capital project cost estimating checklist
TRANSCRIPT
Capital Project Cost Estimating Checklist
Purpose:
This guide presents a high level perspective of the capital project estimating and budgeting
process and it consolidates and summarizes a wide range of King County and industry financial
and management practices that should be considered in order to prepare consistent capital project
cost estimates. It does not impose new requirements, constitute official policy nor instruct staff in
how to prepare capital project cost estimates.
Definition of a Capital Project Cost Estimate
A capital project cost estimate (herein referred to as “estimate”) is the forecasted cost associated
with labor (staff, consultant, management and construction), acquisitions, material, and
equipment that are required to complete a project within a specified schedule according to a
scope of work defined by charter and design documents.
Importance of Project Budgets and Cost Estimates
The process of planning, estimating and control is an integral part of a capital project and a key
to its success. The reliability of capital project cost estimates at every stage of the project
delivery process is vital for responsible project, program and fiscal management.
King County capital projects policies require formal budget cost estimates be presented to
sponsors/management for review no less than three times during their lifecycle: planning,
initiation and baseline. In addition to these specific budget presentation and approval
requirements, budget projections are generally updated at 60%, 90% and 100% design levels to
ensure the project can still be completed within authorized funding limits and to notify finance
departments of pending cash flow and budget requirements. Each successive estimate builds
upon the known scope, degree of project definition, and decreasing unknowns to more accurately
predict the expected cost. The document entitled Key Deliverables by Phase Checklist (a partial
excerpt of the applicable cost items is shown below) demonstrates the relationship between a
project’s timeline, estimate deliverables, and level of expected accuracy.
Figure 1 Excerpt from Key Deliverables by Phase Checklist
I. Planning Phase V. Close-Out Phase
Line
No.
List of Key Deliverables by Phase Re
qu
ire
d fo
r
Ba
se
lin
e A
pp
rov
al
Planning / Concept Alternatives Analysis Alternative Selected /
Design at 30% - 40%
Project Baseline
Scope / Schedule / BudgetDesign Refinements
Ad for Construction
Start of Construction or
InstallationSubstantial Completion /
Beneficial Use
Final Acceptance or End of
Construction / Installation Close-Out
11 Life Cycle Cost Analysis Draft Updated Final
14 Project Budget Draft Updated Proposed Baseline BaselineFinal Performance
Report
15 Costs Estimate (phase level) ROM Draft Updated Updated Final
16Phase and Contract Level Annual
Cash Flow ForecastDraft Updated Updated Final
Track, Monitor, and Refine
Track, Monitor and Refine
Track, Monitor and Report Performance
III. Final Design IV. Implementation PhaseII. Preliminary Design Phase
Scalable Cost Estimating
Scalability in cost estimating recognizes that projects of varying sizes and complexity require
modifying project management tools and techniques to manage project risks, and predict project
costs. Selection of an estimating method and process is dependent upon many factors including
the purpose of the estimate, the time available to produce the estimate, the project’s
characteristics, level of complexity and size, the amount of project documentation available, and
the estimating resources available.
A Project Cost Estimating Checklist illustrating potential cost elements during a project’s
lifecycle is attached for reference and guidance. After the Implementing Agency (IA) has
determined the applicable level of project complexity, use the checklist to identify the required
deliverables and sub deliverables, estimate their cost and then distribute those costs by phase.
The Project Cost Estimating Checklist is shown below.
:
Cost Estimate Types and Accuracy Ranges
Estimate types are defined by the level of design that was available to define the scope of work.
The accuracy of an estimate varies depending on the estimating method used, the amount of
project information, and the amount of time for estimate preparation. The Association of the
Advancement of Cost Engineering International (AACEI) classifies estimates into five different
class types (AACE recommended practice no. 18R-97). AACE’s cost estimate classification
matrix correlates the primary estimating characteristic of a project and the degree of project
definition, showing secondary characteristics that could occur during a project. The matrix
shown in Table 1 below summarizes how King County capital phases relate to AACE estimate
classes, degree of project definition, estimate use, and accuracy range and preparation effort.
