origin spring gully

Upload: david-smith

Post on 05-Apr-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Origin Spring Gully

    1/14

    SPRING GULLY PROJECT

  • 7/31/2019 Origin Spring Gully

    2/14

    SPRING GULLY DEVELOPMENT AREA

    Gas Plant3x3500 HP compression36TJ/d capacity

    Pipeline89km transmission pipeline147km gathering system

    Wellhead42 wells

    Evaporation Pond15-20,000 kl/d capacity

  • 7/31/2019 Origin Spring Gully

    3/14

    Delivered under EPCM project management philosophywith key disciplines managed by Origin employees

    Origin is Project Manager

    Multiple Contracting Philosophy

    Shedden Uhde Management System

    Cost Control

    Contracting/Procurement/Expediting

    Engineering Design

    Origin Staff Imbedded throughout Team under OriginProject Director

    Operations Staff Employed from Start

    Field Supervision engaged by Origin

  • 7/31/2019 Origin Spring Gully

    4/14

    Spring Gully Project Schedule

    June 2005July 2005First gas

    May 2005April 2005Complete Gas Plant

    March 2005Nov 2004Complete PipelineConstruction

    Feb 2005Feb 2005Complete GatheringSystem

    Oct 2004Jul 2004Complete DetailedEngineering

    Actual DateForecast Date

  • 7/31/2019 Origin Spring Gully

    5/14

    Environmental Approvals

    Extensive baseline environmental

    studies completed. Hydrology Flora/Fauna Soils Groundwater European Heritage

    Noise Environmental Management Plan

    approved by regulatory authorityand environmental licence issued.

    Baseline studies identified twoecosystems and two fauna speciesprotected by CommonwealthLegislation (EPBC Act).

    The development was referred forapproval under the EPBC Act andfound to be a not controlledaction.

    Brigalow Scaly Foot

    Squatter Pigeon

  • 7/31/2019 Origin Spring Gully

    6/14

    Native Title & Cultural Heritage Approvals

    Cultural Heritage Agreements have been reachedwith the relevant Native Title parties for the area.

    Representatives of Traditional Owner groups areemployed to checkall proposed newdisturbances andmonitor earthworksactivities.

    An Indigenous LandUse Agreement (ILUA)

    was reached with theNative Title party for

    PL204.

  • 7/31/2019 Origin Spring Gully

    7/14

    How CSG is trapped

    Unlike conventional natural gas reservoirs, where gas is trapped bybuoyancy underneath a sealing rock within the pores (holes) in thereservoir rock, gas in coals is adsorbed onto the surface of the coals(micropores and fractures) and held in place by the water pressure. This

    means a structural trap is not necessary to retain CSG, howeverundersaturation with gas can occur if the water pressure is higher than inthe past, meaning more water must be produced to obtain the same gasvolume

    SAND GRAIN

    PORE SPACE

    FACE CLEAT

    BEDDING PLANE

    BUTT CLEAT

  • 7/31/2019 Origin Spring Gully

    8/14

    CSG Vs Conventional Production

    Because the micropore surface area of coals is much larger than theporosity in conventional reservoirs, coals can retain much larger volumes

    of gas over the same thickness and area. However the productioncharacteristics of a coal is more dominated by the fracture network(cleats and joints) and this means drilling is generally targeted towardareas with a higher chance of dense, open fractures

    StableProductionDewatering Decline

    Methane

    Pro

    duction

    Time

    Water

    Methane

    Production

    Time

    Water

    CSG Production Profile Conventional ProductionProfile

    Typical conventional sandstone field(6.5m thick, 1500m depth) in theSurat Basin contains 2.2 PJ/km2 ofrecoverable gas

    Typical CSG field (20 mthick, 500m depth) in theSurat Basin contains 5.1PJ/km2 of recoverable gas

  • 7/31/2019 Origin Spring Gully

    9/14

    WELLHEAD & SEPARATOR

    WELLHEAD & SEPARATOR

    TYPICAL WELL SPACING 1.0 - 1.5km2

    COALDEPTH~700 -800m

    UNDER REAMING

    PUMP

    PUMP

    FLARESTACK

    GAS FACILITY

    EVAPORATION PONDS

    GasL

    ine

    Barren Rock

    Coal Seams

    Overburden

    Barren Rock

    WATER PUMP

    WELL CASING

    CASING

    Water

    Line

    SalesGasLine

    WaterLi

    ne

    GasLi

    ne

  • 7/31/2019 Origin Spring Gully

    10/14

    Spring Gully Gathering Facilities

    Water

    Gathering

    Flowlines

    Permeate (Salt Water)to Evaporation Ponds

    Fresh Water

    to irrigation orcreek discharge

    Gas and Water Gathering Flowlines

    Possible re-injection of pond brine

    to depleted coal seams

    Reverse Osmosis F ield Trial

    Sales Gas Compressor

    Gas

    Gathering

    Flowlines

    Evaporation Pond & Storage

    Pigging Facility

    Sales Gas Pipeline

    Wellhead & Separator

    Irrigation

    Creek Discharge

  • 7/31/2019 Origin Spring Gully

    11/14

    Wellhead

    Drive Head

    RemoteTelemetry

    Unit

    Water & Gas Metering System

    Water & Gas Separator

    Gas fired hydraulicdrive unit

    UNDER-REAMHOLE

    WATER

    PUMP

    CASING

    CEMENT TOSURFACE

    OVERBURDEN G

    ASGAS

    TA

    RGET

    S

    EAM

  • 7/31/2019 Origin Spring Gully

    12/14

    Cavitation Rig Layout

    COAL COLLECTIONPITS

    CATWALK ANDPIPE RACKS

    BLOOIE LINE

    CAVITATION RIG BOP STACK

    RIGFLOOR

    MUDTANKS

  • 7/31/2019 Origin Spring Gully

    13/14

    Cavitation - Well Schematic

    PLAN VIEW

    SHEARFAILUREZONE

    TENSILEFAILUREZONE

    ORIGINALWELLBORE

    CAVITY

    ENHANCED PERMEABILITY ZONEEQUALS PRODUCTION INCREASE

  • 7/31/2019 Origin Spring Gully

    14/14

    Fracture Stimulation Well Schematic