presentation 25-07-10

Upload: sam-abdul

Post on 10-Feb-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/22/2019 Presentation 25-07-10

    1/23

  • 7/22/2019 Presentation 25-07-10

    2/23

    Foreword Summary

    Transmission System

    Demand Supply Scenario

    Gas Production

    Drilling Program

    Evacuation Needs

    Simulation ResultsEvacuation Options

    Evaluation of Options

    Sector Capabilit ies

    Major Challenges

    Conclusions

    Contents___________________

  • 7/22/2019 Presentation 25-07-10

    3/23

    Foreword________________ PB and its companies are implementing a

    number of projects to improve current gas

    supply situation at the earliest. Among IOCs,Chevron plans to increase BY, JB & MB fieldproductions over the next 3 years.

    Chevrons plan was reviewed by EMRD on23 June 2010. Findings of a simulation exercisedone by PB were also placed in the reviewmeeting.

    A comprehensive gas evacuation plan has nowbeen drawn as directed. Results of the analysiswith particular focus on evacuation ofChevrons additional gas are now presented forreview and decision by EMRD.

  • 7/22/2019 Presentation 25-07-10

    4/23

    A network simulation exercise was done under thesupervision of PB using GTCLs Pi p el i n e St u d i o Software.

    Planned gas production from various fields and

    demand projection (mmscfd) up to Y 2015 wereused as inputs in the exercise:

    New Pipelines required for full evacuation of

    additional gas were identified through carefulexamination/evaluation of options.

    Pipelines include long distance new trunk linesand also loop-lines required for de-bottlenecking of

    existing system, targeted for completion withinnext 2-4 years.

    Summary___________________

    37823412340228222487Production

    37463591334130432520Demand

    20152014201320122011

  • 7/22/2019 Presentation 25-07-10

    5/23

    BKB

    Hub

    CGS

    Demra

    Siddhir-

    ganj

    TFA

    TFA

    Feni GF

    BKB

    BFA

    BFA

    BFA

    20

    30

    LEGEND

    Firm lines: Existing

    Dotted lines: Under Implementation/Proposed

    KTL

    JB

    BY

    BB

    FNG

    24

    24

    14 20

    1230

    JFA

    RSD

    HBJ

    2014

    30 24

    30 24

    24

    JFA

    MBMuchai

    HBJ Hub

    TGF

    Bangura GF

    24

    24

    30

    30 30

    AshuganjMS

    APS/AFC

    DhanuaMS

    WestZone

    TFA TFATFA/

    GPS/

    UFFL/

    PUFF

    24

    3012

    3030

    30

    24

    1212

    Elenga

    MS

    TFA/

    RPCLTFA/

    JFCL

    MonohordiMS

    24

    Meghna

    Salda

    Gas Transmission System____

  • 7/22/2019 Presentation 25-07-10

    6/23

    DemandSupply Scenario____

    Present demand-supply scenario is imbalanced by nearly a 20% gap based on daytotal demand. At peak hourly demand rates, gas off-take exceeds throughput by a

    higher margin to the tune of 30%.

    Gas demand projection (mmscfd) of six PB marketing companies upto Y 2015 is asfollows:

    The production augmentation plan of Petrobangla including that of IOCs, Chevron in

    particular, is aimed at minimizing the demand-supply imbalance at the fastestpossible time

    4162398937123382280119812363Gross Demand

    37463591334130432520Demand at 90% LF

    16716010468777BAPEX/SGCL

    2021991971361027691PGCL

    305303301308181131131JGTDCL

    530523512502485250380KGDCL

    120110105100905472BGSL

    2838269424932268193614701689TGTDCL

    20152014201320122011

    Future DemandPresent

    Availability

    Present

    Demand

    Company

  • 7/22/2019 Presentation 25-07-10

    7/23

    Gas Production_____________ Total gas production in the country is around 2000 mmscfd.

    PB companies produce 947 mmscfd (47% of total). 393 mmscfd will badded by Y 2012 and 180 mmscfd by Y 2015.

    Chevron fields produce 900 mmscfd (45% of total). 180 mmscfd will beadded by Y 2011, 380 mmscfd by Y 2012 and 380 mmscfd by Y 2013.

