fairfax bridge rehabilitation program - bridge preventive...

55
Fairfax Bridge Rehabilitation Program - Bridge Preventive Maintenance Program Creek Road Bridge - Creek Road Bridge Presented by the Team of Presented by the Team of January 29, 2014

Upload: others

Post on 05-Mar-2020

9 views

Category:

Documents


0 download

TRANSCRIPT

Fairfax Bridge Rehabilitation Program- Bridge Preventive Maintenance Program

Creek Road Bridge - Creek Road Bridge

Presented by the Team ofPresented by the Team of

January 29, 2014

Bridge Design Process

� Project team explores both repair and j p preplace options through assessments

� Options will be presented to Town Council p pwith input from community

� Selected option is submitted to Caltransto Caltrans 

� Caltrans makes funding determination

2

Project Schedules

BPMP Schedule

Creek Road Bridge Schedule

3

Tonight’s Agenda

6:40 Introduction/Background Valerie Taylor, Nelson\NygaardG T T M F fGarrett Toy, Town Manager, Fairfax

6:50 Presentation: Bridge PreventiveMaintenance Project (BPMP)

C R d

Nader Tamannaie, CaliforniaInfrastructure Consultancy (CIC)

Canyon Road Spruce Road Marin Road

20 Q & A All7:20 Q & A All

7:35 Presentation: Creek RoadBridge Rehabilitation Project

Nader Tamannaie, (CIC)

8:00 Q & A All

8:15 Group exercise, Creek RoadBridge: Preferences & Concerns

All

48:30 Summary and Next Steps Garrett Toy

Bridge Preventive MaintenanceBridge Preventive Maintenance

Bridge Preventive Maintenance program (BPMP)(BPMP)

� Bridges inspected every 2 yearsg p y y� Federal Highway Bridge Program (HBP)Under stewardship of Caltrans� Under stewardship of Caltrans

� Program fixes preventive maintenance issues not routine maintenanceissues, not routine maintenance

� NEPA/CEQA environmental studies & agency permits required when working in the creekpermits required when working in the creek

� 88.53% funded by HBP, the rest by Fairfax

6

Why Is BPMP Needed?

� The bridges are 85 years old or older� Original concrete and construction� Original concrete and construction workmanship not the best

� Bridges not well‐maintained over the yearsg y� BPMP improves safety and will prolong the bridge life and at lost cost to Fairfaxg

7

Fairfax Bridges in BPMP

8

Bridge Terminology - Topside

9

Bridge Terminology – Below Deck

10

Canyon Road Bridge

11

Canyon Road Bridge Maintenance Needs:Absent wingwallAbsent wingwall

12

Canyon Road – Partial Wingwall

13

Canyon Road – Approach Guard Rails

14

Canyon Road – Repairs Concept Plan

15

Construction Period

� Canyon Road Bridge: 3 weeks

16

Spruce Road Bridge

17

Spruce Road Bridge Maintenance needs:Cracked Deck SlabCracked Deck Slab

18

Spruce Road – Repairs Concept Plan

Spruce Road – Repairs Concept Plan

19

Construction Period

� Spruce Road Bridge: 2 weeks

20

Marin Road Bridge

21

Marin Road Bridge Maintenance Needs –Toppled wingwallToppled wingwall

22

Marin Road Bridge – Cracked wingwall & SpallsSpalls

Headwall

23

Marin Road – Repairs Concept Plan

24

Construction Period

� Marin Road Bridge: 2 weeks

25

BPMP Summary

PREVENTIVE MAINTENANCE ITEMS FOR FAIRFAX BRIDGES

Treat Bridge D k

Repair Cracks

Repair Existing

Remove Unused Utilit

Optional Actions

Install Narrow

Install Bridge

Replace Bridge in

Bridge

Deck Cracks & Spalls

Existing Wing-wall Utility

pipesNarrow Bridge Signs

Bridge Approach

Rail

Bridge in Next 10-15 Years

C M hCanyon Road

Metha-crylate Yes Two No Two Two No

Spruce Polyester Yes None Yes None One YespRoad

yConcrete Yes None Yes None One Yes

Marin Road No Yes Two No None None Maybe

26

Road

Environmental Permits Needed

AGENCY PERMIT NEEDED

US Army Corps of Engineers

(USACOE)

