envirecover energy from waste · plant operation will be in line with the commissioning protocol...

14
Envirecover Energy From Waste Simon Ganley Plant Manager

Upload: others

Post on 15-Apr-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Envirecover Energy From Waste · Plant operation will be in line with the Commissioning protocol ... Abatement in service Plant operation will be in line with the commissioning protocol

Envirecover Energy From Waste

Simon Ganley Plant Manager

Page 2: Envirecover Energy From Waste · Plant operation will be in line with the Commissioning protocol ... Abatement in service Plant operation will be in line with the commissioning protocol

� Commissioning Plan � Commissioning Activities � Activities of specific interest

What We’ll Cover Today

Page 3: Envirecover Energy From Waste · Plant operation will be in line with the Commissioning protocol ... Abatement in service Plant operation will be in line with the commissioning protocol

ColdCommissioning HotCommissioning CommercialOpera3on

P1

P2

P3

P4

P5

P6

Commissioning Time Line

Page 4: Envirecover Energy From Waste · Plant operation will be in line with the Commissioning protocol ... Abatement in service Plant operation will be in line with the commissioning protocol

�  Phase 1 to 2

�  Phase 3

�  Phase 4

�  Phase 5

�  Phase 6

Commissioning Phases

Page 5: Envirecover Energy From Waste · Plant operation will be in line with the Commissioning protocol ... Abatement in service Plant operation will be in line with the commissioning protocol

�  Phase 1 ›  Refractory Lining dry out 6 days and boil out 6 days

�  Emissions monitored by CEMS �  Low noise operation �  No Waste burnt

�  Phase 2 ›  Start up on normal auxiliary burners 15 days

�  Emissions monitored by CEMS �  Low noise operation steam flow through a silencer �  Plant operation will be in line with the Commissioning protocol �  No Waste Burnt

Phase 1 to 2

Page 6: Envirecover Energy From Waste · Plant operation will be in line with the Commissioning protocol ... Abatement in service Plant operation will be in line with the commissioning protocol

�  Phase 3 ›  3.1 First fire with waste and steam circuit testing 10 days

�  Emissions monitored by CEMS – Emissions tuning with Abatement in service

�  Plant operation will be in line with the commissioning protocol

›  3.2 Steam Turbine testing 10 days �  Testing and synchronization �  Fine set up of the CEMS

›  3.3 Operational tests 5 days

Phase 3

Page 7: Envirecover Energy From Waste · Plant operation will be in line with the Commissioning protocol ... Abatement in service Plant operation will be in line with the commissioning protocol

Illustration of Operation

Page 8: Envirecover Energy From Waste · Plant operation will be in line with the Commissioning protocol ... Abatement in service Plant operation will be in line with the commissioning protocol

�  Optimisation of the process 8 weeks ›  Optimises the plant operation ›  Testing of Turbine and Generator ›  Emissions monitored by CEMS ›  QAL 2 (Emissions extractive test completed)

Phase 4

Page 9: Envirecover Energy From Waste · Plant operation will be in line with the Commissioning protocol ... Abatement in service Plant operation will be in line with the commissioning protocol

�  Take over tests 5 weeks ›  Live tests – Main plant operation

�  Plant start and stop �  Full abatement in service �  Monitored by CEMS

›  Compliance with contract conditions �  EA permit compliance �  14 days stable operation

Phase 5

Page 10: Envirecover Energy From Waste · Plant operation will be in line with the Commissioning protocol ... Abatement in service Plant operation will be in line with the commissioning protocol

�  Reliability tests ›  60 days continuous operation ›  Performance tests ›  Full abatement in service ›  Monitored by CEMS

� Commercial handover

Phase 6

Page 11: Envirecover Energy From Waste · Plant operation will be in line with the Commissioning protocol ... Abatement in service Plant operation will be in line with the commissioning protocol

�  Phase 1 and 2 CEMS monitored

�  Phase 3 to 6 CEMS Monitored and recording

�  Phase 3 and 4 Permit in action and EA Notified if Emissions exceeded

�  Phase 5 and 6 EA Permit enforced and applied to plant operation

Emissions

Page 12: Envirecover Energy From Waste · Plant operation will be in line with the Commissioning protocol ... Abatement in service Plant operation will be in line with the commissioning protocol

�  Refractory dry out ›  Utilising external auxiliary burners ›  Interest to the operations team – Correct dry out = robust and

effective refractory

�  Boiler Boil Out ›  Boil and blow out of any debris left in the steam piping ›  Utilises a low pressure and low velocity steam flow technique ›  Low pressure and low velocity – low noise and visual impact

Activities of special interest

Page 13: Envirecover Energy From Waste · Plant operation will be in line with the Commissioning protocol ... Abatement in service Plant operation will be in line with the commissioning protocol

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100% Pe

rce

nta

ge

of E

mis

sio

ns L

imit

Pollutant

Average emissions performance of UK Energy from Waste Plants

Page 14: Envirecover Energy From Waste · Plant operation will be in line with the Commissioning protocol ... Abatement in service Plant operation will be in line with the commissioning protocol

Questions and Answers