    Remaining 160 mmscfd (8% of total) is produced by two other IOCs:Tullow (120 mmscfd) and Cairn (40 mmscfd). Cairn will add 30 mmscfdfrom Sangu (south) by Dec 2010.

    Total additional PB + Chevron + Cairn production will be:

    210 mmscfd by Y 2011

    + 773 mmscfd by Y 2012

    + 380 mmscfd by Y 2013

    + 180 mmscfd by Y 2015.

    1543 mmscfd

  • 7/22/2019 Presentation 25-07-10

    8/23

    152013501340134011851055947977Sub-total :

    Kapasia/

    Mubarakpur

    60606060601500

    Sundalpur/

    Srikail/

    15151515151500Semutang

    15151515151500Meghna

    888888815Shahbazpur

    5656565636363634Bakhrabad

    383838383823811Salda

    3333333333333335Narsingdi

    25251515151572Sylhet

    1616161616161618Beanibazar

    12797979797979797Kailashtila

    6565656565452532Fenchuganj

    12484848449494953Rashidpur

    260260260260260260260260Habiganj

    678578578578478428408420Titas

    Dec-15Dec-14Dec-13Dec-12Dec-11Dec-10Existing

    Production

    Existing

    Capacity

    PRODUCTION AUGMENTATION PLAN (mmscfd) - Petrobangla Fields

  • 7/22/2019 Presentation 25-07-10

    9/23

    42823912390233222487217720392020Total :

    5005005005000000

    LNG IMPORT (Equivalent mmscfd)

    22622062206214821302112210921043Sub-total:

    00000000Block-7

    2000000000Offshore bidding 2008

    30303030303000Sangu (South)

    4040404040404035Sangu

    22222223Feni

    120120120120120120120100Bangura

    108010801080900720720720600Bibiyana

    360360360160160606075Moulvibazar

    430430430230230150150230Jalalabad

    Dec-15Dec-14Dec-13Dec-12Dec-11Dec-10ExistingProduction

    ExistingCapacity

    PRODUCTION AUGMENTATION PLAN (mmscfd) - IOC FIELDS

  • 7/22/2019 Presentation 25-07-10

    10/23

    13931223122312231068938893919Sub-total :

    1515151515000Mubarakpur

    1515151515000Kapasia

    1515151515000Srikail

    15151515151500Sundalpur

    15151515151500Meghna

    5656565636363634Bakhrabad

    383838383823811Salda

    3333333333333335Narsingdi

    10474747474747474Kailashtila

    6565656565452532Fenchuganj

    12484848449494953Rashidpur

    220220220220220220260260Habiganj

    678578578578478428408420Titas

    Dec-15Dec-14Dec-13Dec-12Dec-11Dec-10

    Grid Intake VolumesExisting

    Production

    Existing

    Capacity

    PROJECTED GRID INTAKE VOLUMES AGAINST AUGMENTED PRODUCTION (mmscfd) - By Petrobangla

    Fields

  • 7/22/2019 Presentation 25-07-10

    11/23

    39653595359532152330202019451927Total :

    5005005005000000

    LNG Import (Equivalent to mmscfd)

    20721872187214921262108210521008Sub-total:

    00000000Block-7

    2000000000Offshore bidding 2008

    30303030303000Sangu (South)

    22222223Feni

    120120120120120120120100Bangura930930930750720720720600Bibiyana

    360360360360160606075Moulvibazar

    430430430230230150150230Jalalabad

    Dec-15Dec-14Dec-13Dec-12Dec-11Dec-10

    Grid Intake VolumesExistingProduction

    ExistingCapacity

    PROJECTED GRID INTAKE VOLUMES AGAINST AUGMENTED PRODUCTION (mmscfd) - By IOC Fields

  • 7/22/2019 Presentation 25-07-10

    12/23

    Drilling Program ___________

    Short Term (Up to Dec. 2010)

    - Work over : 6 wells

    - Appraisal : -

    - Exploration : 1 well

    Mid Term ( Up to Dec. 2013)

    - Work over : 1 well- Appraisal : 10 wells

    - Exploration : 3 wells

    Long Term ( Up to Dec. 2015)

    - Appraisal : 9 wells

    - Development : -

    - Exploration : -

    Short Term (Up to Dec. 2010)

