ibl @ october rrb

12
IBL @ October RRB G. Darbo & H. Pernegger RRB – October 2010 o IBL @ October RRB Slides for Marzio’s RRB talk CERN, October, 11 th 2010 G. Darbo & H. Pernegger

Upload: marcello-hilton

Post on 30-Dec-2015

62 views

Category:

Documents


0 download

DESCRIPTION

IBL @ October RRB. Slides for Marzio’s RRB talk CERN, October, 11 th 2010 G. Darbo & H. Pernegger. IBL Detector. Material from Raphael/Neal. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: IBL @ October RRB

IBL @ October RRBG. Darbo & H. Pernegger RRB – October 2010o

IBL @ October RRBIBL @ October RRB

Slides for Marzio’s RRB talk

CERN, October, 11th 2010

G. Darbo & H. Pernegger

Page 2: IBL @ October RRB

IBL @ October RRBG. Darbo & H. Pernegger RRB – October 20102

Material from Raphael/NealThe Insertable B-Layer (IBL) is a fourth layer added to the present Pixel detector between a new beam pipe and the current inner Pixel layer (B-layer).

ISTIBL Support Tube

Alignment wires

PP1 Collar

IBL DetectorIBL Detector

IBL Staves

Sealing service ring

IBL key Specs / Params

•14 staves, <R> = 33.25 mm•CO2 cooling, T < -15ºC @ 0.2 W/cm2

•X/X0 < 1.5 % (B-layer is 2.7 %)•50 µm x 250 µm pixels•1.8º overlap in ϕ, <2% gaps in Z •32/16 single/double FE-I4 modules per stave•Radiation tolerance 5x1015 neq/cm2

IBL key Specs / Params

•14 staves, <R> = 33.25 mm•CO2 cooling, T < -15ºC @ 0.2 W/cm2

•X/X0 < 1.5 % (B-layer is 2.7 %)•50 µm x 250 µm pixels•1.8º overlap in ϕ, <2% gaps in Z •32/16 single/double FE-I4 modules per stave•Radiation tolerance 5x1015 neq/cm2

Page 3: IBL @ October RRB

IBL @ October RRBG. Darbo & H. Pernegger RRB – October 20103

IBL LayoutIBL LayoutBeam-pipe reduction:• Inner R: 29 25 mm

Very tight clearance:• “Hermetic” to straight tracks in Φ (1.8º

overlap)

• No overlap in Z: minimize gap between sensor active area.

Material budget:• IBL Layer (with IST): 1.5 % of X0

• Other Pixel layers: ~2.7 % of X0

Beam-pipe (BP) extracted by cutting the flange on one side and sliding (guiding tube inside).

IBL Support Tube (IST) inserted.

IBL with smaller BP inserted in the IST

Page 4: IBL @ October RRB

IBL @ October RRBG. Darbo & H. Pernegger RRB – October 20104

IBL Technical Design ReportIBL Technical Design ReportATLAS TDR includes:

• Overview and motivation for the project

• Study of the physics performance

• Technical description of the project with baseline and options for critical issues

• Three sensor technologies.

• Beam-pipe, extraction/insertion, installation, ALARA.

• Organization of the project and resources

Editorial team:M. Capeans (technical editor), G. Darbo,

K. Einsweiller, M. Elsing, T. Flick,M. Garcia-Sciveres, C. Gemme,H. Pernegger, O. Rohne and R. Vuillermet.

Approved by the ATLAS Collaboration Board (October 2010 ATLAS Week)

• 43 Institutions and 300 people in IBL

CERN-LHCC-2010-13, ATLAS TDR 19

Page 5: IBL @ October RRB

IBL @ October RRBG. Darbo & H. Pernegger RRB – October 20105

Physics PerformancePhysics Performance

b-tagging performance crucial for:• New Physics (3rd generation !)

• observation of H → bb through boosted WH production

Main conclusions of IBL performance Task Force: • performance at 2x1034 with IBL is equal to or better than

present ATLAS without pile-up

• w/o IBL and 10% B-layer inefficiency: b-tagging ~ 3 times worse at 2x1034 than today

b-tagging with pile-up & inefficiencies

b-tagging with pile-up 2 jets of 500 GeV event with 2 x 1034 pile-up Same event w/o pile-up

IBL

IBL

Physi

cs &

Perf

orm

ance

Task

Forc

e –

M.

Els

ing e

t al.

Page 6: IBL @ October RRB

IBL @ October RRBG. Darbo & H. Pernegger RRB – October 20106

The New Front-end Chip (FE-I4)

The New Front-end Chip (FE-I4)

18

160

FE-I3(Pixel) FE-I4

(IBL)

80 columns

336 rows

19

mm

20.2 mm60 KGD / Wafer

Page 7: IBL @ October RRB

IBL @ October RRBG. Darbo & H. Pernegger RRB – October 20107

Sensor Technologies for IBLSensor Technologies for IBL

Planar sensors (3 producers)

• slim edge n-in-n & n-in-p

• require the lowest temperature and high bias voltage.

• have very well understood manufacturing sources, mechanical properties, relatively low cost, and high yield.

ATLAS Pixel FE-I3 diamond module

IBL FE-I4 diamond sensors

Thin n-in-p

Planar Sensor

3D Sensor

450 µm

n-in-n slim edge

IBL layout

3D column

11 µm

3D sensors (3 producers)

• Active edge, single/double side

• require the lowest bias voltage, intermediate operating temperature, and achieve the highest acceptance due to active edges.

