lehigh township board of supervisors i. ii ...lehigh township board of supervisors minutes of the...
TRANSCRIPT
LEHIGH TOWNSHIP BOARD OF SUPERVISORS
Minutes of the June 25, 2019, Meeting
I. CALL TO ORDER. The Lehigh Township Board of Supervisors held their second
monthly meeting on Tuesday, June 25, 2019, at 7:00 p.m. at the Lehigh Township
Municipal Building, 1069 Municipal Road, Walnutport. Present were Cindy Miller, Phil
Gogel, Mike Jones, Darryl Snover, and Keith Hantz, along with Attorney David
Backenstoe, Phil Malitsch and Alice Rehrig. Chairman Darryl Snover called the meeting
to order with the Pledge of Allegiance.
II. CONDITIONAL USE HEARING—LEHIGH VALLEY RESORT AND SPA. A
conditional use application was filed by Hilltop Center, LLC and the Jaindl Land
Company to have an Event Barn and Event Pad on the Lehigh Valley Report and Spa
property. There are three sections of the Zoning Ordinance that will be considered as part
of this application:
Section 180-18.1.C.5. This is one of the criteria in the Planned Residential Report
Community Zoning District which is the zoning district in which this plan is located. The
proposed use of an event barn and event pad or an event center are permitted uses within
the existing seminary building. Because the applicant is proposing these uses outside of
the existing building, conditional use approval is required as stated in the Zoning
Ordinance.
Section 180-54, Standards for Special exceptions and Conditional Uses. There are
several minor areas of this section that the Board would need to look at, but the most
important section to the applicant is the section that states no preliminary plan approval,
subdivision or land approval, can be granted by the Board of Supervisors where a
conditional use is necessary. This means that the Board of Supervisors cannot act on the
subdivision and land development aspect of a project until the conditional use hearing
has taken place and approval has been granted.
Section 188-128, Conditional Use Criteria. This section has several provisions which
need to be met which include, the Board cannot grant a conditional use application unless
they have a written review letter from the Planning Commission. There are different
aspects of what is required to be submitted as part of the application. Attorney
Backenstoe and the Zoning Officer have reviewed the application to ensure all of these
criteria have been met. There are general criteria which also need to be met, some of
which do not apply to this application. These criteria include the proposed use shall be
consistent with the purpose and intent of this chapter. the proposed use shall not detract
from the use and enjoyment of adjoining nearby properties, the proposed use will not
effect a change in the character of the subject property's neighborhood, adequate public
facilities are available to serve the proposed use such as sewer, water or other utilities,
compliance with the floodplain requirements which is not applicable for this application
since it is not within a flood plain, compliance with any specific criteria of the zoning
Supervisor Minutes
June 25, 2019
Page 2
ordinance if it is applicable to the propose use, which in this case, there are no specific
criteria listed in the ordinance and that the proposed use will not substantially impair the
integrity of the Township's Comprehensive Plan. Through the witnesses, questions and
answers, and presentation of documents, the Board will need to decide if these criteria
have been met.
The burden is on the applicant to prove their case, but a conditional use is guided by the
same legal principles as a special exception, which is really a permitted use to which
conditions can be applied. Assuming the applicant can show the Board that he can meet
the general criteria that was previously discussed, their use would really be permitted.
The Board would have the right to attach conditions to the approval as they see
necessary. If there are objectors present, they would have the right to question the
witnesses and at the end of the applicant’s presentation, they would have the right to
make their own presentation. The only way a conditional use or special exception
application can really be defeated would be if the objector shows that this particular use
is more detrimental or harmful to the community than other uses like it.
The following exhibits are introduced by the Township into the record:
T1 The formal appeal petition that was filed.
T2 The memorandum from Zator Law with additional information.
T3 The waiver of time limitation which was submitted to the Township so that the
hearing could be held during this meeting.
T4 The legal notice which was posted on the property and a picture of the posting.
T5 The proof of publication from the advertisement.
T6 The review letter from the Planning Commission dated June 5, 2019.
Attorney Zator, legal counsel for the applicant, had no objection to the exhibits presented
by Attorney Backenstoe. In addition to Attorney Zator, David Jaindl, Adam Jaindl,
Howard Kutzler, Bruce Anderson, John McRoberts, Fred Ebert, and Marissa Harper were
present on behalf of the applicant. Attorney Zator requested that with respect to setting
conditions as part of the approval, he would request that there be dialog regarding any
conditions the Board may be considering as part of the approval process, other than the
water and sewer. They recognize that they need to provide for public water and sewer to
a project this size and have no objection to that being a condition of the approval.
Attorney Zator provided a packet of exhibits that were marked as exhibits A1 through
A12.
Supervisor Minutes
June 25, 2019
Page 3
Testimony of David Jaindl.
Exhibit A1 is an aerial rendering of the vision that Mr. Jaindl has for the property. Mr.
Jaindl acquired the property from the Diocese of Philadelphia and subsequently went
through a rezoning process and will be coming soon before the Board with his land
development plan. The existing seminary building is 124,000 square feet and the convent
building which is 9,000 square feet which will be the spa area. They are adding several
buildings on the outside which will be hotel uses, an event barn and event pad.
Exhibit A4 is a rendering of the proposed barn type structure. It will be post and beam
construction. He has previously salvaged old barn structures, but this one will be new. It
will be similar to his current office. The venue which they are trying to achieve is the
repurposing of a beautiful 124,000 square foot building and take advantage of their
experience in agriculture to create a farm to table event. They will be growing largely
organic crops, some convention crops, and some teaching to visitors. The building sits
on approximately 550 acres with approximately 140 acres of agriculture land. He is
looking to bring life back into the historic structure on this site. There were other parties
who were interested in this property, but they wanted to retain salvage rights which was a
disappointing option. When he purchased the property, he self-imposed a condition that
they would not demo the site because it was too nice of a building. Other historical sites
in the region have been demolished, such as Martin Towers or the State Hospital because
it didn’t make financial sense to rehab the structures. They looked at this differently.
When they first came before the Township, he said it needs to be a partnership between
them and the Township because it is a challenge and that has not changed.
Exhibit A5 is the proposed floor plan of the event barn. The rendering and floor plan
have not been finalized, but they are substantially close to what is envisioned.
Exhibit A6 is a type of tent that would be used on the event pad. The event pad could be
used as an ancillary use to the main structure or a separate function. It could also
possibly be used in conjunction with the Event Barn as part of a wedding venue.
The events that are envisioned for the Event Barn and the Event Pad are largely for
weddings as there is a beautiful chapel in the main building. There could also be fund
raising events, holiday parties, anniversaries, banquets, and other ancillary events other
than a wedding event. They are envisioning celebrating family, community, agriculture,
and general wellbeing. They are working with professionals for the management of the
site. They still intend on being involved with the project after it is up and running, but
have hired a professional group that has experience in managing facilities such as this to
handle the day to day operations. It will be focused on agriculture, which his people will
be directly involved with and it will supplement the management side of the facility. It
will be the farm to table and the venue.
Supervisor Minutes
June 25, 2019
Page 4
Exhibit A3 is the Planning Commission’s review letter (Also Township Exhibit T6).
This review letter comments on noise and whether there would be a need for additional
insulation in the Event Barn. He does not believe it will be necessary because of how far
from the property line the barn will be located, but they also recognize that they have an
obligation to minimize the noise at the property line and they will do so by fully
complying with the Township ordinances.
It was Mr. Jaindl’s goal to work as much as possible with the land as it exists and not
disturb more than what is necessary. They will have crop farming, small orchards, and
vineyards on existing grades. They are trying to limit the amount of cuts and fills that are
required as much as possible. The style of the barn is meant to be complimentary to the
existing structures. It will be consistent with the farm to table aspect and agriculture in
nature. That is why the structure is going to be detached and surrounded by the
agriculture.
Although the property is being referred to as the Lehigh Valley Resort and Spa, that will
not be the final name of the facility. The final name of the facility will be introduced at
the appropriate time and will be something consistent with the area. It will be a resort
with 206 or 207 rooms and a luxury spa. There will be some inside and outside facilities.
