pq-box 100 quick start instructions - hv power 100 quick start... · pq-box 100 – quick start...
TRANSCRIPT
Page 1 of 8 PQ-Box 100 Quick Start v1.9.doc
PQ-Box 100 – Quick Start Instructions
These instructions are provided for the purpose on providing a quick start to PQ-Box 100
installation and operation. Please refer to the user handbook for full details.
Please avoid these two errors:
Enter the L-L nominal primary system
voltage (e.g. 440V, 11,000V, 220,0000V.
For single phase circuits enter the
equivalent L-L value (e.g. 400V for a
230V circuit.
Do not set the Measuring
interval too fast.
Read section 1.5c
Check the LCD before leaving site:
1) Are the voltages and currents showing correct primary values (i.e.
correct CT & VT ratios have been set)?
2) Are power values correct? Check for + vs - (correct VT/CT
phasing and polarity)?
3) Is the device recording?
Page 2 of 8 PQ-Box 100 Quick Start v1.9.doc
This quick start describes:
Section 1) Using WinPQ mobil software and laptop to set the PQ-Box 100 parameters (preferred)
Section 2) Setting unit up using LCD display only
Section 3) Decommissioning
1 Setup of PQ-Box 100 using USB connection to PC
This guide assumes that WinPQ mobil has been correctly installed on PC, and PQ-Box 100 has
compatible firmware.
These instructions detail powering the PQ-Box 100 from external source, and using laptop to setup
the PQ-Box 100 and to also display online measurements (phasor diagram) to confirm correct
VT/CT connection.
1.1 On site connect PQ-Box 100 power supply cables (the two black leads labelled
“Aux/Supply”) to a suitable voltage source (100-280 Vac or 140-220 Vdc). The supply leads
do not have any polarity.
The supply leads can be connected to the measuring circuit (if voltage range is suitable).
However, if power outage of more than 20 seconds occurs, the PQ-Box 100 will shut down.
Approx 20 seconds after return of power the PQ-Box 100 will commence recording again.
1.2 The PQ-Box 100 will now boot up. Wait approx 20 seconds until the main LCD measurement
screen shows before connecting USB cable to PQ-Box 100. Also ensure computer is fully
booted up before connecting USB cable. Do not rush making USB connections, otherwise
connection problems may occur. Follow the PC instructions if USB drivers need to be
installed.
1.3 Check free memory reported on the PQ-Box 100 LCD screen. For PQ-Box 100 with no data
stored, approx 970 MB should be reported (488 MB for earlier PQ-Box 100’s). Download
data from the PQ-Box 100 or delete as required. Confirm sufficient memory will be available
for intended recording period (Refer 1.5c).
1.4 Using the PC software, open the Setup PQ-Box 100 screen (Main menu: Data/PQ-Box
Configuration).
Select “Load setup from Box” if you want to see and update current PQ-Box 100 settings.
Alternatively click on “Basic settings” to select default values (this will set default parameters
for advanced Limit, Oscilloscope and 10ms RMS recorder)- note that the new values will need
to be uploaded back to the PQ-Box 100 (i.e. “Send new setup to Box”).
Page 3 of 8 PQ-Box 100 Quick Start v1.9.doc
1.5 Enter correct settings for:
A) Configuration:
Select appropriate frequency and do not check the other two boxes
B) Converter configuration:
Select the appropriate system type. Scroll to see more selection
(For three phase systems, 4-Wire will cause PQ-Box 100 LCD to show L-E voltages & 3-wire
will show L-L voltages)
A
D
C
B
E
Page 4 of 8 PQ-Box 100 Quick Start v1.9.doc
C) Measuring parameter:
Nominal Voltage:
The Nominal Voltage setting should be the nominal (target) primary system voltage. For
example 11,000 or 33,000. However, to set these values, the L-N value must be entered, i.e.
6350 or 19052 respectively.
Normally you would not enter secondary VT values (63.5/110V).
This setting also relates to Transducer Factor settings.
If a single phase voltage is being measured (e.g. 230 Vac), set Nominal Voltage to the 230
Vac and ignore the display L-L value.
Measuring Interval:
Please request “HV Power hints and tips: PQ-Box 100 Power Quality Recorder, Issue 1” for
detailed description of selection of Measuring Interval (referred to as Measurement Cycle on
the PQ-Box 100 LCD).
