operation result of the hachinohe microgrid demonstration project · 2014-12-12 · main driving...
TRANSCRIPT
MITSUBISHI!ELECTRIC!
1
Operation Result of the Hachinohe
Microgrid Demonstration Project
5th Microgrid Symposium (San Diego)!
Yasuhiro Kojima Advanced Technology R&D Center
Mitsubishi Electric Crop., Japan
MITSUBISHI!ELECTRIC!
2
1.!Objective
2.!System Overview
3.!Control Concept
4.!Operation Results
1.!Interconnected operation
2.!Islanding operation
MITSUBISHI!ELECTRIC!
3
1.Objective
Photovoltaic
Total:130kW Wind turbine
Total:20kW
•" Stabilization of weather-dependent energy is one of the
main driving factor of Microgrid in Japan.
•" Objectives of Microgrid Demonstration Project:
•" Demonstration of Microgrid system as a new way of
introducing PVs, WTs, or other Renewable Energy
Sources (RES).
•" Development, operation, and evaluation of Microgrid
system with the ability to stabilize and control total
energy including weather-dependent energy.
MITSUBISHI!ELECTRIC!
4
Hachinohe Project: •" Demand: Seven building facilities, sewage plant
!" Electricity: maximum 610kW at Hachinohe City hall,
four schools and office building.
!" Heat: 10Gcal/day at Sewage plant
•" Energy supply: Only RESs
!" Electricity: 510kW(170x3) biogas engines,
130kW PVs, 20kW WTs,
100kW lead-acid battery
!" Heat: 1.0t/h wood boiler and 4t/h gas boiler
•" Energy management
!" 5.4km Private line (electricity & communication)
!" Interconnected with commercial grid at a single
point.
!" Control error target: Within 3% every 6 minutes
moving average
2. System overview
This project is jointly undertaken by Mitsubishi Research Institute,
Mitsubishi Electric Corporation, and Hachinohe City with the support of the
New Energy and Industrial Technology Development Organization(NEDO)
MITSUBISHI!ELECTRIC!
Sewage Plant
5
Private distribution line!5.4km
GEs!510kW!
Battery!±100kW!
PV!100kW!
PV!10kW!
PV!10kW!
WT!4kW!
WT!8kW!
PV!10kW!
Demand!50kW!
Demand!360kW!
Demand!50kW!
Demand!50kW!
Demand!50kW!
WT!8kW!
Demand!50kW!
2. System overview
Hachinohe
Aomori!
Utility Grid
Digestion Chamber
Digestion Gas (Methane)
Wood boiler (1t/h)
Gas Boiler (4t/h)
Heat
Gas tank
MITSUBISHI!ELECTRIC!
6
•" To satisfy both of economical (or environmental) optimization and
electric power quality, !" Control system consists of four functions to handle enormous
dimensions of the problems. !" Implement local control system considering islanding
operation.
Object Function Abstract Interval Time unit,
Period
Optimization
(Economical &
Environmental)
Weekly Operation
Planning(WOP)
Calculation of the optimal fuel supply, the
storage plan of electricity and heat in a
week timeframe.
1day 30-minute unit,
8 days
Economic Dispatching
Control(EDC)
Redispatch generation based on the
difference between forecasted and actual
data.
3min 3-minute unit,
2 hours
Quality
(Tie-line flow
and frequency)
Flat Tie-Line Control
(Central Frequency
Control)
Simply central P-I control for generation
is installed to reduce the fluctuation of tie-
line power flow. 1sec -
Local Frequency
Control
(Islanding mode)
High-speed compensation of battery
output using local frequency observation
is installed. 10msec -
3. Control Concept
MITSUBISHI!ELECTRIC! 3. Control Concept!
•" Coordination of gas engines and battery, local control
and central control
7
Inter-connecting mode Intentional islanding mode
Gas Engines
(SYNC)
Set-point control (40sec lag)
APFR (PF=1.0~0.95)
Set-point with droop (2Hz/100%)
AVR (and CCC)
Battery
(INV)
Set-point control (response in
10 millisecond)
APFR (PF=1.0)
Set-point control
APFR
Frequency
control
High speed P and Q compensation
using battery
Phase
unbalance
control
Negative sequency compensation
using PV PCS!
Central
Control
"Economic Dispatching Control
"Flat Tie-line Control
"Economic Dispatching Control
"Frequency Control
"Phase unbalance control
Control
Error Tie-line power flow fluctuation! Frequency fluctuation
MITSUBISHI!ELECTRIC!
8
4.1 Interconnecting operation(1)
Target has
been achieved
in 99.99% of
operation time
•" Example of Economic Dispatching Control and Flat Tie-line Control under inter-connecting operation
•" Target precision:
–" Maintain six minutes moving average of tie-line power flow within 3% of scheduled value
MITSUBISHI!ELECTRIC!