They will be taking two of the existing rooms and converting them into one room so there
will be approximately 43 rooms inside the building. It will be a wedding venue; the
chapel will be kept intact as much as they can; a banquet hall, event center, and hotel. It
will be a unique, world class facility that they hope to get started as early as this fall.
Elizabeth Skrapits, 311 Cherryville Road, asked how far the event barn will be from
Cherryville Road. Mr. Jaindl commented it is approximately 500 feet. Ms. Skrapits also
questioned what steps will be taken if an extra layer of insulation is not needed. Mr.
Jaindl commented they do not believe it will be necessary but they will be looking into it.
Ms. Skrapits noted that the acoustics are very odd on this property and feels research
needs to be done. Mr. Jaindl commented he understands the concern and they will be
looking into it.
Jerry Prichard, 4280 Cashew Drive, questioned of Mr. Jaindl ever foresees a casino
coming onto the site. Mr. Jaindl commented he doesn’t see it. It is not one of the
permitted using in the ordinance and not something that he would prefer.
Testimony of Bruce Anderson:
Mr. Anderson is a Senior Manager at the Pitcock Company. Exhibit A7 is Mr.
Anderson’s resume. Based upon Mr. Anderson’s resume and experience, it was agreed
that he could be considered an expert in civil engineering.
Supervisor Minutes
June 25, 2019
Page 5
Mr. Anderson testified that with the exception of the conditional use approval, the land
development plan set and the conditional use site plan meets zoning requirements.
Exhibit A8 is the site plan that was submitted as part of the applicant’s exhibit. Attorney
Zator noted that the site plan that was submitted is limited in scope because the purpose
of the conditional use hearing was for the Event Barn and the Event Pad, not the overall
project. They didn’t want to confuse matters by having the officially submitted
conditional use plan go beyond the Event Barn and Event Pad. In addition, there is a
provision in the ordinance that says if there is a material change to the site plan, then
there is a need to get a reapproval of the conditional use. Since the land development
review and approval process has not yet been completed, they didn’t want to have the site
plan reflect everything that is going on with the land development plan in case there is an
adjustment that needs to be made to the plan. The focus of this hearing is really on the
Event Barn and Event Pad.
In order to obtain conditional use approval, the applicant needs to demonstrate their
compliance with certain requirements of the ordinance. Mr. Anderson’s testimony
addressed these requirements as noted below.
Section 180-128.C.1. The requirement that what is being proposed is consistent with the
purpose and intent of the Zoning Ordinance as noted in Section 180-3 which reads the
Chapter is adopted for the purpose of promoting the health, safety, and general welfare of
the community and to further the following specific objectives:
A. To guide and regulate the orderly growth, development, and redevelopment of the
Township in accordance with a comprehensive plan of long term objectives,
principals, and standards benefitial to the interest and welfare of the people. The
proposed use is consistent with this because it is a component of the
redevelopment of this tract, the repurposing of the Seminary Building. Even
though they are a separate structure, they are still part of the redevelopment and
the comprehensive planning of this tract is embodied within the ordinance that
was passed to have this use within the PRRC Zone. What is being proposed is
consistent with the PRRC amendment to the Zoning Ordinance.
B. To protect the established character and social and economic well being of both
public and private property. This proposal is consistent with this by the nature of
this development because it tends not to concentrate the development and
therefore protects the well being of the private property. The buffers, berms, and
landscaping will also protect the private property. The development will also be
improving the public roadway, Cherryville Road. It will also be enhancing the
utility structure within the Township as well.
Supervisor Minutes
June 25, 2019
Page 6
C. To promote in the public interest utilization of land for uses which it is most
appropriate. The proposal fosters this by the use being imbodied within the
PRRC ordinance where it envisions the repurposing and redevelopment of this
site.
D. To secure safety from fire, panic, and other dangers and to provide adequate light,
air, and convenience of access. The plan for the proposed use has been reviewed
by the Fire Marshall and determined to be adequate. It also is spread over the
acreage so it is not confined or concentrated in one area and therefore allows for
the light and air. The convenience of access is demonstrated by the roadways of
the development, trying to follow the topography of the site and minimizing the
number of cuts and fills.
E To prevent overcrowding of land or buildings and to avoid undue concentration of
Population. The proposal meets this requirement because of the uses being spread
out, away from a concentrated focus. It doesn’t overcrowd the land; it works with
the land. It will be a vastly open area even after the project. Crops and vineyards
will be integrated on the site. There will be an agricultural element amongst the
buildings and paths.
F. To lessen and, where possible, to prevent traffic congestion on public streets and
highways. This requirement will be met with the widening of Cherryville Road to
provide a left and right turn lane into the facility allowing the through traffic on
Cherryville Road to be unimpeded. The development’s traffic has been included
in the Township’s Act 209, overall traffic study and the study was developed
using the resort’s traffic figures.
G. To conserve the value of buildings and to enhance the value of land throughout
the Township. This is met because the repurposing of the Seminary was the
driving force though this whole development. It’s whole genesis is to save the
building and increase its value from the neglected building. The value of the land
is exhibited by the agriculture which is envisioned for the remaining areas around
the buildings. The Event Barn and Event Pad are an integrated portion of the
overall project.
Section 180-128.C.2. The proposed use shall not detract from the use and enjoyment of
adjoining nearby properties. The separate natures of the two facilities will not crowd the
property. They are situated so as to not obstruct any views from or of the property and
Supervisor Minutes
June 25, 2019
Page 7
not to impair the use of the adjoining properties. It’s a large tract on a hilltop and being
used as gently as they possibly can.
Section 180-128.C.3. The proposed use will not effect a change in the character of the
subject property's neighborhood. The Event Barn and Event Pad are complimentary uses
to the resort function of the facility. Buffers and landscaping have been included and
they will comply with the pertinent noise ordinance. It is believed that the character of
the neighborhood was taken into account when the PRRC zoning district was developed.
Section 180-128.C.4. Adequate public facilities are available to serve the proposed use
(e.g., schools; fire, police, and ambulance protection; sewer, water, and other utilities;
vehicular access; etc.). The requirements of this section will be met and further discussed
when Fred Ebert testifies. The public utilities are integral to the project.
Section 180-128.C.5. The application complies with the requirements of Floodplain
Management. This is not applicable to this application. The Event Barn and Event Pad
are not located within a floodplain.
Section 180-128.C.6. The proposed use shall comply with those criteria specifically
listed and all other applicable regulations of the Zoning Ordinance. The Event Barn and
Event Pad will comply with all over requirement of the ordinance.
Section 180-128.C.7. The proposed use will not substantially impair the integrity of the
Township's Comprehensive Plan. The process of adopting the PRRC zoning ordinance
had to take the Comprehensive Plan into consideration. This particular use came directly
from the process and the PRRC ordinance. It will enhance the natural surroundings by
bringing in the agriculture which is currently on the site as well as bring jobs to the
Towship and a financial boost. It is intended to be a premier facility and enhance the
previously underutilized seminary building.
Attorney Zator noted that these forgoing requirements are subjective in nature and
because there are no objective criteria in the ordinance, there is nothing additional the
applicant needs to prove. However, recognizing the ordinance’s provision requiring the
Planning Commission to prepare a report, there are certain things that the Planners are to
consider in doing that. The advisory report from the Planning Commission is to address
items such as location of the use in relation to the needs and growth pattern of the
Township, adequacy of the site area and arrangement of the buildings, driveways,
parking areas, off street truck loading spaces and other pertinent features of the plan.
Some of these items have been commented on in the Planning Commission’s letter and
some haven’t. He suggested the items that were not commented on, the compliance is
self-evident.
Supervisor Minutes
June 25, 2019
Page 8
With regard to the location of the conditional use in relationship to the needs and growth
pattern of the Township, the anticipated traffic to be generated by this development has
been included in the Township’s Act 209 study and the uses were anticipated in the
PRRC ordinance.
In regard to the adequacy of the site area and the arrangement of the buildings, the
existing principal uses of the seminary and spa are already there. The Event Barn and
Event Pad are located nearby so that they are complimentary to the main buildings. They
haven’t been placed in a tight cluster at the top of the hill. They are working together
with the topography. The site triangles at intersections, curvatures, and cross sections
have been studied by the Planning Commission. The Fire Marshal has also reviewed the
plan.