Table 1 Estimating Type and Expected Accuracy Range
King County’s Capital Project Management Work Group (CPMWG) and King County
Ordinance 16764 recommend the AACE cost estimate classification matrix serve as the
guideline for determining expected accuracy ranges. King County Ordinance 16764 requires
high-risk capital projects seek appropriation approval by phase, and establishes standardized
requirements for capital project reporting and cost estimating. The ordinance states that prior to
establishing a baseline, high risk projects with a range of potential project costs shall budget the
highest cost in the range.
Methods of Estimating
There are three commonly used estimating methods. The determination of which method to use
is dependent upon factors such as project characteristics, level of complexity, total project
budget, and maturity level of project definition and deliverables.
1. Cost Curves – This method uses historical cost curves, scale-up or scale down factors,
and cost ratios. Cost curve estimates are typically used to produce conceptual or
feasibility estimates based on a minimal amount of information with a short estimate
preparation time and few estimating resources.
2. Conceptual Parametric This method uses parametric factors to estimate elements of a
project. Parametric factors are typically used when preliminary layouts, flow sheets, and
equipment lists are available to calculate cost items that apply to a reference cost source.
Its accuracy is based on the selection of comparable factors and an analogous cost
reference. Parametric estimates are typically used to produce pre-design or early design
development estimates based on preliminary design information with a short estimate
preparation time and minimal estimating resource availability.
3. Detailed Unit Cost – This method is based on a detailed quantity take-off using defined
engineering data. This data may include detailed plans, process flow diagrams, electrical
diagrams, equipment data sheets, structural sketches/details, soil data, and specifications.
Equipment and unit costs are typically based on vendor quotations. This is the most
comprehensive estimating method and is used to produce definitive estimates during final
design phases and for bidding. Accordingly, the detailed unit cost method requires the
longest estimate preparation time and the greatest quantity of estimating resources.
Developing Capital Project Budgets and Estimates
For consistency, uniformity, and tracking/ reporting purposes, project costs are usually organized
into three major categories: Construction, Non-Construction and Project Contingency.
Construction costs are often referred to as implementation costs. Non-construction costs are also
referred to as soft capital or allied. The construction and non-construction categories are further
broken down for reporting and management purposes into sub-categories that group similar costs
together by topic. Figure 3 below is an example of a summary level project cost by category
report:
Figure 3 Sample Cost Report (from King County PRISM)
2013 ANNUAL BUDGET/FORECAST
Dec (open) 2013Current Forecast%Spent
Difference
Spent %Spent
Difference
ANNUAL ACTUALS
YTD
Spent YTDYTD
Spent LTD
LTD
%Spent
LTD
%Spent
Dec (open) 2013Dec (open) 2013
Current Forecast
Cost Report for 2003-01 Garrison Creek Relief - Kent Planning Zone
LIFETIME ACTUALS & BUDGET/FORECAST ESCALATED
2013Dec % Diff
CONSTRUCTION
Construction Contracts
Owner Furnished Equipment
Outside Agency Construction
Other Capital Charges
NON-CONSTRUCTION
Engineering Services
Planning & Management Services
Permitting & Other Agency Support
Right-of-Way
Misc. Service & Materials
Non-WTD Support
WTD Staff Labor
Indirect Burden
PROJECT RESERVE
Project Contingency
SETTLEMENTS, REIMBURSEMENTS, & LDs
Settlements, Reimbursements & LDs
Uncommitted/Adjustment
PROJECT TOTAL
Revenues
TOTAL WITH REVENUES
12/20/2013 | Page 1 of 1
Construction Costs
Construction or implementation costs represent any tangible cost that contributes to the physical
cost of constructing the asset or project. Such costs are generally not directly controllable by the
owner. They can be estimated, quantified, and determined with relative certainty. However,
because of public procurement requirements and market conditions, the actual costs have a
degree of uncertainty.
