a combined solution for sediment remediation and waterfront development a combined solution for...

24
A Combined Solution for Sediment Remediation and Waterfront Development John T. Finn, P.E. GEI Consultants, Inc. . Dredging 2012

Upload: godfrey-austin

Post on 05-Jan-2016

222 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

A Combined Solution for Sediment Remediation and

Waterfront Development

John T. Finn, P.E.

GEI Consultants, Inc.

.

Dredging 2012

Page 2: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

The Problem

Dredging 2012

Page 3: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

• Removal of Sheen-Producing Sediments

• Protection of Existing Bulkheads

• Capping of Remaining Sediments

• On-site Solidification of Dredged Sediments

• Preparation for Waterfront Redevelopment

A Complex Problem: A Combined Solution : John Finn, GEI

Dredging 2012

Page 4: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

Location: A Slip in New Bedford Harbor

Page 5: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

Manufactured Gas and Tar Plant 1880 - 1960

OUTER SLIPIN

NER

SLIP

Dredging 2012

Page 6: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

Outer Slip:

- Remove all sheen-producing sediment in top foot

- No off-site disposal:

Place all dredged sediment in Inner Slip

- 2-foot Composite Cap

Inner Slip - Solidify dredged sediment and existing sediment/soil

to bedrock

- Prepare the site for waterfront redevelopment

Minimum Remedy Requirements

Dredging 2012

Page 7: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

Remediation – Plan View

Cell 2 Cell 1

Capping Area

Fixed Turbidity Curtain

Dredged Areas for Tar Removal

Dredged Area for Cap Installation

ISSMixing Plant

Water Treatment

Facility

Sheet Pile Walls

Inner Slip ISS & Fill Area

Page 8: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

• Protection of bulkhead stability

• Final elevation allows sufficient draft for boat traffic

• Limited capacity of Inner Slip:

- Account for expansion upon solidification

- Account for expansion/settling upon dredging/placement

Dredging Requirements and Constraints

Dredging 2012

Page 9: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

Dredging Behind Dual Curtains & Booms

Dredging 2012

Page 10: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

Dredging of Outer Slip

Page 11: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

Vapor & Odor Suppression Foam

Dredging 2012

Page 12: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

GPS Positioning of Dredge Bites

Page 13: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

Capping of Remaining Sediments

Benthic Sand – 12 inches

Stone Armor – 3 inches

Gravel – 3 inches

AquaBlok – 6 inches

Sand Fill – thickness varies

Page 14: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

AquaBlok

Dredging 2012

Page 15: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

Cap Placement

Dredging 2012

Page 16: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

Solidification: Inner Slip – Section View

Cell 2 Cell 1

Existing Bulkhead

Top of Bedrock (El. -24.2)

New Sheet Pile Closure Walls

Top of Dredge SpoilsTop of Sediments

Mean High WaterMean Low Water

Top of Dredge Spoils

Top of Bedrock (El. -39.0)

Page 17: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

Soil Mixing to Solidify Sediments

Page 18: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

• 1,350 cubic yards dredged• 18,000 ft2 dredge area• 190 - eight foot diameter ISS columns• 37 - three foot diameter ISS columns• 7,000 - cubic yards of sediment and soil

mixed• 427 ton of AquaBlok

Dredging, Capping, and ISS Statistics

Page 19: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

Site Ready for Waterfront Development

Dredging 2012

Page 20: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

Questions?

Thank You

Dredging 2012

Page 21: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

• Environmental Business Council’s

2012 Award for Collaboration

• Study of In-Situ Solidification of Contaminated Sediments, Sponsored by the Electric Power Research Institute (EPRI)

Post-Scripts

Dredging 2012

Page 22: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

• MassDEP leadership streamlined complex permitting– Reached out to federal, state & local regulators– Coordinated multi-agency team approach – Hosted & facilitated 2 critical multi-agency meetings 

• Public engagement– Public notice soliciting public comments on

10/23/2010 – Public meeting on 12/8/2010 with USEPA and

MassDEP

• Innovative MCP site closure strategy

Coordinating Multiple Agencies

Page 23: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

• MassDEP– Release Abatement Measure Plan– 401 Water Quality Certification– Chapter 91 License

• EPA – TSCA 61C – Risk-Based Cleanup Plan

• U.S. Army Corps of Engineers, New England District– Category 2 General Permit

• New Bedford Conservation Commission - Wetland Order Of Conditions

• Property Owner Agreement: Fueling Terminal Ops

Permitting and Legal Framework

Dredging 2012

Page 24: A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T

Dredge Cut Lines

Min.

Max.

El -14.

El -15.

Min.

Max.

El -14.5

El -14.

Tolerance Near Bulkheads Tolerance In All Other Areas

Dredging 2012