Item 4 in the Planning Commission letter relates to no off street parking on the paved
paths. The applicant began the process by complying with the parking requirements that
are needed for this facility and have demonstrated on the overall site plan that total
parking requirements are met. Because this is an integrated facility, the parking lots will
be shared amongst the various venues, including the Event Barn and Event Pad. There
will be attendants directing the people into which parking lot people need to park in and
the paths are there for pedestrians to traverse and are only eight feet wide so there really
is not a place for people to pull off and park. The fire lane that goes around the southeast
side starts out at 20 feet of paved area and transitions to 15 feet of paved area and 5 feet
of reinforced turf strong enough to support wheel loads of the fire vehicles. The Fire
Marshall has concurred with this arrangement. This fire route will be designated as
emergency vehicles only and for staff vehicles to move around the site. Parking will be
prohibited.
Item 8 in the Planning Commission letter relates to loading and unloading at the service
barn only and Item 5 requires the construction of the service barn simultaneously or prior
to the use of the Event Barn or Pad. The Service Barn is located to the north of the Event
Barn and its purpose is to receive deliveries from off site suppliers. The deliveries will
be broken down for distribution around the site by smaller vehicles. The Event Barn will
not be receiving deliveries from off site tractor trailers. The vehicles that will be
transferring the supplies around the site will be much smaller. The trash management
will be in the Service Barn. Trash will be removed from the Event Barn and brought to
the Service Barn. The belief of the comment that loading and unloading will only take
place at the Service Barn was that it was aimed at off site tractor trailer trucks. There will
need to be smaller trucks maneuvering throughout the site to deliver supplies.
Pertinent features of the site are also to be considered. There is a water feature labeled on
the site plan as proposed detention/retention basin, but in reality, it will be an amenity
and a hopefully a suitable photographic viewpoint. It is intended to be an attractive
Supervisor Minutes
June 25, 2019
Page 9
landscaped space that will also function as a detention basin. There will also be buffering
and landscaping between Cherryville Road and the Event Barn driveway. There will be
paved paths that allow pedestrians to traverse the site.
Item 3 on the Planning Commission report requires a snow removal area be provided.
The principle detriment of plowing snow is that is usually takes up parking spaces. They
have plenty of area outside the parking lots so they don’t necessarily need to leave snow
on the parking areas. There will be areas shown on the plan.
Phil Gogel requested clarification on the 20 foot roadway which will decrease to 15 feet.
Mr. Anderson commented it will start at 20 feet at the east end of the service area to the
Event Barn and extend to the first intersection of the pedestrian path. At that point, it will
transition to the 15 foot driveway to the back of the new hotel segments. It will be 15
feet of paved area and then 5 feet of reinforced turn. They are trying to be functional and
work with the site. Aesthetics are also important.
Adam Raker, 1120 Municipal Road, commented it was testified that the site will be
compliant with all other aspects of the Zoning Ordinance. Have there been or will there
be additional variances requested. Mr. Anderson commented the variances that were
needed were already granted. Mr. Raker also requested that the exhibits that the Board
had be made available for the public to see during the hearing. Mr. Anderson reviewed
the exhibits and also offered Sheet 7 of the full land development plan set (last revised
June 17, 2019) as an additional exhibit to show the overall layout of the site. This will be
Exhibit A13.
Cindy Miller commented in looking at Exhibit A8, there is a shaded area shown on the
plan near the kitchen area. Will this be the proposed area for delivery of supplies and
how will the vehicles travel through the site to get there? Bruce Anderson commented
they will go back and forth between the Event Barn and the Service Barn without going
on Cherryville Road. They will follow the service driveway and the Event Barn
driveway to access the delivery side of the Event Barn. Cindy Miller also questioned the
type of vehicles that will be making the deliveries to the Event Barn. Mr. Anderson
commented it could be a variety ranging from a golf cart size, gators, pickups. David
Jaindl commented it could possibly be a straight type of truck, but most likely pick up.
Jerry Pritchard, 4280 Cashew Drive, questioned who will pay for the cost of the turning
lanes. Mr. Anderson commented it will be the developer. Mr. Pritchard also questioned
who will maintain the turning lanes once they are installed. Mr. Anderson commented
the Towship will be maintaining them. Mr. Pritchard questioned if there are intentions of
providing an additional access in and out of the site as this project progresses. Mr.
Anderson acknowledged there will be an additional access.
Supervisor Minutes
June 25, 2019
Page 10
Beth Trexler, 255 Cherryville Road, commented their home is level with Cherryville
Road; it doesn’t sit below the road like the other homes on that lane. With the parking lot
being built up by ten or twelve feet, they have a concern with the headlights shining into
their second floor. Why does the parking lot need to sit up the ten to twelve feet? Mr.
Anderson commented it is because of the terrain. The terrain rises the further east you go
on the site, so rather than cutting the lot down, they are going to terrace it into the higher
elevation of the site. There will be greenery around the parking lot. They are not
anticipating any issues with lights shining into the homes.
Ed Ziegler, 248 North Walnut Street, Slatington, questioned if there will be a heliport on
this site. David Jaindl commented they are not proposing one at this point. Mr. Ziegler
questioned if there will be an ambulance on site during large events. Mr. Jaindl
commented he doesn’t anticipate having an ambulance on site, but if it is needed for the
event, he will.
Mike Jones questioned if the parking lot lights and Event Barn lights will be on a timer
and automatically shut down at a certain time. Mr. Anderson commented they will more
than likely economize the use of electric lights whenever possible, but they will need to
balance it with access and safety. If they can go dim or dark, they will.
Phil Gogel questioned what the elevation of the parking lot is compared to the street Mr.
Anderson commented it is eight to ten feet higher. Phil Gogel noted he can understand
why there would be a concern regarding the lights.
Testimony of Fred Ebert:
Fred Ebert is the President of Ebert Engineering. Exhibit A9 is Mr. Ebert’s resume. Mr.
Ebert is a professional engineer with an area of expertise in water and waste water
engineering. Based upon Mr. Ebert’s resume and experience, it was agreed that he could
be considered an expert in this field.
At this stage of the approval process, not having any plans approved, feasibility is the
normal standard pertaining to water and sewer. For this development, they have far
exceeded this and gone down the approval process pretty extensively with both the water
and sewer and procuring it to the point of implementation, rather than just feasibility.
Addressing Comment 6 in the Planning Commission’s letter which indicates that
approval should be conditioned upon final agreements for water and sewer. The status of
the sewerage for this project is that there will be 34,650 gallons of sewerage generated
per day for the first phase of the project. It will go down by a combination small low
pressure and gravity system to the existing Pennsville Treatment system. The existing
Supervisor Minutes
June 25, 2019
Page 11
treatment plant has enough capacity to serve this phase of the project. The treatment
plant rated capacity is 60,000 per day and they are currently using 15,000 gallons per day.
The developer has executed an agreement with the Lehigh Township Municipal
Authority to reserve capacity of 35,000 per day. This agreement is Exhibit A11. They
have also gone as far to submit and start the approval process with the Pennsylvania
Department of Environmental Protection with a sewage facilities planning module. They
had a joint meeting with the PA DEP and the Municipal Authority where they reviewed
the flows and confirmed that the Planning Module is the correct method to go through.
They will be installing a small pump station at the treatment plant. DEP was so
supportive of their Planning Module that they are allowing them to do a concurrent
review of the construction of this along with the module. They went through all their
proposed flow calculations for the uses so that DEP agrees with the amount of flows that
will be generated. They didn’t want to get to the end of the process and find out that DEP
didn’t agree with their flow calculations and they needed to reserve more capacity. They
also discussed future phases of this project. Right now, everything from a waste water
aspect can be contained without an expansion of the existing treatment plant. The only
thing they need to do is install an inflow pump station.
