operation result of the hachinohe microgrid demonstration project · 2014-12-12 · main driving...

18
MITSUBISHI ELECTRIC 1 Operation Result of the Hachinohe Microgrid Demonstration Project 5 th Microgrid Symposium (San Diego) Yasuhiro Kojima Advanced Technology R&D Center Mitsubishi Electric Crop., Japan

Upload: others

Post on 10-Jan-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Operation Result of the Hachinohe Microgrid Demonstration Project · 2014-12-12 · main driving factor of Microgrid in Japan. •" Objectives of Microgrid Demonstration Project:

MITSUBISHI!ELECTRIC!

1

Operation Result of the Hachinohe

Microgrid Demonstration Project

5th Microgrid Symposium (San Diego)!

Yasuhiro Kojima Advanced Technology R&D Center

Mitsubishi Electric Crop., Japan

Page 2: Operation Result of the Hachinohe Microgrid Demonstration Project · 2014-12-12 · main driving factor of Microgrid in Japan. •" Objectives of Microgrid Demonstration Project:

MITSUBISHI!ELECTRIC!

2

1.!Objective

2.!System Overview

3.!Control Concept

4.!Operation Results

1.!Interconnected operation

2.!Islanding operation

Page 3: Operation Result of the Hachinohe Microgrid Demonstration Project · 2014-12-12 · main driving factor of Microgrid in Japan. •" Objectives of Microgrid Demonstration Project:

MITSUBISHI!ELECTRIC!

3

1.Objective

Photovoltaic

Total:130kW Wind turbine

Total:20kW

•" Stabilization of weather-dependent energy is one of the

main driving factor of Microgrid in Japan.

•" Objectives of Microgrid Demonstration Project:

•" Demonstration of Microgrid system as a new way of

introducing PVs, WTs, or other Renewable Energy

Sources (RES).

•" Development, operation, and evaluation of Microgrid

system with the ability to stabilize and control total

energy including weather-dependent energy.

Page 4: Operation Result of the Hachinohe Microgrid Demonstration Project · 2014-12-12 · main driving factor of Microgrid in Japan. •" Objectives of Microgrid Demonstration Project:

MITSUBISHI!ELECTRIC!

4

Hachinohe Project: •" Demand: Seven building facilities, sewage plant

!" Electricity: maximum 610kW at Hachinohe City hall,

four schools and office building.

!" Heat: 10Gcal/day at Sewage plant

•" Energy supply: Only RESs

!" Electricity: 510kW(170x3) biogas engines,

130kW PVs, 20kW WTs,

100kW lead-acid battery

!" Heat: 1.0t/h wood boiler and 4t/h gas boiler

•" Energy management

!" 5.4km Private line (electricity & communication)

!" Interconnected with commercial grid at a single

point.

!" Control error target: Within 3% every 6 minutes

moving average

2. System overview

This project is jointly undertaken by Mitsubishi Research Institute,

Mitsubishi Electric Corporation, and Hachinohe City with the support of the

New Energy and Industrial Technology Development Organization(NEDO)

Page 5: Operation Result of the Hachinohe Microgrid Demonstration Project · 2014-12-12 · main driving factor of Microgrid in Japan. •" Objectives of Microgrid Demonstration Project:

MITSUBISHI!ELECTRIC!

Sewage Plant

5

Private distribution line!5.4km

GEs!510kW!

Battery!±100kW!

PV!100kW!

PV!10kW!

PV!10kW!

WT!4kW!

WT!8kW!

PV!10kW!

Demand!50kW!

Demand!360kW!

Demand!50kW!

Demand!50kW!

Demand!50kW!

WT!8kW!

Demand!50kW!

2. System overview

Hachinohe

Aomori!

Utility Grid

Digestion Chamber

Digestion Gas (Methane)

Wood boiler (1t/h)

Gas Boiler (4t/h)

Heat

Gas tank

Page 6: Operation Result of the Hachinohe Microgrid Demonstration Project · 2014-12-12 · main driving factor of Microgrid in Japan. •" Objectives of Microgrid Demonstration Project:

MITSUBISHI!ELECTRIC!

6

•" To satisfy both of economical (or environmental) optimization and

electric power quality, !" Control system consists of four functions to handle enormous

dimensions of the problems. !" Implement local control system considering islanding

operation.

Object Function Abstract Interval Time unit,

Period

Optimization

(Economical &

Environmental)

Weekly Operation

Planning(WOP)

Calculation of the optimal fuel supply, the

storage plan of electricity and heat in a

week timeframe.