Examples of such physical costs include construction contracts and change orders, owner
procured equipment, design contingency, sales tax, utility work performed by non-County
agencies, work directly implemented by county forces and certain miscellaneous costs such as
utilities and chemicals used during testing and startup. A brief description of each category and
subcategory is included below:
Construction
Construction Contracts
Construction Contract(s) – The final expected cost of public works construction
contract(s) that will implement construction. Revised Code of Washington (RCW)
39.04.010 http://apps.leg.wa.gov/RCW/default.aspx?cite=39.04.010 , "Public work"
means all work, construction, alteration, repair, or improvement other than ordinary
maintenance, executed at the cost of the state or of any municipality, or which is by
law a lien or charge on any property therein. Many King County construction
contracts are advertised and awarded through the low bid or small work roster
methods. Design Build (DB), General Contractor/Construction Manager (GCCM),
Job order Contracting (JOC), Unit Price (UP), small works roster, work order as well
as other methods of contracting are also utilized.
Construction Contracts Mitigation – The cost of any tangible mitigation construction
that is not co-mingled into an above general construction contract.
Construction Design Uncertainty Factor – See contingency section below
Construction Contract Change Order Contingency – See contingency section below
Retail Sales Tax – Unless specifically exempted, retail sales tax must be collected on
behalf of all public works contracts. Retail sales tax is generally excluded from the
contract price per the bid documents. Retail sales tax is paid to contractors based
upon the rate of the jurisdiction where the work is physically performed.
Owner Furnished Equipment
Procurement Contracts – Occasionally, situations arise where a capital agency will
choose to furnish material or equipment to a contractor. This generally results if
specialty material and equipment have long purchase, fabrication and delivery cycles
that would jeopardize completion schedules if procured by a contractor.
Outside Agency Construction
Utility Relocations – Many agencies do not allow outside agencies to work on their
utilities. Outside agency construction includes the cost of contracts with agencies
outside of King County that perform utility relocation work related to a construction
project.
Other Capital Charges
Direct Implementation – Would include the cost of public works implementation
performed by a Division’s own labor forces (where allowable by law).
KC Direct Implementation – Would include the cost of public works implementation
performed by other King County labor forces (where allowable by law).
Miscellaneous Capital Costs – Includes funds spent by a Division due only to
construction and that should be capitalized. Examples include utilities and chemicals
necessary during testing and startup, owner controlled insurance or direct art
purchases (not 1% for the arts).
An example of the summary sheet for a capital construction estimate is shown below in figure 4.
Figure 4 Example Total Cost of Construction Estimate
DESCRIPTION
ConstructionEstimateSummarized
byMajorWBSTopic % AMOUNT % AMOUNT % AMOUNT % AMOUNT % AMOUNT % AMOUNT
Demolition 2.3% 25,000.00$ 2.1% 25,000.00$ 1.8% 25,000.00$ 2.3% 30,000.00$ 2.3% 30,000.00$
Utilities 1.1% 12,000.00$ 1.0% 12,000.00$ 1.5% 20,000.00$ 1.5% 20,000.00$ 1.7% 22,000.00$
PumpStationModification 15.9% 175,000.00$ 14.6% 175,000.00$ 14.8% 200,000.00$ 15.3% 200,000.00$ 16.2% 210,000.00$
StorageTank 36.4% 400,000.00$ 41.7% 500,000.00$ 53.6% 725,000.00$ 55.4% 725,000.00$ 56.9% 740,000.00$
ConveyanceLines 22.7% 250,000.00$ 25.0% 300,000.00$ 18.5% 250,000.00$ 19.1% 250,000.00$ 18.8% 245,000.00$
Street/SidewalkRestoration 1.8% 20,000.00$ 1.7% 20,000.00$ 1.5% 20,000.00$ 1.5% 20,000.00$ 2.3% 30,000.00$
Landscaping 1.6% 18,000.00$ 1.5% 18,000.00$ 1.7% 23,000.00$ 1.8% 23,000.00$ 1.8% 23,000.00$
