    BRIEF AND DETAILED SPECIFICATIONS OF PAVEMENT QUALITYCONCRETE (PQC)

    PURPOSE:-

    The purpose of this Quality Plan for Construction of Pavement

    Quality Concrete (PQC) is to provide detailed Construction

    Methodology, Materials used, Resources deployed.

    SCOPE:-

    The Scope of this Segmental Quality Plan/ Methodology shall covers

    the construction of pavement quality concrete insertion of dowel

    bars, tie bars in accordance with the requirement of Technical

    Specifications and in conformity with the line, grades and cross

    sections shown in drawings.

    It covers the following activities:

    Selection, Testing and Acceptance of all incorporated Materials forPQC.

    Design of Mixes for PQC and Trials, Acceptance etc.

    Details of Plant, Equipment / Machinery as required in execution of

    PQC.

    Batching, Mixing, Transporting, Placing, Finishing and Curing ofConcrete for PQC.

    Mechanized Texturing and Curing operation for PQC.

    http://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    2/28

    Joint Cutting and application of Joint Sealing compound as approved.

    Quality Assurance and Control Checks during operation and post

    concreting

    DEFINITIONS:-

    The words like contract, Contractors, Engineer (Synonymous to

    Engineer's representative), Drawing, Employer, Government, Works,

    Worksite used in this Quality Plan shall be considered to have themeaning as understood from the definitions pertaining Quality

    Management System Developed for the Particular Project.

    The following abbreviation shall have the meaning as set forth below:

    MORT & H: Ministry of Roads Transport & Highways

    NHAI: National Highways Authority of India

    BIS: Bureau of Indian standards

    QA: Quality Assurance

    PQC: Pavement Quality Concrete

    MTC: Manufacture's Test Certificate

    ITP: Inspection Test Plan

    CROSS REFERENCE:-

    http://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    3/28

    This Segment Quality Plan should be read in conjunction with the

    following documents:

    ISO 9001 2000 Quality management system

    Contractor Document / Technical Specifications

    MoRTH/IS/ASTM /ACI Codes, where applicable

    IRC: SP: 57-2000, Guideline on Quality system for roads.

    RESPONSIBILITY:-

    S.

    NO

    Activity Description

    Performing

    Checking/

    Verifying

    Approving

    01 Preparation Quality Plan Section-incharge &

    QC

    Engineer

    Works

    Manager &

    QC

    Manager

    Project

    manager

    02 Selection and Testing of

    various materials for PQC,Mix Design & Trials etc

    prior to start of activity

    Section-in-

    charge &QC

    Engineer

    Works

    Manager &QC

    Manager

    Project

    manger

    03 Survey, setting out fixing

    of string lines prior to startof PQC

    Surveyor Section-in-

    charge /Site

    Engineer

    http://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    4/28

    Engineer

    04 PQC Paver deployment atvarious locations and

    other logistics

    management etc.

    Section-in-charge /

    Site

    Engineer

    WorksManager

    Project

    Manager

    05 Batching & Mixing of

    concrete as per approvedDesign mix

    Batching

    Plantin-charge

    QC

    Engineer /Lab

    technician

    06 Control of movement of

    Paver and maintenance0checks / control during

    operation

    Paver

    engineer/

    Supervisor

    Paver- in

    charge

    Project

    MechanicalEngineer

    for effective

    control ofPaving

    operation07 Transportation,

    Placing, Compaction andfinishing of PQC layers,

    Section-in-

    charge /Site

    Engineer

    QC

    Engineer /Lab

    technician

    Engineer

    08 Texturing, curing JointCutting and Sealing

    operations for PQC

    Section-in-charge /

    Site

    Engineer

    QCEngineer

    / Lab

    technician

    Engineer

    09 Inspection & Testing ofPQC as per approved ITP

    and maintaining allformats.

    QCEngineer /

    LabTechnician

    QCManager /

    QCEngineer

    Engineer

    PROCEDURE:-

    The detailed Construction Methodology involved in execution of PQC

    including Quality Assurance & Control etc. has been described in the

    following sub-chapters.

