FIG Congress 2010 Facing the Challenges – Building the Capacity Sydney, Australia, 1116 April 2010 1 Natural Approach to Mine Rehabilitation Waste Dumps Mine requirements Move the dirt cost effectively Meet regulatory requirements • Regulators Reduce the footprint Protect local environment – water quality, drainage patterns, dust and noise Community input Minimise disturbance Return land to pre-mined use

Upload: others

Post on 17-Jun-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Natural Approach to Mine Rehabilitation · Natural Surface Waste Dump 3D View of Traditional Design • Long slopes without channels, promote rill and gully erosion – Needs artificial

FIG Congress 2010 

Facing the Challenges – Building the Capacity 

Sydney, Australia, 11‐16 April 2010  1

Natural Approach to Mine Rehabilitation

Waste Dumps

• Mine requirements – Move the dirt cost effectively

– Meet regulatory requirements

• Regulators – Reduce the footprint

– Protect local environment – water quality, drainage patterns, dust and noise

• Community input – Minimise disturbance

– Return land to pre-mined use

Page 2: Natural Approach to Mine Rehabilitation · Natural Surface Waste Dump 3D View of Traditional Design • Long slopes without channels, promote rill and gully erosion – Needs artificial

FIG Congress 2010 

Facing the Challenges – Building the Capacity 

Sydney, Australia, 11‐16 April 2010  2

Something just tells you it isn’t right . . .

Waste Dump Construction

• Mines build the waste dump to fit the most dirt in the smallest footprint – leads to flat-topped pyramid.

• The flat gradient slopes can be up to 1:3 (=18º, 33%) • Water flow control structures are constructed

– Contour banks and – Rock drains

• Retention Ponds are built to hold turbid water

Slope = 18 º

Page 3: Natural Approach to Mine Rehabilitation · Natural Surface Waste Dump 3D View of Traditional Design • Long slopes without channels, promote rill and gully erosion – Needs artificial

FIG Congress 2010 

Facing the Challenges – Building the Capacity 

Sydney, Australia, 11‐16 April 2010  3

Contour Banks, Rock Drains, Retention Ponds

Problems with Waste Dumps

• Need Long term maintenance

– Erosion and infrastructure failures

• Erosion leads to water quality issues

• Often do not provide habitats and biodiversity

Page 4: Natural Approach to Mine Rehabilitation · Natural Surface Waste Dump 3D View of Traditional Design • Long slopes without channels, promote rill and gully erosion – Needs artificial

FIG Congress 2010 

Facing the Challenges – Building the Capacity 

Sydney, Australia, 11‐16 April 2010  4

New Approach to Mined Land Rehabilitation

• Combines knowledge of fluvial geomorphic principles with CAD programs and Machine Guidance to enable the construction of “natural” landforms.

• Drainage Patterns

A network of tributaries that join together to form larger channels – each characterised by gradient slope, discharge volume and sinuosity

New Approach to Mined Land Rehabilitation

• Ridge line profiles – complex gradient slopes

• Channel Cross sections – allow for variable flow

(Rosgen, 1996) (Rosgen, 1996)

Floodplain

Bankfull

Baseflow

Floodplain

Bankfull

Baseflow

Page 5: Natural Approach to Mine Rehabilitation · Natural Surface Waste Dump 3D View of Traditional Design • Long slopes without channels, promote rill and gully erosion – Needs artificial

FIG Congress 2010 

Facing the Challenges – Building the Capacity 

Sydney, Australia, 11‐16 April 2010  5

Contour Maps

Natural Surface Waste Dump

3D View of Traditional Design

• Long slopes without channels, promote rill and gully erosion – Needs artificial down-drains

• Water quality – turbid run-off

• Minimal diversity for vegetation and wildlife

• Does not blend with surrounding terrain

Page 6: Natural Approach to Mine Rehabilitation · Natural Surface Waste Dump 3D View of Traditional Design • Long slopes without channels, promote rill and gully erosion – Needs artificial

FIG Congress 2010 

Facing the Challenges – Building the Capacity 

Sydney, Australia, 11‐16 April 2010  6

3D View of GeoFluv Design

• Complex slopes with smaller sub-watersheds to reduce erosion

• Water run-off less turbid • Natural slope and habitat diversity for vegetation

and wildlife • Blends with surrounding terrain

Build with Machine Guidance

Page 7: Natural Approach to Mine Rehabilitation · Natural Surface Waste Dump 3D View of Traditional Design • Long slopes without channels, promote rill and gully erosion – Needs artificial

FIG Congress 2010 

Facing the Challenges – Building the Capacity 

Sydney, Australia, 11‐16 April 2010  7

What does it look like when it is built ?

LA Plata Mine – New Mexico USA

GeoFluv ‘laboratory’ and Results

One year later