The measuring interval is the number of seconds over which permanent recording data (long
term line graphs) is averaged. This setting does not influence the high speed oscilloscope or
high speed RMS recorder functions. The PQ-Box 100 measures most “permanent recording”
measurements each ½ cycle, and the average of each of these values is recorded at the end of
each measurement interval. The maximum and minimum ½ cycle values (of voltage and
current) are also recorded at the end of each measurement interval, therefore there is little
advantage in selecting a shorter measuring interval. A shorter duration creates larger data
files.
Normally a 600 second setting is used (10 minutes) to conform with EN 50160 reporting.
HV Power recommended measuring interval:
Monitoring duration Measuring Cycle
Less than 12 hours 1 second*
Less than 2 days 120 seconds
Less than 1 week 600 seconds
*Flicker measurements will be recorded as zero data
values if the measuring interval is set to less than 60
seconds.
For very short tests, to obtain easy to view graphs, make sure the PQ-Box 100 records for at
least 10 measuring intervals.
Page 5 of 8 PQ-Box 100 Quick Start v1.9.doc
It is recommended that measuring interval is set such that permanent recording only takes
approx. 50 % of available memory. This allows sufficient room for a large amount of “event
data”. Oscilloscope and RMS “event” recordings each require approx 100 kb of memory
(assuming 50 ms and 1000 ms of pre-trigger time respectively, and 500 and 3000 ms of
recorder time).
As a guide to the memory requirements for permanent recorded data (only):
Measuring interval Time to generate
1 MB data
(approx)
Time to generate
100 MB data
(approx)
1 sec 3 minutes 5 hours
10 sec 30 minutes 2 days
30 sec 90 minutes 6.25 days
60 sec 3 hours 12.5 days
300 sec (5 minutes) 15 hours 62 days
600 sec (10 minutes) 1 day 6 hours 125 days
D) Ripple Control Signal
Enter the frequency of the ripple control signal. The other settings only apply to PQ-Box
100’s with additional Ripple Control Monitoring functionality enable, and default values
should generally be used.
E) Transducer factor
Assuming VT/PT/CVTs are in circuit and the PQ-Box 100 is connected to the secondary
circuits, the transducer conversion factor (knu) is the ratio of primary to secondary voltage,
e.g. 33 kV / 110 V = 300.
In most cases the “UNE” setting will be 1, as Neutral to Ground VT's are not normally used.
Assuming intermediate CTs are being used, the current conversion factor (kni) is the ratio of
primary to secondary current, e.g. 600 A / 5A = 120.
Note that if
20/200A Switchable clamps (111.7004) are being used on 200A setting, the CT factor
should be set to 10
5300A Rogowski clamps are being used, a correction factor of X2 must be applied to
the current conversion factor.
1.6 Check the Limits, Oscilloscope, 10ms RMS recorder screens for desired setup, and then
“Send new setup to box”. Default “Basic settings” are fine.
Page 6 of 8 PQ-Box 100 Quick Start v1.9.doc
1.7 Assuming PC time is correct, press “Synchronize time”.
Note that reported PQ-Box 100 time on the PC Setup screen, is that of when a setting file is
uploaded or downloaded, it does not otherwise update.
1.8 Connect the PQ-Box 100 voltage leads to the measurement source Using appropriate care and
precautions, connect in order, the green earth lead, neutral (blue) and then the 3 red leads to
the circuit to be measured. (Do not connect to measuring circuit if it is greater than 690 V L-
L, 400 V L-N/E).
If neutral connection does not exist, then connect the PQ-Box 100 (blue) neutral lead to the
PQ-Box 100 (green) earth lead. (or vice versa)
Confirm all voltages displayed on the PQ-Box 100 LCD are the correct primary values.
Connect the supplied clamp CT’s to the “I” terminal on the PQ-Box 100 and then connect
one-by-one to the measuring circuit.
Ensure the current readings on the PQ-Box 100 LCD are correct primary values. To confirm
correct polarity/phasing either:
A) Use the PC online measurement functions (Main menu Data/Online) to display
“Details” tab, and confirm correct primary voltage, current and power values are
being measured. Use the phasor diagram “U/I/Phase” to confirm correct direction of
CT clamps etc.
B) Use the PQ-Box 100 page button (third button from top) and toggle through the LCD
screen measurements. Play close attention to +/- signs on power readings, as these can
be used to identify if a CT connection is reversed.
1.9 Disconnect USB cable from PQ-Box 100.
1.10 Press the PQ-Box 100 [PLAY/STOP] button to start recording.
1.11 Check that:
Rec. = ON (this may take 2-3 seconds to update).