The water will be an interconnection with the City of Bethlehem. Lehigh Township is
located within the PUC franchise area of the City of Bethlehem. There is a draft inter
municipal agreement or bulk water agreement, that has been prepared by the City of
Bethlehem and given to the Municipal Authority. The City of Bethlehem has prepared a
will serve letter certifying they have the capacity to service them for both domestic
drinking water and fire protection needs. This letter is Exhibit A10. There are three off
site easements that will be required. There also is one off site agreement for wastewater
as well. They have agreements in writing with those property owners to obtain the
easements. Once the complete design process and Township approval process has been
completed, they will finalize the easements and have them recorded. At the June meeting
of the Municipal Authority, they authorized their solicitor to prepare a will serve letter
that they will provide water in accordance with the City of Bethlehem agreement. They
have also certified capacity for the waste water treatment plant as part of the planning
module process. The key components of the water and sewer needs are that they have
obtained capacity for water and sewer, obtained all off site easements, and met with the
regulatory body, DEP, so that they know the appropriate forms and regulatory process
and share all important facts with them so that the developer understands what approvals
will be needed. Every meeting they have, they have the Authority present.
Attorney Backenstoe requested clarification on the sewer capacity agreement with the
Municipality. Was this agreement for the first phase? Mr. Ebert confirmed it was for the
first phase and the first phase included the entire land development that was referred to
by Mr. Anderson, A13, approximately 12.7 acres of non-residential use, including the
Supervisor Minutes
June 25, 2019
Page 12
Event Barn and Pad. Attorney Backenstoe questioned if there is anticipated further
residential development for this project? Attorney Zator commented there is not a
residential component with the current plan, but it would be fair to say that there would
be a residential component to a future phase. Attorney Backenstoe questioned if the
future phase will require an expansion of the sewer plant. Mr. Ebert commented an
expansion will be required. The ultimate the buildout of the entire property, including a
portion in Allen Township will require approximately 200,000 gallons per day. The
existing treatment plant has a 60,000 gallon per day capacity. They will be working with
the Authority regarding extra capacity. They have obligated to build a plant which will
accommodate 260,000 gallons per day. If the Authority does not want the extra capacity,
they will not build it. The development plans for this have not been submitted to the
Township for consideration at this time. Attorney Backenstoe questioned if this current
phase is dependent upon any future phase or will it be able to stand alone throughout
time. Mr. Ebert commented that the intention is to build the future phases, but it is his
understanding that this phase is able to stand alone.
Attorney Backenstoe also requested clarification regarding the water service to the site.
He noted there is a will serve letter from the City of Bethlehem, but they will not be
providing the water directly to the developer. They are actually providing the water to
the Municipal Authority. Mr. Ebert commented once the project is built, they will
become customers of the Towship Municipal Authority. The bulk purchase agreement is
between the City of Bethlehem and the Lehigh Township Municipal Authority. The
Municipal Authority will purchase the water in bulk from the City of Bethlehem, then
resell the water to the development as their customer. Attorney Backenstoe questioned if
there is a will serve letter from the Municipal Authority. Mr. Ebert commented they do
not physically have it at this time. At the June 6 meeting of the Municipal Authority,
they authorized their engineer to prepare the will serve letter, to be approved by their
solicitor, and subsequently provided to the developer. They anticipate receiving this
letter by Friday. The bulk water service agreement with the City of Bethlehem has been
received by the Municipal Authority in draft. Attorney Backenstoe questioned how the
water will be getting to the project site. He didn’t recall it being included with any of the
submissions. Mr. Ebert commented they did not previously provide this because at the
time of submission, they had not received all of the easements. Since that time, they have
received all the easements. The lines will travers across the farm fields. There is a City
of Bethlehem low pressure water main coming out of their reservoir by an identified
connection point. At this connection point, there will be a meter pit installed. This will
be the transition from the City of Bethlehem to the Lehigh Township Municipal
Authority. The developer will install it going off road, around the farm field, following
an electric powerline, going underneath the creek. They will put a water booster station
on the Pennsville treatment plant property. It will then be conveyed through another
offsite easement onto the Jaindl property. It will be designed to meet all the operating
Supervisor Minutes
June 25, 2019
Page 13
pressures at the Seminary which is the highest building at the highest point of the
property. All the easements that are necessary to execute this plan have been secured, but
not recorded. They do have an agreement with all the parties subject to any final
revisions that may happen during the final plan development process. The only roadway
effected by this will be Indiantrail Road where they will need to transverse the roadway.
Cindy Miller questioned if there is an expansion that needs to be done physically to the
existing plant building for Phase 1 and then for Phase 2. Mr. Ebert commented in Phase
1, the plant won’t need to be expanded, but because they are coming in by gravity, they
will be installing a pump station for the waste water on the Pennsville Waste Water
Treatment Plant property. They are working with the Authority so they can potentially
phase out their existing pump station and come into that by gravity. There will also be a
water booster station on the Pennsville Treatment Plant property, which currently is
actually the Township’s land. They will need to do a lot line adjustment with the
Township. They are also proposing to place an emergency generator on the site that will
be sized for the ultimate build out of the treatment plant site . They would be phasing out
the authorities existing older generator now and replacing it with a new oversized
generator for the new treatment plant, the water booster station and the existing treatment
so that they wouldn’t be doing things twice. Cindy Miller questioned how much land
will be needed from the Township to do this. Mr. Ebert commented they have met with
the Authority and the lot size they would like would be approximately two acres. This
would provide for the expansion of the treatment plant, the water booster station, the
pump station and stormwater management facilities. The Authority wanted to have room
for future expansion as needed in the future so that they wouldn’t need to do another lot
line adjustment. They have a water and sewer subcommittee that meets one a month and
they are attending the Authority’s meetings monthly which results in meeting with them
every two weeks. Based on Mr. Ebert’s recollection from the joint meeting that was held
between the Municipal Authority and the Board of Supervisors, the Supervisors asked for
the recommendation of the Authority. They wanted the developer to work with Authority
and then have the Authority come back to the Board of Supervisors with a
recommendation as to how much land was needed. The amount of land and the lot line
adjustment is ultimately a decision between the Authority and the Township. The
developer will never own the land. The developer is only doing the construction. They
are working with the Authority’s engineer. The Authority’s engineer will be doing the
engineering for the lot line adjustment plan since it will ultimately be theirs. His
company will be doing the mechanical design for the site. Cindy Miller commented that
the Township would then need to agree with the Municipal Authority’s recommendation
to give the land before this could move forward. Mr. Ebert commented that was correct.
The first step in the process, at the direction of the Board of Supervisors, by motion at the
Supervisor Minutes
June 25, 2019
Page 14
meeting, for all the facilities to be located on a single location by the Authority’s existing
property. The direction was to come back with a recommendation of how much land
they want for consideration by the Board of Supervisors.
Mike Jones questioned if the two acres was the total amount of land that was needed or
an additional amount of land that is needed. Mr. Ebert commented it is an additional
amount of land. The actual size of the land is 1.89 acres. The improvement would fit on
1.5 acres of land, but to make a better shaped lot, they squared it off.
Cindy Miller questioned if the Municipal Authority has figured out how they will
maintain the piping. Mr. Ebert commented the questions pertained to accessing the pipe
with the slopes. They have provided the Authority with profiles of how they would be
accessing the pipe. The concern was the mowing of the easement because they should be
done once or twice per year and they don’t have a four wheel drive truck. Mr. Ebert
explained to them that this is a common issue amongst authorities. The maintenance of
the easements becomes a contracted service with either a local farmer or someone else
who is contracted to maintain the easement and mow it with a brush hog twice a year. In
most cases, it is not a prudent decision to own the tractor that is needed to access these
easements. While the hillside is steep, you are accessing it from the side so there is only
a five to seven percent grade all the way up except for the last little bit, right behind the
hotel where it is steep, but a very short run. The profiles and access were discussed with
the Authority at length. Their greatest concern was with the amount of equipment they
thought would need to be purchased to maintain the easements. Once they learned how
other authorities handle this type of situation, the comfort level increased. They are also
going to be flagging the easements and walking it with as least two of the Board members
prior to this being completed so they not only see it on the plan but also in the field.
