Consorcio INTERVIAL 2012MINISTERIO

DE TRANSPORTE

CORREDORES PRIORITARIOS PARA LA PROSPERIDAD

CONTRATO DE OBRA : 544 DE 2012. MEJORAMIENTO , GESTION SOCIAL,

PREDIAL Y AMBIENTAL DEL PROYECTO TRANSVERSAL MEDELLIN – QUIBDO , FASE 2

PARA EL PROGRAMA CORREDORES PRIORITARIOS PARA LA PROSPERIDAD.

Page 2: Presentacion medellin quibdo febrero 2013

TRANSVERSAL MEDELLIN – QUIBDO FASE 2

ALCANCE: GESTION SOCIAL, PREDIAL , AMBIENTAL Y MEJORAMIENTO DEL PROYECTO TRANSVERSAL MEDELÍN - QUIBDÓ

Consorcio

INTERVIAL 2012

Page 3: Presentacion medellin quibdo febrero 2013

Consorcio INTERVIAL 2012MINISTERIO

DE TRANSPORTE

CORREDORES PRIORITARIOS PARA LA PROSPERIDAD

TRANSVERSAL MEDELLIN – QUIBDO , FASE 2 CONSORCIO CORREDORES LAX 051

PROGRAMA DE INVERSIONES

CONTRATO ORIGINAL FECHA DE PROGRAMA MONTO (COP) %

DE A

Valor del Contrato: $254,560,365.87

100.00%Período de Ejecución: 08-ago-12 07-nov-16

Periodo de Ejecución: 08-ago-12 07-nov-16

Importe Estimado:

Importe Estimado Acumulado:

Período Transcurrido:

Importe Erogado: ASIGNACIONES (VIGENCIAS FUTURAS

CTO 544-2012 AÑOS IMPORTES C/IVA (MCOP)

Primera Asignación 08-ago-12 31-dic-12 $7,248,601.19 2.85%

Segunda Asignación 01-ene-13 31-dic-13 $32,416,470.58 12.73%

Tercera Asignación 01-ene-14 31-dic-14 $84,916,470.58 33.36%

Cuarta Asignación 01-ene-15 31-dic-15 $91,916,470.58 36.11%

Quinta Asignación 01-ene-16 16-oct-16 $38,062,352.94 14.95%

SUMA $254,560,365.87 100.00%

Page 4: Presentacion medellin quibdo febrero 2013

Consorcio INTERVIAL 2012MINISTERIO

DE TRANSPORTE

CORREDORES PRIORITARIOS PARA LA PROSPERIDAD

CONTRATO DE INTERVENTORIA : 601 DE 2012.

INTERVENTORIA INTEGRAL QUE INCLUYE PERO NO LIMITA A LA INTERVENTORIA TECNICA, FINANCIERA, ADMINISTRATIVA, JURIDICA,

GESTION SOCIAL, PREDIAL Y AMBIENTAL DEL PROYECTO CORREDOR TRANSVERSAL MEDELLIN – QUIBDO , FASE 2 PARA EL PROGRAMA CORREDORES PRIORITARIOS PARA LA PROSPERIDAD MODULO 1.

CORREDORES PRIORITARIOS PARA LA PROSPÉRIDAD

Page 5: Presentacion medellin quibdo febrero 2013

ENERO 31 DE 2013

CTO N° OBJETO CONTRATISTA VALOR FECHA INICIO FECHA TERMINACION

544 DE 2012

Mejoramiento, gestión social, predial y ambiental del proyecto Corredor Transversal Medellín – Quibdó, Fase 2, para el programa de Corredores Prioritarios para la Prosperidad.

CONSORCIO CORREDORES

LAX 051254.560.365.898 08/08/2012 18/11/2016

601-2012

Interventoría integral que incluye pero no se limita a la interventoría técnica, financiera, administrativa, jurídica, gestión social, predial y ambiental del Proyecto Corredor Transversal Medellín - Quibdó, Fase 2, para el programa Corredores Prioritarios para la Prosperidad, Módulo 1

CONSORCIO INTERVIAL 2012

10.979.979.752,00 09/07/2012 07/11/2016

CONDICIONES CONTRACTUALES

Page 6: Presentacion medellin quibdo febrero 2013

Consorcio INTERVIAL 2012MINISTERIO

DE TRANSPORTE

CORREDORES PRIORITARIOS PARA LA PROSPERIDAD

PROFESIONALES ACTUALES ENCARGADOS DEL PROYECTO

POR INVIAS : ING. JAVIER CAÑON BONILLA Gestor Técnico del Proyecto ING. GUSTAVO OTALVARO PAUCAR Supervisor del Contrato – Terr. Antioquia