    - Work over : -

    - Appraisal : -

    - Exploration : 1 well

    Mid Term ( Up to Dec. 2013)

    - Work over : -- Appraisal : -

    - Development :19 wells

    Long Term ( Up to Dec. 2015)

    - Appraisal : -

    - Development : 3 wells

    - Exploration : -

    PB Chevron

  • 7/22/2019 Presentation 25-07-10

    13/23

    Evacuation Needs________

    For increased Production - PB

    Among PB fields, the entire increased production of TGF (270 mmscfd) can/would be

    evacuated without flowing through Compressor Stations. To this end 30 inch dia. 61 km

    loop line project has been taken up for completion by Y 2013.

    Increased production of other three PB fields KGF, FGF & RGF (145 mmscfd) over the

    existing production of 150 mmscfd (total 295 mmscfd) will be needed to be evacuated

    through Muchai & Ashuganj Compressor Stations by Y 2012.

    For increased Product ion Chevron

    JBF :

    Present production of 150 mmscfd is being evacuated by existing pipelines leaving

    behind a stranded production of 80 mmscfd.

    Total 230 mmscfd existing production capacity can/would be evacuated once MuchaiCompressor Station is commissioned by Y 2011 followed by Ashuganj Compressor

    Station to be commissioned by Y 2012.

    Additional 200 mmscfd in Y 2013 would require a new evacuation route because this

    volume can not be passed through existing pipelines and Compressor Stations to be

    installed.

  • 7/22/2019 Presentation 25-07-10

    14/23

    MBF: Present production of 60 mmscfd is being evacuated by existing pipelines.

    Total additional production of 300 mmscfd by Y 2012 together with existing 60 mmscfd

    (total 360 mmscfd) can/would be evacuated once Muchai Compressor Station is

    commissioned by Y 2011 followed by Ashuganj Compressor Station to be commissioned by

    Y 2012.

    BYF

    Present production of 720 mmscfd is being evacuated by existing pipelines.

    150 mmscfd out of total additional production of 360 mmscfd by Y 2013 would be required

    by and supplied to the two Bibiyana IPPs targeted for completion by Y 2013 leaving 210

    mmscfd for evacuation to the national gas grid

    Total additional production of 210 mmscfd by Y 2013 available for national gas grid together

    with existing 720 mmscfd (total 930 mmscfd) can not all be evacuated by the existing

    pipelines and Compressor Stations.

    Taking into account 1160 mmscfd (max) capacity of Muchai Compressor Station and

    considering the production of above mentioned PB & Chevron fields which must be routed

    through the Muchai Compressor station, the calculated volume of BYF that can be

    passed through this compressor station is only 275 mmscfd.

    Therefore, the remainder 930-275 = 655 mmscfd of BYF production must have a altogethernew evacuation route to be established at the soonest.

    Evacuation Needs (contd.)____

  • 7/22/2019 Presentation 25-07-10

    15/23

    Evacuation of Chevrons planned additional 300 mmscfd from Moulvibazar GF :

    Construction of 22 km parallel pipeline from Moulvibazar GF to Muchai Manifold

    Station.

    2.

    Evacuation of Chevrons planned additional 560 mmscfd from Jalalabad GF

    and Bibiyana GF :

    Option-A : JBF-BYF-Muchai-Ashuganj-Monohordi through Compressor

    Stations at Muchai & Ashuganj(210 km)

    Option-B : JBF-BYF-Dhanua bypassing Compressor Stations (190 km)

    Option-C : JBF-BYF-Muchai-Ashuganj-Monohordi Dhanua- Elenga

    Bypassing Compressor Stations at Muchai & Ashuganj (300 km)

    1.

    Description of PipelineSl. No

    Simulation Results__________

    Pipelines required to evacuate additional production from upstream of Muchai

    Compressor Station

  • 7/22/2019 Presentation 25-07-10

    16/23

    Dhanua to Elenga : This section of pipeline (30 inch dia. 52 km) is part of

    approved project namely Monohordi-Dhanua-Elenga-East bank of Jamuna Bridge

    project. Construction of Monohordi-Dhanua and Elenga-East Bank section is

    ongoing under ADB finance. Financing for Dhanua-Elenga section need to bearranged.