Sandy Hopkins, 1187 Oak Road, noted that after the 35,000 gallons has been allocated to
the development, there will only be 10,000 gallons remaining for any additional
development. Mr. Ebert commented that would be correct for the defined public sewer
service area of the Pennsville plant. There has not been any new connections or
development lands besides this project in the existing service area, but they are still
providing the 10,000 gallons of unallocated sewage. Sandy Hopkins commented just
because there hasn’t been any development, doesn’t mean there won’t be with all the
farm lands around the area. Mr. Ebert commented those farmlands may not be or most
likely are not included in the public sewer service area. In order to be included in the
area, they would need to go to the Township first and requests to be added to the area and
then get approval by DEP. Just because farmlands are located adjacent or nearby doesn’t
mean they have the right of public sewer service. They would have to go through the
process to be put in there. When the treatment plan was sized, it was sized for the
Pennsville area and basically this property. Ms. Hopkins questioned the projections for
Supervisor Minutes
June 25, 2019
Page 15
the build out of the land. Mr. Ebert commented that the total projected sewage needs for
lands that are owned by Jaindl Land Development Company in both Lehigh and Allen
Township’s is a total of 200,000 gallons per day. This total is subject to full land
development approval and facilities approval.
Cindy Miller commented the concern with the removal of sludge from the facility was
discussed during the joint meeting. Has there been a determination on this? Mr. Ebert
commented the Municipal Authority’s plan is not to land apply it or use reed beds, but to
haul it as liquid sludge to the Lehigh County Authority. That is the direction and selected
alternative right now of the Authority. They believe the most cost effective means for
them to handle the sludge, based on the recommendation of the operator and the engineer,
was to have it removed as a liquid, aerobically digested to reduce the volume and haul it
away to another facility for disposal.
Adam Raker, 1120 Municipal Road, questioned where the easement that will need to be
mowed are located in relationship to the project and the current facility. Mr. Ebert
commented on they are located on lands owned by Jaindl Land Development Company.
They are currently areas not developed, but some of them can and will be developed and
others will most likely never be developed. They will be transitioning from a wooded
condition to a meadow condition to a lawn condition. Mr. Raker questioned where the
Authority’s responsibility would pick up within the easement. Mr. Ebert commented it
will be the easement area. They will be offering for dedication all the sanitary sewage
facilities and the water main from the treatment plant or source all the way up into the
development. The water and sewer easements will be 30 feet wide and if it is only water
or only sewer, they will be 20 feet wide. The Authority would maintain whatever is
located within the easement. They would not be responsible for maintaining any sewer
laterals outside the easement area going into private buildings. These would remain
private like in any other public utility. Mr. Raker commented he was not understanding
why the Municipal Authority would be responsible for lines on private property. Mr.
Ebert commented the development would be customers of the Authority; no different
than anyone else in the service area. In addition, it is required by DEP that the mains are
municipal ownership. All the mains have to be dedicated to the Municipality. When
they met with DEP, that was one of their primary points, that they would be dedicating
and the Authority was accepting of the mains. Otherwise, it would have been mandated
because there will potentially be residential customers owning the properties and they
want to be certain that it will be maintained to a municipal standard. Mr. Raker
questioned if the developer will be responsible for a greater rate or increased maintenance
cost because to serve the project, a pipe is being run that the Authority will now be
responsible for and other people may or may not be able to tap into it. Mr. Ebert
commented the benefit to the Authority is that they are getting an asset donated to them
for free and are also getting the customers. It could be set up as a separate rate district so
Supervisor Minutes
June 25, 2019
Page 16
that it is set up so that the customers are paying for their service area. The rate would
include a capital replacement amount so that there is money available for future
replacement. Mr. Raker noted the replacement cost will be much greater in the future,
especially if there is not an increased rate. Mr. Ebert commented that is why the line
must be installed and built to Authority standards, just like they were building the line
themselves. The design will be approved by the Authority and the construction will be
inspected by the Authority to meet their standards. There would also be a maintenance
period from the initial installation. The maintenance and repair of this main would be no
different than any other sewer main. Mr. Raker commented there will be an easement to
be maintained as well as the entire length of main but yet there will not be an additional
rate charged. Mr. Ebert commented the project will have to subsidize the rate. The
project will need to stand on its own. For right now, there may be an unusual amount of
main that is being run, but when the residential component is complete, there will be less
linear feet per property than a normal municipal system. This is why it is set up as a
separate rate district so that one district does have to subsidize another district. Mr.
Raker commented he is glad this project is here and hopes it moves forward.
Paul Nikisher, 668 Lone Lane Road, questioned what the distance of the easement that
the Authority will be responsible for. Mr. Ebert commented the length of the main is
over a mile long. Mr. Nikisher questioned what the distance is between the main and the
private service. Mr. Ebert commented the Authority would be responsible for the main
and the lateral to a point approximately 10 feet from the side of the easement. At that
point it would become a private line, just like any other home. The right of way line is
the dividing line between the public and private laterals. Mr. Nikisher questioned if the
line that is running on Mr. Jaindl’s property wouldn’t be private. Mr. Ebert commented
that the main line that is being run in the easement will be dedicated to the Authority as a
public line. This dedicated line will run next to properties that Mr. Jaindl will be
subdividing into smaller lots. Once everything is done, it will look like a more traditional
layout, but right now, you are running a line over a large field which is not subdivided.
This area will eventually be subdivided into numerous lots and future property owners. If
after the maintenance period ends, and the resort is the only customer on the system and a
repair is needed and it causes a rate increase, the rates for the resort will end up
increasing. Things break which is why there is a projected capital improvement amount
included in the rates so that over time, the cost of the repair is easier to afford.
Phil Gogel commented until the development goes through Phase 2, there will really only
be one customer or entity being served. There are no guarantees that the residential or
second phase will happen. Mr. Ebert commented that is correct; if there is only one
customer, the entire operating budget of the water and sewer system will be borne by that
customer. David Jaindl noted that this one customer is the equivalent of 137 residential
customers. Mr. Ebert noted that the rate for the system will be set at an amount that is
Supervisor Minutes
June 25, 2019
Page 17
needed to operate the system in Phase 1. This would be no different than the Cherryville
system other than there is a greater water supply and the ability to offer fire protection.
Testimony of Howard Kutzler:
Howard Kutzler is the Land Use Manager at the Jaindl Land Company. Exhibit A12 is
Mr. Kutzler’s resume. He has over 30 years of professional private and public experience
in land use planning and implementation, as well as the delivery of planning and zoning
and emergency services. Mr. Kutzler also has the AICP credential which is a
certification from the American Institute of Certified Planners, a division of the American
Planning Association. Mr. Kutzler also had prior service with the Lehigh Valley
Planning Commission, Director of Planning and Development for Municipalities, and a
Manager of two different Townships. Based upon Mr. Kutzler’s resume and experience,
it was agreed that he could be considered an expert in land planning and land use
development.
Mr. Kutzler noted that this project will not generate any school aged children.
With regard to Item 2 in the Planning Commission’s review letter pertaining to Fire
Safety and Item 7 pertaining to the approval of the paths by the Fire Marshall, the project
has had several reviews by the Fire Marshall. After his initial review, they had obtained
the services of a local fire code and delivery of services expert. They have met two times
with the Fire Marshall and had several calls with the Fire Marshall. They have worked to
have the plans revised to address his comments regarding having fire access to the site, to
the Event Barn and to the Event Pad. They have most recently had his comments
memorialized in their May submission to the Planning Commission review and they are
awaiting his subsequent review letter. They believe they have addressed all of the
comments and concerns of the Fire Marshall. If there would be more items that he feels
needs to be addressed, the developer will have them addressed. There was support of the
project by the Fire Marshall provided his comments were addressed.
Lehigh Township is not a high crime area and served by their own Police Department and
have back up support by numerous local departments and Pennsylvania State police. The
Township is served primarily by Northampton Regional Emergency Service which is an
advanced life support service which operates full time. They also do stand by services if
it is needed for a major event. The area is well served by emergency services and in
collaboration with the Fire Department, this facility will be well served.
Attorney Backenstoe questioned what the foot print of the proposed barn will be.
Attorney Zator commented it will be 15,000 square feet. It is also depicted on the Exhibit
that was submitted. The Event Pad will be 100 feet by 120 feet.
Supervisor Minutes
June 25, 2019
Page 18
Attorney Zator requested the Exhibit that were presented be admitted into the record.
There was no objection to this and the exhibits were accepted.
Attorney Zator commented he believes they have met all the standards of the ordinance
for the proposed conditional use of an Event Barn and Event Pad. He did note that they
technically were subjective standards and doesn’t believe there was any testimony that
was adverse to this application.
