esp / col applications meteorological data requirements and regulatory conformance issues ping wan...
TRANSCRIPT
ESP / COL Applications
Meteorological Data Requirements and
Regulatory Conformance Issues
Ping Wan Bechtel Power Corporation
The Eleventh Nuclear Utility Meteorological Data Users Group MeetingOctober 2006
2
U.S. Nuclear Energy
Quick facts
- 103 nuclear plants
- 20% of the nation’s electricity
- 90.7% capacity factor
- No new contracts since 1975
- No new plants since 1995
- >23,000 MWe of new capacity since 1990
3
U.S. Energy Demand
1980 19901970 2015 2025
Commercial Use
Residential Use
Source: U.S. Department of Energy
3,839BkWh
2003
2003
Industrial Use
5,787BkWh
2005
50 Percent More Electricity Needed by 2025
4
U.S./DOE - Nuclear Power 2010
Call for building new nuclear power plants by 2010.
Support engineering of advanced designs.
Validate regulatory process.
Develop concepts to mitigate financing risks.
Cost share industry/government.
5
Proven Technology
Approved- ABWR
- AP 600
- AP 1000
- System 80+
Certification Process- ESBWR
- ACR 1000
- EPR
6
Part 52 Licensing Process
Early Site Permit
Application
Staff Review
ACRS Review
Mandatory Hearing
Early SitePermit
Decision
EquivalentEnvironmental
Information
OR
Application for Design
Certification
Staff Review
ACRS Review
CertificationRulemaking/
Hearing
Decision on Design
Certification
EquivalentDesign
Information
OR
Applicationfor CombinedLicense (COL)
Staff Review
ACRSReview
Mandatory Hearing
Decision on COL
Constructionand ITAACCompletion
Finding onITAAC
Design
Siting
COL
7
Demonstrating the Process
Government and Industry
NuStart
COL E S P
Energy Bill NP-2010
Certification
9
Used Of Meteorological Data
Use of Data
Application
Development
Regulatory
Review
Plant Operation
Atmospheric dispersion estimates for both postulated accidental and routine airborne releases of effluents X X X
Comparison with offsite sources to determine the appropriateness of climatological data use for design considerations X X
Evaluation of environmental risks from radiological consequences of a spectrum of accidents X X
Evaluation of non-radiological environmental impacts X
X
Development of emergency response plans
XX
X
10
Regulatory Requirements and Guidance
NRC Regulations
NRC Regulatory Guidance
NRC Review Guidance
Industry Standards / Guidelines
11
Regulatory Requirements and Guidance (conti-)
Sample List
R.G. 1.23 (Proposed Rev. 1)
RS-002 (2003)
NUREG-0800,Draft Rev. 3 (1996)
NUREG-1555 (1999)
Draft DG 1145 (2006)
NUREG-0654, 0696, 0737
ANS / ANSI 3.11 (2005)
NEI 01-02 (ESP) & 04-01 (COL)
12
Meteorological Tower and Instrument Siting
The objective of the onsite meteorological program is to provide measurements which represent the general site area as well as the overall site meteorology without structure influence.
Essential siting Criteria (R.G. 1.23, Proposed Rev. 1)
Base of the tower at approximately the same elevation as the finished plant grade of the new units
Location of tower upwind of the existing and new plant cooling system
Upper measurement level of the tower within the TIBL for coastal or lakeshore sites
Sensor location at least 10 obstruction heights away from such obstructions
Wind sensors located on mast away from tower structure influence
Ambient temperature and humidity sensors located away from existing and proposed moisture sources
13
Meteorological Parameters Measured
On the primary tower Wind speed and wind direction at 2 levels (at 10 meters and 60
meters, which generally coincides with the routine release level for LWRs), and at the stack release height (if applicable)
Delta-T between 10 meters and 60 meters, and 10 meters and the stack release height
Ambient temperature at 10 meters Atmospheric moisture at 10 meters, and at the top of the cooling
tower (if applicable) Precipitation at or near the tower
At the backup tower Wind speed , wind direction, and horizontal wind direction
fluctuation at 10 meters
14
Length & Currentness of Records
For an ESP Application At least one annual cycle of onsite meteorological data Meteorological data in the form of joint frequency
distribution of wind speed, wind direction by atmospheric stability class as described in R.G. 1.23
An electronic listing of all hourly averaged data
For a COL Application At least 2 consecutive annual cycles (preferably 3 or more
whole years), including the most recent 1-year period Meteorological data format and electronic listing same as
for the ESP Application
15
Other Regulatory Requirements
Data Acquisition and Data Reduction
System Accuracy
Instrument Surveillance, and
Quality Assurance and Documentation
Regulatory Requirements on these areas can be found in various Regulatory Guides (e.g., R.G. 1.23, Proposed Rev. 1 & Draft DG 1145) and Review Guidance Documents (e.g., RS-002, NUREG-0800, Draft Rev. 3 and NUREG-1555)
17
Use of Existing Meteorological Data
Conformance Issues Confirm Representativeness of the Data
Met tower and instrument siting Meteorological parameters measured
Determine Data Quality Data acquisition (data recording/transmission) Data reduction (data processing/substitution) Instrument surveillance (calibration, maintenance, QA/QC)
Assess Completeness of the Data Set Annual data recovery rates Length of records
18
Confirm Representativeness of Data
Met tower and sensor siting
Influence/Interference factors (including existing & proposed units) to be considered:
Surrounding terrain (e.g., hills, rivers & valley) Nearby natural- & man-made obstructions (e.g., trees & plant
structures Plant heat dissipation system (e.g., lakes & cooling towers) Related construction activities (e.g., earthmoving, heavy
equipment hauling & concrete batch plant operation)
Met tower & the new units have similar meteorological exposure.
