/0
8/2
010
3/0
9/2
010
3/1
0/2
010
3/1
1/2
010
3/1
2/2
010
3/0
1/2
011
3/0
2/2
011
3/0
3/2
011
3/0
4/2
011
3/0
5/2
011
3/0
6/2
011
3/0
7/2
011
3/0
8/2
011
3/0
9/2
011
3/1
0/2
011
3/1
1/2
011
3/1
2/2
011
3/0
1/2
012
3/0
2/2
012
3/0
3/2
012
3/0
4/2
012
3/0
5/2
012
3/0
6/2
012
3/0
7/2
012
3/0
8/2
012
3/0
9/2
012
3/1
0/2
012
3/1
1/2
012
3/1
2/2
012
3/0
1/2
013
3/0
2/2
013
3/0
3/2
013
3/0
4/2
013
3/0
5/2
013
3/0
6/2
013
3/0
7/2
013
3/0
8/2
013
3/0
9/2
013
3/1
0/2
013
3/1
1/2
013
3/1
2/2
013
3/0
1/2
014
3/0
2/2
014
3/0
3/2
014
3/0
4/2
014
3/0
5/2
014
3/0
6/2
014
3/0
7/2
014
3/0
8/2
014
3/0
9/2
014
3/1
0/2
014
3/1
1/2
014
3/1
2/2
014
3/0
1/2
015
3/0
2/2
015
3/0
3/2
015
3/0
4/2
015
3/0
5/2
015
3/0
6/2
015
3/0
7/2
015
3/0
8/2
015
3/0
9/2
015
RL
(m)
Rain
fall (
mm
)
Angas Mine Rainfall Records
Rainfall Actual Water level RL(m) Spillway RL (m) Target RL
39
SEEPAGE DRAIN FLOWS
0
5
10
15
20
25
05
/09
/08
05
/11
/08
05
/01
/09
05
/03
/09
05
/05
/09
05
/07
/09
05
/09
/09
05
/11
/09
05
/01
/10
05
/03
/10
05
/05
/10
05
/07
/10
05
/09
/10
05
/11
/10
05
/01
/11
05
/03
/11
05
/05
/11
05
/07
/11
05
/09
/11
05
/11
/11
05
/01
/12
05
/03
/12
05
/05
/12
05
/07
/12
05
/09
/12
05
/11
/12
05
/01
/13
05
/03
/13
05
/05
/13
05
/07
/13
05
/09
/13
05
/11
/13
05
/01
/14
05
/03
/14
05
/05
/14
05
/07
/14
05
/09
/14
05
/11
/14
05
/01
/15
05
/03
/15
05
/05
/15
05
/07
/15
05
/09
/15
Drain 1 Drain 2 Drain 3 Drain 4 Drain 5 Total Flow (L/min)
40
22. APPENDIX J – TSF MONITORING BORES
5.5
6
6.5
7
7.5
8
8.5Ja
n-1
5
Feb
-15
Mar
-15
Ap
r-1
5
May
-15
Jun
-15
Jul-
15
Au
g-1
5
Sep
-15
pH
pH
TSFA TSFB TSFD Leading indicator Leading indicator
0
5000
10000
15000
20000
25000
30000
35000
Jan
-15
Feb
-15
Mar
-15
Ap
r-1
5
May
-15
Jun
-15
Jul-
15
Au
g-1
5
Sep
-15
EC (
uS/
cm)
EC
TSFA TSFB TSFD Leading Indicator
41
TSF B has recorded cadmium under detection limits since January 2010
0
0.005
0.01
0.015
0.02
0.025
0.03
0.035
Jan
-15
Feb
-15
Mar
-15
Ap
r-1
5
May
-15
Jun
-15
Jul-
15
Au
g-1
5
Sep
-15
As
(mg/
L)
Arsenic
TSFA TSFB TSFD Leading Indicator
0
0.002
0.004
0.006
Jan
-15
Feb
-15
Mar
-15
Ap
r-1
5
May
-15
Jun
-15
Jul-
15
Au
g-1
5
Sep
-15
Cd
(m
g/L)
Cadmium
TSFA TSFB TSF D Leading Indicator
42
0
0.05
0.1
0.15
0.2
0.25
0.3
0.35
Jan
-15
Feb
-15
Mar
-15
Ap
r-1
5
May
-15
Jun
-15
Jul-
15
Au
g-1
5
Sep
-15
Pb
(m
g/L)
Lead
TSFA Pb TSFB TSF D Leading Indicator
0
0.5
1
1.5
2
2.5
3
3.5
Jan
-15
Feb
-15
Mar
-15
Ap
r-1
5
May
-15
Jun
-15
Jul-
15
Au
g-1
5
Sep
-15
Zinc
TSFA TSFB TSF D Leading Indicator
Zn (
mg/
L)
43
0
0.2
0.4
0.6
0.8
1
1.2
Jan
-15
Feb
-15
Mar
-15
Ap
r-1
5
May
-15
Jun
-15
Jul-
15
Au
g-1
5
Sep
-15
Mn
(m
g/L)
Manganese
TSFA TSFB TSFC TSFD
0
0.5
1
1.5
2
2.5
0
20
40
60
80
100
120
140
160
180
200
Jan
-15
Feb
-15
Mar
-15
Ap
r-1
5
May
-15
Jun
-15
Jul-
15
Au
g-1
5
Sep
-15
Fe (
mg/
L)
Iron
TSFB TSFD Leading Indicator TSFA
44
23. APPENDIX K – TSF SEEPAGE DRAINS
45
24. APPENDIX L – WEED AND PEST SURVEY 2015
TERRAMINAUSTRALIALIMITED
AngasZincMineWeedandPestSurvey
July 2015
Angas Zinc Mine Weed and Pest Survey July 2015
1
1 Introduction
The 2015 approved Care and Maintenance Plan requires an annual winter weed and pest survey, to
demonstrate that the site continues to decrease in weeds and pests from previous surveys
conducted in the same season. This survey was conducted by Terramin environmental staff in July
2015, with the results in the report compared to the survey undertaken in the July 2014 winter
survey.
Upon review of the 2014 winter weed and pest survey, it was noted that general environmental