1day 30-minute unit,

8 days

Economic Dispatching

Control(EDC)

Redispatch generation based on the

difference between forecasted and actual

data.

3min 3-minute unit,

2 hours

Quality

(Tie-line flow

and frequency)

Flat Tie-Line Control

(Central Frequency

Control)

Simply central P-I control for generation

is installed to reduce the fluctuation of tie-

line power flow. 1sec -

Local Frequency

Control

(Islanding mode)

High-speed compensation of battery

output using local frequency observation

is installed. 10msec -

3. Control Concept

Page 7: Operation Result of the Hachinohe Microgrid Demonstration Project · 2014-12-12 · main driving factor of Microgrid in Japan. •" Objectives of Microgrid Demonstration Project:

MITSUBISHI!ELECTRIC! 3. Control Concept!

•" Coordination of gas engines and battery, local control

and central control

7

Inter-connecting mode Intentional islanding mode

Gas Engines

(SYNC)

Set-point control (40sec lag)

APFR (PF=1.0~0.95)

Set-point with droop (2Hz/100%)

AVR (and CCC)

Battery

(INV)

Set-point control (response in

10 millisecond)

APFR (PF=1.0)

Set-point control

APFR

Frequency

control

High speed P and Q compensation

using battery

Phase

unbalance

control

Negative sequency compensation

using PV PCS!

Central

Control

"Economic Dispatching Control

"Flat Tie-line Control

"Economic Dispatching Control

"Frequency Control

"Phase unbalance control

Control

Error Tie-line power flow fluctuation! Frequency fluctuation

Page 8: Operation Result of the Hachinohe Microgrid Demonstration Project · 2014-12-12 · main driving factor of Microgrid in Japan. •" Objectives of Microgrid Demonstration Project:

MITSUBISHI!ELECTRIC!

8

4.1 Interconnecting operation(1)

Target has

been achieved

in 99.99% of

operation time

•" Example of Economic Dispatching Control and Flat Tie-line Control under inter-connecting operation

•" Target precision:

–" Maintain six minutes moving average of tie-line power flow within 3% of scheduled value

Page 9: Operation Result of the Hachinohe Microgrid Demonstration Project · 2014-12-12 · main driving factor of Microgrid in Japan. •" Objectives of Microgrid Demonstration Project:

MITSUBISHI!ELECTRIC!

9

4.1 Interconnecting operation (2)

•" Analysis result of power quality

–" Fluctuation of weather-dependent energy and demand

increases gradually over 1 minute,

–" fluctuation of control result decrease over 1minute.

#Our control system reduce fluctuation of weather-

dependent energy effectively

Page 10: Operation Result of the Hachinohe Microgrid Demonstration Project · 2014-12-12 · main driving factor of Microgrid in Japan. •" Objectives of Microgrid Demonstration Project:

MITSUBISHI!ELECTRIC!

10

4.2 Islanding Operation (1)

•" One-week intentional islanding operation

(disconnected from the utility grid) was

performed in Nov. 2007.

OBJECTIVE

•" Develop microgrid EMS for island or remote area

•" Confirm the control performance in more difficult

conditions

ASSUMED PROBLEMS

•" Frequncy

Inertia of the gas engine (GE) is too small to stably

maintain frequency in the case of large load fluctuation.

•" Three phase unbalance

Negative sequence current of GE caused by three phase

unbalance is bigger than tolerated dose of GEG(15%)

Page 11: Operation Result of the Hachinohe Microgrid Demonstration Project · 2014-12-12 · main driving factor of Microgrid in Japan. •" Objectives of Microgrid Demonstration Project:

MITSUBISHI!ELECTRIC! 4.2 Islanding Operation (2)!

Assumed problems and actions!

11

Problems! Actions!

Frequency!

2.6Hz drop with 50kW AC

startup with one GEG

(target: 0.5Hz)!

High speed (10 msec) local

frequency control using

battery inverter!

Voltage!6% drop with AC startup

(Target: 6%)

Local control using battery

inverter

Phase

Unbalance!

10A negative sequence

current (target: 2.8A)!

"Phase switching reduces 5A.

"Install negative sequence

compensator using PV PCS!

