Outfall Canal Remediation ProjectsOutfall Canal Remediation Projects
US Army Corps of EngineersBUILDING STRONG®
AgendaAgenda PCCP Update Outfall Canal Status
►OFC-03►OFC-04A►OFC-06►OFC-05
Weekly Coordination MeetingsWeekly Coordination Meetings
BUILDING STRONG®28 June 2011
PCCP Updatep 26 May 11- Agency Report submitted to GAO Week of 6 Jun 11 – Protestors’ Responses Duep Late Jun 11 – Agency Replies Due 4 Aug 11 - GAO Decision Due Post Award and Formal Partnering Conferences on hold Post Award and Formal Partnering Conferences on hold Construction completion expected to slip to 2015
BUILDING STRONG®38 June 2011
OFC-03 (London Ave Canal) Construction Contract Awarded to Integrated Pro
Services, LLCA d d 7 D 10 Awarded 7 Dec 10
Notice to Proceed issued 22 Dec 10 Construction Complete Construction Complete
► Original project - 21 May 11► Additional 2,100 lf - 30 June 11
Type of Work - Sheet pile for seepage and embankment added at crown to reduce stick-up- 85% Complete
BUILDING STRONG®8 June 2011 4
OFC-03 (London Ave Canal) Status STATUS: STATUS:
► Original Project • Sheet pile – 100% complete• Embankment - 100% complete• Embankment - 100% complete
► Additional 2100 lf• Sheet pile - 48% complete• Embankment – 30% completep
► Red Zone was held 3 May 11► Turnover to NFS once grass is established.
TWO WEEK LOOK AHEAD► Sheet pile- Approx.1,100 lf remains to be installed by 22 June 11► Embankment- Approx 1 500 lf remains to be complete by 30 June 11► Embankment Approx. 1,500 lf remains to be complete by 30 June 11► Handrails to be installed by 28 June 11► Sheet pile delivery for Reaches 7 & 8 - 10 Jun 11► Pre-Final scheduled for Tuesday 14 Jun 11
BUILDING STRONG®
► Pre Final scheduled for Tuesday, 14 Jun 11
8 June 2011 5
OFC-03 (London Ave Canal) Status ISSUES:
► Jet pack from Orleans by 10 Jun 11 for sheet pile installation along Reaches 7 & 8.
► Leaking water pipe repair south of Filmore Ave at. Pratt Drive
BUILDING STRONG®8 June 2011 6
OFC-03
BUILDING STRONG®8 June 2011 7
Concrete Embankment Looking North between Filmore and DPS4
BUILDING STRONG®88 June 2011
Concrete Embankment Looking South between DPS4 and FilmoreS a d o e
BUILDING STRONG®98 June 2011
Leaking Water Pipe South of Filmore at Pratt Drive
BUILDING STRONG®108 June 2011
Leaking Water Pipe South of Filmore at Pratt Drive
BUILDING STRONG®118 June 2011
OFC-04A (Orleans Ave Canal)
Construction Contract Awarded to Integrated Pro Services, LLCLLC
Awarded 18 Feb 11 Notice to Proceed issued 28 Feb 11 Construction Complete 28 Jun 11 Type of Work - Sheet pile for seepage, embankment added at
crown to reduce stick-up stability berms and Deep Soil Mixingcrown to reduce stick up, stability berms and Deep Soil Mixing for strengthening the canal walls- 40% Complete
BUILDING STRONG®8 June 2011 12
OFC-04A (Orleans Ave Canal) Status
STATUS► Stability Berm -100% complete► Sheet pile - 76% complete (770 lf)► DSM - 23% complete (322 lf)► Red Zone Meeting was held 1 Jun 11► Turnover to NFS once grass is established.
TWO WEEK LOOK AHEAD► Sheet pile – approx. 240 lf remains to be installed by 14 Jun 11► DSM –approx. 1,100 lf remains to be compete by 18 Jun 11► Jet Grouting- to be complete by 24 Jun 11► Jet Grouting to be complete by 24 Jun 11► Pre-Final Inspection 28 Jun 11
BUILDING STRONG®13
OFC-04A (Orleans Ave Canal) Status
ISSUES► Jet Grouting-area under I-610 bridge
Th C t t t bl t ld h t il d i t d f• The Contractor was not able to remove old sheet pile designated for removal. Old pile is interfering with sheet pile driving in the area. Jet grouting will be performed in the area of interference.