weeds, which are not declared under the Natural Resources Management Act 2004 (SA) were
treated as declared weeds in the 2014 report. Strictly speaking this is incorrect and subsequently
resulted in an unusually high percentage of declared weeds versus non‐declared plants and bare
ground/litter in the report. The graphs in this report have been updated in order to rectify this error
and reflect the extent of weeds present onsite. In January of 2015, the Department of Environment,
Water and Natural Resources updated the “declared weeds” status to include 24 new species, and
alter the status of a further 22 species previous declared, including Onion Weed, which is now not
listed in the Act as requiring action. Onion Weed was listed up until 2015 and was included in the
2014 survey as declared.
2 Methodology
Seven step‐point monitoring transects have previously been established within the mining lease
(Appendix 1). GPS co‐ordinates and location descriptions for each site are documented in Table 1.
Step‐point monitoring allows the comparison of relative abundance of weeds and native plants as
well as pest activity over time within each transect area. Repeating step point transects annually
using the same locations and the same number of steps per transect allows direct, simple
comparisons of weed abundance over time to be made. Photo monitoring also allows comparison of
vegetation changes over time (Photos 1‐14).
The step‐point monitoring procedure is as follows;
1. Photo documentation of start point of transect
2. Step out entire transect proceeding in the direction of the end point, doing the same
number of steps as was done the previous year
3. At completion of each right stride, record the species underfoot (declared weed, introduced
plant or native)
4. Pest activity around each area can be observed and noted. Observations can include shells,
droppings, burrows etc.
Table 1: Location and GPS co‐ordinates of step‐point transects
Transect Number
Location Description GPS Co‐ordinates
Start Point End Point
1 Western Paddock 0310427,6096588 South‐west
Angas Zinc Mine Weed and Pest Survey July 2015
2
2 STEDS wetland 310639,6097353 310443,6097305
3 Visitors viewing area 310589, 6097165 310774, 6097244
4 North west of exploration house 310334,6096563 310341, 6096702
5 Front entrance 310412, 6097083 310301, 6097013
6 South of the Magazine, along fence line 311220, 6096477 310991,6096454
7 Eastern paddock 311219,6096493 311392,6096513
Weeds are defined as any plant that is declared under the Natural Resources Management Act 2004
(SA) in South Australia. Natives and introduced plants are described as ‘other plants’ in this report. It
is acknowledged that some ‘other plants’ includes agricultural species (e.g. a grain crop plant) or an
introduced plant that is not a declared weed but is potentially a nuisance to biodiversity.
Angas Zinc Mine Weed and Pest Survey July 2015
3
3 Discussion and Results
Photo documentation of each transect and graphical representations of the survey results have been
included below (photos 1‐14 and figures 1‐7 respectively). To compare against last year’s results, the
number of declared weeds, other plants, bare ground and litter was recorded at each transect and
divided by the number of steps taken to derive a comparable percentage. These results are then
summarised below in each transect section. A summary of the weed and pest survey is located in
Section 4.
