This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989 REAL-TIME MINING MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN MINERAL RESOURCE EXTRACTION FUTURE MINING CONFERENCE SYDNEY, 5 TH OF NOVEMBER 2015 JÖRG BENNDORF, DELFT UNIVERSITY OF TECHNOLOGY ON BEHALF OF THE REAL-TIME MINING CONSORTIUM

Upload: others

Post on 26-May-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN …

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989

REAL-TIME MINING MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN MINERAL RESOURCE EXTRACTION

FUTURE MINING CONFERENCE

SYDNEY, 5TH OF NOVEMBER 2015

JÖRG BENNDORF, DELFT UNIVERSITY OF TECHNOLOGY

ON BEHALF OF THE REAL-TIME MINING CONSORTIUM

Page 2: MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN …

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989

PARTNERS

2

Page 3: MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN …

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989

BACKGROUND

Potential of critical raw materials in Europe classified by deposit sizes (PROMINE) 3

Page 4: MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN …

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989

The main barriers to overcome for the successful economic exploitation:

o effective grade control, which will maximize resource potential along the whole value chain

o minimization of handling zero-value material introduced by

dilution, thus reducing unnecessary expenditure of energy and financial resources and

o management and control of the geological uncertainty due to

limited information available.

BACKGROUND

4

Page 5: MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN …

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989

Main Source of Risk: Geological Uncertainty

Limited Information 1:10.000.000

Complex Geology

Tight product specifications

5 Foto: Neves Corvo Mine

Page 6: MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN …

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989

THE TRADITIONAL APPROACH Mine Design Equipment Selection Reserve Estimation

Exploration and Data Collection

Resource Modelling

Production Scheduling and Operation

Processing and Sale

SILO 1 SILO 2 SILO 3 SILO 4 SILO 5

6

Page 7: MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN …

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989

NEW INFORMATION POTENTIAL

Increasing Availability of Sensor Based Online Data:

• Material characterization (geo-chemical, textural and

physical properties)

• Equipment performance, upstream and downstream (e.g.

efficiency, down-time)

• Equipment location and material tracking (e.g. GPS, UPS) 7

Foto: MIBRAG

Page 8: MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN …

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989

THE REAL-TIME MINING APPROACH

8

Page 9: MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN …

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989

THE REAL-TIME MINING PROJECT OBJECTIVE Overall objective: to develop an innovative technical solution for resource-

efficient and optimal high precision/selective mining in geologically complex

settings using online data.

Hypothesis: recovery can be significantly increased by changing mineral

resource management from a ‘batch-type’ to a near-continuous model-based

controlled activity

9

Page 10: MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN …

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989

REAL-TIME MINING BUILDING BLOCKS

10

Page 11: MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN …

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989

EXTRACTION METHODS RTM CYCLIC EXTRACTION

Drill Hole

Core

Sample

Ore zone

Muck- pile

LHD

Ore- pass

Ore Transfer

BIN

Crusher

BIN

A

B

C

Control decision points

Sensors for material characterization

Sensors for machine performance

Sensors for geo-referencing (positioning and material tracking)

Selective Loading

Scheduling

Dispatching

11

Page 12: MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN …

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989

REAL-TIME MINING REAL-TIME DATA

(Lead: RWTH Aachen)

Lead: TU Delft

Lead: SonicSampDrill 12

Page 13: MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN …

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989

TEST CASE 1

“Reiche Zeche” Research Mine Freiberg, Germany Source: Description „Test Site Mine ‚Reiche Zeche‘, Freiberg, Saxony, Germany“ provided by TU Bergakademie Freiberg

Page 14: MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN …

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989

TEST CASE 2

“Neves Corvo” Copper Mine Portugal (Massive sulphide ore and associated stockwork zone) Source: lundin mining

Page 15: MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN …

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989

CASE STUDY UPDATING

15

Sensor

Predict

Measure

Reconcile

GC Model

Grade Control (GC) Model

1. Reconcile – Extracted Blocks

2. Update – Scheduled Blocks

Extraction Performance

1. Improve production forecasts

2. Optimize control decisions

(proact)

Page 16: MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN …

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989

CASE STUDY UPDATING

Predicted Measurements

Actual Measurements

Reconciliation Software

Prior Block Model

Forward Prediction

Measurement File

Material Tracking/ Material

Flow Simulation in

the Mine

Updated Block Model

replace

Sensor

Source: Wambeke, T & Benndorf, J (2015). Data assimilation of sensor measurements to improve production forecast in resource extraction. In s.n. (Ed.), Proceedings of the 17th annual conference of the international association for mathematical geosciences, IAMG2015 (pp. 236-245). Houston: IAMG.

Page 17: MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN …

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989

Simulations

Mean Field

x SMU scale

x

CASE STUDY UPDATING

17

Page 18: MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN …

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989

Simulations

Mean Field

x SMU scale

x

18

CASE STUDY UPDATING

Page 19: MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN …

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989

Optimal value

Optimal value

Acceptable range

Acceptable range

Penalty applied

Dai

ly p

rodu

ctio

n in

kt

Gra

de in

%

Forecast of process KPI’s for a given extraction schedule

CASE STUDY OPTIMIZATION

Page 20: MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN …

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989

Simulation based optimization of extraction schedule to improve extraction performance

CASE STUDY OPTIMIZATION

Page 21: MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN …

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989

ADVANCE WITHIN RTM

21

Page 22: MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN …

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989

THREE TAKEAWAYS 1. Real-Time Mining is an exciting European Union funded

H2020 project and integrates multiple disciplines

2. Making best use of online production information can lead to a shift in paradigm from a batch-type to a continuous process monitoring and control and can create significant value

3. Real-Time Mining will demonstrate this hypothesis in full industrial scale case studies (TRL 6/7).

22

Page 23: MOVING TOWARDS CONTINUOUS PROCESS MANAGEMENT IN …

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 641989

23

Thank you for your attention and

Glückauf