Clean Water Act, Section 404 Permit

(most likely a Nationwide Permit)(USACOE) (most likely a Nationwide Permit)

Regional Water Quality Control Clean Water Act, Section 401 Certification

Board (RWQCB) or Waiver

CA Department of Fish & Game

(DF&G)Lake and Streambed Alteration Agreement

27

Construction Period Recap

� Canyon Road Bridge: 3 weeks� Spruce Road Bridge: 2 weeks� Marin Road Bridge: 2 weeks� Work may be concurrent or back‐to‐back

28

Bridge Closure Requirements

BRIDGE TEMPORARY BRIDGE CLOSURE REQUIREMENTSG O G C OSU QU S

Canyon• Close bridge for 4-5 hours after 12 p.m.

Canyon Road • Allow emergency vehicles to cross the bridge

• Publicize the dates and hours well ahead of the closure

Spruce Road

• Close bridge for 3 days to place polyester concrete • Detour the traffic and post the project area for the detour

P bli i th d t d h ll h d f th l• Publicize the dates and hours well ahead of the closure

Marin Road • No bridge closure will be necessary.

29

Road

Next Steps

� Perform Field Review with Caltrans environmental staff on February 4th

� Submit the BPMP Assessment Reportp

� Request authorization for design, including environmental studies

� Obtain agency permits

Finish final design hold another workshop� Finish final design, hold another workshop, prepare bid package, advertise for construction

Request authorization for construction30

� Request authorization for construction

Questions & AnswersQuestions & Answers

C k R d B id Creek Road Bridge Seismic Retrofit

More Bridge Terminology

Girder

ColumnSubstructure

Bent

Abutment

33Footing (under column & below ground)

Bridge Terminology, Continued

34

Project Area

Project Site

35

Bridge Plan View & Adjacent Parcel Lines

36

Attributes of the Existing Bridge

Built in 1929� Built in 1929� Four‐span Concrete T‐Beam10 f t l h ld id lk� 10‐foot lanes, no shoulders, narrow sidewalks

� Articulated superstructure on concrete bents� “Shallow” foundations� N. abutment experienced washout in 2005� Marin County a seismically Active region� Bridge not a “lifeline” structure

37

Bridge Assessment & Goals

� Known to be seismically vulnerable since 1990sy� No record plans available� Test engineers took cores from concrete, used� Test engineers took cores from concrete, used GPR to locate rebar in concrete, mapped spalls

� Geotechnical engineer drilled borings to g ginvestigate the foundation soils

� CIC performed new analysis according to t it icurrent criteria

� Goal is to learn from each other what is best to do about the bridge

38

do about the bridge

How is the Bridge Seismically Vulnerable and Subject to Collapse?Subject to Collapse?

� Bridge will experience ground accelerations up to 1.35 g

� Superstructure will unseat due to seismic movement

� Columns will fail – too much bending� Bent caps will fail – too much bending� Foundations will fail – too much rotation� Bridge considered as Category 1 Bridge, subject to collapse

39

j p

Seismic Retrofit and Alternate Solutions

� Three alternative concepts plus the p pcost of retrofitting the bridge– Infill walls, enlarged footings, restrainer , g g ,cables, shear keys and seismic approach slabs

– Infill walls, waffle slabs, restrainer cables and shear keys

– Infill walls, large diameter cast‐in‐drilled‐hole (CIDH) piles, restrainer cables and shear keys

– Address preventive maintenance needs too

40

Concept Plan For Retrofit Alternate 1

41

Consider Bridge Widening for Retrofit

� Accomplish seismic retrofit by building an “anchor’ structure along the north edge

� Complement retrofit with infill walls and l l blarge CIDH piles at abutments

� Gain standard vehicular lanes, bike lanes d d d id lk l i d land standard sidewalks, more multimodal

� Width increased from 28 feet to 44 feet� Implement traffic calming measures � Address preventive maintenance needs

42

p

Retrofit through Widening Concept Plan

43

Consider Bridge Replacement as a Way to Address seismic Deficienciesto Address seismic Deficiencies