  • 7/24/2019 Pavement Quality Concrete (Pqc)

    5/28

    Survey and Setting out for PQC:

    The following steps are involved in Setting out of string wire before lying

    PQC:

    Center line of Carriageway will be marked at every 50M intervals on

    DLC surface by using Total station.

    Approval of survey and setting will be ensured and survey check sheet

    CGGC 34 17 01 is filled prior to commencement of the laying activity.

    Material Required:

    Cement:

    Any of the following types of cement may be used with prior approval

    of the Engineer:

    (i) Ordinary Portland Cement IS: 269

    (ii)

    Portland Slag Cement IS: 455

    (iii)

    Portland Pozzolana Cement IS:1489

    Cement to be used may preferably be obtained in bulk form. It shall be

    stored in accordance with stipulations contained in Clause 1014 and shall

    http://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    6/28

    be subjected to acceptance test prior to its immediate use.

    .

    Coarse Aggregate:

    Aggregates to be used in the construction of PQCwill be Crushedaggregates .

    The aggregate complying IS: 383 will be used.

    Max Size of coarse aggregate 25mm as per MoRTH 601.2.3.2(Fourth Revision : August 2001).

    Fine Aggregate:

    Clean, natural sand from River Banas form location Triveni 20km

    form Ladpura will be used. The material conforming IS: 383 is

    ensured.

    The fine aggregate shall consist of clean, natural sand or crushed

    stone sand or a combination of the two and shall conform to IS: 383.

    Fine aggregate shall be free from soft particles, clay, shale, loam,cemented particles, mica, organic and other foreign matter. The fine

    aggregate shall comply with MoRTH 602.2.4.3.(Fourth Revision :

    http://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    7/28

    August 2001).

    (The grading limits for all in aggregates shall be per IS:383 for 20mm

    nominal size Aggregate for Pavement Quality Concrete )

    Sieve Designation

    Percentage passing the Sieveby Weight

    40 mm 100

    20 mm 95100

    4.75 mm 3050

    600 micron 1035

    150 micron 06

    Water:

    Water used for mixing and curing concrete conforming to IS:

    456: 2000.

    In case of PQC During hot weather, water for preparation of

    concrete will be taken form water chilling plant.

    http://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    8/28

    Admixtures:

    Admixture conforming to IS: 6925 and IS: 9103 to improve

    workability of concrete or extension of setting time to be done.

    Storage of materials :

    Aggregates:

    Aggregate will be stock piled separately and sufficient distance will

    be maintained from each fraction to avoid intermingling.

    Storage space must be easy to inspection, removal and restorage

    of materials.

    Regular testing of aggregate stock pile will be exercised to ensure

    required gradation control.

    Cement

    Bulk cement will be stored in bulk storage containers having

    200MT capacity and the number of such bulkers will be sufficient

    to cater to the requirement at site.

    Water

    Water will be tanks covered at top and cleaned at regular

    intervals. The intake of pipe will be enclosed to exclude silt and

    http://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    9/28

    other solid materials and there shall be a minimum depth of 0.60

    m of water below the intake at all times.

    Proportioning of concrete

    Concrete Strength

    The pavement concrete should be a class M-40 concrete with a

    minimum 28 days compressive characteristic strength of 40 MPa

    1. Characteristic flexural strength at 28 days = 4.5 MPa

    2.

    Target mean strength at 28 days = 5.80MPa

    3.

    Water cement ratio =0.45 Maximum

    4.

    Slump as per IS: 1199 =31+/-15 mm

    Minimum flexural characteristic strength of 4.5 MPa.

    The ration between the 7 & 28 days strengths of 4.5 Mpa.

    For each batch

    7days (avg.)

    The average flexural strengths ( R7) =

    28 days (avg.)

    R7 to be determined for three decimal levels.

    http://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://2.bp.blogspot.com/-_mNecpRWkPA/Tz_zmo1efdI/AAAAAAAABHM/95xR1kJExwQ/s1600/image002-794602.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    10/28

    (Flexural strength of any Six consecutive 7day test result) >4.50+1.65*s

    S: Standard deviation of the group.

    Workability:

    The control of workability will be done by the slump test

    Slump will be controlled so that mix is compacted and finished

    without undue flow.