Harmonics! No problems!Install protection relay just in

case

Page 12: Operation Result of the Hachinohe Microgrid Demonstration Project · 2014-12-12 · main driving factor of Microgrid in Japan. •" Objectives of Microgrid Demonstration Project:

MITSUBISHI!ELECTRIC! 4.2 Islanding Operation (3)!

12

$%&/AFC!

Battery inverter control!

Ref.

Freq.

Dead band P control

Q control

Dead band 2

Ref.

Voltage

Dead band

Dead band 2

P

D

P

D

Local control using battery inverter

Page 13: Operation Result of the Hachinohe Microgrid Demonstration Project · 2014-12-12 · main driving factor of Microgrid in Japan. •" Objectives of Microgrid Demonstration Project:

MITSUBISHI!ELECTRIC! 4.2 Islanding Operation (4)

•" High speed frequency control with battery

–" Keep within 0.5Hz under largest power deviation

13

(1) Gas engine emits kinetic

energy as electric power,

so frequency drops rapidly.

(2) Local control system detects

frequency drop,

and increases output of rechargeable

battery to keep frequency constants.

Page 14: Operation Result of the Hachinohe Microgrid Demonstration Project · 2014-12-12 · main driving factor of Microgrid in Japan. •" Objectives of Microgrid Demonstration Project:

MITSUBISHI!ELECTRIC!

Point A! Point B!Point C

4.2 Islanding Operation (5)!

14

Utility grid G GEs (170kWx3)

PV PCS

100kVA

Schools

City

hall

Offic

e (1) Measurement of

each phase PQV!

(3) Negative sequence current target!

Microgrid EMS

(2) Calculate

positive and negative sequence

current!

(4) Negative sequence current

Every 1 sec.

Phase unbalance control (negative sequence

current compensation)

+

Page 15: Operation Result of the Hachinohe Microgrid Demonstration Project · 2014-12-12 · main driving factor of Microgrid in Japan. •" Objectives of Microgrid Demonstration Project:

MITSUBISHI!ELECTRIC!

GE’s output

PCS output Total

demand

15

4.2 Islanding Operation (6)!

Example of phase unbalance compensation

Ne

gative s

equence c

urr

ent [A

] P

ow

er

[kW

]

Time

Time

Page 16: Operation Result of the Hachinohe Microgrid Demonstration Project · 2014-12-12 · main driving factor of Microgrid in Japan. •" Objectives of Microgrid Demonstration Project:

MITSUBISHI!ELECTRIC!

Holiday (10 mins)!Weekday (24 hours)!

4.2 Islanding Operation (7)!

•" Weekday (Left figure)

–" Midnight: Battery charges surplus power of GEG

–" Morning: Three GEs and battery track rapid rising

•" Holiday (Right figure)

–" Noon: GE can track PV fluctuation!

16

Page 17: Operation Result of the Hachinohe Microgrid Demonstration Project · 2014-12-12 · main driving factor of Microgrid in Japan. •" Objectives of Microgrid Demonstration Project:

MITSUBISHI!ELECTRIC! 4.2 Islanding Operation (8)!

17

'()*+,*-./0!

12)3*4!

5678796:;!

<*=,>4!

58796:;?@?A77B!

5879C:;?@?DD9E6B!

5F2G?*))H)@?I79J:;!

±0.2Hz!99.85%

'KH>423*0!

12)3*4!

58LBMA7A8LKN!

<*=,>4!

58L97B?@?A77B!

58C97B?@?DD9DDB!

5F2G?*))H)?@?JB!

±2.0%!99.99%

'O*324PQ*?=*+9?.,)90!

12)3*4!

5RP4SP-?A6B!

5MC9ET?U?VWN!

<*=,>4!

5A6B?@?A77B!

5JB?@?DD9DXB5!

Y4%!99.97%

':2)ZH-P.=0!

12)3*4!

5RP4SP-?6B!

<*=,>4!

5697B?@?A77B!

5[97B?@?DD9DDB!

5F2G?*))H)?[9AB!

Y3%!99.99%

Page 18: Operation Result of the Hachinohe Microgrid Demonstration Project · 2014-12-12 · main driving factor of Microgrid in Japan. •" Objectives of Microgrid Demonstration Project:

MITSUBISHI!ELECTRIC!

18

Conclusion

•" We develop 4 layers energy

management system for microgrid.

•" Inter-connecting operation

–" Fluctuation of weather-dependent

generation is effectively reduced.

–" Over 50% reduction of CO2 emission.

•" Islanding operation

–" Prove ability to supply height quality power

using only renewable energy sources