implementing renewable energy at water utilities

54
© 2012 Water Research Foundation. ALL RIGHTS RESER © 2012 Water Research Foundation. ALL RIGHTS RESERVED. No part of this presentation may be copied, reproduced, or otherwise utilized with

Upload: priscilla-shaw

Post on 01-Jan-2016

36 views

Category:

Documents


1 download

DESCRIPTION

Implementing Renewable Energy at Water Utilities. Project 4424 November 8, 2012. Outline. Why renewable energy? Renewable energy technologies Implementation considerations Procurement options Funding opportunities - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.© 2012 Water Research Foundation. ALL RIGHTS RESERVED. No part of this presentation may be copied, reproduced, or otherwise utilized without permission.

Page 2: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Implementing Renewable Energy at

Water UtilitiesProject 4424

November 8, 2012

Page 3: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Outline

• Why renewable energy? • Renewable energy technologies• Implementation considerations• Procurement options• Funding opportunities• Case studies - opportunities,

challenges, and barriers to project implementation

Page 4: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Why renewable energy?

• Economic Benefits—Offset purchased power—Possible green credits, REC, carbon

credits

• Environmental Benefits—Reduce carbon footprint—Mitigate effects of the water-energy

nexus

• Social Benefits—Very positive public perception

Page 5: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Projected Electricity Price

Page 6: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Cost To Treat Water Is Increasing

Cost of energy is increasing

Water demands are increasing

Energy to treat water is increasing

Page 7: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Renewable Energy Outlook

Page 8: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Environmental Benefits• 1000 KWH of purchased electric utility

power releases an average of 0.61 tons of CO2 equivalent.

• Renewable reduces grid losses. US average grid losses = 6.5%

• 1000KWH generated locally actually saves 1065KWH of electric utility generation

(Source: USEPA eGRID2012)

Page 9: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Water-Energy Nexus

• 1kWh of purchased electric energy requires ~25 gallons of fresh water to produce

• Water treatment and distribution average energy usage: 1250 - 2500 kWh/MG

• For every million gallons treated, an additional 31,250 to 62,500 gallons of water resources are consumed.

Page 10: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Renewable Energy Technologies

• Solar• Wind• Micro-hydro• Geothermal• Tidal • Biomass

Page 11: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Solar• Advantages:

—Widely available—Mature technology—Low maintenance costs—Prices are decreasing

• Disadvantages: —Intermittent power generation—Power output depends on solar irradiance—Large footprint

Page 12: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Types of Solar Systems

• Photovoltaic Systems – Converts sun light energy into electric energy

• Thermal Systems – Recovers thermal energy from sun light

Page 13: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Page 14: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Wind

• Advantages: —Small site footprint—Mature technology

• Disadvantages: —Low persistent noise

depending on design—Aesthetic concerns—Intermittent nature—Sufficient wind not available in

many areas

Page 15: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Page 16: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Micro-hydro• Advantages:

—Low maintenance costs

—Mature technology—Installation in a

pipeline or outfall• Disadvantages:

—Power output is dependent on elevation changes

—Limited availability in small sizes

Page 17: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Types of Micro-hydro Systems

• Hydroturbines• Pumps as Turbines

Source: VATech Hydro

Page 18: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Tidal

• Advantages: —Predictable—High energy density

• Disadvantages:—High capital investment—Location limited to tidal areas—Effect on marine life—Not a mature technology

Image Source: www.reuk.co.uk

Page 19: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Geothermal

• Advantages: —Geothermal HVAC is a

mature technology—Predictable

• Disadvantages:—High capital investment—Potentially high

maintenance costsImage Source: www.geothermalhvacsystems.com

Page 20: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Biomass• Advantages:

—High energy generation potential

—Large variety of feedstock

• Disadvantages:  —Air Emissions—Controversial NIMBY (not in my

backyard)—High capital investment—Potential air permitting issues

Page 21: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

LEED

• Constructing a LEED building is also a means of reducing energy consumption—Building thermal efficiency—HVAC and lighting efficiency—“Green” building materials

Page 22: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Implementation Considerations

• Space constraints• Cost of purchased energy• Utilization of renewable energy

considerations• Coordination with the electric utility• Community impacts• Funding opportunities• Project delivery considerations

Page 23: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Utilization of Renewable Energy

WATER TREATMENT FACILITY

UTILITY METER

UTILITY SERVICE

RENEWABLE ENERGY SYSTEM

Offset Purchased Utility Power

Source

OR

Sell Energy Directly To Electric Utility

Page 24: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Utilization of Renewable Energy

• Offsetting purchased power benefit depends on the purchased power rate—Time of use energy and demand

charges—Demand ratcheting—Minimum billing demand limits

• ALL UTILITY RATES ARE DIFFERENT!