    The exact slump required at plant and site will be exercised duringtrail patch.

    Separation Membrane :

    Two applications of approved wax-based white pigmentedcuring compound will be applied on DLC.

    First coat will be applied immediately after DLC laying and

    compaction and the other before start of PQC.

    The process of application will be done using mechanical sprayer.

    The other parameters will be meeting the additional specificationClause- A-12.

    Preparation of base :

    Any visible defects / cracks more than 10mm size to be required

    by fine cement concrete mix.

    Surface will be made clean of dirt or extraneous material and free

    from damage before application compound.

    http://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    11/28

    Joints:

    The exact location and type of joint to be transferred at site as

    mentioned in drawing.

    Concrete Penetrometer and testing as per ASTM C 403 will be

    used in monitoring setting of concrete / Maturity of concrete and

    saw cutting period.

    Initial saw cut of 3mm wide , 100mm depth in transverse and

    longitudinal direction will be provided after initialset(approximately 6~8hrs).

    Final saw cutting 10~12mm wide ,20~25mm depth will de

    provided after 14days of curing at accommodate joint sealant.

    The staggering of transverse joints with reference to the base will

    be minimum 0.3m.

    Transverse joints:

    Contraction joints will be provided at every 4.5m interval except

    where expansion joints are provided.

    Transverse joints to be provided at the junction of the approach

    slabs of bridged and the rigid pavement and special location e.g.

    transition sections i.e. transition of flexible vs. rigid pavement.

    Transverse joints will be straight within specified tolerances.

    Expansion joints will be provided at the junction of the approach

    slabs of Bridges and the rigid pavement.

    http://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    12/28

    Contraction Joint:

    Contraction joints will be as per the drawing given by NHAI

    Expansion Joints:

    Joint filler board for Expansion joint will be premoulded joint

    filler as per MoRTH spec. 602.2.7

    Premoulded joint filler conforming As per IS: 1838 or BS: 2630

    Thickness of the joint = 20-25 mm

    Tolerance limit will be within +/-1.5mm

    It shall be 25 mm less in depth than the thickness of the slab

    The filler for each joint shall be furnished in a single piece for the

    full depth and width required for the joint.

    Holes to accommodate dowel bars will be as accurately board or

    punched to give a sliding till on the dowel bars.

    Dowel bars for expansion joint will as per

    Joints will be provided at the junctions of rigid and flexible

    pavement with transition slab as per the drawings.

    Where due to unavoidable conditions (for example:- joints at two

    contract package) joint are to be provided, dowel bars are fixed

    into the rigid pavement.

    The adjacent slabs shall be completely separated from each other

    http://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    13/28

    by filling joint filler board.

    Transverse construction joint

    Transverse construction joint shall be placed when concreting is

    done after a day's work.

    It will be provided at the regular location of contraction joints using

    dowel bars.

    The joint will be made butt type.

    Longitudinal joints

    Tie bars shall be provided at the longitudinal joints as per the

    drawing given by NHAI.

    Dowel bars

    These shall confirm to the requirements of IS: 432, IS: 1139 and

    IS: 1786 as relevant. The dowel bars shall confirm to Grade S 240

    and tie bars to Grade S 415 of I.S.

    It should be mild steel round, free from dirt, loose rust, scale

    straight and burring restricting slippage in the concrete.

    The dowel bars will be supported on cradles / dowel chairs in

    prefabricated joint.

    Dowel bars will be positioned at the mid depth of the slab with in a

    tolerance of + 20mm.

    http://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    14/28

    Dowel bars shall be covered by a thin plastic sheath for at least

    2/3 of length from one end for dowel bars in Contraction joint or

    half the length plus 50mm for expansion joints.

    The sheath shall se tough, durable and of an average thickness

    not less 1.25mm

    The dowel bars will be inserted by vibration method in the plastic

    concrete.

    For Expansion joints, a closely fitting cap 100mm long cotton

    waste placed over sheathened end of each dowel bar.

    Tie bars

    Free form oil, dirt, loose rust and scale.

    In longitudinal joints shall be deformed steel bars of strength 415

    MPa complying with IS: 1786.

