Long Term Control PlanLong Term Control PlanPublic MeetingPublic Meeting
Wednesday, November 16, 2005Wednesday, November 16, 2005
![Page 2: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/2.jpg)
Today’s MeetingToday’s Meeting
• Toledo’s Consent Decree
• Background Information
• Long Term Control Plan
• Plan Purpose
• Plan Input
• Proposed Plan
• Next Steps
![Page 3: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/3.jpg)
Consent Decree Consent Decree RequirementsRequirements• The City of Toledo’s Consent Decree with USEPA and
OEPA requires the following• Improvements to the WWTP
• Control of sanitary sewer overflows
• Development and implementation of a Long Term Control Plan for Combined Sewer Overflows (LTCP)
![Page 4: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/4.jpg)
Consent Decree Consent Decree ImplementationImplementation
• WWTP improvements• 11 major projects• $140 million
• Sanitary Sewer Overflow Control• 13 major projects• $35 million
• Combined Sewer Overflow Control• 26 projects (planned)• Over $250M (proposed)
![Page 5: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/5.jpg)
WWTP ConstructionWWTP Construction
![Page 6: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/6.jpg)
SSO Control ProjectsSSO Control Projects
![Page 7: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/7.jpg)
CSO Long Term Control CSO Long Term Control PlanPlan
• Subject of tonight’s meeting
• Culmination of over two years of study
• Involved the public and stakeholders along the way
![Page 8: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/8.jpg)
Public Input for PlanPublic Input for Plan
• Public input included:• 2 community telephone surveys• 6 public meetings• 17 Community Program Advisory Committee
meetings devoted to the Long Term Control Plan
![Page 9: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/9.jpg)
Long Term Control Plan – Long Term Control Plan – ContentsContents• Actions – projects or
programs• Schedules – when
projects will happen• Where – locations where
projects will be constructed
• Costs – project expenditures; financing plan
![Page 10: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/10.jpg)
ObligationsObligations
• The consent decree requires that the LTCP evaluate a range of CSO control alternatives based on:• Pollution reduction benefits• Instream water quality conditions• Construction and operations costs
• The consent decree requires that work included in the plan be completed by August 31, 2016
![Page 11: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/11.jpg)
City’s Combined AreaCity’s Combined Area
![Page 12: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/12.jpg)
Existing ConditionsExisting Conditions
• Currently 32 overflows
• 17 square miles of CSO area
• Discharge 33 times per year
• Discharge 625 million gallons per year
![Page 13: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/13.jpg)
CSO Control Work has been CSO Control Work has been PerformedPerformed
• The City constructed three major tunnel systems to store excess flow
• The City has implemented a number of sewer separation projects to build separate sewer systems
![Page 14: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/14.jpg)
CSO Area to TunnelsCSO Area to Tunnels
![Page 15: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/15.jpg)
Sewer Separation Sewer Separation ProjectsProjects
![Page 16: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/16.jpg)
Alternatives ConsideredAlternatives Considered
• Flow storage and/or treatment• Storage basins and tunnels with screening and other
treatment capability
• Sewer Separation• Construction of new sewers for eliminating
combined systems
• Flow reduction/rerouting• Small-scale measures to reduce the amount of flow
to the sewer system
![Page 17: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/17.jpg)
Recommended PlanRecommended Plan
• Proposed Plan• Reduces number of overflow locations
from 32 to 23• Reduces frequency from 33 to 4 (untreated)• Reduces volume from 625 MG/year to 144 MG/year• Reduces typical pollutant discharge by 86%-89%• Reduces bacterial discharge by 90%
![Page 18: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/18.jpg)
Recommended PlanRecommended Plan
• Includes 26 projects• Estimated cost of over $250M (2005 dollars)• Reduces Ottawa River discharge to 2 times/
year• Reduces Maumee River discharge to 4 times/
year• Reduces Swan Creek discharge frequency to 3
times/year, disinfects the discharge that does occur
![Page 19: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/19.jpg)
Plan for Ottawa RiverPlan for Ottawa River
![Page 20: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/20.jpg)
Plan for Maumee River Plan for Maumee River (Upper)(Upper)
![Page 21: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/21.jpg)
Plan for Maumee River Plan for Maumee River (Lower)(Lower)
![Page 22: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/22.jpg)
Plan for Swan CreekPlan for Swan Creek
![Page 23: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/23.jpg)
Implementation Time FrameImplementation Time Frame
• Ottawa River: 2006 – 2014
• Maumee River: 2006 – 2016
• Swan Creek: 2007 – 2016
![Page 24: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/24.jpg)
Selected Control MethodsSelected Control Methods
• Storage basins
• Storage pipelines
• Optimization of existing tunnels
• Addition of disinfection capabilities to tunnels
• Flow reduction
• Sewer separation
![Page 25: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/25.jpg)
Storage Basin ExamplesStorage Basin Examples
• Vast majority of work is below ground
• Will require above ground building for support facilities
• Takes about 2 - 3 years to construct
Birmingham CSO basinBirmingham CSO basin
Leib Screening/ Disinfection Leib Screening/ Disinfection Facility - DetroitFacility - Detroit
![Page 26: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/26.jpg)
Storage PipelineStorage Pipeline
• Essentially large sewer underground that will provide storage volume
• Small support building required in vicinity
• Takes 1 – 2 years for construction
![Page 27: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/27.jpg)
Expected Facility LocationsExpected Facility Locations
• Storage Basins• Joe E. Brown Park OR Windermere Blvd.• I – 280 / Front Street interchange area• Private property at Oakdale and Miami• City property next to I-75 on north side of Maumee
River
• Storage Pipelines• International Park• Adjacent to Jamie Farr Park
![Page 28: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/28.jpg)
Tunnel ImprovementsTunnel Improvements
• Improve tunnel hydraulics to reduce frequency
• Reduce flow area (Swan Creek South)
• Improve cleaning, other operations items
• Add disinfection capability
![Page 29: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/29.jpg)
Facility LocationsFacility Locations
![Page 30: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/30.jpg)
Sewer Separation/ Flow Sewer Separation/ Flow Reduction AreasReduction Areas
![Page 31: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/31.jpg)
Project CostsProject Costs
• All costs are based on 2005 cost index
• Actual costs at implementation will be impacted by the rate of inflation and the final project design
• Estimated overall cost: >$250 million
• Rates will be impacted by timing of projects and financing method uses
![Page 32: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/32.jpg)
What is Next?What is Next?
• Plan was submitted in draft form to USEPA
• Conference call held with USEPA this afternoon
• Report submittal delayed until December 16, 2005 at EPA request
• Draft executive summary will soon be available on the TWI Web site, along with an area to provide comments
• Public comments on the plan are welcome
![Page 33: LTCP meeting 11-16-05](https://reader037.vdocuments.site/reader037/viewer/2022103016/555e89ffd8b42abd468b552f/html5/thumbnails/33.jpg)
Display BoardsDisplay Boards
• Display boards around the room provide an enlarged view and information about various projects
• Please stop by the boards and ask questions!
• Comment forms are provided