This is a final project I did in my estimating class while attending The Ohio State University. The project being estimated was the Suburban Steel Maintenance Building in Gahanna, OH. I logged 43 hours on this project. No software was used, and all estimates were done by hand. Of approximately 20 bids in the class, my group was 1 of 3 responsive bidders.

TRANSCRIPT

Page 1: Estimating Project

SSMB 298-3450-2012Suburban Steel Maintenance BuildingGahanna, OH

[GBS CONSTRUCTION INC.]

Page 2: Estimating Project

GBS Construction INC.• Kirk Swinehart- Spring 2014• Ryan Blessing- Spring 2014• Kyle Garrison- Autumn 2013

[GBS CONSTRUCTION INC.]

Page 3: Estimating Project

Project Overview[GBS CONSTRUCTION INC.]

Page 4: Estimating Project

Panel vs. CMU Wall[GBS CONSTRUCTION INC.] Task 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

Block (12')+ Grout+ Reinforcement

Bond Beam + Grout

Block (12')+ Grout+ Reinforcement

Bond Beam+Grout

Cleaning

Painting

Task 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25Hanging Panels

Painting

CMU Wall Ghant Chart

PC Panel Wall Ghant Chart

Cost Comparison

•CMU Wall-$185,307.21(does not include footings)

•PC Wall Panels-$ 129,263.77(does not include footings)

Page 5: Estimating Project

Walls• Material-$126,930.62

• Labor-$2,677.49

• Equipment-$14.33

• 19.75%

[GBS CONSTRUCTION INC.]

Page 6: Estimating Project

Floor• Material-$17,740.52

• Labor-$5,996.76

• Equipment-1,143.17

• 3.79%

[GBS CONSTRUCTION INC.]

Page 7: Estimating Project

Roof• Material-$72,280.64

• Labor-$17,476.58

• Equipment-$3,185.24

• 14.16%

[GBS CONSTRUCTION INC.]

Page 8: Estimating Project

Thermal• Material-$28,608.88

• Labor-$14,438.13

• Equipment-$795.74

• 6.68%

[GBS CONSTRUCTION INC.]

Page 9: Estimating Project

HVAC• Material-$17,858.21

• Labor-$35,362.88

• Equipment-N/A

• 8.43%

[GBS CONSTRUCTION INC.]

Page 10: Estimating Project

Gas and Compressed AirGas

•Material-$1,879.55•Labor-$1,827.15•Equipment-N/A•.55%

Compressed Air •Material-$4,445.30•Labor-$2,486.60•Equipment-N/A•1.06%

[GBS CONSTRUCTION INC.]

Page 11: Estimating Project

Water and Sanitary[GBS CONSTRUCTION INC.]

Water•Material-$2,186•Labor-$1,349.35•Equipment-N/A•.54%

Sanitary•Material-$32,915•Labor-$6,434.20•Equipment-N/A•6.00%

Page 12: Estimating Project

Fire Suppression • Material-$210.00

• Labor-N/A

• Equipment-N/A

• .03%

[GBS CONSTRUCTION INC.]

Page 13: Estimating Project

Electrical• Material-$41,408.08

• Labor-$24,092.24

• Equipment-N/A

• 9.98%

[GBS CONSTRUCTION INC.]

Page 14: Estimating Project

Other Costs • Material-$126,087.86

• Labor-$37,772.63

• Equipment-$8,966.47

• 26.33%

[GBS CONSTRUCTION INC.]

Page 15: Estimating Project

Project Total[GBS CONSTRUCTION INC.]

Total Including O&P-$766,331.77

Project Duration Estimate- 9 months