    It should protect from corrosion for 75mm on each side of the joint

    by applying bituminous paint.

    The coating shall be dry when the Tie Bars are used.

    It should be perpendicular to the line of the joint, with the center of

    each bar on the intended line of the joint within a tolerance

    of +50mm and with a minimum cover of 30 mm below joint

    groove.

    Weather and Seasonal Limitations:

    Concreting during monsoon months:

    http://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    15/28

    Sufficient supply of tarpaulin or other waterproof cloth will be

    provided along the line of work.

    Any concrete damaged by rain will be removed and replaced.

    If the damage is limited to texture it will be retextured.

    Concreting in Hot Weather:

    Care will be taken in reducing temperature of concrete such as

    use of

    Chilled water, sprinkling of chilled water over aggregates.

    Guide wires

    Use of guidewires

    Each guidewire shall be at a constant height above and parallel to

    the required edges of the slab as described in the contract /

    drawing within a vertical tolerance of + 3 mm.

    The guidewires shall be supported and stakes preferably not more

    then 8 m apart by connectors capable of fine horizontal and

    vertical adjustment.

    The stack shall be positioned and the connectors maintained at

    their correct height and alignment before commencement of work.

    The guidewire shall be erected and tensioned for at least 2 hours

    before concreting that section.

    http://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    16/28

    Care will be taken to avoid any disturbance to the guidewire

    during paving by any construction equipment or any other means.

    CONSTRUCTION:-

    10.1 Concrete production, transportation, Paving, Texturingand Curing:-

    A batching plant of 120cum per Hr. capacity has to use for

    Production of Concrete

    Dumpers having hydraulic jack system to unload having capacity

    35 Mt (Approx. 9 cum) concrete will be deploy for transportation of

    concrete.

    Paving will be carried out in full carriageway width of 8.5 m length.

    The Paver used will be slip from Paver.

    The slip from-paving machine shall compact the concrete by

    internal vibration and shape it between the side forms with a

    conforming plate and oscillating finishing beams.

    The final finish of the surface will be done by super smoother

    attached to the rear portion of the Paver.

    Manson Trolley will be placed in between Paver and Texturing

    and Curing Mechine (TCM) for rectification of any surface defects.

    The alignment of the Paver shall be controlled automatically from

    the guide wire by 4 set of level sensors and 2 set of steering

    http://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    17/28

    sensors attached to the Paver.

    Planning and preparation will be done to pave at least at an

    average uniform speed of one m / min.

    The surface of concrete slab will Tine-textured in a direction

    parallel to the longitudinal axis of the carriageway.

    Texturing / Tining will be done with a specified machine specially

    designed for the purpose for providing grooves at a uniform

    spacing of 18 mm to 21mm.

    Depth = 3mm to 4mm

    Width = 3mm

    Curing of PQC using curing compound will be followed by

    texturing by the same TCM.

    Curing will be taken care at the edges also.

    The curing compound will be resin based aluminized reflective

    curing compound.

    After providing initial cut entire PQC will be covered with Hessian

    cloth and water turned for 14 days.

    Trail length:

    The Trial length will be constructed at least one month advance

    before starting of concrete paving work.

    Trial length of 60mm with same width, Depth etc as per

    permanent work will be done at nearer to site.

    Transverse joints and longitudinal joint of each type that are to be

    included in the pavement work will be constructed and assessed

    http://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    18/28

    in the Trial length.

    Density:

    At least 3 cores drilled when the concrete is not less than 7 days

    old.

    11.2 Strength:

    Minimum of thirty (30) beams for flexural strength and thirty cubes

    for compressive strength will be prepared form the concrete

    delivered to the paving plant.

    Each pair of beams and cubes will be representing a different

    batce of concrete.

    Compressive and flexural strength will be after 28 days curing.

    At the age of 28 days thirty cores with diameter 150 mmshould be

    saw cut from the slab.

    The cores will be saw cut in both ends to provide a specimen

    height of 300 mm +/-15mm.

