Kopeopeo Canal Sediment Remediation Project Community Liaison Meeting Tuesday 19 July 2016 Brendon Love, Project Manager

Upload: nguyenphuc

Post on 20-Mar-2018

218 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Kopeopeo Canal Sediment Remediation Project · PDF fileKopeopeo Canal Sediment Remediation Project ... f d i o x i n a b o v e t h r e s h o l d ... • Final report to Independent

Kopeopeo Canal Sediment Remediation Project

Community Liaison Meeting

Tuesday 19 July 2016

Brendon Love, Project Manager

Page 2: Kopeopeo Canal Sediment Remediation Project · PDF fileKopeopeo Canal Sediment Remediation Project ... f d i o x i n a b o v e t h r e s h o l d ... • Final report to Independent

2

Meeting agenda topics

• Communications – Abby Tozer

• Recent sediment sampling results – Brendon Love

• Update on variation application – Brendon Love

• Independent Monitor feed back – Andrew Kohlrusch

• Update on tender process – Brendon Love

• Other matters – Brendon Love

• Wood waste site progress - Ken Tarboton

Page 3: Kopeopeo Canal Sediment Remediation Project · PDF fileKopeopeo Canal Sediment Remediation Project ... f d i o x i n a b o v e t h r e s h o l d ... • Final report to Independent

Recent sediment sampling results

• Sediment sampling and analysis was carried out in the canal and adjoining drains / wetlands (link to sampling locations)

• The purpose of the sampling was:

– To baseline the canal prior to handing the project site to the contractors

– To ensure that contaminant levels within side drains and areas not previously investigated were below remediation targets

3

Page 4: Kopeopeo Canal Sediment Remediation Project · PDF fileKopeopeo Canal Sediment Remediation Project ... f d i o x i n a b o v e t h r e s h o l d ... • Final report to Independent

Sample Locations - West• Samples circled in red

are above remediation target of 60 pg I-TEQ/g

• These are in privately owned part of canal outside of project scope and MfE deed funded area

Page 5: Kopeopeo Canal Sediment Remediation Project · PDF fileKopeopeo Canal Sediment Remediation Project ... f d i o x i n a b o v e t h r e s h o l d ... • Final report to Independent

Sample Locations - EastSamples circled in red are above remediation target of 60 pg I-TEQ/g

Page 6: Kopeopeo Canal Sediment Remediation Project · PDF fileKopeopeo Canal Sediment Remediation Project ... f d i o x i n a b o v e t h r e s h o l d ... • Final report to Independent

Bulk of dioxin (86%) above remediation threshold will be removed by current project

0%

10%

20%

30%

40%

50%

60%

70%

SH30 west580-2,650m

SH30 west0- 580m

Section 1 Section 2 Section 3 Stopbanks(Gateway)

Saltmarsh

Per

cen

t o

f d

ioxi

n a

bo

ve t

hre

sho

ld

Location

Percent of Total Dioxinabove threshold of 60 pg I- TEQ /g

Section 1

Section 2

Section 3

SH30 west (580m)

SH30 west (580m - 2,650m)

Stopbanks (Gateway)

Saltmarsh

86%

86%

Page 7: Kopeopeo Canal Sediment Remediation Project · PDF fileKopeopeo Canal Sediment Remediation Project ... f d i o x i n a b o v e t h r e s h o l d ... • Final report to Independent

Actions proposed

• Some locations are outside of the scope of the consents and project funding deed

• Further sampling has been completed to define the extent of elevated contaminants –analysis underway

• Once defined, remediation or management options can be considered.

• Additional funds & approval of new consents will be required

• Land is not owned by BoPRC

7

Page 8: Kopeopeo Canal Sediment Remediation Project · PDF fileKopeopeo Canal Sediment Remediation Project ... f d i o x i n a b o v e t h r e s h o l d ... • Final report to Independent

• Containment of contaminant upstream of SH30 is required to ensure current project objectives are not compromised (e.g. re-contamination)

Actions proposed (cont.)

8

• Floodgates now in normal operation

• Discussions with landowners underway

• Project team considering alternative delivery approaches (e.g. east to west)

Page 9: Kopeopeo Canal Sediment Remediation Project · PDF fileKopeopeo Canal Sediment Remediation Project ... f d i o x i n a b o v e t h r e s h o l d ... • Final report to Independent

Update on variation application

• Consent variation application lodged on 18 April 2016

• s92 request received and responded to

• Focus has been on water quality in discharge and further consideration of flood mitigation control measures

• Final report to Independent Commissioner in late July

• Decision expected in August

9

Page 10: Kopeopeo Canal Sediment Remediation Project · PDF fileKopeopeo Canal Sediment Remediation Project ... f d i o x i n a b o v e t h r e s h o l d ... • Final report to Independent

RFP process

• Two very strong tenders evaluated based on non-price attributes

• Prices received outside of budget

• Negotiation underway with preferred contractor

• Focus to develop revised implementation plan that meets FY16/17 budget and long term project goals

10

• Competitive Dialogue undertaken Feb.-April.

• Stage 2 RfP closed on 27 May

• RFP responses evaluated

Page 11: Kopeopeo Canal Sediment Remediation Project · PDF fileKopeopeo Canal Sediment Remediation Project ... f d i o x i n a b o v e t h r e s h o l d ... • Final report to Independent

Other matters

• Fence installed between the canal and Keepa Road walkway/cycleway

• Filtrate results still close to detection limit (5 pg I-TEQ/L)

• Baseline Air Quality report online

• Bioremediation cell testing ongoing

• Some vegetation clearance and mulching completed along canal

11

Page 12: Kopeopeo Canal Sediment Remediation Project · PDF fileKopeopeo Canal Sediment Remediation Project ... f d i o x i n a b o v e t h r e s h o l d ... • Final report to Independent

Picograms analogy

12

Page 13: Kopeopeo Canal Sediment Remediation Project · PDF fileKopeopeo Canal Sediment Remediation Project ... f d i o x i n a b o v e t h r e s h o l d ... • Final report to Independent

Wood waste site progress

• Contaminated site working group (CSWG) meetings (Feb, April, July 2016)

• Revised draft management plans being written

• Sites prioritised for site inspections based on desktop assessment of risk

• Site inspections underway to assess risks, wood waste cover and reinforce management plan requirements by owners / lessees

• New signage proposed for CSWG approval – 26 July

13

Page 14: Kopeopeo Canal Sediment Remediation Project · PDF fileKopeopeo Canal Sediment Remediation Project ... f d i o x i n a b o v e t h r e s h o l d ... • Final report to Independent

Questions?

14

Page 15: Kopeopeo Canal Sediment Remediation Project · PDF fileKopeopeo Canal Sediment Remediation Project ... f d i o x i n a b o v e t h r e s h o l d ... • Final report to Independent

15

Recent sampling locations

Powdrell Rd