power sector planning and development: lessons from thailand’s and international experience...
TRANSCRIPT
Power Sector Planning and Development:Lessons from Thailand’s and international
experience
Chuenchom Sangarasri Greacen9 March 2013
WORKSHOP ON “ELECTRIC POWER DEVELOPMENT & CHALLENGES IN MYANMAR: SHARING EXPERIENCES OF THE MEKONG REGION”
Tonga Puri Hotel, Nay Pyi Taw, Myanmar
The engine of sustainable economic & social development
Environment
People(peace,
democracy, justice) Improved
living standards &economic opportunity:- Wealth generation- Access to electricity
- Education- Health
Electricity
Power sector planning in a nutshell Mechanism:
• Assess needs,• Source supply• To meet objectives (e.g. reliability, job creation)
• At reasonable price
Approaches to planning:• Centralized (top-down) • Decentralized (bottom-up)
Approaches to electrification• Off-grid/mini-grid• Grid extension
Centralized & decentralized generation
โรงไฟฟ�าสายสงไฟฟ�าแรงส�ง
สถานี�ไฟฟ�าแรงส�ง
หม้�อแปลงจำ�าหนีาย
สายจำ�าหนีาย
แรงดั�นีไฟฟ�าระดั�บส�ง
แรงดั�นีไฟฟ�าระดั�บกลาง
Gasifier/Solar farm/Biogas Plant
Cogeneration BiomassPlant/Large solar farm
HV substation
Distribution transformer
LV distribution
MV distribution
HV Transmission
Power sector planning in a nutshell Mechanism:
• Assess needs,• Source supply• To meet objectives (e.g. reliability, job creation)
• At reasonable price
Approaches to planning:• Centralized (top-down) • Decentralized (bottom-up)
Approaches to electrification• Off-grid/mini-grid• Grid extension
• There may not be a “one-size-fit-all” solution • Diverse context and situation require diverse approaches
What is the best approach for a country?
Large Plants
Customers
Small Power Producer
Mini-Grid
Customers
Parallel approach: extending the grid and encouraging rural mini-grids
NationalGrid
Top-down Bottom-up
Thailand’s approach
• Rural electrification = grid expansion + mini-grid– Community-scale power generation systems (e.g.
microhydro) were forced to abandon their generation and mini-grids when grid electricity arrived
• Centralized, monopoly (single buyer) model with strong emphasis on large-scale generation
• Deterministic forecast, top-down planning process• Little participation in decision-making and sector
development
Planning of capacity additions(Total capacity requirement = peak demand + 15% reserve margin)
Demand forecast
• Demand treated as given• Deterministic model
– Main assumptions: • GDP growth• Energy elasticity (electricity growth/GDP growth)• Population growth• Econometric model with some end-use data (e.g. floor
space for offices or appliance ownership and efficiency for residential sector) if available
Source: Energy for Environment Foundation, Study Project for Load Forecast – Executive Summary.
Total Final Energy Consumption & GDP
4.10
4.20
4.30
4.40
4.50
4.60
4.70
4.80
3.05 3.10 3.15 3.20 3.25 3.30 3.35 3.40 3.45 3.50 3.55
log (GDP)
log
(Ene
rgy)
Energy demand is 1.4 times higher than GDP growth
Energy-GDP Elasticity
Avg.'85-20011998 1999 2000 20011994 1995 1996 19971990 1991 1992 1993
1.401.07Energy Elasticity 0.97
1985
1.47 1.08 1.511.24 1.34 1.64 1.94 -3.50 0.58 0.970.47
Source : EIA,DOE, BP Statistic Review of World Energy, EGAT
Energy Elasticity = ∆t Energy Consumption/ ∆t GDP
Ave. Energy Elasticity
1.4 : 1.0
New Target1 : 1
or lower
Thailand
The government used to assume a constant Energy Elasticity of 1.4 but the assumption did not hold.