► Concerns:• Encountering obstructions while driving sheet pile• Encountering obstructions while performing DSM
BUILDING STRONG®148 June 2011
OFC-04A
BUILDING STRONG®8 June 2011 15
New Sheet Pile
Old Sheet Pile
BUILDING STRONG®
BUILDING STRONG®8 June 2011 17
BUILDING STRONG®188 June 2011
BUILDING STRONG®198 June 2011
BUILDING STRONG®208 June 2011
OFC-06 (Orleans Ave Canal)( )
Construction Contract Awarded to Progressive gConstruction Company, LLC
Awarded 23 Dec 10 Notice to Proceed issued 6 Jan 11 Construction Complete 13 Apr 11p p Type of Work - Stability berm for strengthening
the canal levees. The stability berm is 100% Complete► Approx. 1,000 linear ft of berm
BUILDING STRONG®8 June 2011 21
OFC-06 (Orleans Ave Canal) Status( )
Red Zone was held 2 March 2011P Fi l h ld 31 M h 11 d h li t Pre-Final was held on 31 March 11 and a punch list was developed.
Project was substantially complete on 31 March 11 Project was substantially complete on 31 March 11. Re-hydro seeding completed 4 Jun 11. Punch list completion 7 Jun 11Punch list completion 7 Jun 11. Turnover to NFS once grass is established.
BUILDING STRONG®8 June 2011 22
OFC-06
BUILDING STRONG®8 June 2011 23
Drainage Headwall at Orleans Avenue Canal
BUILDING STRONG®248 June 2011
Re-Hydro Seeded Berm at Orleans Avenue Canal
BUILDING STRONG®258 June 2011
OFC-05 (17th Street Canal)
Construction Contract Awarded to Bailey CKY JV Awarded 9 Dec 10 Awarded 9 Dec 10 Notice to Proceed issued 28 Dec 10 Construction Complete 30 Jun 11Construction Complete 30 Jun 11 Type of Work – Jet Grouting for strengthening the canal
walls and embankment added at crown to reduce stick-80% C l tup -80% Complete
BUILDING STRONG®8 June 2011 26
OFC-05 (17th Street Canal) Status STATUS:
► Red Zone was held 2 May 11.► Embankment Rebuild- 10%► Jet Grouting- 92%► Rip Rap- 100%► Grouting of Obstruction at WB 578+00 Completed 6 June 11► G ou g o Obs uc o a 5 8 00 Co p e ed 6 Ju e► Turnover to NFS once grass is established.
TWO WEEK LOOK AHEAD TWO WEEK LOOK AHEAD► East side panels completed 7 June 11, levee rebuild ongoing, complete
by 24 June 11 ► West side panels complete by 20 June 11 levee rebuild ongoing► West side panels complete by 20 June 11, levee rebuild ongoing,
complete by 28 June 11► Reach 16 Surveys being conducted to determine if improvements are
needed
BUILDING STRONG®
► Pre-Final Inspection 30 Jun 11.
8 June 2011 27
OFC-05 (17th Street Canal) Status ISSUES:
► Reach 16 may need 6” to 18” of embankment at the toe of► Reach 16 may need 6 to 18 of embankment at the toe of the levee, determination will be made after the survey is analyzed.
► If rain delays levee rebuild, 16 hour operations, sunrise to sunset, may be necessary to stay on schedule.
► AFE being requested
BUILDING STRONG®8 June 2011 28
OFC-05
BUILDING STRONG®8 June 2011 29
17th Street West side Obstruction
BUILDING STRONG®308 June 2011
17th Street West side Obstruction
BUILDING STRONG®318 June 2011
17th Street West side Obstruction
BUILDING STRONG®328 June 2011
17th Street Canal Reach 16
BUILDING STRONG®338 June 2011
17th Street Canal Reach 16
BUILDING STRONG®348 June 2011
17th Street Canal Reach 16
BUILDING STRONG®358 June 2011
Weekly Construction Status MeetingsWeekly Construction Status Meetings
OFC-05 - 17th Street Canal - Weekly status meetings are held at the job trailer located at 6780 Bellaire on Tuesdays at 1000.
OFC-03 - London Avenue Canal - Weekly status meetings are held at the job trailer at 5701 Pratt Drive (directly across from DPS #4) on Tuesdays at 0830.
OFC-04A - Orleans Avenue Canal – Weekly status meetings are held at the job trailer located at Marconi & Filmore on Wednesdays at 0830.
BUILDING STRONG®8 June 2011 36