IBL Kick-off Meeting - Introduction G. Darbo – INFN / Genova IBL kick-off Meeting, 8 July 2009 o
IBL Project Introduction
IBL Kick-off Meeting Thoiry, July 8th
G. Darbo - INFN / Genova
Indico AGENDA page: • http://indico.cern.ch/conferenceDisplay.py?confId=56905
IBL Kick-off Meeting - Introduction G. Darbo – INFN / Genova IBL kick-off Meeting, 8 July 2009 2
Welcome This kick-off meeting aims to:
• Have together the IBL Management Board and the Institute Leaders
• Present the status of the design and of the resources that needs: human and money
• Have a feedback from Institutes how contribution could come: what are the wishes in the deliverables and task to cover
• See what in the project is over covered and what is not
• Define a baseline of the IBL construction MoU
This meeting is important for the IBL to converge and to become a real project
IBL Kick-off Meeting - Introduction G. Darbo – INFN / Genova IBL kick-off Meeting, 8 July 2009 3
IBL kick-off Meeting – Draft Agenda 9:00 – Introduction – G.Darbo (20 min)
• What is IBL project – first project in the upgrade phase I – deliver a 4th layer for the pixel detector – model of resources
• Scope of the meeting 9:30 – Technical Presentation of IBL project - H. Pernegger (30 min)
• Where exists a technical baseline • Where are open technical options and what are the planned steps for a convergence • Where technical solutions have not discussed or are very little developed • Manpower figure
10:15 Coffee Break 10:45 Project Cost – G. Darbo (20 min) 11:15 Round table – “Wishes and Interest of Institutes” – Chair C. Gößling 12:45 Lunch 14:15 Sharing of Work – “Interactive Session” G.Darbo, C. Gößling
• Fill online a table with work sharing – “the big picture” • Keep note of inputs from round table
16:45 Coffee Break 17:15 Memorandum of Understanding – M.Nordberg
• What should be inside – look at ATLAS construction MoU • How to map “the big picture” into the MoU
18:00 End of the meeting
IBL Kick-off Meeting - Introduction G. Darbo – INFN / Genova IBL kick-off Meeting, 8 July 2009 4
IBL Organization The IBL (Insertable B-Layer) is an ATLAS Upgrade project:
• It will deliver a fourth pixel layer, including a new beam-pipe, to the Inner Detector • When delivered, it will become a part of the Pixel Detector and of the Inner Detector
and the organization will be “absorbed” into the Pixel & ID The organization structure has:
• IBL MB: Management Board to execute the project • IBL IB: Institute Board, which starts today as an extension of the existing Pixel IB and
will be chaired by C, Goessling.
Module WG
IBL MB (Management Board)
Stave WG
I&I WG
Off-det WG
IBL IB (Institute Board)
Pixel Institutes
in IBL
New Institutes
in IBL
ATLAS UPO
ATLAS UPGRADE
IBL
IBL PL IBL TC
IBL Kick-off Meeting - Introduction G. Darbo – INFN / Genova IBL kick-off Meeting, 8 July 2009 5
Management Board (MB)
Module WG (2 coordinators)
• FE-I4 • Sensors • Bump-Bonding • Modules • Test & QC • Irradiation
Stave WG (1 Phys + 1 Eng.)
• Staves • Cooling Design & Stave Thermal Management • HDI • Internal Services • Loaded Stave • Test & QC
IBL Integr.-Install. (2 Eng.)
• Stave Integration • Global Sup. • Beam Pipe (BP) • Ext.services inst. • IBL+BP Installation • Cooling Plant • Test & QC
Off-detector (1 Phys + 1 E.Eng.)