Choice of supply options considered in the PDP by EGAT
700 MW Coal-fired power plant
700 MW gas-fired combined cycle plant
230 MW gas-fired open cycle plant
1,000 MW nuclear plant
Hydro imports are politically negotiated outside of PDP processDSM/EE, RE, Distributed generation not integrated in the optimization process
• EGAT (also MEA & PEA) became “Poster-child” of World Bank, other foreign aid institutions– Access to soft loans, technical assistance, etc.– Rapid growth of sector and electrification rates– Rapid economic growth and industrial development
Outcome of Thai top-down, centralized, monopoly model
Thailand’s Fuel Mix for Power Generation
Many successes but there are also lessons learned…
• Over-projection of GDP and demand forecasts leading to cycle of over-investments
• Abandonment and discrimination of community-scale, decentralized energy systems
• High dependency on imports• Impacts and conflicts• Inequality• Inefficiency• Uncompetitive and debt-ridden economy
Comparison of GDP: forecast vs. actual
PDP2007 forecast
Case 2007 2008 2009 2010 20115-yr Avg 2012 2013 2014 2015 2016
5-yr Avg
Low 4 4.5 4.7 4.5 4.5 4.4 4.8 5 5 5.3 5.3 5.1
Base 4.8 5 5.2 5 5 5.0 5.3 5.5 5.5 5.8 5.8 5.6
High 5 5.5 5.7 5.5 5.5 5.4 5.8 6 6 6.3 6.3 6.1Actual 5.0 2.5 -2.3 7.8 1.0* 2.8 *Bank of Thailand's estimate, as reported in Matichon newspaper on Feb 4, 2012
• GDP is the main assumption affecting the power demand forecast
• Assumptions of GDP growth used in PDP2007 vs Actual.
Past demand forecasts compared to actual peak demand (MW)
Used in PDP2010
Actual demand
Over-projections of demand leads to…
• Over-expansion• Cycles of over-investments and burden on
ratepayers• No incentive to promote energy efficiency and
renewable energy• Unnecessary social, environmental impacts
– Conflicts, violence and inequality
Pak Mun Dam Story
• A World Bank funded project completed in 1994• Run-of-river 126 MW hydroelectric dam on a main tributary of
Mekong River• Source of on-going conflicts due to impacts on fish migration
and livelihood of people
Photo: http://en.wikipedia.org/wiki/Pak_Mun_dam
Electricity productionand consumption(GWh)
1700 families relocated
Loss of livelihood for >6200 families
Loss of 116 fish species (44%)
Fishery yield down 80%
65MaeHongSong
Sou
rce: M
EA
, EG
AT, S
earin
, Gra
ph
ic: Gre
en
World
Fou
nd
atio
n
Dams Shopping Malls
Pak
Mun
Dam
Impacts of Pak Mun Dam alone
MBK
123
81
75
Siam Paragon
Central World
Changing energy intensity over 20-yr period
Data source: Energy Information Administration 2008
Office of the National Economic and Social Development Board
O F F I C E O F T H E P R I M E M I N I S T E R
Low Quality
EducationLow Quality labour
Insufficient in
R&D Investm
ent
Slow Technology Development
Low
Qua
lity
for R
aw-m
ater
ial,
mac
hine
ry a
nd e
quip
men
t
(Low margin/return)
Low B
asic
infra
struc
ture
and L
ogisti
c
deve
lopm
ent
Enabling factors:MACROECONOMICMANAGEMENT
No
imm
unity
/ H
igh
vola
tility
Fi
nanc
ial S
yste
m Lack of Saving
Lack of regulation on
industrial product’s
quality control
LowValue Creation
High Import
Contents & Sheer
size of export to GDP
High Energy Intensity& Low Efficiency& Unsustainable
structure
Macroeconomic Analysis
Thailand’s power sector: sustainable economic development?
• Evident economic, material development…• …but not sustainable
– Needs to rely on ever-increasing energy imports– Vulnerability to supply disruptions due to high level
of centralization• Unproductive, inefficient consumption only made
possible by borrowing from the past (plundering resources) and the future (debt to be repaid)– Government debt now >40% of GDP – Household debt at 20-23% of income, to rise to 40%
Thailand’s economic, power sector growth
Sustainable or quality economic, social
development
Energy obesity from unhealthy consumption habits that are financed
by debt
≠
Is there a better way?