    2.

    Khatihata to BhadugarB.Baria (TGF L-A): Construction 24 inch dia. 12 km high

    pressure (1135 psig) pipeline to evacuate 200 mmscfd additional gas productionfrom Titas Gas Fields.

    1.

    Bangabandhu Bridge West End to Nalka: This section of pipeline (30 inch dia.

    15 km) is part of approved project namely East Bank of Jamuna Bridge to Nalka,

    Hatikamrul to Ishwardi to Bheramara project. Construction of Hatikamrul to

    Ishwardi to Bheramara section is ongoing under ADB finance. Financing for

    Bangabandhu Bridge West End to Nalka section need to be arranged.

    3.

    Description of PipelineSl. No

    Pipelines required for de-bottlenecking of existing transmission system.

    Simulation Results (Contd.)_______

  • 7/22/2019 Presentation 25-07-10

    17/23

    Mubarakpur GF to Baghabari: Construction of 12 inch ND X 30 km pipeline from Mubarakpur gas field to

    Baghabari CGS is needed for evacuation of gas from Mubarakpur gas field.4.

    Srikail GF to AB Pipeline: Construction of 8 inch ND X 3 km pipeline from Srikail gas field to AB pipeline MLV-

    2 (Karoibari) intake point is needed for evacuation of gas from Srikail gas field.3.

    Description of PipelineSl.

    No

    Sundalpur GF to Feni : Construction of 12 inch ND X 30 km pipeline from Sundalpur gas field to Bakhrabad-

    Chittagong pipeline intake point at Feni is needed for evacuation of gas from Sundalpur gas field.2.

    Kapasia GF to Amraid: Construction of 12 inch ND X 4 km pipeline from Kapasia gas field to Monohordi-

    Dhahua pipeline intake point at Amraid is needed for evacuation of gas from Kapasia gas field.

    1.

    Simulation Results (Contd.)_______

    Pipelines required for hook up of new gas fields.

    Pipeline required for evacuation of LNG.

    Description of PipelineSl. No

    Maheshkhali to Rangadia: Construction of 30 inch Dia X 90 km pipeline from Maheshkhali LNG receiving

    station to Rangadia hook-up point of Chittagong Ring Main for evacuation of LNG.

    1.

  • 7/22/2019 Presentation 25-07-10

    18/23

    Evacuation Options_____________

    Evacuation Route : Option-A : JB-BY-Muchai-Ashuganj-Monohordi (210 km)

    Flow through Compressor Stations, required Comp cap (Muchai 2010, Ashuganj-2350 mmscfd)

    Evacuation Route : Option-B : JB-BY-Dhanua (190 km)

    Flow through Compressor Stations, required Comp cap (Muchai 1160, Ashuganj-1500 mmscfd)

    Evacuation Route: Option-C : JB-BY-Muchai-Ashuganj-Elenga (300 km)

    Flow not through Compressor Stations, required Comp cap (Muchai 1160, Ashuganj-1500

    mmscfd)

    Simulation exercise was carried out for evacuation of 790 mmscfd out of a total 940 mmscfd

    additional gas production by Chevron from its three fields by Y 2013 considering the balance 150

    mmscfd to remain dedicated for the two Bibiyana IPPs.

    Taking into account Muchai Compressor Station designed capacity of 1160 mmscfd and that of

    Ashuganj Compressor Station 1500 mmscfd, a quantity of 850 mmscfd gas will be needed to be

    evacuated bypassing the Muchai & Ashuganj Compressor Stations.

    To address the above evacuation need the simulation exercise presents three different options

    complying with steady state convergence which are as follows and pictorially depicted in the next

    three linked slides:

  • 7/22/2019 Presentation 25-07-10

    19/23

    Does not converge due to pressure

    mismatch

    Converges with a 34 inch dia pipelineConverges with a 34 inch dia pipelineSimulation

    convergence

    Option-COption-BOption-ACriteria

    JBF-BYF-Muchai-Ashuganj-Elenga

    bypassing compressors

    JBF-BYF-DhanuaJBF-BYF-Muchai-Ashuganj-Monohordi

    through compressors

    Route

    BDT 3500-4000 CroresBDT 2300-2500 CroresBDT 3200-3500 CroresEstimated Cost

    Will be limited to existing gas fields

    only

    Proximity to future gas source locations in

    Sunamganj & Netrakona Districts.