Page 25: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Renewable energy systems may not always offset demand charges

1 3 5 7 9 11 13 15 17 19 21 23 25 27 290

500

1000

1500

2000

2500

3000

3500

4000

4500

5000

Billing Period Demand Profile

Plant De-mand kW

De

ma

nd

(k

W)

Period of low or no renewable energy generation during peak period (rain event, downtime, etc.)

No offset during peak period

Page 26: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Selling Energy Directly to Electric Utility

• Generated energy can be sold to electric utility

• Many electric utilities are required to meet Renewable Energy Portfolio Standards

• Energy generated from renewable sources may be “valuable” to some electric utilities

Page 27: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Renewable Portfolio Standards and Goals

Source:dsireusa.org

Page 28: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Electric Utility Coordination Considerations

• Parallel operation protection requirements—System modification can be expensive

• Billing rate contract impacts—“Grandfathered” rates

Page 29: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Community Impacts

• View shed impacts—Solar and wind systems

• Noise—Biomass and wind systems

• Air emissions—Biomass systems

Page 30: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Procurement Options

• Direct ownership• System owner finances design,

construction, and operation and maintenance

• Third party project delivery• A third party finances design,

construction, and / or operation and maintenance through a power purchase agreement (PPA)

Page 31: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Direct Ownership

• Advantages• Control power output• Can be built using traditional design-

build or design-bid-build practices

• Disadvantages• Requires upfront capital• Direct negotiation with electric utility • Municipalities generally do not qualify

for government tax credits

Page 32: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Third Party Project Delivery

• Advantages• No or reduced upfront capital costs• Possibly no maintenance costs• Reduced risk

• Disadvantages• Lower economic return• Long term price changes• May have protracted negotiation• PPA’s not available in all states

Page 33: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Power Purchase Agreements

Page 34: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Third Party Agreements Vary

1. Locate renewable energy on-site, and buy power through a PPA

2. Use a PPA to buy renewable energy generated off-site

3. Generate revenue from leasing land — Locate renewable energy on-site, but

power is sent to the electric utility grid

Page 35: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Funding Resources

• Incentives are constantly changing• Appendix to the report lists current

federal and state incentives • EPA, Energy.gov, Grants.gov• DSIRE – Database of State Incentives for

Renewable Energy • State and local energy offices

Page 36: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Funding Opportunities

• Government and non-profit grants—ARRA (2009) funds have been committed

• Bonds and Loans• Tax Rebates and Tax Credits• Tax Rebates: Increase tax refund• Tax Credits: Reduce the tax liability

• Federal Investment Tax Credit until 2016• Not available to municipal governments, but

would be advantageous to non-municipal entities

Page 37: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Project Steps

1. Review plant energy use, the available technologies and determine how the energy will be used

2. Evaluate the capital investment, financing options, and incentives

3. Identify the project barriers and risks4. Identify public impacts 5. Determine the project delivery

method

Page 38: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Project Challenges

• Upgrading existing structures• Roofs, walls, valve vaults, etc.

• Electrical upgrades• Renewable energy equipment

compatibility with electric utility requirements

• Coordination with electric utility • Paralleling

• Community Feedback

Page 39: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Case Studies1 City of Portsmouth NH LEED Silver Building2 City of Raleigh NC Solar PV3 Dania Beach FL LEED Gold Building4 East Bay MUD – Sobrante WTP CA Solar PV5 East Bay MUD – Walnut Creek WTP CA Solar PV6 Inland Empire CA Wind7 Metropolitan Water District CA Solar PV8 Portland Water Bureau OR Solar PV9 Portland Water Bureau OR Micro-hydro

10 Southern Nevada Water Authority NV Solar PV11 Southern Nevada Water Authority NV Solar Thermal12 Sydney Water, NSW AUS Micro-hydro

Page 40: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Case Study Sections

Part 2: Renewable Energy DataTechnology Year InstalledRated Power Output, kW Annual Energy Generated, kWhCapital Cost, USD O&M Cost, USDSimple Rate of Return Average Utility Energy Cost, $/kWhFinancing Energy Savings, USD

Part 3: Project Implementation

Project Drivers

Project Risks

Project Barriers

Type of Contract

Special Permits

Mandates or incentives

Community Acceptance

Part 1: Treatment Plant Information Raw Water Source Population Served

Design and Average Flow

Annual Electricity Consumption

Annual Energy Consumption

Utility Governance Structure

Page 41: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Case Studies

• Solar – Sothern Nevada Water Authority, NV

• Wind – Inland Empire Utility Agency, CA

• Micro-hydro – Portland Water Bureau, OR

Page 42: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

SolarSouthern Nevada Water AuthorityAlfred Merritt Smith Water Treatment Facility

About the project• 130 kW solar PV system• Demonstration project with a local university• Most power comes from a gas-fired

combined cycle power plant and smaller hydropower facilities

• SNWA wrote the RFP, completed the preliminary design, and contracted the final design and permits to a consulting engineering firm

Page 43: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

SolarSouthern Nevada Water AuthorityAlfred Merritt Smith Water Treatment Facility

Project Drivers• Project was an opportunity to

become familiar with the technology

Project Risks• Approval by the purveying members that control the budget

Type of Contract• Design-Build Contract

Community Acceptance• The facility is in the Lake Mead National Recreation Area,

however, there no concerns about the solar installation.