Yes!
(Full report available for download at
www.palangthai.org)
Not all energy demand/GDP $$$ are equal: some industries have high energy, environmental costs but
low value to economy
กล�ม้อ�ตสาหกรรม้ High Energy, Low VA, Low RCA
ส�ดัสวนีความ้เข้�ม้ข้�นีข้อง
การใช้�พล�งงานี
ส�ดัสวนีม้�ลคาเพ&'ม้ตอผลผล&ต
ดั�ช้นี�ความ้ไ ดั�เปร�ยบ
ทางการแข้งข้�นี(RCA)
อ�ตสาหกรรม้เหล*กและ เหล*กกล�า 0.331 0.151 0.19 การผลิ�ตสีทา น้ำ� ามั�น้ำชั�กเงา 0.183 0.323 0.25
การผลิ�ตผลิ�ตภั�ณฑ์� พลิาสีต�ก 0.18 0.3 0.91 การผลิ�ตผลิ�ตภั�ณฑ์� อโ ลิหะอ��น้ำ ๆ 0.178 0.336 0.5
การฟอก การพ�มัพ� การย้!อมั 0.177 0.27 0การผลิ�ตเคร��องย้น้ำต�แลิะก�งห�น้ำ 0.15 0.24 0.21การผลิ�ตเคร��องเร�อน้ำท�ท�า ด้!วย้โ ลิหะ 0.146 0.253 0.56แบตเตอร�แลิะหมั!อเก'บประจุ*ไ ฟฟ,า 0.142 0.264 0.59การผลิ�ตเคร��องจุ�กรแลิะอ*ปกรณ�ทางเกษตร 0.131 0.33 0.08การผลิ�ตอ*ปกรณ�รถไ ฟ 0.126 0.276 0.01
เคร��องมั�อเคร��องใ ชั!ไ ฟฟ,าอ�� น้ำ ๆ 0.125 0.313 0.95 การผลิ�ตผลิ�ตภั�ณฑ์� ทางเคมัอ��น้ำ ๆ 0.122 0.319 0.41
การผลิ�ตเคร��องจุ�กรแลิะอ*ปกรณ�พ�เศษ 0.116 0.246 0.27การผลิ�ตผลิ�ตภั�ณฑ์� จุากกระด้าษ 0.115 0.172 0.72
การผลิ�ตสี�น้ำค!าอ*ตสีาหกรรมัอ��น้ำ ๆ 0.101 0.346 1.24การผลิ�ตน้ำาฬิ�กา 0.085 0.415 1.74การผลิ�ตเคร��องด้น้ำตรแลิะ เคร��องกฬา 0.078 0.345 1.87
การบรรจุ*กระป3อง แลิะการเก'บร�กษาผ�ก ผลิไ มั! น้ำ� าผลิไ มั! 0.074 0.341 2.26การผลิ�ตผลิ�ตภั�ณฑ์� จุากไ มั!แลิะ ไ มั!ก4อก 0.074 0.358 2.83
การผลิ�ตรองเท! า ย้กเว!น้ำรองเท! าย้าง 0.072 0.388 1.94การผลิ�ตเคร��องเร�อน้ำเคร��องตกแต5งท�ท�า ด้!วย้ไ มั! 0.072 0.507 1.82
การผลิ�ตผลิ�ตภั�ณฑ์� อาหารอ��น้ำ ๆ 0.071 0.478 1.85การผลิ�ตอ*ปกรณ�การถ5าย้ภัาพแลิะสีาย้ตา 0.071 0.428 1.52การท�า เน้ำ� อกระป3อง 0.064 0.392 1.02การผลิ�ตผลิ�ตภั�ณฑ์� หน้ำ�งสี�ตว� 0.064 0.445 2.57
การอบ การบ5มัใ บย้าสี6บ 0.061 0.404 1.22 อ*ตสีาหกรรมัเคร��องด้��มัท� ไ มั5มัแอลิกอฮอลิ� แลิะน้ำ� าอ�ด้ลิมั 0.059 0.426 1.08
อ*ตสีาหกรรมัเก�ย้วก�บผลิ�ตภั�ณฑ์� เชั�อก 0.051 0.418 1.11 โ รงงาน้ำท�า น้ำ� าตาลิ แลิะผลิ�ตภั�ณฑ์� อ��น้ำ ๆ 0.045 0.383 6.07
BOI investment privileges
should take into account
energy, economic
value considerations
High energy intensity
Low value added
Low competitiveness
Iron smelter industry
Demand for electricity is not a given.We can choose wisely what kind of industries or
economic activities are worth supporting (e.g. given investment privileges) based on their energy,
environmental costs and value to economy (local job creation, local content, value creation)
Government Policy Frameworkaccording to Energy Industry Act 2007
4 dimensions of energy security
Energy Industry Act 2007 Indicators
Availability - Resource Adequacy- Min. dependency on imports- Diversification
- Reserve margin ≥15%- % energy imports-Shares of fuels