Estimator'sAllowance 18.2% 200,000.00$ 12.5% 150,000.00$ 6.7% 90,000.00$ 3.1% 40,000.00$ -$
SubtotalDirectConstructionCosts 100.0% 1,100,000.00$ 100.0% 1,200,000.00$ 100.0% 1,353,000.00$ 100.0% 1,308,000.00$ 100.0% 1,300,000.00$ -$
GeneralConditions 7.0% 77,000.00$ 7.0% 84,000.00$ 7.0% 94,710.00$ 7.0% 91,560.00$ 7.0% 91,000.00$ 0.0% -$
Subtotalw/GC's 1,177,000.00$ 1,284,000.00$ 1,447,710.00$ 1,399,560.00$ 1,391,000.00$ -$
Overhead 8.0% 94,160.00$ 8.0% 102,720.00$ 8.0% 115,816.80$ 8.0% 111,964.80$ 8.0% 111,280.00$ 0.0% -$
Profit 4.0% 50,846.40$ 4.0% 55,468.80$ 4.0% 62,541.07$ 4.0% 60,460.99$ 4.0% 60,091.20$ 0.0% -$
Subtotalw/GC's,OH&P 1,322,006.40$ 1,442,188.80$ 1,626,067.87$ 1,571,985.79$ 1,562,371.20$ -$
MarketConditionsAdjustment 5.0% 66,100.32$ 3.0% 43,265.66$ 2.0% 32,521.36$ 1.0% 15,719.86$ 0.0% -$ 0.0% -$
DesignContingency 25.0% 330,501.60$ 20.0% 288,437.76$ 15.0% 243,910.18$ 10.0% 157,198.58$ 0.0% -$ 0.0% -$
Escalation 4.0% 66,242.04$ 4.0% 69,373.48$ 3.0% 56,099.34$ 2.0% 34,583.69$ 1.0% 15,623.71$ 0.0% -$
TotalContractEstimateatBid 1,784,850.36$ 1,843,265.70$ 1,958,598.75$ 1,779,487.92$ 1,577,994.91$ -$
ConstructionChangeOrderContingency 10.0% 178,485.04$ 10.0% 184,326.57$ 10.0% 195,859.88$ 10.0% 177,948.79$ 10.0% 157,799.49$ 10.0% -$
StateRetailSalesTax 9.5% 186,516.86$ 9.5% 192,621.27$ 9.5% 204,673.57$ 9.5% 185,956.49$ 9.5% 164,900.47$ 9.5% -$
TotalContractEstimatewithCont./Tax 2,149,852.26$ 2,220,213.54$ 2,359,132.20$ 2,143,393.20$ 1,900,694.87$ -$
OwnerFurnishedEquipment
OutsideAgencyConstruction
OtherCapitalCharges
TotalCostofConstrution 2,149,852.26$ 2,220,213.54$ 2,359,132.20$ 2,143,393.20$ 1,900,694.87$ -$
Bid(Sample)
Construction
InitialEstimate(Class5)
ExampleTotalCostofConstructionEstimate
Gate2(Class4) Baseline/Gate3(Class3) 60%(Class2) 90%orFinal100%(Class1)
Non-Construction or Allied Costs
Non-construction, or allied costs represent the costs associated with planning, design and
coordination of the asset or construction project, and are often budgeted as a percent of
construction. Such costs are generally thought to be controllable via the owner’s assertion of
scope, quality and budget during the planning and design process. Examples of such costs
include engineering costs, planning and management costs including construction management,
the cost of permits and doing business with other local agencies, miscellaneous services and
materials and all non-construction county labor. Land and easement acquisition costs are also
included with the non-construction, soft or allied cost category. However, land and easement
costs are generally excluded from measures such as allied cost.
Non-Construction
External Engineering Services
Engineering Design Services – Engineering design services related to building new,
upgrading or rehabilitating existing facilities.
QA/QC Services – Also known as peer review or value engineering services. Services
for evaluating a project’s functions and ways to achieve the functions at the lowest
total cost.
Engineering Services During Construction – Engineering services performed during
implementation (phase 4 construction). Services include design consultation and
review of submittals, RFI’s and change requests.
External Planning and Management Services
Planning or Study Services – External consulting, professional or engineering
services used during planning (phase 1) aimed at determining the need or direction of
a project or program.
Program/Project Management Services – External consulting or professional
contracts used to assist with program and/or project management.
Construction Management Services – External construction management services
including inspection, resident engineering, cost and schedule support, office support,
project control services, safety and quality management and monitoring and
coordinating daily construction activities.
Other Consulting Services – Specialized services such as information technology,
communications, marketing, etc.
Other Technical Services – Scientific services including pollution monitoring, seismic
survey data analysis, chemical analysis, etc.