• their manufacturability with high yield and good uniformity must be demonstrated.

Diamond sensors (2 producers)

• polycrystalline CVD (pCVD)

• require the least cooling and have similar bias voltage requirements to planar sensors.

• their manufacturability with high yield, moderate cost, and good uniformity must all be demonstrated.

Selection in summer 2011

Three candidate sensor technologies address the IBL requirements with different trade-offs:• Prototyping with FE-I4 – qualification with irradiation (5x1015 neq/cm2) and test beam – production yield

Page 8: IBL @ October RRB

IBL @ October RRBG. Darbo & H. Pernegger RRB – October 20108

SPARE SLIDESSPARE SLIDES

Page 9: IBL @ October RRB

IBL @ October RRBG. Darbo & H. Pernegger RRB – October 20109

History of IBL Project - Time Line

History of IBL Project - Time Line

1998: Pixel TDR • B-layer designed to be substituted every 3 years of nominal LHC (300 fb-1): due

to then available radiation hard sensor and electronic technologies.

2002: B-layer replacement • became part of ATLAS planning and was put into the M&O budget to RRB.

2008: B-layer taskforce• B-layer replacement cannot be done – Engineering changes to fulfil delayed on-

detector electronics (FE-I3, MCC) made it impossible even in a long shut down.

• Best (only viable) solution: “make a new smaller radius B-layer insertion using technology being developed for HL-LHC prototypes”. This became the IBL.

2009: ATLAS started IBL project:• February: endorsed IBL PL and TC

• April: IBL organization in place (Endorsed by the ATLAS EB)

2010: TDR and interim-MoU• TDR is under approval in ATLAS

• Interim-MoU is collecting last signatures.

Page 10: IBL @ October RRB

IBL @ October RRBG. Darbo & H. Pernegger RRB – October 201010

Interim-MoU - InstitutionsInterim-MoU - InstitutionsThere are 43 institutions in the IBL project

• Large interest for the sensor (22 Institutions)

• Full effort and funding requirements are covered

300 people have expressed their interest to contribute to the project

• many have already started to work.

• In most cases institutes contribute with money where also there is contribution with manpower.

Page 11: IBL @ October RRB

IBL @ October RRBG. Darbo & H. Pernegger RRB – October 201011

Management Board (MB)Management Board (MB)

Module WG(2 cordinators)

•FE-I4•Sensors•Bump-Bonding•Modules•Procurement & QC•Irradiation & Test Beam

Module WG(2 cordinators)

•FE-I4•Sensors•Bump-Bonding•Modules•Procurement & QC•Irradiation & Test Beam

Stave WG(1 Phys + 1

Eng.)

•Staves•Cooling Design & Stave TM•HDI (Flex Hybrid)•Internal services•Loaded stave•Procurement & QC

Stave WG(1 Phys + 1

Eng.)

•Staves•Cooling Design & Stave TM•HDI (Flex Hybrid)•Internal services•Loaded stave•Procurement & QC

Integration & Installation WG

(2 Eng.)•Stave Integration•Global Supports•BP procurement•Ext. services inst.•BP extraction•IBL+BP Installation•Cooling Plant

Integration & Installation WG

(2 Eng.)•Stave Integration•Global Supports•BP procurement•Ext. services inst.•BP extraction•IBL+BP Installation•Cooling Plant

Off-detector(1 Phys + 1 E.Eng.)

•BOC/ROD•Power chain & PP2•DCS & interlocks•Opto-link•Ext. serv .design/proc.•Procurement & QC•System Test

Off-detector(1 Phys + 1 E.Eng.)

•BOC/ROD•Power chain & PP2•DCS & interlocks•Opto-link•Ext. serv .design/proc.•Procurement & QC•System Test

IBL Management Board (MB)Membership:•IBL PL + IBL TC•2 cordinators from each WG•Plus “extra” members

IBL Management Board (MB)Membership:•IBL PL + IBL TC•2 cordinators from each WG•Plus “extra” members

MB ad-interim membership

IBL Project Leader: G. DarboIBL Technical Coordinator: H. Pernegger“Module” WG (2 Physicists): F. Hügging & M. Garcia-Sciveres“Stave” WG (1 Phy. + 1 M.E.): O. Rohne + D. Giugni“IBL Assembly & Installation” WG (2 M.E. initially, a Phy. Later): F. Cadoux + R. Vuillermet“Off-detector” WG (1 Phy. + 1 E.E.): T. Flick + S. Débieux“Extra” members:IBL/Pixel “liaison”: Off-line SW: A. Andreazza, DAQ: P. Morettini, DCS: S. KerstenEx officio: Upgrade Coordinator (N. Hessey), PO Chair (M. Nessi), Pixel PL (B. Di Girolamo), ID PL (P. Wells), IB Chair (C. Gößling)

Page 12: IBL @ October RRB

IBL @ October RRBG. Darbo & H. Pernegger RRB – October 201012

FE-I4 TableFE-I4 Table

FE-I3 FE-I4Pixel size [µm2] 50x400 50x250

Pixel array 18x160 80x336

Chip size [mm2] 7.6x10.8 20.2x19.0

No. of transistors [millions] 3.5 87

Active fraction 74% 89%

Analog/digital current [µA/pix] 26 / 17 10 / 10

Digital current [µA/pix] 17 10

Analog/digital voltage [V] 1.6 / 2.0 1.5 / 1.2