Job Report HVAC EQUIPMENT MARLIM SUL OIL FIELD P-51 OUR CLIENT FELS/TECHNIP - FSTP OPERATORS PETROBRAS DESCRIPTION OF THE PROJECT The Marlim Sul field was discovered in 1987. In 2003 the field had 57 producing wells reaching an average output of 151,000 b/d. The P-51, with a total cost around $830 million, produces approx 180 000 barrels a day. P-51 is a semi-submersible and is installed in deep water at the heavy oil Marlim Sul field in the Campos basin outside Brazil. The rig was built in Rio de Janeiro state by the FELS Se- tal-Technip consortium. The P-51 was contracted in 2004 and production start was in 2009. CHALLENGES The main challenge was that this was the first semi-sub- mersible platform built completely in Brazil and both cus- tomer and shipyard were new to us. Novenco also had to work with two separate engineering teams for the Accommodation and Deckbox area. Meeting the demands in the latest Petrobras specifications was challenging. Petrobras is known for extremely extensive documentation and a complex approval process. Last but not least the stringent sound requirements were difficult to meet in critical areas. SOLUTION Following an extensive bid process, Novenco was awarded two separate purchase orders for the Accommodation and Deckbox. Novenco needed to use two separate project teams due to the extent and complexity of the project. Both teams worked closely together out of Novenco’s main offshore office situat- ed in Oslo, Norway. Purchase orders were carefully coordinated to ensure common suppliers, reducing inspection and delivery costs for both the client and Novenco and ensuring a minimum of spare parts during the lifetime of the platform. SCOPE OF WORK Novenco’s scope of work was complete HVAC system design review, procurement, production, testing and delivery of all VAC equipment detailed overleaf, as well as commissioning assistance after installation. Documentation was very extensive with a total of over 280 of- ficial project documents in Novenco’s documention package. Equipment was produced in accordance with Petrobras latest specifications, including the requirement for painting equipment both internally and externally.

Upload: lamkhanh

Post on 19-Mar-2018

221 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: HVAC EQUIPMENT MARLIM SUL OIL FIELD P-51 - Novenco · PDF fileJob Report HVAC EQUIPMENT MARLIM SUL OIL FIELD P-51 OUR CLIENT FELS/TECHNIP - FSTP OPERATORS PETROBRAS DESCRIPTION OF

Job Report

HVAC EQUIPMENT MARLIM SUL OIL FIELD P-51OUR CLIENT FELS/TECHNIP - FSTP OPERATORS PETROBRAS

DESCRIPTION OF THE PROJECTThe Marlim Sul field was discovered in 1987. In 2003 the field had 57 producing wells reaching an average output of 151,000 b/d. The P-51, with a total cost around $830 million, produces approx 180 000 barrels a day. P-51 is a semi-submersible and is installed in deep water at the heavy oil Marlim Sul field in the Campos basin outside Brazil. The rig was built in Rio de Janeiro state by the FELS Se-tal-Technip consortium. The P-51 was contracted in 2004 and production start was in 2009.

CHALLENGESThe main challenge was that this was the first semi-sub-mersible platform built completely in Brazil and both cus-tomer and shipyard were new to us.Novenco also had to work with two separate engineering teams for the Accommodation and Deckbox area.Meeting the demands in the latest Petrobras specifications was challenging. Petrobras is known for extremely extensive documentation and a complex approval process.Last but not least the stringent sound requirements were difficult to meet in critical areas.

SOLUTIONFollowing an extensive bid process, Novenco was awarded two separate purchase orders for the Accommodation and Deckbox.Novenco needed to use two separate project teams due to the extent and complexity of the project. Both teams worked closely together out of Novenco’s main offshore office situat-ed in Oslo, Norway.Purchase orders were carefully coordinated to ensure common suppliers, reducing inspection and delivery costs for both the client and Novenco and ensuring a minimum of spare parts during the lifetime of the platform.

SCOPE OF WORKNovenco’s scope of work was complete HVAC system design review, procurement, production, testing and delivery of all VAC equipment detailed overleaf, as well as commissioning assistance after installation.Documentation was very extensive with a total of over 280 of-ficial project documents in Novenco’s documention package.Equipment was produced in accordance with Petrobras latest specifications, including the requirement for painting equipment both internally and externally.

Page 2: HVAC EQUIPMENT MARLIM SUL OIL FIELD P-51 - Novenco · PDF fileJob Report HVAC EQUIPMENT MARLIM SUL OIL FIELD P-51 OUR CLIENT FELS/TECHNIP - FSTP OPERATORS PETROBRAS DESCRIPTION OF

Job Report

HVAC EQUIPMENT TECHNICAL DESCRIPTION EQUIPMENT

ADVANTAGESNovenco has up to now delivered VAC equipment to more than 10 different Petrobras platforms, spanning a period of over 10 years. Equipment has been adapted and modified to meet the specifications which Petrobras continually change and improve to meet todays increasing demands from the environment.It is Novenco’s vast experience in supplying their products to Petrobras and other demanding clients in the oil industry which give Novenco a unique advantage.Novenco is one of the very few remaining suppliers of HVAC equipment which produces the main components such as Air Handling Units and fans themselves, ensuring total control over the production process.

SCOPE OF SUPPLY:

ACCOMMODATION AREA:• 14 Floor Fan Coil units• 104 Ceiling Fan Coil units• 25 Centrifugal & Axial Fans • 20 Inlet Air Filter Boxes• 1 Self Contained cooling unit• 40 Inlet and outlet Louvers• 25 Pneumatic Fire Dampers• 18 Tightness Dampers • 10 Pneumatic Dampers Panels• 42 Non Return Dampers • 1 Modulating Dampers • 39 Regulating Dampers • 2 Electrical Air Heaters• 175 Grilles• 257 Diffusers• 117 Control Valves• 121 Shut off & Regulating Valves

DECK BOX AREA:• 29 Inlet Air Filter Boxes• 3 Chilled Water Units• 3 Chilled Water Pumps• 20 Horizontal Modular Floor Fan Coil units • 5 Horizontal Ceiling Fan Coil units• 66 Centrifugal & Axial Fans

• 8 Sound Attenuators• 94 Pneumatic Fire Dampers• 25 Tightness Dampers• 99 Non Return Dampers• 57 Regulating Dampers• 2 Modulating Dampers• 22 Pneumatic Dampers Panels• 289 Grilles• 19 Regulating Water Valves