gauteng provincial legislature | your view – our...
TRANSCRIPT
ROADS AND TRANSPORT PORTFOLIO COMMITTEE
ADOPTED COMMITTEE OVERSIGHT REPORT ON
BUDGET VOTE 9: GAUTENG DEPARTMENT OF ROADS AND
TRANSPORT OF THE APPROPRIATION BILL
31ST JULY 2019
TABLE OF CONTENTS PAGE No:
ACRONYMS 3
EXECUTIVE SUMMARY 4-6
INTRODUCTION 7
1. PROCESS FOLLOWED 7
2. COMMITTEE’S ASSESMENT OF THE BUDGET VOTE 8-14
2.1 Overall Assessment
2.2 Assessment per Programme
3. STAKEHOLDER SUBMISSIONS 14
4. CONCERNS 15
5. RECOMMENDATIONS 15-16
6. ACKNOWLEDGEMENTS 16
7. ADOPTION 16
ACRONYMS
2
BRT BUS RAPID TRANSPORT
DLTCs DRIVER LICENSE TESTING CENTRES
DNO’s DO NOT OPERATE
EPWP EXPANDED PUBLIC WORKS PROGRAMME
FY FINANCIAL YEAR
GMA GAUTRAIN MANAGEMENT AGENCY
GTA GAUTENGTRANSPORT AUTHORITY
GPG GAUTENG PROVINCIAL GOVERNMENT
HOD HEAD OF DEPARTMENT
ITMP25 25 YEAR GAUTENG INTEGRATED TRANSPORT MASTER PLAN
MEC MEMBER OF EXECUTIVE COMMITTEE
NDOT NATIONAL DEPARTMENT OF TRANSPORT
PRASA PASSENGER RAIL AGENCY OF SOUTH AFRICA
PRMG PROVINCIAL ROADS MAINTENANCE GRANT
PTOG PUBLIC TRANSPORT OPERATIONS GRANT
TOLABs TRANSPORT OPERATING LICENSE ADMINISTRATIVE BODYS
3
EXECUTIVE SUMMARY
The Chairperson of the Roads and Transport Portfolio Committee, Honourable D. Dakile,
tables the Committee's Report on Budget Vote 9 of the Appropriation Bill as follows:
In the current financial year, the Committee noted that the Department has been
allocated a budget of R7 708 630 000 financed through the Equitable share amounting to
R4 498 664 000 (58%) and Conditional grants R3 209 966 000 (42%). The Committee
noted that the budget allocation decreased by an amount of R405 583 000 (5%) compared to previous financial year. The budget allocation for Administration, Transport
Regulation, Transport Operation and Gautrain programmes increased whilst the
allocation for Transport Infrastructure decreased compared to previous financial year.
Taking into consideration the budget cut in the Transport infrastructure programme, the
core service delivery programme, the Committee is of the view that there were projects
that were not allocated infrastructure budget due to the lack of their state of readiness.
On the construction and maintenance of road infrastructure, the Committee noted that
the Department has planned to complete designs, maintain, rehabilitate and construct a
number of roads in the province. These include multi-year construction projects of R82
Phase 3 from Walkerville to De Deur, K69 Solomon Mahlangu from R104
Bronkhorstspruit Road to K54 in Mamelodi, K54 from Mamelodi Tsamaya Rd to R104
Pretoria Bronkhort Rd as well as rehabilitation of P39/1 Diepsloot to Muldersdrift and
P175/1 from Vanderbijlpark to Potchefstroom Phase 2. The Committee urges the
Department to ensure that proper project and contract management should be adhered
to in the implementation of these projects in line with project timelines and costs.
On the construction of K46 William Nicol and Sebokeng DLTC & TOLAB, the Committee
noted that the re-advertisement of tenders has been planned for the current financial
year and commencement of construction is earmarked for April 2020. The Committee is
concerned over the further delays in the above-mentioned projects. In relation to K46
William Nicol, that the Department needs to resolve three issues which includes, the
offering of a public apology to the community of Diepsloot at large, resolve on the
payment of monies owed by the previous contractor to sub-contractors and employees
4
as well as the implementation of the findings of the Provincial Government investigation
on the project. This may assist in minimising the challenges that continue to surround
the project and pave the way for a new chapter at the proposed commencement date of
the project.