• Power • DCS • ROD • Opto-link • Ext.serv.design/proc. • Test Beam • System Test
IBL Management Board Membership: • IBL PL + IBL TC • 2 coordinators from each WG • Plus “extra” members
Ad-interim membership IBL Project Leader: G. Darbo IBL Technical Coordinator: H. Pernegger “Module” WG (2 Physicists): F. Hügging & M. Garcia-Sciveres “Stave” WG (1 Phy. + 1 M.E.): O. Rohne + D. Giugni “IBL Assembly & Installation” WG (2 M.E. initially, a Phy. Later): N. Hartman + R. Vuillermet “Off-detector” WG (1 Phy. + 1 E.E.): T. Flick + S. Débieux “Extra” members: Ex officio: Upgrade Coordinator (N. Hessey), PO Chair (M. Nessi), Pixel PL (B. Di Girolamo), ID PL (P. Wells), Pixel Chair (C. Gößling) Offline “liaison” Pixel Off-line coordinator: A. Andreazza TDR editor (temporary): K. Einsweiler
IBL Kick-off Meeting - Introduction G. Darbo – INFN / Genova IBL kick-off Meeting, 8 July 2009 6
MB & WG Operation IBL organization is starting up: Management Board (IBL MB)
• Weekly meeting on Monday – closed meeting – issues tracking
The 4 Working groups (WG) cover the whole project: • WG1 – Module • WG2 – Stave • WG3 – Integration & Installation • WG4 – Off-detector
Mailing lists – open subscription to ATLAS active members • IBL General: [email protected] • WG1: [email protected] (alias [email protected]) • WG2: [email protected] (alias [email protected])
(it was the [email protected]) • WG3: [email protected] (alias [email protected]) • WG4: [email protected] (alias [email protected])
• To subscribe: https://e-groups.cern.ch/
IBL Kick-off Meeting - Introduction G. Darbo – INFN / Genova IBL kick-off Meeting, 8 July 2009 7
Collaborative Workspace https://espace.cern.ch/atlas-ibl/default.aspx
IBL Kick-off Meeting - Introduction G. Darbo – INFN / Genova IBL kick-off Meeting, 8 July 2009 8
IBL Cost Total cost 9.6 MCH:
• Use this cost to “shape the project” – revise when better understanding of the design (TDR)
• Funding Model: M&O-A, M&O-B, New project money • In discussion with the RRB scrutiny group the sharing in the 3 categories • The IBL WBS with costing details will be presented in my next talk
IBL Kick-off Meeting - Introduction G. Darbo – INFN / Genova IBL kick-off Meeting, 8 July 2009 9
When is IBL Ready to Install? Difficult answer…:
• In February (AUW) we have been told that the installation date was delayed by one year • End of 2012 -> end to 2013
• Today we feel that the 2013 is optimistic • Earliest starting date for Phase I is the 2013/2014 shutdown. • The availability of LINAC4 (around 2014) will define the shutdown for
Phase I, upgrade, when the IBL would be installed. • The Upgrade Project Office (May 12th) suggests to use 2014/2015 as a
guideline for the IBL installation date. • We are now working with a schedule that foresee an installation date in
2014/2015 • The FE-I4 and Sensor/Module are on the critical path, and installing earlier
than 2014/2015 would require some compromises in the performance.
IBL Kick-off Meeting - Introduction G. Darbo – INFN / Genova IBL kick-off Meeting, 8 July 2009 10
What to Discuss Today
Define the “big picture” of the coverage of the whole project. • What is covered by interested groups and what is not • See where there are conflicts – can we solve some? • Use the “cost” and “funding model” to size the sharing between countries and
institutes • Annotate input from the discussion (and then from FA) to further develop the
project
IBL Kick-off Meeting - Introduction G. Darbo – INFN / Genova IBL kick-off Meeting, 8 July 2009 11
Contributions to the Project Contributions to the project could come as:
• Participating Institute – M&O-B/New-project • Sensor, Hybridisation, Electronics, Stave & TM, Integration, part of
mechanics • Leading Institute(s) , Contributing Institutes , Interested Institutes "• Leading must be one or maximum two institutes • Leading and Contributed institutes will cover a fraction of the cost for the
given WBS package. Interested Institutes are not charged money/in kind contribution "
• Participation through the Upgrade Project Office – M&O-A • Beam-pipe, IBL insertion/beam-pipe extraction, cooling plant, external
services, power supply, DAQ … • Central design – possible in-kind contribution to deliverables (reduction
of M&O-A contribution)
IBL Kick-off Meeting - Introduction G. Darbo – INFN / Genova IBL kick-off Meeting, 8 July 2009 12
Some “Envelopes” to Shape Participation
IBL Total Cost: 9.6 MCH • M&O-A: 4.0 MCH • M&O-B (for Countries with “pixel M&O-B” budget line – listed in the table): 4.4 MCH
• CZ, F, D-BMBF, D-DESY, I, RZ, US, CERN • New project contributions: 1.2 MCH
• CH, E, N, NL, UK
IBL M&O-B: 4.4 MCH • There are not a-priory boundaries
amongst Countries – use as reference the old Pixel CORE to evaluate how countries are consolidated in the “pixel technology” needed for IBL
• FA will have in “mind” the old CORE contribution in financing the project.