� Remove existing bridge and replace it� New bridge 44 feet wide (Increased from  28’‐2”)

� Same lanes and other geometry as widening� Two‐span box girder bridge on� Two span box girder bridge on 2‐column bent

� Opportunity for multi‐modal accommodationpp y� Opportunity for traffic calming measures

44

Bridge Replacement

45

Construction Period

� Alternate 1 (Retrofit): 6 months (one season)

� Alternate 2 (Widen): 10 months (2 seasons)

Alternate 3 (Replace): 12 months (2 seasons)� Alternate 3 (Replace): 12 months (2 seasons)

46

Traffic Handling During Construction

� Choice 1:– Keep the existing bridge open during retrofit, or widening

– For replacement, remove and replace in two stages

� Choice 2:– Close the road for any of the 3 alternates and detour the traffic

47

Construction Logistics - Detour

48

Alternate Comparisons - Advantages

ALTERNATIVECOSTS

(CONSTRUCTION + ADVANTAGESALTERNATIVE (CONSTRUCTION + Lifecycle & Capital)

ADVANTAGES

1CConstruction: $1.21 m Least amount of creek disturbance

Short one season project1C

(Retrofit only)Lifecycle: 1.97 m Total: $3.18 m

Short one-season project No falsework required Least expensive alternate

Standard bike lanes and sidewalks2

(Retrofit with Widening)

Construction: 2.58 mLifecycle: 1.63 m

Total:$4.21 m

Standard bike lanes and sidewalks A full one-season project No falsework required Multimodal + Conducive to Traffic Calming Multimodal + Conducive to Traffic Calming

3Construction: 3.05 m

Lifecycle: 0 74 m

Standard bike lanes and sidewalks 75 -100 years of life Low maintenance

49

(Replace Bridge)Lifecycle: 0.74 m

Total:$3.79 million Aesthetically pleasing Lowest lifecycle cost Multimodal + Conducive to Traffic Calming

Alternate Comparisons - Disadvantages

ALTERNATIVE DISADVANTAGES

1C

Limited bridge life, 30‐40 years & regular maintenance needed Bridge and sidewalks remain narrow Aesthetically neutral

(Retrofit only) Aesthetically neutral Large CIDH pile installation messy for a couple of weeks Lifecycle and future capital costs (nearly $2 m) paid by Fairfax

2(Retrofit with

Widening)

Existing bridge portion will have limited life (30‐40 year), need moderate maintenance, & will need to be replaced in the future

Most expensive alternateWidening) Lifecycle and future capital costs (nearly $1.6 m) paid by Fairfax

3 Bridge foundation work in creek

M i f l k i k

50

3(Replace Bridge)

May require falsework in creek  Total cost 20% more than retrofit, but 11% less than widening Likely two‐season construction

Retrofit vs. Replacement Decision

� Upfront as well as lifecycle costs p y(the latter on Fairfax)

� Remaining life of existing bridge vs. new bridgeg g g g

� Amenities such as bike lanes and ADA‐compliant sidewalksp

� Bridge aestheticsCIC recommends replacement� CIC recommends replacement

51

Next Steps

� Decide which alternate to go forward� Decide which alternate to go forward with tonight

� Town Council to consider the decision on the February 5th Council meeting

� Perform Field Review with Caltrans on Feb. 11th

� Submit Seismic Retrofit Strategy Report to Caltrans

� Caltrans to approve Seismic Retrofit Strategy Report, its recommendations and costs

52

Process Approval and Bridge Funding

NEPA/CEQA environmental studies and� NEPA/CEQA environmental studies and agency permits required

� Apply to Caltrans for design & environmental� Apply to Caltrans for design & environmental funds

� Design & environmental 100% federally funded� Construction 88.5% federal, 11.5% State, 0% Fairfax

� Same cost‐sharing will apply to replacement� Use it or lose it funding

53

Questions & AnswersQuestions & Answers

Thank you for coming!Thank you for coming!

For more information ‐email:  [email protected]

b it htt //f i f b idwebsite:  http://fairfaxbridges.comphone:  415‐284‐1544 (Daniele or Valerie)