On the construction of the Vereeniging Intermodal Facility, the Committee noted that the
Department had planned to conduct a conditional assessment and provide options on
the best way to proceed with the project and the assessment report is expected in March
2020. The Committee is concerned over the further delays in the above-mentioned
project and would like to encourage the Department to prioritise internal audit of technical
skills required for the implementation of all infrastructure projects. This is because the
Committee is of the view that the failure of this project was mainly because of lack of
internal technical skills required for projects of the nature.
The Committee noted that the allocation for Public Transport Operations Grant (PTOG)
from the National Government has increased compared to previous financial year by R60 063 000 (2,53%). According to the Department, the processes on new tendered
contract, which will take into account various modes as part of one contract, are on-going
whilst negotiated contracts, targeting the DNO’s where they exist and 30% for the
general contracts where the taxi industry, small bus operators and women in transport
can partake, are expected to be finalised by March 2020. The Committee would like to
urge the Department to ensure that all planned targets are implemented in line with set
timelines as the negative impact on commuters is severe.
In the Transport Regulation programme, the Committee noted that there are no
infrastructure projects planned to be implemented on DLTCs and TOLABs until the
infrastructure planning unit completes the Master Plan for Transport Services Centres
that will guide location of the centres and the form they should take for effective service
delivery. The Committee further noted that the Department will be embarking on an audit
and mapping of taxi routes to develop a map of common reference for both industry and
the Department.
5
On the Gautrain Management Agency, the Committee noted that the allocated budget for
the current financial year has been increased compared to the previous financial year by
R208 046 000 (10,69%) and is earmarked for the operational maintenance and
capacitation of the current system. The Committee also noted that the agency has been
appointed as the interim managing agency in the process of establishing Gauteng
Transport Authority (GTA) by the second half of 2019 which will be responsible for driving
the set Provincial vision of integrating the Gautrain, BRTs and metro rail into a modern,
efficient, reliable, affordable and integrated single mass transit system. The Committee
further noted that the agency will lead the process of reviewing the 25-Year Integrated
Transport Master Plan to take into consideration the Gauteng expansion plan and the
latest household travel survey data.
With regards to g-fleet Management, the Committee noted that the entity has planned
targets and confirmed a budget allocation of R944 620 218 for the current financial year
marking an increase of R121 672 000 compared to the previous financial year. The
Committee noted that the allocation will cater for the the acquisition of motor vehicles,
vehicle repairs and maintenance and provision of a comprehensive vehicle tracking
solution.
In conclusion, the Committee urges the Department and its entities to exercise proper
project and contract management and maintain a high level of efficiency and
effectiveness in delivering on key infrastructure projects.
6
INTRODUCTIONThe Committee report covers the alignment of the Department’s appropriation with planned
outputs. The report also assesses the link between the Department’s strategic objectives and
how they contribute to national and provincial outcomes.
Budget Vote 9 is the Gauteng Provincial Government’s plan to deliver services to the people
according to its commitment on transport infrastructure and operations. The Gauteng Department
of Roads and Transport’s overall goal is to provide a world class roads and transport
infrastructure networks and systems that facilitate seamless mobility of goods and people within
Gauteng. Its purpose is to provide an environmentally sustainable road infrastructure and
integrated transport systems and services that are reliable, accessible, safe, and affordable and
which promote socio-economic development in Gauteng.
1. PROCESS FOLLOWED The MEC for Finance tabled the Gauteng Province 2019/20 FY Budget in the Legislature. The
Speaker referred the Vote 9 Budget Appropriation for 2019/20 FY to the Committee, in
accordance with Standing Rule 220(2), for consideration and reporting. The Committee
Researcher prepared and tabled an analysis for discussion and questions emanating from
Budget Statement to the Committee. Following that, the Department tabled the details of the
budget and responses to questions raised to the Committee. The Committee deliberated on and
adopted its oversight report. The report was then tabled for consideration and adoption by the
House.