    The mix will be designed to achieve

    The average flexural strength >4.5

    +1.65*s(Mpa)

    [s=standard

    deviation]

    Strength of any sample >fck1.65 s

    The average compressive strength of the

    cores0.8/ (Average compressive strength

    http://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    19/28

    of the thirty cubes.)

    Temperature Measurement:

    The temperature development in the concrete slab should be

    recorded after every 3 hours during hardening after installment of

    the thermometer & temperature-age relationship should be

    determined.

    It should be measured in the middle of the slab (vertically) at a

    horizontal distance of at least 1000 mm from any free end.

    The temperature should not exceed 70 degree C.

    Inspection Dowel Bars:

    Alignment of dowel bars and construction joint shall be checked

    by measurement relative to guide wires.

    The position of dowel bars, filler board will be measured after

    carefully exposing plastic concrete across the whole width of

    concrete.

    Preparation of joint and sealing of joint grooves:

    Transverse Joint shall not be sealed before 14 days after

    construction

    Joint grooves will be constructed to an additional depth / width as

    mentioned in drawing.

    The groove shall be cleaned and dried at the time of priming and

    sealing

    http://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    20/28

    All grooves shall be cleaned of any dirt or loose material by air

    blasting with filtered, oil-free compressed air.

    Before sealing the temporary seal provide for blocking the ingress

    of dirt, soil etc., shall be removed.

    A height compressible heat resistant paper-backed debonding

    strip as per drawing shall be inserted in the groove.

    In the case of longitudinal joints, heat resistant tapes may be

    inserted to block the leakage though bottom of the joint.

    Sealing with sealants:-

    The primer recommended by the manufacturer should be applied

    for sealants.

    Priming and sealing with applied sealants should not be carried

    out when temperature in the joint groove to be sealed is below 7deg C.

    If hot applied elastomeric type sealant complying AASHTO M282

    is used it shall be heated and applied from a thermostatically

    controlled, indirectly heated preferably with oil jacketed melter and

    pourer having recirculation pump and extruder (This is applied at

    junction of Asphalt and concrete pavements.

    Cold applied polyeurethrene / Polysulphide type complying BS:

    5212-1990Sealan will be mixed and applied according to the time

    limit specified the Manufacture to the concrete pavements.

    Primer will be applied with an appropriate brush.

    Care such as temperature and time of sealing will be emphasized

    to avoid any bulge of sealant during contraction of joint.

    Sealant shall be applied slightly to a lower level than the slab with

    http://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    21/28

    a tolerance of 5+ 2mm.

    The type and details of different joints treatment are tabulated

    below:-

    TYPE OF

    JOINT

    JOINT

    DETAILS & TREATMENT

    Polysulphide

    Sealant(cold)

    Debonding

    Strip

    3~4

    Mm

    Groove

    Soft

    Rope

    Butt

    Joint

    Compressible

    Filler Board

    Longitudinal

    Expansion

    Construction

    Contraction

    Testing of applied Sealant:-

    Joint sealant compound and primer should be tested in:

  • 7/24/2019 Pavement Quality Concrete (Pqc)

    22/28

    Cold applied Polysulphide sealant (according to BS: 5212 Part 2)

    In case if deliveries are made more frequent than testing may be

    reduced to every three months.

    Measurement of texture depthSand Patch Method

    The apparatus as mentioned in MoRTH601.12.1 will be used to

    measure the texture depth.

    The surface texture will be measured as per the method laid down

    in MoRTH601.12.1 and the same is recorded in lab format.

    Opening to Traffic:-

    No vehicular traffic including contractor's vehicles will be allowed

    on the finished surface until a field flexural strength of minimum

    4.50 MPa has been achieved where average flexural strength of

    minimum 3 specimens should exceed 4.50+1.65 s(s=standard

    deviation).

    Each series of test specimens for measurement of flexural

    strength should consists of minimum 3 test specimens.

    Prior to opening to traffic the joints should be sealed and areas

    adjacent to the pavement should be completed to a degree that

    will ensure traffic safety.

    Quality Assurance and Control Checks

    http://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    23/28

    As part of Quality Assurance this Segment Quality Plan for PQC

    has been prepared in line with the specification provided in

    relevant MoRTH clauses, Contract Supplementary Technical

    Specification and other Codes/ Standard / Specifications etc. else

    where mentioned in this Plan.