The evidentiary portion of the record was closed.
Attorney Backenstoe commented the Board can now deliberate, propose condition and
interact with the applicant to determine if the conditions are acceptable because the board
does have the right to approve it and place conditions; however, if the conditions are not
acceptable to the applicant, they can object and file an appeal. It doesn’t mean the
condition cannot be placed; it just means that the applicant has the right to file the appeal
with the court of common pleas. The Board would have the option to deny the
application and state the reasons on the record, approve the application, or approve the
application with conditions. This wouldn’t have to be done tonight, but it would need to
be done in the near future because he would need enough time to provide the written
decision to the applicant within 45 days of tonight.
Attorney Backenstoe noted that some of the conditions the Board may want to consider
would be the incorporation of the Planning Commission recommendation, compliance
with the SALDO, compliance with the Zoning Ordinance, and it be conditioned upon
providing adequate facilities, particularly in respect to the public water and sewer to the
site. As part of the water and sewer, the Board would want to confirm the agreement
between our Municipal Authority and the applicant for adequate service. What will be
happing in the future will need to be discussed, but right now the Board is looking only at
Phase 1, in particular the use of the Event Barn and Pad. The Board does have the right
to imply a condition that there is adequate water and sewer service for the use.
Phil Malitsch commented typically the will serve letters are in hand when an applicant
comes into a hearing like this. This is unique in that the development is more than just
the reason for the conditional use hearing; there is a lot more to it. From a capacity
standpoint, this is a small portion of a larger scheme. He believes the Board needs to
give it the appropriate weight with respect to the complications of these issues. He
doesn’t believe the Board has heard anything to indicate that these things will not happen.
The Board may want to consider a condition that the off site extension is promptly
provided to the Township since it does have the potential to impact Township roads in
some capacity. If the facilities cannot be installed where it is intended, there could be a
problem with providing them to the site. The residents correctly had concerns regarding
Supervisor Minutes
June 25, 2019
Page 19
headlight glare and buffering. The Planning Commission has covered these issues
extensively beyond the advisory report that was provide for the hearing. There is
additional detail provided on the site plan to help mitigate these issues.
Darryl Snover commented that as he looked over the list of items in the Planning
Commission’s letter, it seems as though the applicant has largely met or agreed to
everything listed in the letter. The only thing he didn’t recall being specifically addressed
was Item 5 which says the Service Barn shall be constructed simultaneously with or prior
to the use with the Event Barn or Event Pad. Mr. Jaindl commented that would be their
intention.
Mr. Jaindl addressed the conditions listed in the Planning Commission’s letter as follows:
No. 1. If it is determined that additional soundproofing insulation is needed, they
certainly will put it in, but they don’t want it listed as a condition. Darryl Snover
commented he tended to agree because 500 feet is a long distance and looking at
the size, it doesn’t appear as though you would be having the larger concert type
bands.
No. 2. They absolutely agree with.
No. 3. The Planning Commission’s concern is they don’t want snow stacked on parking
spaces, but in the winter time when the snow events occur, the capacity of the
barn and pad is much less. If the Board really wants this, they will comply with
it, but they don’t believe it is necessary. If there is snow on the parking spaces, it
affects them. They don’t want to keep customers out, but in the winter the
capacity is approximately 60 percent less than what it is in the summer, even on
the best day. Darryl Snover commented in his opinion, what they do with the
snow on their land is up to them.
No. 4. No off street parking on the paved paths makes good sense.
No. 5. The construction of the Service Barn simultaneously with the Event Barn is
largely not an issue, but their focus is primarily on getting the Event Barn going.
This is consistent with the concerns with No. 8 where the loading and unloading
will take place at the Service Barn. There could be circumstances where it would
make sense to have straight body truck, a 24’ box truck, not a tractor trailer,
deliver something such as furniture directly to the event barn. It would be a
smarter way of doing things in certain circumstances. They would prefer to have
No. 8 stricken.
Supervisor Minutes
June 25, 2019
Page 20
Darryl Snover questioned if Mr. Jaindl saw an issue with having the public
utilities available for the event barn. Could the Event Barn function on its own
without the utilities being in place. Mr. Jaindl commented it could, but it is
doubtful because he doesn’t see the Event Barn without the rest of the facility.
Their game plan is to build the rest of the facility and they need public water and
sewer for that.
Phil Gogel questioned whether a noise study should be done. Phil Malitsch
commented there was a lot of discussion about this at the Planning Commission
meeting. Mr. Jaindl commented they have agreed to comply with the Township
ordinances as far as decibel levels at the Township line. If for some reason, they
do not comply, they will make the necessary changes to comply.
Phil Gogel also questioned what is being done regarding the light pollution for the
residents who live across Cherryville Road from the project. Could there be
some type of temporary barrier, like a four foot tall hard barrier, be installed until
the greenery and shrubbery comes in? Mr. Jaindl would prefer not to. He wants
to screen it naturally. A barrier is not the best things aesthetically. There are
other things they can look into. They are intending on having a berm along
Cherryville Road. Phil Gogel commented the lights could still be an issue until
everything matures. Mr. Jaindl commented he plans on being a good neighbor. If
there is a concern, he will absolutely address it. At this point, he can’t say just
how. The 4 foot unnatural barrier doesn’t work at this point, but maybe there is
something else they can do if there is a particular resident that is inflicted by
excessive headlights. Phil Gogel suggested possibly adding additional berming to
the area. Mr. Jaindl commented that could possibly be an option. At this point,
we would request it be accepted as proposed, and he will address it if there is a
particular issue that develops. Phil Malitsch suggested a general condition could
be added that landscaping be provided along Cherryville Road to sufficiently
screen adjoining properties from headlight glare. There is a lot of landscaping
being proposed, but the ordinance requires that there not be too much to obstruct
views of the Seminary. The key will be finding the balance point. Based on what
was provided on the plans so far, he does believe this will be achieved. Mr. Jaindl
commented he would like to build it as proposed and if there is a problem, he is
only a phone call away.
Cindy Miller questioned the intent of the Service barn. At the Planning meeting,
it was discussed that the Service Barn is for the receiving of supplies and to make
the food and deliver it to the Event Barn. Mr. Jaindl commented the Service Barn
is generally a supply house. The supplies will be delivered there and then
Supervisor Minutes
June 25, 2019
Page 21
distributed as need throughout the site. There will not be any food made in the
Service Barn. Cindy Miller commented she believes the Planners wanted the
Service Barn and the Event Barn simultaneously because you would need the
Service Barn to receive the supplies for distribution. Mr. Jaindl commented in his
opinion it is too much big brother. They know what they need on the site. They
will ultimately build the Service Barn, but they don’t want the Service Barn police
to come out if there is a straight struck delivering something to the Event Barn. If
there is a larger load, it may be better and more efficient for the truck to go
directly to the Event Barn. It will not be tractor trailers because he doesn’t want
them going to the Event Barn. Phil Malitsch commented the ordinance requires
that a site be able to facilitate the vehicles making the delivery. It can be required
that the Event Barn be equipped with the appropriate size loading area for the
deliveries that it will receive. It just needs to be planned for. Darryl Snover
commented he doesn’t want to impose what can or can’t come within the property
because Mr. Jaindl is the one who must live with what is allowed in. Cindy
Miller commented there is a loading dock ordinance that he would need to
comply with. Phil Malitsch commented that if the Board is okay with Mr. Jaindl
just complying with the loading dock ordinance, then Item 8 can be removed.
Keith Hantz made a motion to grant conditional use approval for the Event Barn
and Event Pad subject to Items 2, 4, 6, and 7 of the June 5, 2019, Planning
Commission letter, the applicant comply with any and all SALDO and Zoning
regulations, any and all local or state regulations, the applicant procure the
necessary water and sewer service for the facility as evidenced by a service
agreement and/or bulk service agreements, and the applicant submit a water
conveyance line plan as soon as possible to confirm the ability to convey adequate
water to the site which would include the necessary easements in place. Mike
Jones seconded the motion. Mr. Jaindl questioned if the compliance with the
ordinances or state requirements was implying that any variance or waivers that
are granted are considered to be compliance. Attorney Backenstoe confirmed that
to the extent that a variance or waiver was granted, this to be accurate. Phil Gogel
questioned if the adequate screening from headlights should be included as part of
the motion. Keith Hantz commented he was not amending his motion. Mr. Jaindl
commented even though it is not a condition, he does want it on record that as he
previously stated he will address any issues that arise to the neighboring property
owners as a result of the headlights in the parking lot. All voted aye. Motion
carried.