The recorder elapse timer at the top right hand corner of the LCD screen starts.
The LCD voltages and currents on the device keep refreshing every few seconds.
1.12 Use the page button to scroll to LCD screen showing number of events. Press the Manual
trigger button (second button from top) for 1 second. The “Oscilloscope Rec” and “RMS
Recorder” count should increment to 1 (this may take 2-3 seconds to update). This “manual
trigger” takes an oscillograph snap shot of the “as connected” condition. If the number of
events increases rapidly, it is recommended to check connections and settings (especially
nominal voltage setting). You may need to download data to PC, review and upload more
appropriate trigger settings.
1.13 The PQ-Box 100 front panel keys may be locked by pressing the 4th key [Setup] > 5 seconds.
Repeat to unlock.
Page 7 of 8 PQ-Box 100 Quick Start v1.9.doc
2 Setup of PQ-Box 100 without PC
The PQ-Box 100 LCD and front panel keys can be used to alter Network Type, VT and CT ratios
and Measurement Interval settings. If the other settings of the PQ-Box 100 are known to be
acceptable, then the front panel controls can be used to adapt the PQ-Box 100 to a given
application.
By using the LCD only, you do not have ability to view advanced trigger and limit settings as last
set by PC upload. If you are not aware of the last settings, then the PQ-Box should be connected to
a PC to determine these, and potentially download new or default settings if required.
2.1 Refer and follow instructions 1.1 to 1.3 to power up PQ-Box 100.
2.2 Using the bottom button (SETUP) to enter the setup menu. (If the PQ-Box 100 is left for
several seconds, the LCD display will automatically return to main menu).
2.3 Select “Parameterization” by pressing the top key (PLAY/STOP).
2.4 Select “Nominal Voltage” by pressing the (PLAY/STOP) key.
2.5 Enter the PRIMARY nominal voltage (voltage phase-to-phase of the primary circuit (e.g.
11,000 or 33, 000) using the “up” and “down” selections, once levels are satisfactory – select
“OK”.
If measuring a single phase circuit, or connecting to a single phase, enter the equivalent
primary phase-to-phase value. For example if connecting to 1ph 230 V, enter 400 V.
2.6 Select “Measurement Cycle”. Enter the measuring interval using the “up” and “down”
selections, and select “OK” when satisfactory. Refer section 1.5c for recommended values.
2.7 Select “Browse”, then select “Voltage Converter L”. The transducer conversion factor (knu)
is the ratio of primary to secondary voltage, e.g. 33 kV / 110 V = 300. Set the Line voltage
ratio, and then select “OK”.
In most cases the “Voltage Converter N” setting will be 1, as Neutral to Ground VT's are not
normally used.
2.8 Select “Browse”, then select “Current Converter L”. The conversion factor (kni) is the ratio of
primary to secondary current, e.g. 600 A / 5A = 120. Set the ratio, and then select “OK”.
Select “Current Converter N”. The conversion factor (kni) is the ratio of primary to secondary
current, e.g. 600 A / 5A = 120. Set the ratio, and then select “OK”.
Page 8 of 8 PQ-Box 100 Quick Start v1.9.doc
2.9 Select “Browse”, Select “Net Type”, and then “Browse” to “1 conductor” (single phase), “3
conductors” (three phase no neutral) or “4 conductors” (3 phase + neutral). If in doubt, select
4 conductors.
2.10 Select “Back” twice. The PQ-Box 100 may “configure”, then select “Setup”, “Setup” and set
correct data/time (24 hour format). Select “Back” until you are back to the main display.
2.11 Connecting the instrument to live source following instructions 1.8 to 1.13
3 Decommissioning
3.1 Press the Manual trigger button for 1 second (second button from top) to trigger an
Oscillograph snapshot of the end of recording condition. Wait approx. 60 seconds before next
step.
3.2 Press the [START / STOP] key to stop recording.
3.3 Wait and check that : a) Rec. = OFF.
Do not immediately disconnect supply power, as the PQ-Box 100 should be left on till the
“closing measurement” screen disappears.
3.4 Disconnect the PQ-Box 100 voltage leads from the measuring source.
3.5 Disconnect the PQ-Box 100 CT clamps from measuring circuit.
3.6 Disconnect the CT clamps from the PQ-Box 100 connector.
3.7 Disconnect the PQ-Box 100 supply leads.
3.8 Connect laptop and download data if required. Do not delete data from PQ-Box 100, till
downloaded data has first been opened with WinPQ mobil software and verified.