CONSORCIO INTERVIAL 2012 : ING. JOSE JOAQUIN ORTIZ Representante Legal ING. JAIME MORENO SANZ Director de Interventoría ING. CIRO DUARTE DUARTE Residente ING. JOSE J. RAMIREZ MARTINEZ Auxiliar Residente ING. ISABEL CRISTINA PALAU Auxiliar Residente

CONSORCIO LAX 051 ING. SANTIAGO GARCIA CADAVID Representante Legal ING. JOSE Ma OTOYA DUSSAN Director de Construcción ING. MAURO R. NARVAEZ Residente de obra ING. ANDRES M. RAIGOZA Residente de Obra ING. LUIS GUILLEN residente de Obra

Page 7: Presentacion medellin quibdo febrero 2013

Consorcio INTERVIAL 2012MINISTERIO

DE TRANSPORTE

CORREDORES PRIORITARIOS PARA LA PROSPERIDAD

EL CONSORCIO CORREDORES LAX 051 LO INTEGRAN LAS EMPRESAS :

Empresa Mexicana :

TRADECO INFRAESTRUCTURA S.A. DE C.V. 40%

Empresas Colombianas :

CONINSA RAMON H . S.A. 30%SP INGENIEROS S.A.S. 30%

Page 8: Presentacion medellin quibdo febrero 2013

Consorcio INTERVIAL 2012MINISTERIO

DE TRANSPORTE

CORREDORES PRIORITARIOS PARA LA PROSPERIDAD

L O C A L I Z A C I O N D E L P R O Y E C T O

EL “7”

Page 9: Presentacion medellin quibdo febrero 2013

Consorcio INTERVIAL 2012MINISTERIO

DE TRANSPORTE

CORREDORES PRIORITARIOS PARA LA PROSPERIDAD

INICIO FIN KMS. RUTA TRAMO

TRAMO : EL 7 AL 18

PR 39+350 PR 98+500 59.15 6002 EL " 18" - EL "7"

TRAMO : EL 7 LA MANSA

PR 101+980 PR 102+380 0.40

6002 EL "7" - LA MANSA

PR 105+340 PR 105+680 0.34

PR 107+435 PR 107+480 0.05

PR 107+880 PR 108+080 0.20

PR 109+540 PR 109+620 0.08

PR 110+880 PR 113+010 2.13

PR 113+480 PR 114+980 1.50

SUMAS 4.70

TRAMO : LA MANSA - CD. BOLIBAR

PR 0+000 PR 12+100 12.10 6003 LA MANSA - CD. BOLIVAR

LONGITUD TOTAL 75.945 KILOMETROS.

L O C A L I Z A C I O N D E L P R O Y E C T O

Page 10: Presentacion medellin quibdo febrero 2013

Consorcio INTERVIAL 2012MINISTERIO

DE TRANSPORTE

CORREDORES PRIORITARIOS PARA LA PROSPERIDAD

VOLUMENES PRINCIPALES DE OBRA

Page 11: Presentacion medellin quibdo febrero 2013

OBRA A DIC 31 DE 2012 – ACTA N° 6

VALOR OBRA EJECUTADA ACUMULADA – CTO 544 -2012

SUBTOTAL VALOR DE LAS OBRAS = SUMATORIA DE (1) = (A) 232.261.233.208

539.781.670

1.898.185.773

OBRAS COMPLEMENTARIAS Y ADICIONALES (NO MODIFICAR) = (B) 3.963.765.225

VALOR PROVISIÓN PARA AJUSTES EN BÁSICO (NO MODIFICAR)

= ( C ) 3.103.466.807

34.413.047

VALOR BÁSICO DEL CONTRATO INCLUYE OBRAS COMPLEMENTARIAS Y AJUSTES = (D)

