estimating project
DESCRIPTION
This is a final project I did in my estimating class while attending The Ohio State University. The project being estimated was the Suburban Steel Maintenance Building in Gahanna, OH. I logged 43 hours on this project. No software was used, and all estimates were done by hand. Of approximately 20 bids in the class, my group was 1 of 3 responsive bidders.TRANSCRIPT
SSMB 298-3450-2012Suburban Steel Maintenance BuildingGahanna, OH
[GBS CONSTRUCTION INC.]
GBS Construction INC.• Kirk Swinehart- Spring 2014• Ryan Blessing- Spring 2014• Kyle Garrison- Autumn 2013
[GBS CONSTRUCTION INC.]
Project Overview[GBS CONSTRUCTION INC.]
Panel vs. CMU Wall[GBS CONSTRUCTION INC.] Task 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Block (12')+ Grout+ Reinforcement
Bond Beam + Grout
Block (12')+ Grout+ Reinforcement
Bond Beam+Grout
Cleaning
Painting
Task 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25Hanging Panels
Painting
CMU Wall Ghant Chart
PC Panel Wall Ghant Chart
Cost Comparison
•CMU Wall-$185,307.21(does not include footings)
•PC Wall Panels-$ 129,263.77(does not include footings)
Walls• Material-$126,930.62
• Labor-$2,677.49
• Equipment-$14.33
• 19.75%
[GBS CONSTRUCTION INC.]
Floor• Material-$17,740.52
• Labor-$5,996.76
• Equipment-1,143.17
• 3.79%
[GBS CONSTRUCTION INC.]
Roof• Material-$72,280.64
• Labor-$17,476.58
• Equipment-$3,185.24
• 14.16%
[GBS CONSTRUCTION INC.]
Thermal• Material-$28,608.88
• Labor-$14,438.13
• Equipment-$795.74
• 6.68%
[GBS CONSTRUCTION INC.]
HVAC• Material-$17,858.21
• Labor-$35,362.88
• Equipment-N/A
• 8.43%
[GBS CONSTRUCTION INC.]
Gas and Compressed AirGas
•Material-$1,879.55•Labor-$1,827.15•Equipment-N/A•.55%
Compressed Air •Material-$4,445.30•Labor-$2,486.60•Equipment-N/A•1.06%
[GBS CONSTRUCTION INC.]
Water and Sanitary[GBS CONSTRUCTION INC.]
Water•Material-$2,186•Labor-$1,349.35•Equipment-N/A•.54%
Sanitary•Material-$32,915•Labor-$6,434.20•Equipment-N/A•6.00%
Fire Suppression • Material-$210.00
• Labor-N/A
• Equipment-N/A
• .03%
[GBS CONSTRUCTION INC.]
Electrical• Material-$41,408.08
• Labor-$24,092.24
• Equipment-N/A
• 9.98%
[GBS CONSTRUCTION INC.]
Other Costs • Material-$126,087.86
• Labor-$37,772.63
• Equipment-$8,966.47
• 26.33%
[GBS CONSTRUCTION INC.]
Project Total[GBS CONSTRUCTION INC.]
Total Including O&P-$766,331.77
Project Duration Estimate- 9 months