2. COMMITTEE’S ASSESSMENT OF THE BUDGET VOTE
2.1 OVERALL ASSESMENT2.1.1 Departmental ReceiptsThe Committee noted that the Department received R4 498 664 000 (58%) allocation
from the Equitable share, and R3 209 966 000 (42%) conditional grants from the
National Department of Transport. The conditional grants consist of the Public Transport
Operations Grant (PTOG) amounting to R2 436 074 000 mainly for the bus subsidy
programme, Provincial Roads Maintenance Grant (PRMG) amounting to R767 506 000
7
received for routine maintenance of the provincial road network and EPWP Infrastructure
Grant amounting to R6 386 000.
The Committee noted that the allocation of financial resources has decreased from R8 114 213 000 in 2018/19 FY to R7 708 630 000 in current financial year, marking a
decrease of R405 583 000 (5%). The Committee further noted that the Budget allocation
has been reduced in the Transport infrastructure programme, which is the key service
delivery programme of the Department.
2.1.2 Departmental RevenueThe Committee noted that the Department of Roads and Transport, as the Province’s
main generator of revenue, estimated revenue to be collected in the current financial
year amounts to R4 110 915 000 from all the revenue items, with the main contributor to
revenue being motor vehicle registration and licensing fees estimated at R4 025 181 000 (98%). The Committee also noted that the estimated revenue is projected to increase
over the MTEF period due to the growth in vehicle population and higher than anticipated
application of new and renewal of motor vehicle licenses.
2.1.3 Budget Estimates per ProgrammeBudget Vote 9 funds five programmes namely: Administration, Transport Infrastructure,
Transport Operations, Transport Regulation and Gautrain Rapid Rail Link. The table
below reflects the amount appropriated to each programme.
Table 01: Budget Estimation per Programme
Programme (R'000) 2019/20
Change 2018/19 - 2019/20
% Change 2018/19 - 2019/20
Change 2019/20 - 2020/21
% Change 2019/20 - 2020/21
1. Administration 370 347 15 201 4,28% 24 523 6,62%
2. Transport Infrastructure 2 155 661 (715 549) (24,92%) 467 667 21,69%
3. Transport Operations 2 688 745 49 827 1,89% 186 052 6,92%
4. Transport Regulation 340 563 36 892 12,15% 30 668 9,01%
8
5. Gautrain 2 153 314 208 046 10,69% 118 432 5,50%
Total 7 708 630 (405 583) (5,00%) 827 342 10,73%
Source: Research Analysis and Budget Statement 2019/20 FY
The Committee noted that the budget for the Administration, Transport Regulation,
Transport Operations and Gautrain programmes have been increased whilst the budget
allocation for Transport Infrastructure programme has been decreased in the current
financial year. The Committee is concerned over the budget reduction of R715 549 000 (24,92%) in the programme noting the need for enhanced delivery on the design, construction and maintenance of roads infrastructure in the province.
2.1.4 Payments and Estimates per Economic ClassificationIn terms of the economic classification; the Committee noted that 62% of the total
allocation goes to transfers and subsidies with an allocation of R4 779 504 000; the
second largest share goes to current payments with an allocation of R2 252 028 000,
representing 29%; while Payment for Capital Assets constitutes 9% of the allocation
amounting to R677 098 000.
2.2 Assessment per Programme 2.2.1 Programme 1: AdministrationThis programme provides the overall management and administrative support function
for the Office of the Member of Executive Committee (MEC) and the Department. The
programme objectives include rendering advisory, secretarial, parliamentary and
administrative office support services to the MEC; rendering strategic support to the
Department as well as to manage personnel, procurement, finance, administration and
related support services.
The total appropriation for the programme is R370 347 000 which will fund four sub-
programmes namely: Management, MEC’s Office, Corporate Support and Departmental
Strategy. The Committee noted that the allocation increased by an amount of R15 201 000 (4,28%) compared to previous financial year and this has been attributed to
improvements in the condition of service, as well as goods and services for the
9
operational requirements of the units. The Committee further noted that the allocation for
the programme will increase over the MTEF period.
