Page 1: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas

Cavity and Cryomodule R&D

Shekhar MishraILC Program

Fermilab

Talk presented at DOE Annual Program Review 

Breakout Sessions   –   Wednesday, May 17

Page 2: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas ILC Cavity and Cryomodule R&D Goals

• ILC R&D at Fermilab is focused to address the high priority ILC design and technical issues as recommended by ILC-TRC and recently by ILC-GDE R&D Board.

• The main thrust of the ILC Cavity and Cryomodule R&D is to establish technical capabilities in the Superconducting Radio Frequency (SRF) Cavity and Cryomodule technology. The main goals are

– Cavity technology development in the US to routinely achieve > 35 MV/m and Q ~0.5-1e10,

– ILC Cryomodule design, fabrication (cost reduction)

– Fully tested basic building blocks of the Main Linac (Evaluate the integration, reliabilities issues and value engineering).

– LLRF, Instrumentation and Controls development for Main Linac

• Development of U.S. laboratories and industrial infrastructure for the fabrication, processing and testing of high performance SRF cavities, Coupler, Tuner, HOM and Cryomodule.

Page 3: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas Plans for 35 MV/m• Cavity Fabrication, Preparation, Surface Processing, Clean Surface and Clean

environment is the key to achieving a high gradient in the ILC cavities.

• Fermilab is leading the US effort with collaborating laboratories.

– Niobium is being scanned at Fermilab. (Need larger inventory. There are variation from batch to batch, vendor to vendor etc.)

– Cavity is being fabricated at industry under the supervision of Fermilab and Cornell. Jlab will join this soon.

– Cavity is being processed (BCP and EP) and vertical tested at Cornell, Jlab and will be processed at ANL/FNAL

• The processing infrastructure needs more focused effort. Experiences from DESY and KEK suggest that we build this facility at where cavity is dressed, horizontally tested and put in a string.

• We are in process of having this facility at Fermilab by 07.

• Fermilab is fabricating 8 (FY05), 16(FY06), 24-36 (FY07) ILC cavities. More could be needed to

• These cavities will be systematically processed and testing. We would systematically collect data during the fabrication, processing and testing.

• These data would be analyzed for co-relations to understand the process.

Page 4: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas ILC Cavity: R&D

• Material R&D: Fine, Large, Single Crystal

• Fabrication– A number of minor modifications and improvements could

be implemented without impact to the basic cavity design.

• Cavity Preparation

• Buffer Chemical Processing

• Cavity Processing R&D– Electro-polishing (EP) System– High Pressure Rinsing (HPR)– Clean Assembly Procedure

Page 5: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas Cavity Fabrication

• Industrial production of the cavity by Fermilab (ACCEL, AES)

• 8 TESLA Design Cavities ordered• 10 ILC Baseline Design Cavities in FY06

• Cavity fabrication at Jlab• 2 ILC Baseline design and Type-IV• 2 Low Loss Cavity• Several single cell for Process and Material R&D • Material R&D (Fine Grain, Large Grain, Single Crystal)

• Cavity fabrication at Cornell• Re-Entrant Cavities (70 mm)• Re-Entrant Cavities (60 mm)• Several single cell for Process R&D

• Cavity fabrication at KEK (US-Japan)• Cavities of TESLA, Low Loss and ICHIRO design

Page 6: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas

Cavity Fabrication, Processing and Testing Road Map

Cavity FabricationBy Industry

Cavity Dressing &Horizontal Testing

@ Fermilab

BCP and EPProcessing @ Cornell

BCP and EPProcessing

@ Jlab

BCP and EPProcessing @ ANL/FNAL

Vertical Testing @ Cornell

Vertical Testing @ Jlab

Vertical Testing @ FNAL

Exists

Developing

Page 7: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas Cavity Measurements

• RF measurement of the ACCEL Cavities at Fermilab.

Accelerating field amplitude in cavity axes.

0

0.2

0.4

0.6

0.8

1

1.2

1.4

1.6

0 200 400 600 800 1000 1200Z, mm

Am

plit

ud

e

ACCEL6 ACCEL7 ACCEL9

Page 8: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas ILC Cavity Material Grain size R&D at Jlab

• Study of Single Cell large grain niobium from CBMM, Heraeus and Ningxia

• 5 single cell cavities each from these vendors will be fabricated for statistics.

• Two 9-cell cavities are being fabricated for Fermilab using CBMM ingot.