Affordability - Affordable cost of service- Min. exposure to price volatility
- Electricity cost (B/mo.)- % exposure to oil price
Efficiency - Energy & economic efficiency - Energy intensity (GWh/GDP)
Environment - Min. environmental impacts - GHG emissions- SO2 emissions
Need to make “energy security” and PDP accountable to
government policy frameworkFramework for evaluating PDPs
Insulate roofs to keep cool in
T-5
Prioritize energy efficiency (least-cost supply options)
Prioritize decentralized generation over centralized options:Cogeneration (Combined Heat and Power – CHP)
Comparing PDPs
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
PDP 2010
nuclear
EE/DSM
Others
Oil/gas
RE DEDE
Cogen
Hydro imports
Hydro
Gas
Coal
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
PDP2012
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
PDP2010v2
Dependency on electricity/fuel imports
2010 PDP2010 PDP2010v2
PDP20120
50,000
100,000
150,000
200,000
250,000
Uranium (Kazakhstan/Aus-tralia)
Power imports (Laos/Burma/Malay)
Diesel
Fuel Oil
Gas imports (Burma/Middle East)
Coal imports (Indonesia/Australia)
GWH
Cost of service (Baht/month) change in 2030 compared to 2010
2010 PDP2010 PDP2010v2 PDP20120
50
100
150
200
250
300
350
400
450
500Cost of service (Baht/month)
PDP2010 PDP2010v2 PDP2012
-15%
-10%
-5%
0%
5%3.5%
-13.2%
1.3%
Emissions of air pollutantschange in 2030 compared to 2010
GHG Nox SO2 TSP Hg-50%
0%
50%
100%
150%
200%
250%
300%
350%
400%
450%
PDP2010PDP2010v2PDP2012
Comparing PDPs against different elements of energy security change in 2030 compared to 2010
(Negative value = improved elements of energy security)
SO2 em
issions
GHG emiss
ions
Import
dependen
cy
energ
y inten
sity
Cost of s
ervice
Exposu
re to
oil pric
e risk
s
Concentra
tion (plan
t disr
uption)
PDP2010
SO2 em
issions
GHG emiss
ions
Import
dependen
cy
energ
y inten
sity
Cost of s
ervice
Exposu
re to
oil pric
e risk
s
Concentra
tion (plan
t disr
uption)
42%52% 56%
-17% -13% -21%
-97%
PDP2010v2
-15%
4%18%
-17%
1%
-19%
-97%
PDP2012
Best practices from international experience• Case study of Pacific Northwest, USA (incl. Washington
State) & Integrated Resource Planning (IRP) process
Objectives Defined
Data collection, systems analysis
Demand forecast scenarios (by end use) Meeting electricity requirement:
options
END-USE EFFICIENCY IMPROVEMENTS
T&D IMPROVEMENTS
GENERATIONPLANTS
UNIT COSTS OF ALTERNATIVES
($ / kWh)
LEAST COST MIX
ITERATION
GW
h
YEAR
$/kWh
GWh
Strategies
ImplementationPeriodic
Monitoring
CBA
IRP
Flow
char
t
Source: D’Sa, A. (2005). "Integrated resource planning (IRP) and power sector reform in developing countries." Energy Policy 33(10): 1271-1285.
