Public Meeting of Facility Services Building at Eglinton Station
![Page 2: Public Meeting of Facility Services Building at Eglinton ... · • Crosstown Project Agreements requires CTS to make improvements at Eglinton subway station • TTC has approved](https://reader034.vdocuments.site/reader034/viewer/2022050410/5f872a08f809ec46ca57c72a/html5/thumbnails/2.jpg)
Eglinton Crosstown LRT Project 2
2
• A 19-kilometre route separated from regular traffic • 10-kilometres underground; 9-kilometres at surface in east • 15 underground stations and 10 surface stops • A maintenance and storage facility • Transit communications system • Links to 54 bus routes, 3 subway stations, GO Transit, UP Express station
![Page 3: Public Meeting of Facility Services Building at Eglinton ... · • Crosstown Project Agreements requires CTS to make improvements at Eglinton subway station • TTC has approved](https://reader034.vdocuments.site/reader034/viewer/2022050410/5f872a08f809ec46ca57c72a/html5/thumbnails/3.jpg)
Eglinton LRT Station
Accessible Entrance
![Page 4: Public Meeting of Facility Services Building at Eglinton ... · • Crosstown Project Agreements requires CTS to make improvements at Eglinton subway station • TTC has approved](https://reader034.vdocuments.site/reader034/viewer/2022050410/5f872a08f809ec46ca57c72a/html5/thumbnails/4.jpg)
Eglinton Station – Main Entrance Lobby
![Page 5: Public Meeting of Facility Services Building at Eglinton ... · • Crosstown Project Agreements requires CTS to make improvements at Eglinton subway station • TTC has approved](https://reader034.vdocuments.site/reader034/viewer/2022050410/5f872a08f809ec46ca57c72a/html5/thumbnails/5.jpg)
Eglinton Station – Profile View
LRT Lower Concourse
TTC Subway Platform
LRT Platform
LRT Upper Concourse
![Page 6: Public Meeting of Facility Services Building at Eglinton ... · • Crosstown Project Agreements requires CTS to make improvements at Eglinton subway station • TTC has approved](https://reader034.vdocuments.site/reader034/viewer/2022050410/5f872a08f809ec46ca57c72a/html5/thumbnails/6.jpg)
Eglinton Station - Progress
Completed to Date Demolition of the Salvation Army
Community Church Demolition of the abandoned TTC bus
depot Wet utility relocation at the Yonge-
Eglinton intersection Toronto Hydro relocation along Redpath
Avenue, Duplex Avenue North, east, and west underground
pedestrian tunnel closures Shoring at the Salvation Army site
![Page 7: Public Meeting of Facility Services Building at Eglinton ... · • Crosstown Project Agreements requires CTS to make improvements at Eglinton subway station • TTC has approved](https://reader034.vdocuments.site/reader034/viewer/2022050410/5f872a08f809ec46ca57c72a/html5/thumbnails/7.jpg)
Eglinton Station - Progress
Major 2018 Work • Shoring continues for the
station box and main entrance
• Toronto Hydro relocation
along Hillsdale Avenue, Yonge Street
• New TTC Service Building
at Berwick Portal • Upgrades to subway
station
![Page 8: Public Meeting of Facility Services Building at Eglinton ... · • Crosstown Project Agreements requires CTS to make improvements at Eglinton subway station • TTC has approved](https://reader034.vdocuments.site/reader034/viewer/2022050410/5f872a08f809ec46ca57c72a/html5/thumbnails/8.jpg)
Weekend Subway Closures
• Crosstown Project Agreements requires CTS to make improvements at Eglinton subway station
• TTC has approved 24 closures in 2018 for this work
– Subway will close 2am Saturday mornings and re-open Monday mornings at 5am – Closures necessary because CTS must work on and/or needs access to the
subway tracks and Berwick portal – Work will occur 24 hours a day during the designated weekend closures
• 2018 closures provide benefits to TTC: – Construction of new subway service building – Upgrades/improvements to the subway station
• TTC & CTS coordination to limit overall number of Line 1 closures in 2018: – During 9 of the 24 closures, TTC will undertake states of Good Repair work – 15 out of the 24 Closures will be strictly from St Clair to Lawrence
![Page 9: Public Meeting of Facility Services Building at Eglinton ... · • Crosstown Project Agreements requires CTS to make improvements at Eglinton subway station • TTC has approved](https://reader034.vdocuments.site/reader034/viewer/2022050410/5f872a08f809ec46ca57c72a/html5/thumbnails/9.jpg)
Upgrades/Improvements to Subway Station
• During 2018, weekend closures also facilitate upgrades/improvements to existing subway station: – Smoke evacuation fans – New electrical systems – Improved fire detection systems – New escalators
• Materials and equipment will be delivered on the subway tracks via the
Berwick portal, necessitating the subway closures.