III. APPROVAL OF THE MINUTES
A. Minutes of June 11, 2019. Keith Hantz made a motion to approve these minutes.
Mike Jones seconded the motion. All voted aye. Motion carried.
Supervisor Minutes
June 25, 2019
Page 22
IV APPROVAL OF THE BILLS
A. General Fund Checks 23081 to 23104. Keith Hantz made a motion to approve
these bills. Mike Jones seconded the motion. All voted aye. Motion carried.
V. PLANNING RELATED ITEMS
A. Lehigh Valley Resort and Spa—Update and Waivers. Bruce Anderson, Attorney
Joseph Zator, and David Jaindl were present to represent this plan. There was a
letter from the Planning Commission dated June 6, 2019, recommending seven
waivers and the withdrawal of a previous waiver request. The waivers that are
recommended for approval are as follows:
1. Section 147-24.C.(2) regarding the disturbance of steep slopes over 30
percent. The Township Engineer shall review the slopes along with the
review and approval by the Municipal Authority and their Engineer.
2. Section 147-32.F regarding the Township standard curb standards
3. Section 147-15.B(14) regarding vegetated swales not having a design
velocity greater than 4 feet per second.
4. Section 147-18.C regarding street widths
5. Section 147-18.D.3 regarding intersection side streets shall maintain a
seventy five foot distance from the primary through street
6. Section 147-18.G.4 regarding street curb intersections
7. Section 147-18.I.3 regarding curbing being required in all major
subdivisions or land developments.
8. Section 147-36.J.1.a regarding the size of the barn was withdrawn. The
barn at the proposed size of 15,000 does not require a waiver.
Phil Malitsch commented waiver #1 regarding the steep slopes still requires more
information, but the Planning Commission felt comfortable enough leaving it up
to the engineers to review. With regard to waiver #4 and #5, the developer is
proactively asking for these waivers even though the plan does not have streets on
it at this time. The driveways on this plan may become streets in the future. The
discussion at the Planning Commission was that this waiver applies only to those
sections of current driveways which may become streets in future applications.
Supervisor Minutes
June 25, 2019
Page 23
Phil Gogel questioned if the driveways become streets in the future, will they be
widened? Phil Malitsch commented the waiver that is being recommended is that
the width of the driveways that are being shown would remain that same width if
they become streets. The developer would not be required to go back and retrofit
the streets. The Planning Commission reviewed this pretty extensively and felt it
was appropriate. Attorney Zator commented that is the reason for the request.
They don’t want to have to rebuild what is already built, even though they don’t
need the waiver at this time.
Cindy Miller made a motion to grant the waivers as outlined and recommended in
the Planning Commission’s letter dated June 6, 2019. Mike Jones seconded the
motion. Cindy Miller, Darryl Snover, Keith Hantz, and Mike Jones voted aye.
Phil Gogel was opposed.
Attorney Zator noted the plan will be before the Planning Commission at their
July 8, 2019, meeting.
VI. OLD BUSINESS
A. Cherryville Intersection. Alice Rehrig reported an asbestos abatement proposal
was received from the company who did the asbestos sweep and analysis for the
building. Since the abatement is required, would the Board want to consider
contracting for the abatement separate from the demolition bids? The benefit to
having the Township handle the abatement is that they would be able to control
the cost of the abatement by obtaining proposals from different companies. Based
on the initial proposal that was received, the amount would be low enough that
formal bidding would not need to be done.
Darryl Snover questioned if the abatement can be done separate from the
demolition. Phil Malitsch commented that it can be done. There are pros and
cons. If it is included in the General Contract, the Township will just end up
paying a mark up on it. If it is done separately, then you have two different
contractors working at the site, although this is a small project.
Cindy Miller commented she feels that it should be done separately, but there
should be more than just one bid. Alice Rehrig commented there are an
additional three companies that will be contacted.
Cindy Miller made a motion to pursue the contract for asbestos abatement
provided we get a minimum of three bids for review. Keith Hantz seconded the
motion. All voted aye.
Supervisor Minutes
June 25, 2019
Page 24
Cindy Miller questioned how long the owner of the building has to remove his
personal items. Alice Rehrig commented she sent letters to both owners giving
them until July 21st to remove the items. Cindy Miller questioned why we are
giving so much time. Alice Rehrig commented when she had spoken with
Attorney Backenstoe about this he had suggested 30 days. Attorney Backenstoe
commented he just assumed 30 days would be a reasonable amount of time.
Cindy Miller commented the Historical Society also wants to get into the building
before it is demolished. Alice Rehrig commented the bids are scheduled to be
awarded on July 23, and the demolition wouldn’t take place for roughly a week
after that because the contractors would need time to obtain their performance
bond. Cindy Miller questioned if a week would give the Historical Society
enough time to get in the building. Keith Hantz commented from what he was
told, the only thing the Historical Society wants is the keystone and the stepping
stone outside the front door. Alice Rehrig commented that they also want to take
some pictures. Attorney Backenstoe suggested having a Township Representative
go with the Historical Society when they take the pictures.
Elizabeth Skrapits questioned if there will be any architectural salvage done on
this property. The Board commented it is not being done. Ms. Skrapits
commented a salvage firm may be willing to pay the Towship to take the building
down. The Board commented a salvage firm is more than welcome to bid on the
demolition of the building. The demolition has been advertised in a local
newspaper and also on PennBid which is a state wide site.
B. Maintenance Building. Adam Raker questioned if anything has taken place with
contacting the architect regarding the awarding of the bid. Alice Rehrig
commented W2A has been notified and they will be contacting Attorney
Backenstoe regarding developing a contract. Adam Raker questioned if he could
look at the contract prior to it being accepted. Attorney Backenstoe will provide
the copy. Adam Raker also questioned what the process would be once the
contract is signed. Attorney Backenstoe commented the next thing would be to
set up a meeting to discuss the project with them. Adam Raker commented
typically he would set up a meeting between the architect, the building committee,
and the engineer.
VII. NEW BUSINESS
A. Ash Road Bridge—Request for Payment #2. The second payment request for the
Ash Road Bridge has been received from the contractor for the bridge structure
and beams. The total payment being requested is $62,554.47. The Engineer for
the project has inspected the bridge and found to be acceptable. The project
Supervisor Minutes
June 25, 2019
Page 25
continues to move forward. Since this request, the contractor paved the
approaches and is waiting on the guiderails and line striping.
Keith Hantz made a motion to release Payment No. 2 in the amount of $62,554.47
to Sikora Brothers. Mike Jones seconded the motion. Jerry Pritchard questioned
if anyone actually goes out and looks at what was installed. Alice Rehrig
commented the Engineer who was in charge of the project was at the site and
signed off on the payment request. Keith Hantz questioned what the completion
date is for the bridge. Alice Rehrig commented that it is supposed to be done by
mid to late July, but it appears as though it will be done before then. All voted
aye. Motion carried.
B. Recreation Report. Sandy Hopkins commented the Recreation Board has been in
contact with the YMCA and they are willing to come in to the Towship and do a
four week summer camp at Indiantrail Park. They run the entire program for the
Township. They only thing the Township needs to do it help get the word out.
Mike Jones questioned if it was only going to be open to residents. Sandy
Hopkins commented it is open to anyone. There is a reduced rate for Township
residents.
Cindy Miller made a motion to authorize the Recreation Board to move forward
with the programming through the YMCA and that the fees for the park facilities
be waived. Mike Jones seconded the motion. Paul Nikisher questioned what the
program was and when it was. Sandy Hopkins commented it is a child’s day
camp, ages 5 to 12, from July 22 to August 16. People can sign up for any one or
all of the weeks. The fee is $65 and there is also financial aid available through
the YMCA. They do need a minimum of 15 children per week. Mike Jones
questioned if they are renting the park or is the fee being waived. Sandy Hopkins
commented she would request the park be given to them without charge since
they are providing the service to the Township and Community. They are
providing all the counselors and they have all the required clearances for working
with children. All voted aye Motion carried.