Northwest Power and ConservationCouncil
slide 40
Resource Costs: fair, comprehensive cost comparison
0
20
40
60
80
100
120
140
160
180
200
Conservation New Hydro UltrasupercriticalCoal (ID)
Woody Residue NV CSP > S. ID
Lev
eliz
ed L
ife-c
ycle
Co
st ($
2006
/MW
hr)
Emissions
Transmission & Losses
Integration
Plant Cost
Source Northwest Power and Conservation Council, 6th Plan.
Northwest Power and ConservationCouncil
slide 41
6th Plan Resource Portfolio*
0
1000
2000
3000
4000
5000
6000
7000
8000
2010 2015 2020 2025
Cum
ula
tive
Res
ourc
e (
Ave
rage
Meg
awat
ts)
SCCT
CCCT
Geothermal
New Wind
RPS Wind
EnergyEfficiency
*Expected Value Build Out. Actual build out schedule depends on future conditions
Source Northwest Power and Conservation Council, 6th Plan.
Xayaburi dam vs. RE or EE investment
Economic Multiplier Effect
Source: US Department of Energy, The Jobs Connection: Energy Use and Local Economic Development, http://www.localenergy.org/pdfs/Document%20Library/The%20Jobs%20Connection.pdf Accessed March 8, 2013.
The economic multiplier, also known as the multiplier effect, is a measure of how much economic activity can be generated in a community by different combinations of purchasing and investment.
Lessons for MyanmarThe engine of sustainable economic & social development
Environment
People(peace,
democracy, justice) Improved
living standards &economic opportunity:- Wealth generation- Access to electricity
- Education- Health
Electricity
Large Plants
Customers
Small Power Producer
Mini-Grid
Customers
Parallel approach: extending the grid and encouraging rural mini-grids
NationalGrid
Top-down Bottom-up
Special considerations for Myanmar
• “The last frontier”• How to leverage external
resources while maximizing benefits to the locals and without losing sovereign power
• How to generate income while having sufficient resources to sustainably meet growing domestic needs
Strategy for Myanmar’s power sector planning, policy and development
• Integrated economic and energy policy and planning– Minimize waste, maximize efficiency– Choose economic activities wisely: low energy & resource
intensity, high economic value, high competitiveness– Maximize economic value for each energy investment:
“getting the most bang (jobs, investments, purchasing) for the $$$ invested”
• Prioritize utilization of distributed renewable over non-renewable resources
• Empower participation by citizens, entrepreneurs and communities in power sector planning and development
Thank youQuestions and discussion
Email: chom at palangthai dot orgwww.palangthai.org
Large Plants
Customers
Small Power Producer
Mini-Grid
Customers
Parallel approach: extending the grid and encouraging rural mini-grids
NationalGrid
Power export $ Donor funds $Electrification Fund
Regulatory framework allows for fair treatment of both
Centralized energy is also more costly
Thailand
PDP 2007 requires 2 trillion baht to implement, comprising:
million B• generation 1,482,000• transmission 595,000
Transmission adds 40% to generation
costs
Decentralized generation brings down costs
Ireland – retail costs for new capacity
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
100% Central / 0% DE 75% / 25% 50% / 50% 25% / 75% 0% Central / 100% DE
% DE of Total Generation
Euro
Cen
ts /
KW
h
O&M of New Capacity Fuel
Capital Amorization + Profit On New Capacity T&D Amorization on New T&D
