origin spring gully
TRANSCRIPT
-
7/31/2019 Origin Spring Gully
1/14
SPRING GULLY PROJECT
-
7/31/2019 Origin Spring Gully
2/14
SPRING GULLY DEVELOPMENT AREA
Gas Plant3x3500 HP compression36TJ/d capacity
Pipeline89km transmission pipeline147km gathering system
Wellhead42 wells
Evaporation Pond15-20,000 kl/d capacity
-
7/31/2019 Origin Spring Gully
3/14
Delivered under EPCM project management philosophywith key disciplines managed by Origin employees
Origin is Project Manager
Multiple Contracting Philosophy
Shedden Uhde Management System
Cost Control
Contracting/Procurement/Expediting
Engineering Design
Origin Staff Imbedded throughout Team under OriginProject Director
Operations Staff Employed from Start
Field Supervision engaged by Origin
-
7/31/2019 Origin Spring Gully
4/14
Spring Gully Project Schedule
June 2005July 2005First gas
May 2005April 2005Complete Gas Plant
March 2005Nov 2004Complete PipelineConstruction
Feb 2005Feb 2005Complete GatheringSystem
Oct 2004Jul 2004Complete DetailedEngineering
Actual DateForecast Date
-
7/31/2019 Origin Spring Gully
5/14
Environmental Approvals
Extensive baseline environmental
studies completed. Hydrology Flora/Fauna Soils Groundwater European Heritage
Noise Environmental Management Plan
approved by regulatory authorityand environmental licence issued.
Baseline studies identified twoecosystems and two fauna speciesprotected by CommonwealthLegislation (EPBC Act).
The development was referred forapproval under the EPBC Act andfound to be a not controlledaction.
Brigalow Scaly Foot
Squatter Pigeon
-
7/31/2019 Origin Spring Gully
6/14
Native Title & Cultural Heritage Approvals
Cultural Heritage Agreements have been reachedwith the relevant Native Title parties for the area.
Representatives of Traditional Owner groups areemployed to checkall proposed newdisturbances andmonitor earthworksactivities.
An Indigenous LandUse Agreement (ILUA)
was reached with theNative Title party for
PL204.
-
7/31/2019 Origin Spring Gully
7/14
How CSG is trapped
Unlike conventional natural gas reservoirs, where gas is trapped bybuoyancy underneath a sealing rock within the pores (holes) in thereservoir rock, gas in coals is adsorbed onto the surface of the coals(micropores and fractures) and held in place by the water pressure. This
means a structural trap is not necessary to retain CSG, howeverundersaturation with gas can occur if the water pressure is higher than inthe past, meaning more water must be produced to obtain the same gasvolume
SAND GRAIN
PORE SPACE
FACE CLEAT
BEDDING PLANE
BUTT CLEAT
-
7/31/2019 Origin Spring Gully
8/14
CSG Vs Conventional Production
Because the micropore surface area of coals is much larger than theporosity in conventional reservoirs, coals can retain much larger volumes
of gas over the same thickness and area. However the productioncharacteristics of a coal is more dominated by the fracture network(cleats and joints) and this means drilling is generally targeted towardareas with a higher chance of dense, open fractures
StableProductionDewatering Decline
Methane
Pro
duction
Time
Water
Methane
Production
Time
Water
CSG Production Profile Conventional ProductionProfile
Typical conventional sandstone field(6.5m thick, 1500m depth) in theSurat Basin contains 2.2 PJ/km2 ofrecoverable gas
Typical CSG field (20 mthick, 500m depth) in theSurat Basin contains 5.1PJ/km2 of recoverable gas
-
7/31/2019 Origin Spring Gully
9/14
WELLHEAD & SEPARATOR
WELLHEAD & SEPARATOR
TYPICAL WELL SPACING 1.0 - 1.5km2
COALDEPTH~700 -800m
UNDER REAMING
PUMP
PUMP
FLARESTACK
GAS FACILITY
EVAPORATION PONDS
GasL
ine
Barren Rock
Coal Seams
Overburden
Barren Rock
WATER PUMP
WELL CASING
CASING
Water
Line
SalesGasLine
WaterLi
ne
GasLi
ne
-
7/31/2019 Origin Spring Gully
10/14
Spring Gully Gathering Facilities
Water
Gathering
Flowlines
Permeate (Salt Water)to Evaporation Ponds
Fresh Water
to irrigation orcreek discharge
Gas and Water Gathering Flowlines
Possible re-injection of pond brine
to depleted coal seams
Reverse Osmosis F ield Trial
Sales Gas Compressor
Gas
Gathering
Flowlines
Evaporation Pond & Storage
Pigging Facility
Sales Gas Pipeline
Wellhead & Separator
Irrigation
Creek Discharge
-
7/31/2019 Origin Spring Gully
11/14
Wellhead
Drive Head
RemoteTelemetry
Unit
Water & Gas Metering System
Water & Gas Separator
Gas fired hydraulicdrive unit
UNDER-REAMHOLE
WATER
PUMP
CASING
CEMENT TOSURFACE
OVERBURDEN G
ASGAS
TA
RGET
S
EAM
-
7/31/2019 Origin Spring Gully
12/14
Cavitation Rig Layout
COAL COLLECTIONPITS
CATWALK ANDPIPE RACKS
BLOOIE LINE
CAVITATION RIG BOP STACK
RIGFLOOR
MUDTANKS
-
7/31/2019 Origin Spring Gully
13/14
Cavitation - Well Schematic
PLAN VIEW
SHEARFAILUREZONE
TENSILEFAILUREZONE
ORIGINALWELLBORE
CAVITY
ENHANCED PERMEABILITY ZONEEQUALS PRODUCTION INCREASE
-
7/31/2019 Origin Spring Gully
14/14
Fracture Stimulation Well Schematic