3.1 Transect 1
Transect 1 is located in the northern half of the Western SEB area (Appendix A).
The trend in the increasing abundance of non‐declared plants has continued from 2014 into 2015,
with an increase from 68% to 92%. There has been a substantial increase in grass covering the site,
from 5% to 44%, while the proportion of sow thistles (Sonchus oleraceus) has remained constant
( ͌36%). Significantly, there was no sightings of Black Nightshade (Salanum nigrum) or Horehound
(Marrubium vulgare) within the transect, when compared to 2014. Notably, the occurrence of bare
ground has decreased dramatically over the last 24 months, from 89% to 8%, which is likely to
contribute to healthy nutrient cycling. Throughout the year, there have been observances of
kangaroos in the western SEB area.
Photo 1: Transect 1 – Western Paddock 2014 Photo 2: Transect 1 – Western Paddock 2015
Angas Zinc Mine Weed and Pest Survey July 2015
4
Figure 1: Comparisons of transect 1 results between winter surveys of 2014 and 2015
3.2 Transect 2
Transect 2 located in the STEDS wetland continued to have no declared weeds present throughout
the transect. The most significant change in the transect has been the decrease in bare ground, from
47% to 5%, and the emergence of native Saltbush Atriplex sp on the transect. The native wetland
species, Marsh Club‐rush (Bolboschoenus caldwellii) continues to thrive in the area. Rabbit faeces
were also observed along the transect.
Photo 3: Transect 2 –STEDS wetland 2014 Photo 4: Transect 2 – STEDS wetland 2015
30 8
68
92
2 0
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
jul‐14 jul‐15
Bare/litter Non‐declared plants Declared weeds
Angas Zinc Mine Weed and Pest Survey July 2015
5
Figure 2: Comparisons of transect 2 (wetlands) results between winter surveys of 2014 and 2015
47 5
53
95
0 0
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
jul‐14 jul‐15
Bare/litter Non‐declared plants Declared weeds
Angas Zinc Mine Weed and Pest Survey July 2015
6
3.3 Transect 3
Transect 3 is located on the eastern side of the entrance, alongside the Visitor’s Viewing area.
Horehound has continued at a steady rate, and as a result of this, will become a focus of weed
spraying in the area in the coming 12 months. There were no occurrences of the declared Skeleton
Weed Chondrilla juncea observed. The continuing trend of decreasing bare ground which has been
seen in the majority of areas continued on transect 3, with a higher percentage of annual and
perennial grasses present. Snails were also observed often along the transect.
Photo 5: Transect 3 – Visitor viewing 2014 Photo 6: Transect 3 – Visitor viewing 2015
59 27
13
44
28 29
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
jul‐14 jul‐15
Bare/litter Non‐declared plants Declared weeds
Angas Zinc Mine Weed and Pest Survey July 2015
7
Figure 3: Comparisons of transect 3 (visitor viewing area) results between winter surveys of 2014
and 2015
3.4 Transect 4
Transect 4 is located to the north‐west of the AZM exploration and core shed areas. Transect 4 has
shown a steady decrease in declared weeds over the preceding 24 months, from covering 9% of the
transect to 2%. There has been approximately a 33% decrease in observed occurrences of bare
ground. The occurrences of non‐declared plants has increased steadily, largely due to an increase in
annual and perennial grasses, and a significant decrease in the occurrence of marshmallow and non‐
declared thistles.
Photo 7: Transect 4 – Exploration 2014 Photo 8: Transect 4 – Exploration 2015
Figure 4: Comparisons of transect 4 (exploration shed area) results between winter surveys of
2014 and 2015
3.5 Transect 5
Transect 5 is located to the east of the front entrance.
There has been a significant decrease in declared weeds along transect 5, with the focus of
horehound eradication being successful over the preceding 12 months. Transect 5 has seen a
marked increase in the occurrence of bare ground, largely as a result of weed spraying to eradicate
32 19
59
79
9
2
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
jul‐14 jul‐15
Bare/litter Non‐declared plants Declared weeds
Angas Zinc Mine Weed and Pest Survey July 2015
8
horehound in the area. The occurrence and size of native trees has increased since 2014, resulting in
a 7% increase along the transect. In 2014, Transect 5 was completed with 86 steps, however in July
2015, it was decided that rather than cease the survey, a 90° turn would be taken south.
Photo 9: Transect 5 ‐ Front entrance 2014 Photo 10: Transect 5 – Front entrance 2015
Figure 5: Comparisons of transect 5 (front entrance) results between winter surveys of 2014 and
2015
3.6 Transect 6
Transect 6 is located along the south east boundary, to the south of the TSF.