Source: World Alliance for Decentralized Energy, April 2005
ROIC = Net profit after tax Invested capital EGAT 6.4%
MEA PEA
• Financial criteria for utilities link profits to investments– Thailand uses outdated
return-based regulation– WB’s promoted financial
criteria such as self financing ratio (SFR) also have similar effects
• ROIC (Return on Invested Capital means: the more you invest, the more profits
Incentive structure for utilities:the high their investment budget, the more profits
5.8%
Result : EGAT favors capital-intensive investments (centralized
plants) by its organization or subsidiary companies.Allowing more EE or RE generation hurts EGAT’s bottom
line
Coal18%
Natural Gas73%
Renewable2%
Hydro3%
Fuel Oil0.34%
Imported4%
Diesel0.03%
53
Thailand’s Fuel Mix for Power Generation
Total Installed Capacity: 31,517 MW (2010)
Source: Puget Sound Energy
Pacific NW: meeting growing demand through mainly investments in RE and EE
Source: Northwest Power and Conservation Council
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
Coal-fired (ICG) (MW)
CCGTurbine (MW)
SCGTurbine (MW)
Wind (MW)
Energy Efficiency (aMW)
Cu
mu
lati
ve C
ap
aci
ty (
MW
)*
Source: Charles, Gillian and Tom Eckman. 2010. Regional Conservation Progress Report – Results from 2010. Regional Technical Forum. http://www.nwcouncil.org/energy/rtf/consreport/2010/Default.asp
Cost of new conservation less than $0.02/kWh
Source: Charles, Gillian and Tom Eckman. 2010. Regional Conservation Progress Report – Results from 2010. Regional Technical Forum. http://www.nwcouncil.org/energy/rtf/consreport/2010/Default.asp
Insulate roofs to keep cool in
T-5
Source: The 5th NW Electric Power and ConservationPlan
Supply options in NW USA
Source: The 5th NW Electric Power and ConservationPlan
Supply options in NW USA
Energy waste in a typical pumping system
Important conceptual framework
• Rural electrification ≠ grid expansion• Rural electrification = off-/mini-grid + grid expansion
• Planning for domestic electricity demand (electrification) = Power Development Plan (PDP) process
• Planning for hydropower export should be treated separately, with consideration of other ways of generating income (e.g. tourism, agriculture, industrial development) as alternatives
Power sector development strategy
• Energy security– Ability to meet demand through sustainable and
efficient utilization of resources at reasonable cost• Alternative energy development• Energy prices and safety• Conservation and efficiency• Environmental protection
Thailand’s experience
• Emphasis of top-down centralized model• Treating demand as given• Emphasis on expansion and unsustainable
centralized technology options• Lack of meaningful participation
Strategy
• Efficient, sustainable utilization of resources– Self-reliance
• Self-reliance
– Efficiency (production and consumption)– Sustainable utilization of natural resources– Value to economy– Leveraging external resources– Role of private sector– Myanmar being “the last frontier”
Total Final Energy Consumption & GDP
4.10
4.20
4.30
4.40
4.50
4.60
4.70
4.80
3.05 3.10 3.15 3.20 3.25 3.30 3.35 3.40 3.45 3.50 3.55
log (GDP)
log
(Ene
rgy)
Energy demand is 1.4 times higher than GDP growth
Energy-GDP Elasticity
Avg.'85-20011998 1999 2000 20011994 1995 1996 19971990 1991 1992 1993
1.401.07Energy Elasticity 0.97
1985
1.47 1.08 1.511.24 1.34 1.64 1.94 -3.50 0.58 0.970.47
Source : EIA,DOE, BP Statistic Review of World Energy, EGAT