Sensor elevations & measurements (wind speed, wind direction, delta-T, dew point & precipitation) on the met tower meet regulatory requirements for the new units
19
Upper Level Wind and Temperature Measurement Heights
R.G. 1.23 Requirements
at least 2 levels (e.g., approximately 10 and 60 meters) of wind measurements
Implicitly indicated that the 60 meters, upper measurement level as the level of the routine releases
Conformance Issues
Some of the new reactor designs (e.g., AP1000, EPR & ABWR) could have radiological release point higher or lower than 60 meters
Ensure that separation between the Delta-T levels (i.e., 10 meters and the upper level) is no less than 30 meters.
Ensure that the proposed data collection system (existing or new) is capable of capturing representative data.
20
Dew Point Measurement Height
R.G. 1.23 Requirements
Monitor atmospheric moisture at approx. 10 meters and at a height where the measurements represent the resultant atmospheric moisture content, if cooling towers are used
Conformance Issues
Majority of U.S. nuclear plants measured Dew Point at 10 meters only (i.e., once-through cooling system)
Additional Dew Point measurements at higher level may be required for new plants, if cooling tower are used.
Ensure that the Dew Point data are adequate and reliable, when use existing data. (Dew Point sensors are know to be difficult to maintain.)
21
Thermal Internal Boundary Layer Effects
R.G 1.23 Requirements For sites near a large body of water, the upper
measurement level should be within the TIBL during sea or lake breeze conditions.
Conformance Issues Depending on the relative location of the met tower to the
TIBL, and to the proposed units, X/Q estimates for the new units could be under-predicted, unaffected or over-predicted.
The impacts from under-predictions need to be accurately quantified and factored in making the site-specific X/Q estimate.
The Potential implications on facility design due to over-predictions need to be evaluated.
23
Data Substitution
Regulatory Requirements
There are many methods of acquiring data from meteorological measurement systems which are acceptable to the NRC Staff.
Conformance Issues
Valid measurements from a redundant sensor at the same level or at a different level (with adjustment) can be used.
Replacement of a large amount of missing primary tower Delta-T data with back-up tower sigma-theta data from a nearby should be avoided.
24
Use of Nearby Existing or Regional Data
Regulatory Requirements
No clear regulatory guidance on the subject available
Draft DG-1145 indirectly suggested: Wind rose comparisons (both seasonal and yearly) X/Q estimates based on XOQDOQ, PAVAN and/or ARCON96
Conformance Issues
Using reactor specific DCD limit values in lieu of making direct X/Q calculations can be considered. However, one could lose the design margin that is potentially afforded by using onsite met data.
25
Climatic Representative
Regulatory Requirements
Evidence should be provided to show how well the existing met data represent long-term conditions at the proposed site.
Conformance Issues
The climatic representativeness of the onsite met data can be checked by comparison with nearby stations with similar geographical locations and topographical settings that have reliable long-term met data.
Alternatively, a demonstration of representativeness can be made using data collected by the same system, if a long-term valid and reliable data base is readily available.
26
Issuance of R.G. 1.23, Third Proposed Rev. 1
Status
NRC plans to issue a Draft Revision 1 of R.G. 1.23 by October 2006
Conformance Issue
Issuance of Draft R.G. 1.23, Rev. 1 may be late coming for those applicants with submittals planned for 2007 or 2008.
NRC indicated no major changes expected in the Draft Rev. 1. However, the applicants must be prepared to address any changes in the revision.
27
Dispersion Modeling Guidance & Tools
Sample List
Types of X/Q Estimates NRC Guidance Tools
Routine & Accidental Radiological Releases
R.G. 1.111
R.G. 1.145
XOQDOQ
PAVAN
Control Room Habitability Evaluation (for both chemical and radiological releases)
R.G. 1.194
NUREG/CR-6210
R.G. 1.78
NUREG-0570
NUREG/CR-1152
ARCON96
HABIT
Emergency Planning (Near Real-time Predictions)
(* Modifications required – adding plume tracking capability)
R.G. 1.23
NUREG-0654
NUREG-0696, 0737
No NRC-sponsored codes
MESODIF-II*
CALPUFF*
Environmental Impacts of Cooling Tower Plume
No specific guidance EPRI Model - SACTI
28
Hypothetical Deployment Schedule and Financial Commitment for New Nuclear Generation
1 2 3 5 6 7 8 9 10 11 12
ESP
COL
100%
0%
4
~~
~~
Start
ApplicationSubmit
Application SER Issued
EIS Issued
LWA-1 ESP Issued
Year
Start
ApplicationSubmit
ApplicationSER Issued
LWA-2 Issued
COL Issued
Site EngineeringFOAK Engineering
Procurement PlanningSite Specific Engineering
COL Preparation COL Review
HearingsESP Prepare ESP Review
Hearings
SitePreparation
First Safety-Related Concrete
ConstructionITAAC
Fuel LoadIn Service
Plant DeploymentCumulative
COLEngineering
ESP6665-4/04-1
Expenditures
PlantDeployment
Engineering
29
Conclusions
Criteria for a successful ESP or COL Application To have a valid, accurate, adequate and representative
meteorological data base is vitally important;
Planning or selecting a data collection system, and conducting a thorough examination of the data by a professional meteorologist are highly recommended; and
Close coordination and cooperation between the regulatory agency and permit applicants is highly desirable for the following reasons:
Relevant guidance from both the NRC and industry is not comprehensive and precise;
Issuance of R.G. 1.23, Rev. 1, DG-1145 and NUREG-0800, Rev. 3 is expected to be in the near future; and
Applicants should be prepared to address the new and/or the revised regulatory guides.