kathleen ratcliffe bc2/linac installation [email protected] april 16,...
TRANSCRIPT
Kathleen Ratcliffe
BC2/Linac Installation Coordination [email protected]
April 16, 20071
BC2 / Linac Installation CoordinationKathleen Ratcliffe
Kathleen Ratcliffe
BC2/Linac Installation Coordination [email protected]
April 16, 20072
Agenda
BC2 / Linac Installation CoordinationObjectives
Overall Schedule
Documentation and Release
Issues and Concerns
Close Out / Action Items
Kathleen Ratcliffe
BC2/Linac Installation Coordination [email protected]
April 16, 20073
Responsibilities
Mike Saleski / Safety SystemsChan / Linac Project ManagementRatcliffe / Installation Manager
Greg Diaz (MFD) / Field Installation R.F. Boyce / BC2 Area Design and IntegrationPhil Cutino / L3 Design and Integration / Linac Water UpgradesLori Shewchuk / LCLS CFPonciano Rodriguez / Cable InstallationBob Fuller / Controls Checkout
Kathleen Ratcliffe
BC2/Linac Installation Coordination [email protected]
April 16, 20074
Installation Objectives
Install, Check out, and Control all components and systems from BC2 thru L3
Beamline components represented by Emma’s current MAD Deck
All other that is necessary for safe and reliable commissioning
Water, Vacuum, AC Power, Air, Purge Gas, RF Systems
Safety SystemsRadiation Shielding, BCS, MPS, and PPS
Kathleen Ratcliffe
BC2/Linac Installation Coordination [email protected]
April 16, 20075
Overall Schedule
P3 consistent with AD Downtime ScheduleStart Date 9/4/07End Date 12/3/07
Schedule Considerations:Hardware availabilityDavis Bacon / Cable PullingPPS Certification
Linac/Damping Rings/E+/CIC/LCLSI/BSYEstimated 11/5/07 thru 11/9/07 day shift andEstimated 11/12/07 thru 11/16/07 day shift
Rolling Power OutagesGeneral Laboratory Resources
Kathleen Ratcliffe
BC2/Linac Installation Coordination [email protected]
April 16, 20076
Special Conditions
Limited 2 Shift Operations
Aggressive Schedule for BC2 area de-installation
No allowance for schedule drift
Temporary lighting during rolling power outages
Equipment needs to move from sector 19 down to sectors 24 thru 29
Kathleen Ratcliffe
BC2/Linac Installation Coordination [email protected]
April 16, 20077
LCLS AD Downtime Schedule
Kathleen Ratcliffe
BC2/Linac Installation Coordination [email protected]
April 16, 20078
Cable Installation Planning
Kathleen Ratcliffe
BC2/Linac Installation Coordination [email protected]
April 16, 200710
BOM Installation
Kathleen Ratcliffe
BC2/Linac Installation Coordination [email protected]
April 16, 200711
Documentation Status
BC2 StatusDesign and Integration Engineer – Richard F. BoyceThree designers currently assigned to this areaDesign is 80% completeCompleted PDR on 12/17/06 (committee: P. Emma, G. Bowden, S. DeBarger and E. Doyle)FDR- end of April 2007
18 April 2007, BC2 Support Tables Installation2 May 2007, BC2 Vacuum Chamber Installation9 May 2007, BC2 Vacuum Supports Installation23 May 2007, BC2 Magnet and Support Install
Drift chambers in fabricationSupport drawings in check cycleEverson Tesla is fabricating bend magnetsSupport stands released to fabrication
Kathleen Ratcliffe
BC2/Linac Installation Coordination [email protected]
April 16, 200713
Documentation Status
BC2 installation drawings
Kathleen Ratcliffe
BC2/Linac Installation Coordination [email protected]
April 16, 200714
Documentation Status
L3 StatusIntegration Engineers – Phil Cutino and Richard F. BoyceOne designer is currently working on BC2 and two designers on L3 designCompleted PDR on 12/19/2006FDR in MayCompleted preliminary installation drawingsCompleted all waveguide designs for Linac and request have been submitted to MFD (except long waveguides which were made in 2006)
Kathleen Ratcliffe
BC2/Linac Installation Coordination [email protected]
April 16, 200715
Documentation Status
Typical installation drawings (sector 25-2)
Kathleen Ratcliffe
BC2/Linac Installation Coordination [email protected]
April 16, 200716
Product Assurance & Safety
Following safety documents are required prior to installation or operation
Safety Overview ApprovalWork authorization approval from LCLS and ADPenetration permitsEarthquake approvalsBuilding inspection approvalsElectric safety approvalsRP approvalsNon-ionizing approvals
Kathleen Ratcliffe
BC2/Linac Installation Coordination [email protected]
April 16, 200717
Safety Overview Committee Approval
Kathleen Ratcliffe
BC2/Linac Installation Coordination [email protected]
April 16, 200718
Issues and Concerns
2007 Downtime Installation2007 downtime 10 weeks vs. 2006 downtime 17 weeksReconfiguring 13 Linac girders vs. 3 in 2006More waveguides in Linac housing to be installedLonger distance for equipment hatch to areas of installationDavis Bacon Linac installations maybe competing with LTU installationsWater work less than 2006 installationHardware and cable installations co-habitat same areaNot much time for control to check out hardware