Energy Elasticity = ∆t Energy Consumption/ ∆t GDP
Ave. Energy Elasticity1.4 : 1.0
New Target1 : 1
or lower
Thailand
0.89
1.61
2.14
1.801.69
1.81
1.36
0.97
1.351.48
1.85
1.42 1.45 1.47 1.44 1.49
-4.62
0.25 0.30
1.77
2.77
1.46
0.94
1.24 1.15 1.07
0.81 0.73
0.11
1.34
-3.86
2.54
-5.00
-4.00
-3.00
-2.00
-1.00
0.00
1.00
2.00
3.00
2012(Q
1-Q
3)
Electricity Elasticity (Yearly)
Source: http://doc-eppo.eppo.go.th/key_indicators/elasticity/EE_EI_ELE.ppt
LN(PG) = 1.6985 LN(GDP) -13.8995R
10.60
10.70
10.80
10.90
11.00
11.10
11.20
11.30
11.40
11.50
11.60
14.40 14.50 14.60 14.70 14.80 14.90 15.00
LN
(PG
)
LN(GDP)
Power Generation Elasticity (1992-2001)
Power Generation Elasticity AVG. = 1.6985
Source: http://doc-eppo.eppo.go.th/key_indicators/elasticity/EE_EI_ELE.ppt
LN(PG) = 1.0661 LN(GDP) -4.3664R 5
11.40
11.50
11.60
11.70
11.80
11.90
12.00
12.10
14.85 14.90 14.95 15.00 15.05 15.10 15.15 15.20 15.25 15.30 15.35 15.40
LN
(PG
)
LN(GDP)
Power Generation Elasticity (2002-2011)
Power Generation Elasticity AVG. = 1.0661
Source: http://doc-eppo.eppo.go.th/key_indicators/elasticity/EE_EI_ELE.ppt
14.4 14.3 14.715.6
16.3 16.817.5 18.1 18.0
18.719.6
20.921.6
22.323.2
24.124.7
26.6
29.028.1
29.130.2
30.9 30.8 31.2 31.4 31.5 31.3 31.031.7
32.5 32.433.6
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
GW
h /
Billion B
aht
Electricity Consumption Intensity
Source: http://doc-eppo.eppo.go.th/key_indicators/elasticity/EE_EI_ELE.ppt
ใน้ำความัเป8น้ำจุร�ง มัความัไมั5แน้ำ5น้ำอน้ำจุาก เหต*การณ� “ ” ท�ไมั5คาด้หมัาย้
• การพย้ากรณ�ไฟฟ,าหร�อเศรษฐก�จุมั�กจุะไมั5ได้!น้ำ�าเหต*การณ� “ท�ไมั5” คาด้หมัาย้ มัาพ�จุารณาเพราะย้ากแก5การคาด้หมัาย้
– ต�วอย้5างเชั5น้ำ ว�กฤตการเง�น้ำใน้ำป; 2540 การพ* 5งสี6งของราคาน้ำ� ามั�น้ำโลิก ความั ร*น้ำแรงทางการเมั�อง แลิะอ*ทกภั�ย้ร!าย้แรงใน้ำรอบ 50 ป;
• ใน้ำอน้ำาคต ความัไมั5แน้ำ5น้ำอน้ำจุากภัาวะเศรษฐก�จุโลิก สีถาน้ำการณ�ด้!าน้ำ การเมั�องใน้ำประเทศ แลิะสีภัาพภั6มั�อากาศท�แปรปรวน้ำ คาด้ว5าจุะย้�งมั
อย้65ต5อไป
1990 1995 2000 2005 2010
-15.0
-10.0
-5.0
0.0
5.0
10.0
Actual GDP growth (%)
Comparison of trend lines with historical peak consumption
y = 4E-60e0.0731x
R2 = 0.9433
0
10,000
20,000
30,000
1985
1987
1989
1991
1993
1995
1997
1999
2001
2003
2005
2007
2009
MW
Historic peak demand เอ'กซ์� โพเน้ำน้ำเชัย้ลิ (Historic peak demand)
y = 831.43x - 2E+06
R2 = 0.9894
0
10,000
20,000
30,000
1985
1987
1989
1991
1993
1995
1997
1999
2001
2003
2005
2007
2009
MW
Historic peak demand เชั�งเสี!น้ำ (Historic peak demand)
Exponential Linear
Past demand trajectory was linear but how come the official demand projections have
always assumed exponential trend and over-estimated?
Source: Energy for Environment Foundation, Study Project for Load Forecast – Executive Summary.
Source: Energy for Environment Foundation, Study Project for Load Forecast – Executive Summary.
Source: Energy for Environment Foundation, Study Project for Load Forecast – Executive Summary.
Source: Energy for Environment Foundation, Study Project for Load Forecast – Executive Summary.
Source: Energy for Environment Foundation, Study Project for Load Forecast – Executive Summary.
Source: Energy for Environment Foundation, Study Project for Load Forecast – Executive Summary.
Needed: bottom up forecasts
• Thailand should invest in load forecasts that use a bottom-up approach
• using industry-specific and sector-specific data on:– electricity demand trends– technology transitions trends