    As a part of Quality Control all the Inspection and Testing

    requirements for various activities involved in laying of PQC will

    be carried out as per relevant MoRTH Specifications & Contract

    Technical Specification atc. As described in Inspection and Test

    Plans attached to this Segment Quality Plan for PQC.

    These Inspection and Test Plans shall consist of type of

    Inspection and name of the Test to be conducted for Product

    Realization, frequency of testing acceptance criteria and category

    of Inspection.

    Inspection and Test Plans should be revised whenever there any

    change in methodology and specifications etc.

    Nonconformities in PQC:-

    Any Non-Conformity observed during field Inspection and also

    during Testing of Materials / mixes / laying system etc. the sameshould be recorded in the specified Nonconformance Report and

    necessary Corrective / Preventive actions should be initiated to

    prevent such things in future.

    QA/QC Engineers are responsible to control the Nonconforming

    products as described in Procedure, and relevant section-in-

    charge site engineers are to take appropriate corrective

    /preventive actions.

    http://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    24/28

    All Product Non-Conformities shall be observed, recorded,

    corrective/preventive actions and closing of NCR's should be as

    per the established documented procedure described in Project

    Quality Plan.

    Safety & Environmental Requirements:

    Hazard Identification, Risk assessment and Risk control measures

    for each activities and sub-activities involved in the present

    Segment shall be identified and necessary action plan shall be

    initiated.

    Environmental Aspects and Impacts associated with various

    activities and sub-activities involved in the present segment and

    their mitigation/control measures shall be identified and necessary

    measures shall be initiated.

    SEQUENTIAL OPERATION OF PQC LAYING

    DLC layer Approval

    Site cleaning, Application of 2ndcoat of curing

    compound as a separation membrane

    Survey, Setting out ,fixing of String line

    http://4.bp.blogspot.com/-Px6xFhEmku8/Tz_zm-P_OsI/AAAAAAAABHg/B9xRv8geXzs/s1600/image004-795896.pnghttp://2.bp.blogspot.com/-himf8Cj3mek/Tz_zm3odIhI/AAAAAAAABHU/T_1flYSAuX4/s1600/image003-795352.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://3.bp.blogspot.com/--JreIKWHA2M/Tz_zmlkPe2I/AAAAAAAABHA/zMmF1Uwzzkk/s1600/image001-793953.pnghttp://2.bp.blogspot.com/-himf8Cj3mek/Tz_zm3odIhI/AAAAAAAABHU/T_1flYSAuX4/s1600/image003-795352.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    25/28

    Transportation of Mix to Site

    Placing Paver and TCM

    Clearance to B/Plant for Production ofconcrete after checking string line &

    Equipment.

    Production of concrete as per the Mix design

    and adjust as per the requirement

    YES

    http://3.bp.blogspot.com/-Ds8eoJUDThQ/Tz_zno0vSFI/AAAAAAAABIE/B0iE58HEwLc/s1600/image007-798544.pnghttp://3.bp.blogspot.com/-aSiLTgOorFQ/Tz_zoG1R4iI/AAAAAAAABIg/TeFO-jk6dH8/s1600/image009-700449.pnghttp://1.bp.blogspot.com/-CRrU1mKpVyk/Tz_zn8Lkr6I/AAAAAAAABIY/8V_V5mlH-lg/s1600/image008-799115.pnghttp://4.bp.blogspot.com/-TLEhbFD8ZB0/Tz_zno98pYI/AAAAAAAABH8/lcZ1KhMGptg/s1600/image006-797966.pnghttp://2.bp.blogspot.com/-himf8Cj3mek/Tz_zm3odIhI/AAAAAAAABHU/T_1flYSAuX4/s1600/image003-795352.pnghttp://2.bp.blogspot.com/-2fSVDiqR0Vs/Tz_znF40OJI/AAAAAAAABHw/isb-VTA4JO8/s1600/image005-796832.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    26/28

    Dumping concrete at regular spacing in front of

    r and start paving

    SEQUENTIAL OPERATION OF PQC LAYING

    NO

    YES

    Monitoring levels through level sensors.