Large Grain TESLA Cavity Shape SC, Chinese Nb

1.00E+09

1.00E+10

1.00E+11

0 5 10 15 20 25 30 35

Eacc [MV/m]

Q0

Test#1/2/3/4

Q - drop

Quench 29 MV/m

Quench @ 33.3 MV/m

Ningxia

Large Grain TESLA Cavity Shape SC, WC_Heraeus Nb

1.00E+09

1.00E+10

1.00E+11

0 5 10 15 20 25 30 35

Eacc [MV/m]

Q0

Test#2/4

Quench at 34.4 MV/m

HeraeusLarge Grain TESLA Cavity Shape SC#2, Ingot"D"

1.00E+09

1.00E+10

1.00E+11

0 5 10 15 20 25 30 35

Eacc [MV/m]

Q0

T=1.99K Series2

Test #1/2Test #1

Quench at 31.2 MV/m

Page 9: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas

50 MV/m in Single Cells !Lower Surface Magnetic Field & Lower Losses

Re-entrant

CornellKEK

Low Loss

Jlab

KEK

Tesla Shape

Need Multi-cells Next

New Shapes Breakthrough

Page 10: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas

Fabricated at Cornell

Proof of Principle Results: Eacc = 47 - 52 MV/m

/Ichiro

Page 11: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas

60 mm aperture similar to LL shape -> 16% lower Hpk/Eacc

New Reentrant Cavity Shape

Work done in Collaboration with KEK

Page 12: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas ILC Cavity Processing• We are using infrastructures at the collaborating laboratories to develop the

processing capabilities and parameters in USA to achieve 25 MV/m with BCP and 35 MV/m with EP.

• These facilities are also being used to train people.

• Cornell:– BCP and HPR – Vertical EP

• Jlab– EP

• Fermilab and ANL (New Facility)– BCP – EP

• We are also sending Fermilab staff to DESY for participation and training in surface processing, vertical and Horizontal testing.

Page 13: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas Check Reproducibility of HPR

Cornell Re-entrant Cavity

3.9.9

3.9.10

Work done in Collaboration with KEK

Page 14: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas

BCP Complete

First ACCEL ILC Cavity at Cornell

HPR Complete

3.9.3.1

Page 15: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas Vertical Test of ACCEL Cavity

Fermilab is sending engineering staff and technician to participate in the BCP and vertical testing at Cornell.

ACCEL8_21apr06

1.000E+09

1.000E+10

1.000E+11

0 5 10 15 20

Eacc (MV/M)

Q

QuenchNo Radiation

60 um BCP (nominal) + 50 um at ACCEL

Low Field: Q >1010, Eacc = 17 MV/m, (Quench)

Q

Eacc (Mv/m)

Page 16: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas Goals for EP Development at JlabEstablish EP processing for ILC 9-cell cavities at Jlab

• Commissioning EP cabinet with Spare DESY 9-cell cavity

• Perform HPR, assembly and testing with S35 cavity to analyze procedure effectiveness and reproducibility

• Investigate standard process procedures to gain a better understanding of current issues (Sulfur precipitation, HF loss during use)– Identify and develop relevant process metrics and QA steps

• Establish and document procedures– Aim is uniform reproducible etching with clean surfaces after rinsing

• Process, test, qualify and prep cavities for FNAL string assembly

Page 17: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas

HPR and Assembly

Alignment Cage

Electropolish Development for ILC

Jlab EP Cabinet

3.9.3.2

Page 18: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas

EP System Alignment Frame and Cathode with ILC Cavity 3.9.3.2

Page 19: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas

ILC Surface Processing Facility Development at ANL/FNAL

• The Joint ANL/FNAL Superconducting Surface Processing Facility (SCSPF), located at Argonne National Laboratory, is a major chemical processing facility capable of electro-polishing and buffered chemical polishing a large quantity and variety of superconducting structures.

• This BCP part of the facility is ready and going through the safety approval. It is expected to be operational end of 06.

• An initial plans has been developed for an EP facility to be build (FY06-07) at ANL/Fermilab Surface Processing Facility at ANL.

• This facility should include the knowledge of EP from the ILC Collaboration.

Page 20: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas Cryomodule Design and Fabrication

• In FY05 Fermilab started on converting the DESY/INFN design of the ILC cryomodule (Type-III+).

• We have formed an ILC Cryomodule working group that is working towards a design of an ILC cryomodule. This design will evolve.

• The Goal is to design an improved ILC cryomodule (Type-IV) and build one at Fermilab by FY08.

High Power testing of the cavities and the fabrication of 1st ILC cryomodule with new design 2008.

Page 21: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas

Cryomodule Fabrication Plans for an RF Unit test at ILCTA

Cryomodule 1 Cryomodule 2Cryomodule 3

DressedCavity Provided

By DESY

Cold MassBy DESY/INFN

CryomoduleAssembled at

Fermilab

March 07

Standard LengthCavity Purchased

By Fermilab

BCP & VTAt Cornell

EP & VTAt Jlab

Cold MassFrom ZanonBy Fermilab

Dressed and HTAt Fermilab

Dec 07 Mid 08

ILC LengthCavity Purchased

By Fermilab (AES/Jlab)

BCP & VTIn USA

EP & VTIn USA

Dressed New Design and HT

At Fermilab

Cold Mass Type-IVFrom US Company

By Fermilab

Page 22: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas

1st US Assembled Cryomodule: Fermilab, DESY and INFN

• DESY will send Fermilab eight 9-Cell 1.3 GHz dressed and horizontally tested cavities. – The present schedule for the delivery of these 8 cavities is around end

of 2006. DESY will attempt to advance this schedule.