Sandy Hopkins commented the YMCA also runs adult programs such as senior
classes, yoga and Zumba. They would be able to do these programs within the
Municipal Building. Right now, they are just working on the summer camp, and
if it goes well, they will move onto the adult programs.
Sandy Hopkins reported that the Recreation Board has been discussing the
vandalism that has been taking place within the parks. It is their recommendation
that the bathrooms be closed overnight when the parks are closed. They were
Supervisor Minutes
June 25, 2019
Page 26
wondering if it would be possible to have the Police Officer who is on duty go to
the parks after they closed and lock up the bathrooms to try to limit the amount of
vandalism that is taking place. The Maintenance Department could open them in
the morning. The Board agreed that the Police should lock the parks when they
are closed.
C. Zoning Report. Liz Gehman commented she will have the property maintenance
code added to the next meeting agenda.
Attorney Backenstoe commented the ordinance increasing the size of the Zoning
Hearing Board has been advertised for adoption at the second meeting in July.
Jerry Pritchard questioned if anyone went out and looked at the fence and bushes
on Church Road? Keith Hantz commented he travels on the road and from what
he can see, it doesn’t seem to be that big of a problem. Alice Rehrig commented
Frank Zamadics recommendation was that the brush be kept trimmed to two feet
or less so that someone in a car can see over it. Paul Nikisher commented he goes
that way and he would also have to agree that it doesn’t look that bad. Liz
Gehman commented this is not a new condition. The fence and plants have been
there for many years. The concern came about when the additional traffic started
traveling on the road because of the detours.
D. Manager’s Report. Alice Rehrig commented she contacted Lisa Meyers from
Boyer and Ritter regarding the Risk Assessment Audit. The only date she would
be available to meet with the Board would be July 23 at 6:00 p.m. The Board
agreed to meet on the 23rd at 6:00 p.m.
Awhile ago, the Township received a grant from Northampton County to conduct
an accessibility study on our facilities. This grant was received as a result of a
requests for funding for the Comp Plan. While speaking with them on a different
matter, the County had recommended Lehigh Valley CILL to do the evaluation.
The cost estimate they provided was $14,500, roughly $3,000 per facility. The
grant is only for $10,000. The purpose of the grant would be to do an evaluation
of the facilities to see what type of changes would be needed to be compliant,
should the Township ever want or need to upgrade their facilities. Certain
Recreation Grants also look at accessibility for park improvements. Alice Rehrig
is also in the processes of obtaining additional estimates. Cindy Miller
commented there is supposed to be a recreation component to the comp plan,
wouldn’t they also be looking at accessibility. Couldn’t that count toward the
grant? Mike Jones questioned if we could just pick a park and do the study.
Supervisor Minutes
June 25, 2019
Page 27
Alice Rehrig commented we could limit it to two or three facilities as well. She
will check the County to see if this can be incorporated into the Comprehensive
Plan in addition to obtaining additional estimates.
One of the potential bidders on the Comprehensive Plan called to question if
consideration would be given to waiving the requirement for liability insurance on
this project. They claim that it is difficult and expenses to carry the insurance.
Cindy Miller commented we wouldn’t want a firm that is not carrying profession
liability insurance. Mike Jones commented he would also agree. Cindy Miller
commented if there is a problem, you wouldn’t be able to go back to them. The
Board agreed that the liability insurance would be necessary.
A request was received from Dean and Roseann Yelles on Magnolia Drive
indicating they would like to be included in the Ag Security Area. Alice Rehrig
will be preparing the resolution for hem to sign and have notarized. Once she
receives it back from them, she will place this on the agenda for adoption.
Several months ago, Alice Rehrig met with a company called ScanTek regarding
document imaging of Township files. Rather than purchasing a program and
hardware, they would provide a scanning service where they would scan our files
into a searchable database. There would not be any additional hardware or
software that would need to be purchased. Cindy Miller questioned where the
data would be housed. Alice Rehrig commented the company keeps a copy in
their files as a second copy, but we would have a second drive that could be
attached to either a computer or loaded into the server. Cindy Miller questioned if
this was discussed with the Technology Company. Alice Rehrig commented that
she didn’t discuss this with them yet because she wanted to get direction from the
Board if they wanted to go the service route of if they wanted to purchase the
equipment and the laser fische software so the scanning could be done by the
Township. The downside to that is that the scanning of the documents becomes
labor intensive for the Township and will take longer to complete. The Scan Tek
program can be converted to laser fische in the future if the Township wanted to
be able to do the scanning. One benefit to the scanning service is that they have
the ability to scan the plan sheets. Based on the amount that was budgeted, we
would be able to have the Zoning Hearing, property files and most of the
subdivision files scanned. Using the service would be the most expedient way to
get the records digitalized. The Board felt it would be best to go with the
scanning service as long as it is compatible with our computer system. Alice
Rehrig will provide the estimate from ScanTek to the Board and check with the
Technology Company to see if there are any concerns with the system.
Supervisor Minutes
June 25, 2019
Page 28
Alice Rehrig questioned how the Board wanted to handle the two additional
vacancies on the Zoning Hearing Board. Did they want to advertise it again or
just contact the two individuals who had previously applied. The Board agreed
the two individuals should be contacted, but the vacancy should also be
advertised.
Cindy Miller commented she would like to have the Planners look at the bids for
the Comprehensive Plan and make a recommendation to the Board since they are
the ones that requested it. Alice Rehrig commented that is one of the reasons she
has the bids due on the 1st so that there would be enough time to get them to the
Planning Commission and the Supervisors before the meetings.
Keith Hantz questioned if the Zoning Hearing Board was made aware that the
Board of Supervisors were looking to increase the size of the Zoning Hearing
Board. Liz Gehman commented they had seen the advertisement. Keith Hantz
commented he thinks it would be a good idea to send the Zoning Hearing Board a
courtesy notice to let them know this is taking place.
Keith Hantz questioned if the Board would consider moving the Department
Reports to an earlier position on the agenda. The Board agreed they could be
moved toward the beginning of the meeting, after the approval of the bills.
1. May Financial Reports. This item will be added to the July 9 meeting
because of the length of this meeting.
E. Solicitor’s Report. Attorney Backenstoe did not have anything specific to report
other than he changed the tree ordinance into a Lehigh Township Ordinance. This
ordinance was created to address virtually every situation that can occur with trees
located in and out of the right of way that can cause a public nuisance. If there is
a situation causing a public nuisance, a representative from the Township, such as
the Zoning Office, Police Chief, or Public Works Director would generate a report
outlining the situation, and then the property owner would be notified and if they
do not remedy the situation, then the Township could remove it at the property
owner’s expense. Paul Nikisher questioned what would happen if the tree was too
large for the Road Crew to handle. Attorney Backenstoe commented the
Township would contract with a tree service.
XIII. PUBLIC COMMENT. Jerry Pritchard wanted to thank Attorney Backenstoe for adding
the additional items to the conditional approval for the Seminary Property.
Supervisor Minutes
June 25, 2019
Page 29
Paul Nikisher questioned who was going to be doing the roof on the garage at
Indiantrail Park. The Board commented it was going to be the Public Works
Crew. Paul Nikisher commented it may be worth looking at asking a local
roofing contractor may be willing to donate the labor for a plaque.
Jerry Pritchard questioned if the Building was the Township’s building or the Fire
Company’s building. Darryl Snover commented it is on the Township’s property,
our building. Jerry Pritchard commented he attended the Recreation Meeting and
the YMCA was going to be needing to store items at the park for their program.
Wouldn’t it be nice to get the roof done before the programs start? A roofing
contractor can come in and get the job done quickly.
Ed Ziegler commented the roof on the Bodish building has been leaking for some
time. There could be areas where the floor may be weak. Before anyone goes
into the building, they should sign a release of liability with the Township.
IX EXECUTIVE SESSION. The Board went into Executive Session to discuss a Collective
Bargaining Agreement. No action was required.
X. ADJOURN. Keith Hantz made a motion to adjourn. Mike Jones seconded the motion.
All voted aye. Motion carried.