The focus of the preceding 12 months in the area surrounding transect 6 has been the eradication of
Skeleton Weed, with the occurrence of individual plants decreasing from 14 to 1 from 2014 to 2015.
11 39
51
60
24
1
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
jul‐14 jul‐15
Bare/litter Non‐declared plants Declared weeds
Angas Zinc Mine Weed and Pest Survey July 2015
9
There has been a noticeable increase in littered ground along the transect as a result of weed
spraying concentrated on the removal of Skeleton Weed in the area. No evidence of hare, rabbit or
fox populations was observed along the fence line or on the TSF wall, however, ants and their nests
and snails were prevalent.
Photo 11: Transect 6 – Magazine 2014 Photo 12: Transect 6 – Magazine 2015
Figure 6: Comparisons of transect 6 (Magazine) results between winter surveys of 2014 and 2015
5 2481
75
14
1
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
jul‐14 jul‐15
Bare/litter Non‐declared plants Declared weeds
Angas Zinc Mine Weed and Pest Survey July 2015
10
3.7 Transect 7
Transect 7 is located outside the ML, to the south‐west of the eastern SEB area.
Transect 7 has seen a steady trend of soursob inhabit the area, between 36% and 38% between
2014 and 2015, however there has been a decrease in declared weeds, with no occurrences of
Capeweed or Skeleton Weed in the area. The dominance of bare ground has subsided, to the benefit
of annual and perennial grasses, and native Saltbush Atriplex sp.
There is significant evidence of snail populations along Transect 7.
Photo 13: Transect 7 – Eastern Paddock 2014 Photo 14: Transect 7 – Eastern Paddock 2015
Figure 7: Comparisons of transect 7 (eastern paddock) results between winter surveys of 20134
and 2015
41 14
58
86
1 0
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
jul‐14 jul‐15
Bare/litter Non‐declared plants Declared weeds
Angas Zinc Mine Weed and Pest Survey July 2015
11
4 Summary
2015 saw an overall reduction in the occurrences of declared weeds onsite, with no declared weeds
along transects 1, 2 and 7. A slight increase of 1% was observed along transect 3, while transects 4, 5
and 6 recorded significant decreases in declared weeds. The majority of sites have recorded a
decrease in available bare ground, and the two instances of increasing bare ground are a direct
result of focussed weed spraying programs focussing on Horehound and Skeleton Weed. Snails
continue to be observed along many of the transects, while instances of rabbit faeces and scratching
have reduced in comparison to 2014.
The focus of the weed spraying programme for the upcoming 12 months will be largely focussed on
eradicating the Horehound which was observed in Transect 3 and continuing to eradicate any
occurrences of Horehound, Skeleton Weed, Boneseed and Salvation Jade that is known to occur.
The continuation of the annual Visual Amenity photographs in the Significant Environmental Benefit
areas, as well as the front entrance has shown growth in native vegetation, and a reduction in the
available bare ground, as a result of increased annual and perennial grasses.
5 References
Moore G, Sanford P & Wiley T (2006) Perennial pastures for Western Australia, Department of
Agriculture and Food Western Australia, Bulletin 4690, Perth.
Natural Resources Management Act 2004 (SA)
Appendix 1: Step Point Transect Locations
Angas Zinc Mine Weed and Pest Survey July 2015
12
Appendix 2: Declared Plants Identified in the July 2014 Monitoring
Angas Zinc Mine Weed and Pest Survey July 2015
13
Species name Common name
Transects locations July 2015
Marrubium vulgare Horehound 3, 4
Chondrilla juncea Skeleton Weed 5
Appendix 3: Percentage of individual Declared Weed Plants within Transects
Item
Transect 1 Transect 2 Transect 3 Transect 4 Transect 5 Transect 6 Transect 7
jul‐14 jul‐15 jul‐14 jul‐15 jul‐14 jul‐15 jul‐14 jul‐15 jul‐14 jul‐15 jul‐14 jul‐15 jul‐14 jul‐15
Steps recorded 100 100 100 100 100 100 100 100 86 100 100 100 100 100
Non‐declared plants 68 92 53 95 13 44 59 79 51 60 81 76 58 86
Declared weeds 2 0 0 0 28 29 9 2 24 1 14 0 1 0
Bare/litter 30 8 47 5 59 27 32 19 11 39 5 24 41 14
% Declared weed per transect 2.0% 0.0% 0.0% 0.0% 28.0% 29.0% 9.0% 2.0% 27.9% 1.0% 14.0% 0.0% 1.0% 0.0%