• DESY and INFN have ordered two cold masses for Type-III cryomodules from Zanon. – DESY will send one of these cold masses to Fermilab for the 1st

cryomodule assembly at Fermilab. – It is expected that this cold mass will be available about Sept.-Oct.

2006.

• Some parts for the 1.3 GHz cryomodule are not provided by Zanon but rather by INFN. – It was agreed that INFN will send these associated parts to Fermilab

and provide parts needed for a 3rd cold mass.  – INFN-DESY will also send the assembly documentation to Fermilab.

• Fermilab will work to achieve the earliest possible delivery date for the DESY four cavity 3.9 GHz cryomodule. This is currently expected to be early in  2007.

Page 23: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas ILC Cryomodule Design Considerations

• Move quad package to middle of cryomodule to achieve better support and alignment.

• Shorten cavity-to-cavity interconnect and simplify for ease of fabrication and cost reduction. Possible superconducting joint.

• Overall improved packing factor.

• Minimize direct heat load to cavity through MC.

• Simplify the assembly procedure.

• MLI redesign to reduce hands-on labor costs.

• More robust design to survive shipping.

• Reliability of tuner motors in cold operation.

• Etc. (we’ve heard many suggestions)

Page 24: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas ILC Cryomodule: Conceptual Model

Page 25: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas

Increasediameter beyond X-FEL

Increasediameter beyond X-FEL

Review 2-phase pipe size and effect of slope

Change in Cryogenic Distribution

Page 26: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas

ILC Cavity Spacing, Dimensions with Blade Tuner

Blade Tuner

35068mm1036.2 mm

Active length = 1036.2 mm x 24 cavities = 24868.6 mm

Packing Factor = 24868.6 / 35068 = 0.71

Page 27: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas 1st Cryomodule Assembly Plans

• Cavity String Assembly Procedures & Fixtures Learning at DESY (February 20 –March 3)

– A draft traveler was written during this visit. It is currently being reviewed by Axel Matheisen for comments.

– Tooling & Fixturing used to assemble the cavity string were identified. Drawing were brought back to Fermilab.

– Assembly sketches, movies and took a lot of pictures and notes.

• Cryomodule #6 Assembly Procedures Learning at DESY (May-June 06)

• CAF Infrastructure ready & operational: May-June 06– MP9 Clean Room installation finished– Cold Mass and Vacuum Vessel Assembly Fixtures received at Fermilab.– Cavity String Assembly Fixtures are being fabricated to be installed

• Assemble 1st Cryomodule (4 months): Start date depends when we receive the kit from DESY

Page 28: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas

Cavity and Cryomodule Assembly Fixtures

Page 29: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas FY07 Plans: Cavities & Cryomodule

• The FY07 plan of the ART will be the continuation of the plan we are undertaking in FY07.

• Cavity Fabrication– ILC Design– New Shape (LL and RE)– Fine, Large and Single Crystal– R&D on material, fabrication etc– 3.9 GHz deflecting cavity design and fabrication

• Cavity Processing and Vertical Testing– BCP, EP and Vertical Testing at Cornell– BCP, EP and Vertical Testing at Jlab– BCP, EP and Vertical Testing at FNAL/ANL (New Facility)– R&D on surface treatment

• Cryomodule Design and Fabrication– Type III+ Fabrication– Type IV Design

• US Industrial involvement in Cavity and Cryomodule Design and Fabrication

• Enhanced University participation in ILC R&D

Page 30: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas Summary

• US-ILC Main Linac: Cavity and Cryomodule R&D program is established to address the key technology issues.– Cavity Gradient– ILC Cryomodule design and fabrication

• R&D is focused on the Baseline design of the cavity and cryomodule.

• We are also working on alternate design for Cavity and material.

• We are upgrading existing infrastructure at US laboratories to cost effectively advance the R&D program on a ambitious schedule.

• We are developing infrastructure at Fermilab for cavity processing and testing and fabrication of cryomodule.

• We are leading the ILC effort in the ILC Cryomodule design.

• We are working with US industry in fabrication.

• We are also working with US industry in ILC Cost Study.

Page 31: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas

Could lab really spend the Money Faster on ILC than its currently funded?

• Yes, Yes and Yes• Fermilab has qualified scientists and engineers who wants to

work on ILC.• We continue to defer investment that would be needed for more

focused R&D.– Cavity R&D: (This is the highest R&D priority for ILC-GDE)

• Niobium • More cavities fabrication at industry. We should fabricate enough to saturate

the pipeline at existing and upcoming processing facilities. • Electron Beam Welding• Surface Processing: We need a pre-production BCP, EP and HPR system at

Fermilab• Vendor development

– Cavity Tuning Device ( A copy of DESY Design)– Vertical testing temperature study– Cryomodule Testing– 10 MWatt Klystron– Cryogenic plant– Industrial fabrication

• US industries could fabricate an RF unit using laboratory infrastructure.

Page 32: ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May

ILCAmericas FTE in ILC R&D at Fermilab: FY06 and FY07