239.328.465.240

539.781.670

1.932.598.820

ADMINISTRACIÓN = ( E ) 23%

IMPREVISTOS (NO MODIFICAR) = (F) 5%

UTILIDAD = (G) 5%

A I U = (H) 33%

IVA = ((D) * 16% + (G)) / ((1+(H)) = (I) 1.439.569.716

3.246.807

11.624.655

VALOR TOTAL OBRA = (D) + (I) = (J) 240.768.034.956

543.028.477

1.944.223.475

AJUSTE ESTUDIOS Y DISEÑOS = (K) GL 1 223.489.900

223.489.900

69.348.990

IVA = ((K) * 16%) = (L) 35.758.384

11.095.838

SUBTOTAL ESTUDIOS Y DISEÑOS = (K) + (L) = (M) 259.248.284

80.444.828

GESTIÓN SOCIAL Y PREDIAL (Incluye IVA 16%) (NO MODIFICAR) = (N)

7.585.486.839

GESTIÓN AMBIENTAL (Incluye PAGA e IVA 16%) (NO MODIFICAR) = (O) 5.947.595.819

IVA DE LOS GESTIONES = (P) 1.866.632.091

VALOR TOTAL BÁSICO DE OBRA 251.218.405.707

539.781.670

2.001.947.810

VALOR TOTAL DEL IVA 3.341.960.191

3.246.807

22.720.493

VALOR TOTAL DEL CONTRATO 254.560.365.898

543.028.477

2.024.668.303

Page 12: Presentacion medellin quibdo febrero 2013

Consorcio INTERVIAL 2012MINISTERIO

DE TRANSPORTE

CORREDORES PRIORITARIOS PARA LA PROSPERIDAD

VELOCIDADES DE DISEÑO LONGITUD PENDIENTES MAXIMAS

TRAMO : LA MANSA - CD. BOLIVAR20 - 30 Km/Hr. 68%

7% EN EL 49% DE LA LONGITUD

40 Km/Hr. 26%50 Km/Hr. 6%

TRAMO : EL 7 AL 1820 - 30 Km/Hr. 43%

VARIABLE Y ACEPTABLE40 Km/Hr. 34%50 Km/Hr. 14%60 Km/Hr. 9%

DATOS PRINCIPALES

Page 13: Presentacion medellin quibdo febrero 2013

Consorcio INTERVIAL 2012MINISTERIO

DE TRANSPORTE

CORREDORES PRIORITARIOS PARA LA PROSPERIDAD

Tramo Ciudad Bolívar- El Siete (PR 12+000 al PR 96+900)

Page 14: Presentacion medellin quibdo febrero 2013

Consorcio INTERVIAL 2012MINISTERIO

DE TRANSPORTE

CORREDORES PRIORITARIOS PARA LA PROSPERIDAD

Tramo El “18” – El Siete (PR 39+950 al PR 96+900)

Page 15: Presentacion medellin quibdo febrero 2013

Consorcio INTERVIAL 2012MINISTERIO

DE TRANSPORTE

CORREDORES PRIORITARIOS PARA LA PROSPERIDAD

PROGRAMA GENERAL DE OBRA20122do. 1er. 2do. 1er. 2do. 1er. 2do. 1er. 2do.