Outside Legal Services – Non-King County legal representation and advice
Testing Services – Testing services during construction including concrete, soils,
welding, materials, etc.
Permitting and Outside Agency Support
Permits and Licenses – Fees assessed by federal, state or local governments for
various permits.
Local Agency Project Costs – Amounts paid to agencies for services provided
including MOA’s, MOU’s, etc.
1% for Art Payment – Required by County ordinance on certain capital projects.
Generally based upon the value of above ground structures (many departments have
exact calculation requirements based upon their particular capital business).
Right-of-Way
Land Purchases/Easements – Cost of land acquisitions, temporary or permanent
easements, right of way acquisitions and relocating occupants and their personal
property.
Local Agency Mitigation – Payments made directly to local agencies, jurisdictions,
etc. when the local entity assumes for the mitigation obligation.
Miscellaneous Services and Materials
Miscellaneous Service and Materials - Such as office and transportation costs, small
equipment, supplies and safety costs, professional development and travel costs,
printing, courier and media services and misc. services and premiums.
King County Staff Labor
Division Staff Labor – County work forces which would include all staff labor except
where staff are engaged in the physical construction of a capital asset.
Indirect Burden associated with Division Staff Labor as defined above except where
staff are engaged in the physical construction of a capital asset.
Contingency Definition and Applications
Contingency is an integral part of the risk management process and is a necessary part of the
capital project budget. Contingency provides a means to mitigate the risk of known or
predictable events that are inherent in capital projects. Contingency levels should be based upon
identified risks, is controlled by the project manager. Contingency is part of the capital project
budget, and should be expected to be spent when risks materialize.
Note: Contingency, no matter its form, is only intended to cover items that fall within the original
project scope of work. The addition of any work beyond the chartered scope or for any work not
included in the initial budget must be approved by management before it can be incorporated
into a project. If approved, the addition of out of scope work or non-funded work would be
grounds for adjusting the scope, rebaselining and would be accompanied by additional budget
and relative contingency.
If potential risks and uncertainties do not materialize as a project progresses, contingency should
be reduced accordingly prior to proceeding to the next phase (requirement is also referenced in
Ordinance 16764).
Note: Contingency, accuracy ranges and range estimating do not mean the same thing and are
not interchangeable.
-Contingency is a provision in the project budget used to mitigate the risk of uncertainties or
unforeseeable events that may occur when executing the scope of a project.
-Expected accuracy range is an indication of the degree to which the final cost outcome for a
given project may vary from the single point estimated cost.
-Range estimating is based upon probabilistic analysis, statistical distributions, and Monte
Carlo modeling and is used to determine the amount of contingency to be added to a
particular estimate to achieve a desired level of confidence that the project will not come
in over that cost.
Within most capital projects, there are three distinct applications of contingency;
construction/design, construction change order and project. Each will be discussed below:
Construction/Design Contingencies
There are several allowances or contingencies that are used to determine the total cost of
construction. Most capital projects use the estimated cost of construction as the basis for
developing the overall project budget. However, during the early stages of planning and design,
many of the project requirements are not defined or available at the time the initial construction
estimate must be prepared, reported or updated. Therefore, allowances or contingencies are
incorporated into the estimates as a means of accounting for the costs associated with lack of
definition and known risks. Known risks, often referred to as known unknowns, encompass
events that are predictable, yet difficult to identify in advance. See the change order section for
an example.
Construction Estimator Allowances
This allowance is familiar to most and is included within the construction estimate by the
estimator. Regardless of how little or how much information is available at the time an estimate
is prepared, the estimator must base the estimate upon a charter document, scope information,
vision, or other available information. Without the benefit of detailed plans and specification, the
estimator generally includes allowances as a means of incorporating costs into the estimate for
items described in the scope of work but not yet sufficiently defined. An example would be an
allowance for mechanical equipment equal to 10% of a structure’s cost. This type of allowance is
not intended to cover general scope uncertainty, changes to the scope or to speculate where the
project may head as design progresses.
Construction/Design Contingency
This is the first true contingency that should be incorporated into the total cost of construction
covers design uncertainty. As a project’s scope solidifies and design progresses, changes in how
to accomplish the scope are likely to occur. Design contingency is used to accommodate minor
changes in the design concept, design detail, etc. that ultimately impact the cost of construction.