2.2.2 Programme 2: Transport InfrastructureThe programme entails supporting social empowerment and economic growth by the
promotion of accessibility and the safe movement of people, goods and services through
the delivery and maintenance of transport infrastructure that is sustainable, integrated
and environmentally sensitive. Key outputs and service delivery measures for the
programme are upgrading and maintenance of provincial road and transport
infrastructure.
The programme funds five sub-programmes namely: Infrastructure Planning,
Infrastructure Design, Construction, Maintenance and Programme Support Infrastructure.
The Committee noted that the total appropriation for this programme amounts to R2 155 661 000 marking a decrease of R715 549 000 (24,92%) compared to the previous
financial year due to the delays experienced in the open tender process for several high-
value construction projects, which meant that Treasury could not allocate budget as there
was no clear state of readiness. The Committee is concerned over the budget reduction in the programme and the impact on the EPWP jobs in line with the Honourable Premier’s SOPA February 2019. The Committee also noted that the
programme’ s allocated budget is expected to increase over the MTEF period.
The Committee noted that the Department has planned to implement a number of
construction and maintenance projects, these also include projects carried over from the
previous financial year and multi-year projects to be completed within the MTEF period.
The projects include the construction of R82 Phase 3 from Walkerville to De Deur, K69
Solomon Mahlangu from R104 Bronkhorstspruit Road to K54 in Mamelodi, K54 from
Mamelodi Tsamaya Rd to R104 Pretoria Bronkhort Rd as well as rehabilitation of P39/1
Diepsloot to Muldersdrift and P175/1 from Vanderbijlpark to Potchefstroom Phase 2.
10
The Committee also noted that regarding construction of K46 William Nicol, the
Department has engaged in the process of re-advertising the tender and construction is
expected to commence by April 2020. The Committee is concerned over the further delays in the above-mentioned projects and the negative impact on the current
state of the project like waste dumping and criminal activities on the site. In
relation to K46 William Nicol, the Committee noted that the Department needs to resolve
three issues which includes, the offering of a public apology to the community of
Diepsloot at large, resolve on the payment of monies owed by the previous contractor to
sub-contractors and employees as well as the implementation of the findings of the
Provincial Government investigation on the project. This may assist in minimising the
challenges that continue to surround the project and pave the way for a new chapter at
the proposed commencement date of the project.
2.2.3 Programme 3: Transport OperationsThe Transport Operations programme entails planning for, regulating and facilitating the
provision of integrated land transport services to enhance mobility of all communities.
The objectives of this programme are to manage the integration of land transport
contracts and to manage, co-ordinate and facilitate transport safety and compliance in all
modes.
The Committee noted that the total allocation for the programme for the current financial
year is R2 688 745 000 marking an increase of R49 827 000 (1,89%) compared to the
previous financial year. The largest share of this programme’s allocation goes to Public
Transport Services amounting to R2 680 190 000 and the allocation caters for the Bus
subsidy contracts. The Committee also noted that the allocation for goods and services
is expected to increase over the MTEF period because of the increase allocations for
Integrated Fare Management System, a 25-Year Integrated Transport Master Plan
(ITMP25) linked project that the Department is implementing with the support of
Gautrain.
The Committee noted that the allocation for Public Transport Operations Grant (PTOG)
from the National Government has increased compared to previous financial year by R60 063 000 (2,53%). The Committee further noted that the new tendered contracts will take
11
into account various modes as part of one contract as informed by an Integrated Public
Transport Network Designs (IPTN) whilst negotiated contracts, will again be informed by
the same IPTN template, targeting the DNO’s where they exist and 30% for the general
contracts where the taxi industry, small bus operators and women in transport can
partake. According to the Department, the processes on new tendered contracts are on-
going whilst negotiated contracts are expected to be finalised by March 2020.