• Additional benefits to TTC/transit users associated with Crosstown construction: – Extension of the subway platform by 25 metres – Upgrading pedestrian tunnels that connect directly to current and future – development
![Page 10: Public Meeting of Facility Services Building at Eglinton ... · • Crosstown Project Agreements requires CTS to make improvements at Eglinton subway station • TTC has approved](https://reader034.vdocuments.site/reader034/viewer/2022050410/5f872a08f809ec46ca57c72a/html5/thumbnails/10.jpg)
New Subway Station Service Building
• Building will be located over the subway tracks at the Berwick portal • Provide improved ventilation and life safety systems for existing subway • Weekend work February – December 2018 • Weekend activities include excavation, shoring and foundation work
![Page 11: Public Meeting of Facility Services Building at Eglinton ... · • Crosstown Project Agreements requires CTS to make improvements at Eglinton subway station • TTC has approved](https://reader034.vdocuments.site/reader034/viewer/2022050410/5f872a08f809ec46ca57c72a/html5/thumbnails/11.jpg)
New Subway Station Service Building
![Page 12: Public Meeting of Facility Services Building at Eglinton ... · • Crosstown Project Agreements requires CTS to make improvements at Eglinton subway station • TTC has approved](https://reader034.vdocuments.site/reader034/viewer/2022050410/5f872a08f809ec46ca57c72a/html5/thumbnails/12.jpg)
New Subway Station Service Building
• Construction of this building is part of larger TTC plan to upgrade ventilation systems on Line 1
![Page 13: Public Meeting of Facility Services Building at Eglinton ... · • Crosstown Project Agreements requires CTS to make improvements at Eglinton subway station • TTC has approved](https://reader034.vdocuments.site/reader034/viewer/2022050410/5f872a08f809ec46ca57c72a/html5/thumbnails/13.jpg)
Description of Construction • Work will occur day and night on each planned subway closure weekend.
• Three basic phases of work planned: micro-piling, pre-cast installation, and material supply and removal work
• Micro-piling phase
– Involves the installation of smaller diameter piles within the TTC subway corridor
– Two micro-pile drill rigs, a mobile crane, and a concrete pump will be used continuously while concrete and steel deliveries will be intermittent. A hydrovac may be required occasionally depending on site conditions.
• Pre-cast Installation
– Involves the delivery and installation of pre-fabricated concrete components
– A mobile crane and various hand tools will be used regularly with intermittent delivery of pre-cast and concrete grout
• Material Supply and Removal
– Parts of Eglinton Station will need to be demolished and re-built. Berwick Portal will be used as the access point for nighttime work within the station
– Construction equipment could involve concrete trucks, mobile cranes, and bin trucks
![Page 14: Public Meeting of Facility Services Building at Eglinton ... · • Crosstown Project Agreements requires CTS to make improvements at Eglinton subway station • TTC has approved](https://reader034.vdocuments.site/reader034/viewer/2022050410/5f872a08f809ec46ca57c72a/html5/thumbnails/14.jpg)
2018 Weekend Subway Closure Schedule
TTC state of good repair closures (9)
TTC state of good repair closures (9)
![Page 15: Public Meeting of Facility Services Building at Eglinton ... · • Crosstown Project Agreements requires CTS to make improvements at Eglinton subway station • TTC has approved](https://reader034.vdocuments.site/reader034/viewer/2022050410/5f872a08f809ec46ca57c72a/html5/thumbnails/15.jpg)
Upcoming Works
*60% rendering
Activity Anticipated Impacts Schedule Interior subway station demolition works
• Work sites on Hillsdale Avenue and Berwick Avenue
• Truck traffic to and from work sites
Feb 10 at 2am -- Feb 13 at 5am
Feb 17 at 2am -- Feb19 at 5am
Feb 24 at 2am -- Feb 26 at 5am
March 3 at 2am – March 5 at 5am
Berwick Avenue Work Site and Truck Routes
Hillsdale Avenue Work Site and Truck Routes
![Page 16: Public Meeting of Facility Services Building at Eglinton ... · • Crosstown Project Agreements requires CTS to make improvements at Eglinton subway station • TTC has approved](https://reader034.vdocuments.site/reader034/viewer/2022050410/5f872a08f809ec46ca57c72a/html5/thumbnails/16.jpg)
Upcoming Works
Activity Anticipated Impacts Schedule Toronto Hydro infrastructure installation
• Work sites on Berwick Avenue in stages as per below
• Pedestrian re-routing • A paid-duty officer will be on duty during
each stage
As early as late February
Approximately 4-6 weeks of work
Regular daytime hours from 7am-11pm
Toronto Hydro infrastructure
works
![Page 17: Public Meeting of Facility Services Building at Eglinton ... · • Crosstown Project Agreements requires CTS to make improvements at Eglinton subway station • TTC has approved](https://reader034.vdocuments.site/reader034/viewer/2022050410/5f872a08f809ec46ca57c72a/html5/thumbnails/17.jpg)
Noise Monitoring and Mitigation
• CTS will be assessing sound levels during construction to ensure noise levels remain within allowable limits and to identify possible mitigation measures for construction activities.
• Noise mitigation measures already planned include: – Continuous and proactive noise monitoring from key locations
adjacent the work site – Acoustic enclosures for pumps and generators – Broadband backup alarms for equipment – Environmental awareness training and toolbox talks for contractors
and employees
![Page 18: Public Meeting of Facility Services Building at Eglinton ... · • Crosstown Project Agreements requires CTS to make improvements at Eglinton subway station • TTC has approved](https://reader034.vdocuments.site/reader034/viewer/2022050410/5f872a08f809ec46ca57c72a/html5/thumbnails/18.jpg)