As with all contingencies, design uncertainty contingency should only be used to cover items
associated with accomplishing the original scope of work. It should be expected that the
contingency will be “spent” as project moves through the design process. Contingency amounts
will depend upon the level of design completion, criteria, and confidence, and should diminish as
the design progresses or is found not needed. Usage or drawdown of the design contingency
should be tracked on a change log.
Pricing or Market Factor Adjustment
When implementation or construction is not scheduled to start for a significant period of time, a
pricing uncertainty or market condition adjustment factor should also be considered. Pricing
uncertainty is not the same as escalation that covers inflation or the future cost of money. Rather,
pricing uncertainty covers market factors that are unique to the construction industry associated
with pricing of future market conditions, labor, materials and equipment for items within the
estimate. This is generally a low figure (less than 5%) as determined by the estimator.
Note: The goal of the construction estimate at any stage of a project is to reflect the expected
total cost of construction. Therefore, it is extremely important that any construction costs
related to insufficient design or pricing uncertainty be included as specific elements and in the
total cost of construction, not in project contingency. Placing such costs in project contingency
not only masks the expected cost of construction but also proportionally underestimates the
associated non-construction costs and overall project costs.
Construction Change Order Contingency
Construction change order contingency – Historical data and experience indicates that once a
construction contract is underway, unforeseen events will occur that will require changes to the
contractual scope or work. Because identifying these changes in advance is not possible, change
order contingency is used to cover the cost of these expected, yet unknown field conditions,
contractor requested change orders, owner requested change proposals or any other changes to
the original contract amount. Paragraph 7.1.2 of CON 7-10-2, (AEP) Project Control Officer
http://www.kingcounty.gov/operations/policies/aep/contractingaep/con7102aep.aspx states “In
applying this P&P, the CONTRACT contingency shall be assumed to be 10% of the initial
CONTRACT value unless otherwise specified by the IA and documented in the project file”.
Therefore, construction budgets should include a 10% contingency to cover the expected costs of
potential change orders. Note that retail sales tax is calculated on both the base and change order
costs.
Note: There are several capital project scenarios that due not lend themselves to the prescribed
10% contingency rule. First, when providing a contractor with owner procured material or
equipment, the value of the change order contingency should amount to 10% of the combined
sum of the contract award amount and the owner furnished material and equipment amount.
Second, construction contracts involving refurbishment, rehabilitation or remodeling of existing
facilities generally require greater than 10% change order contingency as unexpected and
undocumented conditions are often encountered. Usage or drawdown of the construction change
order allowance will be tracked through a change order log. Seek management approval for the
percentages greater or less than 10%.
Project Contingency
Project Contingency is an allowance or safety net in the project budget to accommodate elements
of risk, degree of uncertainty, lack of design definition, desired confidence levels for meeting
initial or baseline requirements directly attributable to the overall scope of work, or the
possibility that execution may not go as expected.
Project contingency is not intended to cover items outside the scope of the project. Project
contingency is also not intended to cover any items known to be within the scope of the project
that were not priced/funded within the estimate due to lack of sufficient design definition or
progress, or due to pricing difficulty. As with all contingencies, project contingency decreases at
each phase as project uncertainty decreases. Need to beware of double counting contingency.
Note: King County does not anticipate, budget or allocate funds in advance for claims that may
or may not occur. Therefore, projects should not reserve funds to cover construction, design,
legal, staff or other costs in anticipation that at some point, a claim may be filed against a
project. Should a claim ever be submitted against a project, seek guidance from management
and the Prosecuting Attorney’s Office (PAO).
Escalation
Escalation is the change in the cost of goods or services over a period of time. Because the
average capital project is many years in duration, the portion of a project’s cost attributable to
escalation can be substantial. In order to ensure that escalation is measurable and calculated
consistently within capital projects. Highlights of escalation rules and methodologies are below:
Project budgets and forecasts should be developed in current year dollars and then
escalated.
Project budgets are generally presented in future year dollars to decision makers and
stakeholders and in annual and long-term budget reports.