On the construction of Vereeniging Intermodal Facility, the Committee further noted that
the Department has planned to conduct a conditional assessment and provide options on
the best way to proceed with the project and the assessment report is expected in March
2020. The Committee is concerned over the lack of technical skills within the Department to provide proper contract and project management since the inception of the project. The Committee is also concerned over the continuous delays and the negative impact on the current state of the projects like vandalism as there is no security deployed within the project currently.
2.2.4 Programme 4: Transport RegulationThe programme entails the provision of a safe environment through the regulation of
traffic on public infrastructure, limited law enforcement, implementation of road safety
education and the registration and licensing of vehicles and drivers. The programme’s
objectives are to monitor and control registration and licensing of all motor vehicles and
to render services regarding the administration of applications in terms of the National
Road Traffic Act (Act 93 of 1996); implement laws and regulations relating to vehicle
registration and licensing, manage, approve and control the registration of transport
operators and the issuing of all licenses and permits required in terms of legislation and
manage, approve and control the registration of transport operators and the issuing of all
licenses and permits required in terms of legislation.
The total allocation for the programme is R340 563 000 marking an increase of R36 892 000 (12,15%) compared to the previous financial year mainly for improvement of
capacity services in the Driver License Testing Centres (DLTCs) and Transport Operating
License Administrative Board (TOLAB) in line with the revised organisational structure.
The programme achieves its objectives through two sub-programmes namely, Transport 12
Administration and Licensing with an allocation of R200 650 000 (59%) and Operator
License and Permits with an allocation of R139 913 000 (41%).
The Committee also noted that regarding the construction of Sebokeng DLTC and
TOLAB, the Department has engaged in the process of re-advertising the tender and
construction is expected to commence by April 2020. The Committee is concerned over the continuous delays and the negative impact on the current state of the project like vandalism as there are no security services deployed within the project currently. According to the Department, no infrastructure projects have been planned to
be implemented on DLTCs and TOLABs until the infrastructure planning unit completes
the Master Plan for Transport Services Centres that will guide where these centres must
be situated and what form they should take for effective service delivery.
The Committee further noted that the Department will be embarking on an audit and
mapping of taxi routes to develop a map of common reference for both industry and the
Department.
2.2.5 Gautrain Rapid Rail LinkThe Gautrain Rapid Rail Link programme is a special project that seeks to plan for,
design and construct the Rapid Rail Link and to ensure its implementation and efficient
management. The programme’s objectives are to manage and oversee the rail link in
terms of the concession agreement.
The total allocation for the Gautrain in the current financial year is R2 153 314 000 mainly
for the operational phase of the project as well as the payment of the patronage
guarantee cost. The budget for Gautrain has been increased by R208 046 000 (10,69%) compared to the previous financial year and is expected to increase over the MTEF
period.
The Committee also noted that the agency has been appointed as the interim managing
agency in the process of establishing Gauteng Transport Authority by the second half of
2019. The transport authority will be responsible for driving the set Provincial vision of
13
integrating the Gautrain, BRTs and metro rail into a modern, efficient, reliable, affordable
and integrated single mass transit system. The Committee further noted that the agency
will lead the process of reviewing the 25-Year Integrated Transport Master Plan to take
into consideration the Gauteng expansion plan and the latest household travel survey
data.
2.2.6 G-fleet Management
The entity’s goals are to achieve and sustain effective client relations, provide clients with
fleet services, develop human capital to support service delivery, streamline and
automate business processes for improved efficiency, achieve effective internal controls
and contribute to 10 Pillars of the Gauteng Province.
The Committee noted that the approved budget for the entity amounts to R993,700 000 for the current financial year marking a decrease of R45 831 000 (6%) compared to the
previous financial year. In terms the approved budget per programme, the Committee
noted the entity realizes its mandate through four programmes namely; Client
Management Services, Corporate Governance and Financial Management, Financial
Services & Operation and Corporate Services.
In the current financial year, the Committee noted that the entity will focus on the
acquisition of motor vehicles, vehicle repairs and maintenance, provision of a
comprehensive vehicle tracking solution and implementation of infrastructure project of
the turnaround strategy to ensure continuous rejuvenation of the entity.