9
4.1 Interconnecting operation (2)
•" Analysis result of power quality
–" Fluctuation of weather-dependent energy and demand
increases gradually over 1 minute,
–" fluctuation of control result decrease over 1minute.
#Our control system reduce fluctuation of weather-
dependent energy effectively
MITSUBISHI!ELECTRIC!
10
4.2 Islanding Operation (1)
•" One-week intentional islanding operation
(disconnected from the utility grid) was
performed in Nov. 2007.
OBJECTIVE
•" Develop microgrid EMS for island or remote area
•" Confirm the control performance in more difficult
conditions
ASSUMED PROBLEMS
•" Frequncy
Inertia of the gas engine (GE) is too small to stably
maintain frequency in the case of large load fluctuation.
•" Three phase unbalance
Negative sequence current of GE caused by three phase
unbalance is bigger than tolerated dose of GEG(15%)
MITSUBISHI!ELECTRIC! 4.2 Islanding Operation (2)!
Assumed problems and actions!
11
Problems! Actions!
Frequency!
2.6Hz drop with 50kW AC
startup with one GEG
(target: 0.5Hz)!
High speed (10 msec) local
frequency control using
battery inverter!
Voltage!6% drop with AC startup
(Target: 6%)
Local control using battery
inverter
Phase
Unbalance!
10A negative sequence
current (target: 2.8A)!
"Phase switching reduces 5A.
"Install negative sequence
compensator using PV PCS!
Harmonics! No problems!Install protection relay just in
case
MITSUBISHI!ELECTRIC! 4.2 Islanding Operation (3)!
12
$%&/AFC!
Battery inverter control!
Ref.
Freq.
Dead band P control
Q control
Dead band 2
Ref.
Voltage
Dead band
Dead band 2
P
D
P
D
Local control using battery inverter
MITSUBISHI!ELECTRIC! 4.2 Islanding Operation (4)
•" High speed frequency control with battery
–" Keep within 0.5Hz under largest power deviation
13
(1) Gas engine emits kinetic
energy as electric power,
so frequency drops rapidly.
(2) Local control system detects
frequency drop,
and increases output of rechargeable
battery to keep frequency constants.
MITSUBISHI!ELECTRIC!
Point A! Point B!Point C
4.2 Islanding Operation (5)!
14
Utility grid G GEs (170kWx3)
PV PCS
100kVA
Schools
City
hall
Offic
e (1) Measurement of
each phase PQV!
(3) Negative sequence current target!
Microgrid EMS
(2) Calculate
positive and negative sequence
current!
(4) Negative sequence current
Every 1 sec.
Phase unbalance control (negative sequence
current compensation)
+
MITSUBISHI!ELECTRIC!
GE’s output
PCS output Total
demand
15
4.2 Islanding Operation (6)!
Example of phase unbalance compensation
Ne
gative s
equence c
urr
ent [A
] P
ow
er
[kW
]
Time
Time
MITSUBISHI!ELECTRIC!
Holiday (10 mins)!Weekday (24 hours)!
4.2 Islanding Operation (7)!
•" Weekday (Left figure)
–" Midnight: Battery charges surplus power of GEG
–" Morning: Three GEs and battery track rapid rising
•" Holiday (Right figure)
–" Noon: GE can track PV fluctuation!
16
MITSUBISHI!ELECTRIC! 4.2 Islanding Operation (8)!
17
'()*+,*-./0!
12)3*4!
5678796:;!
<*=,>4!
58796:;?@?A77B!
5879C:;?@?DD9E6B!
5F2G?*))H)@?I79J:;!
±0.2Hz!99.85%
'KH>423*0!
12)3*4!
58LBMA7A8LKN!
<*=,>4!
58L97B?@?A77B!
58C97B?@?DD9DDB!
5F2G?*))H)?@?JB!
±2.0%!99.99%
'O*324PQ*?=*+9?.,)90!
12)3*4!
5RP4SP-?A6B!
5MC9ET?U?VWN!
<*=,>4!
5A6B?@?A77B!
5JB?@?DD9DXB5!
Y4%!99.97%
':2)ZH-P.=0!
12)3*4!
5RP4SP-?6B!
<*=,>4!
5697B?@?A77B!
5[97B?@?DD9DDB!
5F2G?*))H)?[9AB!
Y3%!99.99%
MITSUBISHI!ELECTRIC!
18
Conclusion
•" We develop 4 layers energy
management system for microgrid.
•" Inter-connecting operation
–" Fluctuation of weather-dependent
generation is effectively reduced.
–" Over 50% reduction of CO2 emission.
•" Islanding operation
–" Prove ability to supply height quality power
using only renewable energy sources