State Transportation Board Meeting December 8, 2016 Meg Pirkle, P.E. Chief Engineer Project Updates 1

Upload: others

Post on 03-Jun-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

State Transportation Board Meeting

December 8, 2016

Meg Pirkle, P.E.

Chief Engineer

Project Updates

1

Page 2: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

Georgia Express Lanes

Projects in Construction:

• I-75 Metro South Express Lanes

• I-85 Express Lanes Extension

• I-75/I-575 Northwest Corridor Express Lanes

Planned Projects:

• Revive 285 (top end)

• SR 400 Express Lanes

• I-285 West Wall Express Lanes

• I-285 East Wall Express Lanes

2

Page 3: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

Express Lanes Program

• Creates a network that provides more reliable and predictable trip times

• Provides a choice for drivers to pay a variable rate toll to bypass congestion, when desired

• Offers a clear path for transit operators

• Provides more reliable travel times in peak periods for motorists and bus patrons

3

Page 4: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

Express Lanes Network

4

Page 5: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

5

Page 6: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

I-75 South Metro Express

• 12 miles - SR 155/ McDonough Road and SR 138/ Stockbridge Highway

• Two reversible Express Lanes; first in Georgia

• Located in the median – lane shift to west

• Variable rate tolls based on demand

• $227 million est. project cost

• Opening early 2017 6

Page 7: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

I-75 South Metro Construction

7

Page 8: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

I-75 S Metro Construction – Mt. Carmel

8

Page 9: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

I-75 S Metro Construction – SR 20 Slip Ramps

9

Page 10: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

I-75 S Metro Construction – SR 155 Slip Ramps

10

Page 11: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

I-75 S Metro Construction – Jonesboro Road

11

Page 12: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

Collaboration with SRTA

• GDOT and SRTA as co-lead agencies

• Executive leadership coordination

• Clearly defined roles and responsibilities

o GDOT manages construction and maintenance

o SRTA manages toll operations, marketing and customer service

• Monthly Taskforce Meetings

o Communications and Outreach

o Incident Management

o Transit

o Operations

12

Page 13: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

13

Page 14: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

I-85 Express Lanes Extension

• 10 miles of newly constructed Express Lanes from Old Peachtree Road to Hamilton Mill Rd

• Extends north of existing I-85 Express Lanes

• New auxiliary lanes

• Variable rate tolls based on demand

• $178 million est. project cost

• Fall 2018 14

Page 15: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

15

I-85 Extension - Groundbreaking

Page 16: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

I-85 Express Lanes Extension

16

Page 17: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

17

I-85 Extension - Construction

Page 18: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

I-85 Extension - Construction

18

Page 19: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

19

Page 20: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

20

• 29.7 miles of newly constructed roadway from Akers Mill Road to Hickory Grove Road on I-75 and to and Sixes Road on I-575

• Two reversible lanes along the west side of I-75 from I-285 to I-75/I-575 interchange

• One barrier-separated lane in the median on both I-75 and I-575 from the I-75/I-575 interchange

• Variable rate tolls based on demand

• $834 million est. project cost

• Public/private partnership

• Spring 2018

Northwest Corridor Express Lanes

Page 21: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

21

• 39 Bridges (5.3 miles total length)

• Georgia’s Longest Land Bridge (1.13 miles)

• 68 Retaining Walls

• 45 Sound Barriers

• 11.4 Miles of Asphalt Roadway

• 11.1 Miles of Concrete Roadway

• 6 New Interchanges

• 14 Toll Zones

• 273 Cameras

October 2016 I-75 at Big Shanty Road

Northwest Corridor Highlights

Page 22: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

22

Florida I-Beams

ATC – I-75 Shift at Terrell Mill

Northwest Corridor Innovations

Page 25: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

GEL Projects Delivery Schedule

25

2016 2017 2018 Cost

Northwest Corridor

$834M

Spring 2018

I-75 South Metro

$227M

Early 2017

I-85 Extension

$178M

Fall 2018

Page 26: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

26

Questions?

Page 27: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

State Transportation Board Meeting

Meg Pirkle, Chief Engineer

December 8, 2016

Revive 285 GARVEE Resolution

27

Page 28: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

28

Page 29: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

Revive 285 Schedule

29

2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

PE

ROW Early Acquisition

CST

Page 30: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

Why GARVEE?

• Advance Acquisitions – Over 300 total parcels to purchase – Majority are complex urban parcels

• Preserve Corridor • Address Imminent Development • Manage Schedule • Prioritize Parcels (by)

– Greatest risk to the program’s success – Extended relocation times – Displacements with long leads

GARVEE will promote Reduced Project Risks and Significant Cost Savings

30

Page 31: GDOT PowerPoint Template - 2015 · 2016-12-08 · marketing and customer service • Monthly Taskforce Meetings ... ROW Early Acquisition CST. Why GARVEE? • Advance Acquisitions

31

Questions?