Semestre Semestre Semestre Semestre Semestre Semestre Semestre Semestre Semestre

TRANSVERSAL MEDELLIN -QUIBDO, FASE II 1090 dias

Preoperativos 40 dias

Adaptacion de Diseños 150 dias

Gestion Socia l y Predia l 540 dias

Gestion Ambiental 730 dias

MANTENIMIENTO GENERAL 960 dias

TRAMO 1 : CD, BOLIVAR - LA MANSA 360 dias

TRAMO 2 ; LA MANSA - EL 7 277 dias

TRAMO 3 : EL 7 - EL 18 600 dias

TRAMO 1 : CD, BOLIVAR - LA MANSA 354 dias

Terracerias 264 dias

Estructura s y Obras de Drena je 160 dias

Pavimentos de Concreto 157 dias

TRAMO 2 : LA MANSA - EL 7 285 dias

Terracerias 74 dias

Estructura s y Obras de Drena je 80 dias

Pavimentos de Concreto 190 dias

TRAMO 3 : EL 7 - EL 18 715 dias

Terracerias 730 dias

Estructura s y Obras de Drena je 340 dias

Pavimentos de Concreto 673 dias

SEÑALAMIENTO 90 dias

IMPREVISTOS 21 dias

2013 2014 2015 2016ACTIVIDAD DURACION

Page 16: Presentacion medellin quibdo febrero 2013

Consorcio INTERVIAL 2012MINISTERIO

DE TRANSPORTE

R E C U R S O S P R I N C I P A L E S M A Q U I N A R I A

2 BULLDOZER CATERPILLAR D6R

4 EXCAVADORA S/ORUGAS HYUNDAI 320 CL

2 CARGADOR S/N CATERPILLAR 950

3 MOTOCONFORMADORA CATERPILLAR 120 H

3 COMPACTADOR MIXTO CATERPILLAR C 5563

1 TRITURADORA PRIMARIA DE QUIJADAS TELSMITH 24"

1 TRITURADORA SECUNDARIA DE CONO TELSMITH 36"

1 GENERADOR DE CORRIENTE 500 KVA CATERPILLAR

1 PLANTA DE CONCRETO CON SILOS CATERPILLAR

1 REGLA VIBRATORIA PARA CONCRETO CATERPILLAR

3 DUMPER CATERPILLAR

1 PERFORADORA S/ORUGAS 350 ING, RAND

1 COMPRESOR PORTATIL 750 PCM ING, RAND

1 MARTILLO HIDRAULICO PARA EXC.

2 RETROEXCAVADORA (PAJARITA) CATERPILLAR 420 D

5 COMPACTADOR DE PLACA BAILARINA INGERSOLL RAND RX 304H

5 VIBRADORES P/CONC. ( COMB. INTERNA)

2 GENERADOR PORTATIL HONDA 6000 WATTS

2 BOMBA P/AGUA 4" DIAM. TRAGALODOS

1 PLANTA DE SOLDAR 300 AMPS LINCOLN

2 TORRE DE ILUMINACION INGERSOLL RAND 10.5 HP

3 REVOLVEDORA P/CONCRETO 1/2 SACO TOKER 8 HP

TRANSPORTADORES PARA TRITURADORA

32 VOLQUETA 14 M3. CAP. NAVISTAR

5 CAMIONETA PICK UP TOYOTA HILUX

2 CAMION NPR VW 5 TON

3 CARROTANQUE PARA AGUA 2500 GAL

4 MOTOSIERRA 36"

5 CORTADORA DE METAL ELECTRICO

2 TANQUE ESTACIONARIO PARA AGUA 2500 GAL.

MAQUINARIA MENOR

VEHICULOS Y EQUIPO DE APOYO

DESCRIPCION MARCA MODELOCANTIDAD

MAQUINARIA MAYOR 5 INSPECTOR DE OBRA MES

2 TOPOGRAFO MES

8 CADENEROS MES

3 MECANICO MES

3 AYUDANTE MECANICO MES

1 ENGRASADOR MES

4 OPERADOR DE EXCAVADORA MES

2 OPERADOR DE BULLDOZER MES

2 OPERADOR DE CARGADOR MES

3 OPERADOR DE MOTOCONFORMADORA MES

3 OPERADOR COMPACTADOR MES

2 OPERADOR DE RETROEXCAVADORA MES

2 OPERADOR DE TRITURADORA MES

3 OPERADOR DE DUMPER MES

10 OBREROS -TRITURADORA MES

2 SOLDADOR MES

5 CONDUCTOR VEHICULO LIVIANO MES

32 CONDUCTOR VOLQUETA MES

10 OFICIAL ALBAÑIL MES

8 OFICIAL CARPINTERO MES

5 OFICIAL FIERRERO MES

2 OPERADOR DE PERFORADORA MES

2 COMPRESORISTA MES

2 POBLADOR (MANEJO DE EXPLOSIVOS) MES

10 CELADORES MES

40 OBREROS MES

PERSONAL OPERATIVO (POR TURNO)

MANO DE OBRA

Page 17: Presentacion medellin quibdo febrero 2013

Consorcio INTERVIAL 2012MINISTERIO

DE TRANSPORTE

CORREDORES PRIORITARIOS PARA LA PROSPERIDAD

AMPLIACION DE LA BANCA – CORTE TIPICO ( TRAMO EL SIETE – EL DIECIOCHO AMPLIACION DE LA BANCA – CORTE TIPICO ( TRAMO EL SIETE – EL DIECIOCHO Y SECTOR DE LA MANSAY SECTOR DE LA MANSA

ETAPA DE CONSTRUCCION DE LA VIA

Page 18: Presentacion medellin quibdo febrero 2013

ETAPA DE CONSTRUCCION DE LA VIA

AMPLIACION DE LA BANCA – CORTE TIPICO ( TRAMO EL SIETE – EL DIECIOCHO AMPLIACION DE LA BANCA – CORTE TIPICO ( TRAMO EL SIETE – EL DIECIOCHO PR 97+800PR 97+800

Consorcio INTERVIAL 2012MINISTERIO

DE TRANSPORTE