Page 44: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

SolarSouthern Nevada Water AuthorityAlfred Merritt Smith Water Treatment Facility

Renewable Energy Data

Technology Solar PV Year Installed 2007

Rated Power Output, kW 130 Annual Energy Generated, kWh 240,000

Capital Cost, USD $1.4 Million O&M Cost, USD NA

Simple Rate of Return 30+ years Average Utility Energy Cost, $/kWh 0.06

Financing Government Energy Savings, USD /yr $14,400

www.snwa.com/env/sustain_solar.html

Page 45: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

WindInland Empire Utility AgencyRancho Cucamonga, CA

About the project: • Average flow of 5 MGD• Provides recycled water to the surrounding

community• Includes primary, secondary, and tertiary

treatment processes for producing recycled water in accordance with California Title 22

• To offset high-carbon emitting operations, IEUA set a goal to operate off the grid by 2020

• Wind power was selected as a viable technology due to its low cost per kilowatt hour and reliability with minimal maintenance

• Additional renewable energy projects by IEUA include solar systems and fuel cells

Page 46: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

WindInland Empire Utility AgencyRancho Cucamonga, CA

Project Drivers• Cost containment, operational reliability,

electricity rate stabilization, and carbon footprint reduction

Project Barriers• Approval from Federal Aviation Administration

Type of Contract• 20 year Power Purchase Agreement with Foundation Wind

Power

Community Acceptance• Positive

Page 47: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

WindInland Empire Utility AgencyRancho Cucamonga, CA

Renewable Energy DataTechnology WindRated Power Output, kW 1,000Capital Cost, USD None

Simple Rate of Return NA

Financing Third Party

Year Installed 2011

Annual Energy Generated, kWh 1,500,000

O&M Cost, USD None

Average Utility Energy Cost, $/kWh 0.115

Energy Savings, USD/yr $100,000+

www.ieua.org

Page 48: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Micro-hydroPortland Water BureauVernon Tank, Portland, OR

About the project • Installed a grid tied micro-hydro turbine rather than replace a 16” PRV• Designed in-house for a flow rate 6.4 – 8.25 cfs through the turbine • The pipeline is 24” reduced to 10” at the turbine

Challenges• Replacement of deteriorated piping and construction of a new valve vault

Financing• $55,000 grant from American Recovery and Reinvestment Act of 2009• $50,000 grant from Oregon Energy Trust upon completion of the project • Energy Trust also paid consultant fees up front for FERC and Oregon

Water Right permitting• Portland Water Bureau also had approximately $35,000 earmarked from

State of Oregon Business Energy Tax Credits (BETC) 

Page 49: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Micro-hydroPortland Water BureauVernon Tank, Portland, OR

Project Drivers• Portland Water Bureau seeking to meet the City’s renewable energy goals

Project Risks• Installing a new generator on an existing 80 year old pipe and providing

adequate thrust restraint for the equipment

Project Barriers• Cost of structures to house the energy generation equipment, and the

cost of upgrading the power supply to meet the generation requirements

Type of Contract• Power Purchase Agreement (PPA)

Community Acceptance• The project is in an underground vault and not seen by the community

Page 50: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Micro-hydroPortland Water BureauVernon Tank, Portland, OR

Renewable Energy Data

Technology Mirco-hydro Year Installed 2012

Rated Power Output, kW 30 Annual Energy Generated, kWh 150,000

Capital Cost, USD 155,640 O&M Cost, USD 1500

Simple Rate of Return 15 years Average Utility Energy Cost, $/kWh 0.07

Financing Third Party Energy Savings, USD/yr $10,500

www.portlandoregon.gov/water/

Page 51: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Summary

• Electricity costs are expected to increase• Installing renewable energy can:

—Reduce electricity costs—Generate revenue for your utility—Reduce carbon footprint

• A variety of funding sources and contract arrangements exist

• Case studies demonstrate that there are a varieties of way to successfully implement projects

Page 52: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Technical Resources

• National Renewable Energy Laboratory

• Department of Energy • Environmental Protection Agency • EPA-NREL Solar Decision Tree

Page 53: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Acknowledgements• Thank you to Linda Reekie and the

Water Research Foundation • Fred Bloetscher (Florida Atlantic University)

• Bill Becker, Ben Stanford (Hazen and Sawyer)

• Thank you to all of the utilities which participated in this project.

Page 54: Implementing Renewable Energy at Water Utilities

© 2012 Water Research Foundation. ALL RIGHTS RESERVED.

Questions