estimating project
TRANSCRIPT
Close Enough Construction
Inc.
Project number SSMB298-3450-2012
Close Enough Construction Inc.
• Ted Srokowski Winter 2013
• Gabriel Page Winter 2013
• Mitch Kneeskern Spring 2014
Close Enough Construction Inc.
• Building for Suburban Steel Supply
• Type of Building 6488SF Maintenance building
• Location 1904 Deffenbaugh Court Gahanna, Ohio
Close Enough Construction Inc.
12 inch CMU vs. Concrete Panel
12 Inch CMU Concrete Panel
• Total Cost $98,081.59
• Time 29 days
• Total Cost $148,720.00
• Time= 6 days
Close Enough Construction Inc.
Walls
• Material Cost $121,680.00
• Labor Cost $13,520.00
• Equipment Cost $13,520.00
• 24.03% of project cost
Close Enough Construction Inc.
Floor
• Material Cost $26,784.28
• Labor Cost $6888.99
• Equipment Cost $117.83
• 5.64% of project cost
Close Enough Construction Inc.
Roof
• Material cost $40,914.21
• labor cost $8,078.20
• Equipment cost $2,664.14
• 8.34% of project cost
Close Enough Construction Inc.
Thermal
• Material cost $17,414.63
• Labor cost $6,431.44
• Equipment cost $447.71
• 3.92% of project cost
Close Enough Construction Inc.
HVAC
• Material Cost $10,436.90
• Labor Cost $3,191.86
• Equipment Cost $0.00
• 2.20% of project cost
Close Enough Construction Inc.
Plumbing Rough-In
• Material Cost $21,236.76
• Labor Cost $6,872.30
• Equipment Cost $0.00
• 4.54% of project cost
Close Enough Construction Inc.
Plumbing Fixtures
• Material Cost $3,395.00
• Labor Cost $840.50
• Equipment Cost $0.00
• 0.68% of project cost
Close Enough Construction Inc.
Fire Suppression
• Material Cost $477.00
• Labor Cost $0.00
• Equipment Cost $0.00
• 0.08% of project cost
Close Enough Construction Inc.
Electrical
• Material Cost $26,553
• Labor Cost $15,862.50
• Equipment Cost $0.00
• 6.85% of project cost
Close Enough Construction Inc.
Final Divisions
• Material Cost $136,159.85
• Labor Cost $62,981.39
• Equipment Cost $52,952.31
• 40.72% of project cost
Close Enough Construction Inc.
Project Total
• Total Project cost less O&P= $618,712.21
• Total Overhead= $74,046.01
• Total Profit= $49,496.98
• Total Project cost with O&P= $742,255.20
• Duration= 8 months