    Will be limited to existing gas fields onlyConnectivity

    Same evacuation corridor as the

    existing one requiring additional land

    acquisition

    Alternative evacuation corridor will be

    developed under this option offering

    increased operational flexibility & overall

    system reliability

    Same evacuation corridor as the existing

    one requiring additional land acquisition

    which presents difficulties at many

    locations due to infrastructure development

    Corridor

    Bypasses Muchai & Ashuganj

    Compressor Loop, but this option

    does not converge in the simulation

    Route is different from Muchai & Ashuganj

    Compressor Loop enhance no additional

    compression capacity needed.

    Passes through Muchai & Ashuganj

    Compressor Loop and Muchai & Ashuganj

    Compressor capacities need to be almost

    doubled.

    Compression

    Developed terrain, Hilly area 2 km,

    Tea & Rubber Garden 10 km.

    Remaining 288 km is normal cross-country land. Involves major river

    crossings (Meghna & 9 others)

    30 km out 190 km is Haor area, remaining

    160 km is normal cross-country land. About

    40 km falls under forest area. Haor arearemains dry for nearly 5 months with paddy

    cultivation. Water table is learnt to remain

    20 feet below land surface and cultivation

    requires irrigations

    Developed terrain, Hilly area 2 km, Tea &

    Rubber Garden 10 km. Remaining 198

    km is normal cross-country land. Involvesmajor river crossings (Meghna & 6 others)

    Terrain Condition

    300 km190 km210 kmLength

    Evaluation of Options________

  • 7/22/2019 Presentation 25-07-10

    20/23

    GTCL operates 9 major high-pressure transmissionpipeline systems (20-30 inches Dia).

    Out of these pipelines initial 5 were built by expatriateEPC contractors.

    Subsequent 4 pipelines were designed & materialsprocured by GTCLs personnel and construction doneby local contractors under GTCL supervision.

    Currently 7 pipeline (12-30 inches Dia) projects underimplementation out of which 3 are near completion.

    Sector Capabilities______________

  • 7/22/2019 Presentation 25-07-10

    21/23

    GTCL now has proven capabilities for Front End Engineering Design and

    Detailed Engineering Design for high pressure transmission pipelines

    Presently 14 nos. of local contractors of Category-1.4 have the proven

    capabilities for constructing high pressure transmission pipelines pipelines

    upto 30 inches Dia

    Regulating & Metering Station FEED is done by GTCL but constructed by

    expatriate EPC contractors. Recently the EPCs use local contractors for in-

    situ fabrication, erection & installation of the stations

    HDD River Crossing work are needed to be done by expatriate EPCs.

    Sector Capabilities (Contd.)__________

  • 7/22/2019 Presentation 25-07-10

    22/23

    Land Acquisition/Requisition for Right of Way (ROW) involves huge

    complication and unexpected delays.

    Long Lead Times are needed for Material Procurement typically

    divided in 7-10 bid packages often requiring re-biddings.

    Pipeline Construction activity is season-bound. Window of

    opportunity typically lasts for maximum six months of the year.

    Financing and project approval is a very protracted process causing

    delay in project implementation.

    Environmental study and clearance is also a circuitous and long

    drawn process. Due to a number of large size transmission pipeline projects being

    implemented, GTCL has human resource limitations as well.

    Major Challenges_____________

  • 7/22/2019 Presentation 25-07-10

    23/23

    Conclusions_______________ Petrobangla observes Option-B (JB-BY-Dhanua) pipeline as the preferred solution

    from operational point of view.

    Considered from route/terrain characteristics point of view, about 30 km length (15%

    of total) presents some challenge which may be overcome by technological

    alternatives for construction to be decided in due course.

    For expeditious implementation the pipeline is recommended for construction under

    a turn-key contract for which necessary draft bid documents are available in GTCL.

    Land acquisition for the ROW need to be started from next dry season (beginning

    Nov 2010). The construction of the pipeline can commence from Nov 2011

    provided the land acquisition is completed by that time.

    The financing of the project to be decided by the GoB expeditiously.