Escalating project or construction costs to their mid-point is common practice and
done by many estimators and consultants. Doing so will factor for escalation twice.
Seek assistance from respective IA Finance Department when determining rate.
Escalation is compounded annually.
Escalation is applied to out-year dollars based upon a project’s annual cash flow
forecast.
Funds already spent are carried forward at face value and not escalated.
For consulting and construction contracts, escalation ceases upon Notice-to-Proceed
(NTP) as forecasted costs are replaced with negotiated/bid values.
Rebaselining
King County’s baselined capital projects may occasionally be faced with circumstances and
events where maintaining the baseline is no longer a useful performance measure for managing
the project. The purpose of rebaselining is to objectively establish a new baseline and to provide
the necessary course corrections to the scope, schedule and/or budget for a project. The results of
rebaselining will yield more accurate and realistic project information to be used as a basis for
variance reporting and performance measurement for the remainder of the project. Rebaselining
will improve the level of information for evaluating project delivery processes, and improve the
accuracy of project status information communicated to the Executive or the Council.
A project should only be considered for rebaselining when the scope, schedule, or budget have
exceeded the allowable threshold and can’t be recovered by applying standard project
management tools and techniques. In no event will a project be rebaselined without prior
written approval by the IA’s Division Director. Rebaselining should not be used to compensate
for poor project management and/or lack of sufficient project control oversight.
The complete rebaselining policy, authored by the Capital Project Management Work Group, is
contained in and authorized by King County Executive Order CIP 8-1 (AEO) (see link below).
Existing King County Estimating Governance (2013)
Known King County codes, legislation and executive orders, policies and procedures that
directly or indirectly influence capital project estimating are as follows:
King County Code
Title 4. Revenue and Financial Regulation
http://www.kingcounty.gov/council/legislation/kc_code.aspx
King County Legislation
Ordinance 16764 – Mandatory Phased Appropriation (formerly referred to as High Risk)
This ordinance states that any capital project over $10 million automatically goes into a pool
of large projects from which certain projects will be picked for addition oversight. The
ordinance defines the criteria providing for appropriation by phases for selected capital
projects and establishes standardized requirements for capital project reporting and cost-
estimating.
King County Executive Orders, Policies and Procedures
CON – Contracting Procurement and Sale Management
(Policies/procedures relating to the procurement, contracting and sale of materials and
services.)
CON 7-7-2 (AEP), Procurement for Capital Projects
http://www.kingcounty.gov/operations/policies/aep/contractingaep/con772aep.aspx
CON 7-8-3 (AEP), Change Order/Amendment Administration
http://www.kingcounty.gov/operations/policies/aep/contractingaep/con783aep.aspx
CIP – Capital Projects
CIP 8-1 (AEO), Development and Implementation of Consistent, Comprehensive
Standards for Reporting, Management, and Performance Measurement of Capital
Projects
http://www.kingcounty.gov/operations/policies/executive/cipaeo/cip81aeo.aspx
Capital Project Management Work Group Phase 1, Standards / Key Deliverables
Key Project Deliverable by Phase Flow Chart
Key Project Deliverable by Phase Checklist
CIP 8-2 (AEO), Improving Project Management Processes and Functions, Investing in
Training and Staff Development, and Assuring Accountability and Transparency on
Capital Projects in KC
http://www.kingcounty.gov/operations/policies/executive/cipaeo/cip82aeo.aspx
Capital Project Management Work Group Phase 2, Scalable Project Management Tools
Project and/or Program Characteristics
Acceptable Project Management Tools
King County Baseline (See CPMWG1 April 30, 2010 Work Plan Deliverable for definition)
King County Pre-baselining (See CPMWG2 Task for definition)
King County Rebaselining Guidelines (See CPMWG1 Nov. 15, 2011 document for definition)
AACE International, Inc.
AACE is recognized as an industry leading association that serves cost management
professionals in the disciplines of project management, estimating, risk management, and claims.
AACE’s recommended practice, the Cost Estimate Classification System provides guidelines for
applying the general principles of estimate classification to project cost estimates. KC Ordinance
16764 states that the level of detail incorporated within each estimate shall be commensurate
with the information available at each phase, and shall be consistent with the AACE’s cost
estimate classification system.