3. STAKEHOLDER SUBMISSIONS
The stakeholders and members of the public present in the meeting submitted the
following submissions: -
Appealed for the re-introduction of Bus subsidised services in Meyerton, Midvaal and
Ekurhuleni;
Appealed for the monitoring of subsidised bus services in Mamelodi as services were not
satisfactory due to shortage of buses;
Appealed for the consideration of the re-introduction of Metrorail services between
14
Pretoria and Hammanskraal;
Appealed to the MEC to engage with North-West and National Government on the poor
services rendered by the North-West Star bus company in the area as well as the
negative impact on commuters who suffer job losses;
Appealed to the Department to consider introduction of subsidy for other modes of
transport e.g. minibus taxis;
There is a need for an engagement with PRASA Metrorail on rail challenges experienced
in the Province and proposed remedial actions;
4. CONCERNSThe Committee is concerned about:
4.1 The budget reduction in the Transport Infrastructure programme and the impact
on the EPWP jobs in line with the Honourable Premier’s SOPA February 2019
as well as on road capacity.
4.2 The lack of leadership and technical skills within the Department to provide
proper contract and project management since the inception of the Vereeniging
Intermodal Facility.
4.3 The continuous delays in the construction of K46 William Nicol and the negative
impact on the current state of the project like waste dumping and criminal
activities on the site.
4.4 The continuous delays and the negative impact on the current state of
the Vereeniging Intermodal and Sebokeng DLTC projects like vandalism as there
are no security services deployed within the project currently.
5. RECOMMENDATIONSThe Committee recommends that the Department should provide a detailed report by 30th August 2019:5.1 On the infrastructure projects that were not allocated budget by Provincial
Treasury due to lack of state of readiness, inclusive of EPWP jobs planned on
the projects and impact on road capacity.
5.2 On the proposed plan to conduct an internal skills audit to capacitate the
Department with technical skills required for the implementation of15
infrastructure projects.
5.3 On the proposed plan to resolve on the payment of monies owed by former
contractor
to sub-contractors and employees on K46.
5.4 On the proposed plan to implement the findings of the Provincial Government
investigation report on K46 William Nicol.
5.5 On the plans in place to ensure the K46 William Nicol project does not turn into a
dumping and crime site.
5.6 On the proposed maintenance plan on the currently utilised part of the K46
William Nicol Drive.
5.7 On the plans in place to prevent vandalism of property within the Vereeniging
Intermodal facility and Sebokeng DLTC & TOLAB.
6. ACKNOWLEDGEMENTSThe Committee's gratitude goes to the Honourable MEC M. Mamabolo, Acting HOD M.
Mampuru and Senior Managers and Officials from the Department of Roads and
Transport, Gautrain Management Agency and g-fleet Management for their co-operation.
Gratitude goes to Members: Ms. R. Kekana, Ms. M. Mosupyoe, Mr. P. Mabunda, Mr. F.
Nel, Mr J. Engelbrecht, and Mr M. Ledwaba for their deliberations and commitment
during the budget process.
On behalf of the Committee, the Committee's appreciation and gratitude also goes to the
following persons: Group Committee Coordinator, Mr. T. Bodibe; Researcher Mr. F.
Thaba; Committee Coordinator Mr. S. Mthiyane; Committee Administrator, Ms. H.
Mtshizana; Hansard Recorder Ms. N. Zondo; Information Officer, Mr L. Ncume; Media
Officer, Ms T. Nzuke; Public Participation Officer, Mr. B. Dhlomo and Service Officer, Ms.
S. Sithole for their devoted assistance.
7. ADOPTION After due consideration, the Roads and Transport Portfolio Committee adopted the report
on Budget Vote 9 of the Appropriation Bill for 2019/20 FY.
16
In terms of Rule 117(2)(c) read together with Rule 164, the Portfolio Committee on
Roads and Transport recommends that the report on Budget Vote 9 of the Appropriation
Bill for 2019/20 FY be adopted, taking into account the concerns and recommendations
tabled in this report.
-------------------------------------------------------Hon. D. DakileChairperson: Roads and Transport Portfolio Committee
17