IBL New project: 1.2 MCH • New money is needed and new Countries are interested and have the key
technical expertise to be added.
OLD Pixel CORE Sharing
IBL Kick-off Meeting - Introduction G. Darbo – INFN / Genova IBL kick-off Meeting, 8 July 2009 13
Matching Responsibilities, Deliverables & Money
Contribution in funds to the project to match taken responsibilities and deliverables:
• ~80 % covered from Leading and Participant Institutes (through their FA) • ~20 % are “tax” - weighted on the fraction of the total contribution
There are 3 large common orders (2.5 MCH) • Sensors (0.5 MCH) – Spread in cost for different technologies (0.3 to 1.6
MCH) from planar, 3D and diamond. • Spread the cost to several countries – everybody interested in sensors
– readjust in the future
• FE-I4 (1.35 MCH) - Bonn and LBNL (Leading) have large contribution, CPPM, Genova and Nikhef contribute. Geneva propose itself as “big” contributor.
• Bump-bonding (0.65 MCH) – We need two vendors qualified for a tender. There are no reasons to have two for production (small quantity).
IBL Kick-off Meeting - Introduction G. Darbo – INFN / Genova IBL kick-off Meeting, 8 July 2009 14
“Implicit” Rules IBL project is appealing to an Institute if:
• Has continuity of contribution from prototyping, design, construction, qualification till commissioning and running of the detector
• A deliverable (or part of a deliverable) is associated to the money that is put in • can use resources existing in the lab or can help in increasing the technical/engineering expertise.
Detector is small and we could be tempted into doing many early assembly steps (module assembly, bare stave assembly, stave loading with modules, cooling plant, internal services) in a centralized place.
• Could seem a more efficient way to get a better performing detector…
… but it would not work, because: • CORE detector and leading technical expertise is spread in many labs, and we (and the labs) would
loose such expertise with this construction model • Funding Agencies would be very sensitive, and would react negatively to finance a project with this
construction model
Rule: do as much as possible in the labs, and when designing keep in mind this as a strong constraint!
• Only detector integration and large system test need to be centralized in a single place.
IBL Kick-off Meeting - Introduction G. Darbo – INFN / Genova IBL kick-off Meeting, 8 July 2009 15
Explicit Rule: MoU The IBL project cannot be constructed on “Taxes”:
• M&O-B and New project money will come only when an MoU will be signed
MoU means that the construction responsibilities are clearly defined and accepted by the players in the game:
• Funding Agencies will not release money if they will not see a corresponding role of their Institutes in the IBL project
• Keep this in mind when later today we will tentatively assign construction responsibilities
MoU will finally define • Construction responsibilities • Contribution to deliverables and funds
IBL Kick-off Meeting - Introduction G. Darbo – INFN / Genova IBL kick-off Meeting, 8 July 2009 16
Scheme to Help Convergence Use IBL WBS (mainly deliverable based) to associate Institutes using 3
categories: • Leading Institute(s) : one or max two – resources and money
contribution • Contributing Institutes : resources and money contribution • Interested Institutes : do not bring money
• Leading institutes need fair balance with: • Expertiese on the item and technical background • Resources available – potentially available • Contribution in money from the own Country
• Use the cost in the WBS in assigning WBS packages to Leading/Contributing institutes
IBL Kick-off Meeting - Introduction G. Darbo – INFN / Genova IBL kick-off Meeting, 8 July 2009 17
Practicality: Template
Select WBS: • Assign Institutes (1 , 2 , 3 ) • Assign percentage of money contribution (MO-B/New Project) • Leave a tax: flexibility to the project, or in case of low package coverage • Evaluate conflict level • M&O-A items can be taken in kind and money contribution will be deducted.