    Check the mix as per therequirement i.e. Slump,Temperature, Air content

    etc and meets as per design ?

    Reject the Mix and find out Root Cause

    http://2.bp.blogspot.com/-himf8Cj3mek/Tz_zm3odIhI/AAAAAAAABHU/T_1flYSAuX4/s1600/image003-795352.pnghttp://2.bp.blogspot.com/-himf8Cj3mek/Tz_zm3odIhI/AAAAAAAABHU/T_1flYSAuX4/s1600/image003-795352.pnghttp://2.bp.blogspot.com/-S5UaPVNPxJc/Tz_zo01V2HI/AAAAAAAABJE/Avb2_2hvMuk/s1600/image012-703076.pnghttp://1.bp.blogspot.com/-yvV8U1MOOV0/Tz_zpMMjk1I/AAAAAAAABJQ/IJbxCK09Ow8/s1600/image013-703967.pnghttp://4.bp.blogspot.com/-ccZ3wKYX7Fs/Tz_zod8V5OI/AAAAAAAABIo/3pe_jCY61fY/s1600/image010-700989.pnghttp://4.bp.blogspot.com/-3HLRzr0BHYY/Tz_zpOr6OoI/AAAAAAAABJc/5x7W40Xn5fo/s1600/image014-704920.pnghttp://3.bp.blogspot.com/-DdPHuitBaPs/Tz_zoQVkXTI/AAAAAAAABI4/X8UpntAIYJQ/s1600/image011-701626.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    27/28

    Fixing of Dowel bars and tie bars by DBI & TBI

    as per Drawing

    Rectification of surface defects (if any) manuallyby Mesons.

    Texturing & curing by TCM and Test rate of

    spraying.

    Fixing of Stopper after End of day's Work.

    Initial Joint cutting after setting of concrete

    Cleaning of joint and fixing backup rod.

    SEQUENTIAL OPERATION OF PQC LAYING

    Covering PQC with hesian cloth and water

    curing for min.14 days.

    Removal of hesian cloth and final joint cutting

    Cleaning of joint and providing soft rope,debonding strip, polysulphide sealant,

    compressible filler board , butt joint asmentioned in Table-2 in PQC methodology

    Test texture depth by Sand Patch Method

    http://2.bp.blogspot.com/-himf8Cj3mek/Tz_zm3odIhI/AAAAAAAABHU/T_1flYSAuX4/s1600/image003-795352.pnghttp://2.bp.blogspot.com/-himf8Cj3mek/Tz_zm3odIhI/AAAAAAAABHU/T_1flYSAuX4/s1600/image003-795352.pnghttp://2.bp.blogspot.com/-himf8Cj3mek/Tz_zm3odIhI/AAAAAAAABHU/T_1flYSAuX4/s1600/image003-795352.pnghttp://4.bp.blogspot.com/-3HLRzr0BHYY/Tz_zpOr6OoI/AAAAAAAABJc/5x7W40Xn5fo/s1600/image014-704920.pnghttp://4.bp.blogspot.com/-3HLRzr0BHYY/Tz_zpOr6OoI/AAAAAAAABJc/5x7W40Xn5fo/s1600/image014-704920.pnghttp://4.bp.blogspot.com/-3HLRzr0BHYY/Tz_zpOr6OoI/AAAAAAAABJc/5x7W40Xn5fo/s1600/image014-704920.pnghttp://4.bp.blogspot.com/-3HLRzr0BHYY/Tz_zpOr6OoI/AAAAAAAABJc/5x7W40Xn5fo/s1600/image014-704920.pnghttp://4.bp.blogspot.com/-3HLRzr0BHYY/Tz_zpOr6OoI/AAAAAAAABJc/5x7W40Xn5fo/s1600/image014-704920.pnghttp://2.bp.blogspot.com/-2fSVDiqR0Vs/Tz_znF40OJI/AAAAAAAABHw/isb-VTA4JO8/s1600/image005-796832.png
  • 7/24/2019 Pavement Quality Concrete (Pqc)

    28/28

    Proceed for the next activity