    Plant Commissioning

    & Start-Up

  • 8/12/2019 Plant Commissioning and Startup

    2/31

    Aims of Pre-Commissioning

    The initial start-up of any plant, irrespective of size, type or industry, is aunique occurrence.

    Therefore, start-up poses some special problems. Lack of experience in dealing with these problems has frequently resulted in

    prolonged and costly start-ups.

    This presentation will provide guidelines for all those involved in the

    execution of a project on how to achieve a successful plant commissioning &

    start-up.

    The requirements for start-up oriented thinking at all stages of the project,

    from engineering to commissioning, will be demonstrated.

    Emphasis is on effective planning and use of available resources, both

    material and manpower. Troubleshooting performed during the actual start-up can be very expensive

    and must be done as effectively as possible.

    Effective trouble shooting can minimize the time and cost of going from the

    initial start-up to full production.

  • 8/12/2019 Plant Commissioning and Startup

    3/31

  • 8/12/2019 Plant Commissioning and Startup

    4/31

  • 8/12/2019 Plant Commissioning and Startup

    5/31

  • 8/12/2019 Plant Commissioning and Startup

    6/31

    Aims of Pre-Commissioning

    Ensure the Plant is constructed as designed. Ensure the Plant is clean.

    Ensure all the instrumentation, safety systems and

    machinery are fully functional.

    Ensure all vessel internals is installed correctly.

    Ensure the Plant is leak tight.

  • 8/12/2019 Plant Commissioning and Startup

    7/31

  • 8/12/2019 Plant Commissioning and Startup

    8/31

  • 8/12/2019 Plant Commissioning and Startup

    9/31

    Key to Effective Pre-Commissioning

    Planning and Preparation-milestone & progress report Work closely with the Construction Group

    Divide the Plant into small sections and pre-commission

    each one as it becomes available.

    Hold regular pre-commissioning meetings to check progress

    and to keep all parties informed.

  • 8/12/2019 Plant Commissioning and Startup

    10/31

    Typical List of Systems

    Electricity Portable/Cooling water

    Nitrogen

    Fuel gas/liquid

    Plant/Instrument air

    Hot oil/Steam system

    Other utility systems (AHU)

    Tankage Area

    Security system

  • 8/12/2019 Plant Commissioning and Startup

    11/31

    Planning & Preparation

    Master drawings for cleaning. Master drawings for instrument checks.

    Identify needs for vendor representatives and outside

    contractors.

    Ensure sufficient manpower available.

    Ensure sufficient materials are available.

  • 8/12/2019 Plant Commissioning and Startup

    12/31

    Planning & Preparation

    Prepare systems breakdown and mark-up on a master P&ID. Agree systems with construction.

    Agree timing for hand over of each system (installation-

    commissioning-training).

    Prepare pre-commissioning plan for each system.

  • 8/12/2019 Plant Commissioning and Startup

    13/31

    Pre-commissioning Plan

    Marked-up P&ID showing cleaning points, instruments to beremoved, etc.

    Description of system plan.

    Schedule for activities.

    List of consumables required.

    Requirement for vendor representative.

    Special safety activities.

  • 8/12/2019 Plant Commissioning and Startup

    14/31

    Plant Inspection

    Inspect the plant by system: Main output is a punch list of items to be put right

    Punch list items should be categorized

    -AMust fix

    -BCan be delayed

    Perform regular updates of the punch list

    A weekly punch list review meeting should be held to

    monitor progress

  • 8/12/2019 Plant Commissioning and Startup

    15/31

    Plant Inspection

    Drawing check Piping check

    Equipment check

    Electrical check

    Laboratory check

  • 8/12/2019 Plant Commissioning and Startup

    16/31

    Plant InspectionDrawing Check

    Plant check against P&ID: Positioning of instruments, equipment, valves, pipe

    branches.

    Materials of construction-comply to specification.

    Pipe dimensions

    Equipment check

  • 8/12/2019 Plant Commissioning and Startup

    17/31

    Plant InspectionPiping Check

    Check runs are provided with expansion loops, springsupports and anchor points as required.

    As heat applied to plant, ensure:

    -Spring supports correctly set

    -Heat exchangers have sufficient expansion allowance.

    When plant at normal temperature, check there are no

    piping irregularities.

  • 8/12/2019 Plant Commissioning and Startup

    18/31

  • 8/12/2019 Plant Commissioning and Startup

    19/31

    Plant InspectionEquipment Check

    Vessels: --Erected as Engineering Datasheet

    -Gaskets, clips, bolts, and nuts are correct material and

    fitted correctly

    -Demisters fitted correctly and no gaps between wall and

    pad

    -All flanged connections secure and gaskets of correct

    material

    -Nozzles clear

    -Vessel clean

  • 8/12/2019 Plant Commissioning and Startup

    20/31

    Plant InspectionEquipment Check

    Vessels (cont)-Trays and distributors

    -Tracing and insulation

    -Earth bonding must be checked

    -Take photographs of the internals for future reference

  • 8/12/2019 Plant Commissioning and Startup

    21/31

  • 8/12/2019 Plant Commissioning and Startup

    22/31

    Plant InspectionSafe Vessel Entry

    Safest option is to have NO N2 on site during pre-comm. Remove the max. amounts of toxic vapors or gas

    Before allowing entry to a vessel:

    -Vessel must be isolated from the rest of the plant and

    open to the atmosphere

    -Vessel must be completely free of combustibles and toxic

    gases

    -Combustible and oxygen gas tests must be taken

    throughout the vessel

    -Maximum ventilation must be provided

    -Entry permit must be issued valid for the day of entry

  • 8/12/2019 Plant Commissioning and Startup

    23/31

    Plant InspectionSafe Vessel Entry

    If at any time there is a doubt over excessive gas, then the

    work should be stopped.

    Station someone outside the vessel if the workers safety

    could be jeopardized

    Purpose is to firstly call for assistance NOT to enter Keep vessels that contain self-igniting deposits wet until

    rendered safe

    Safe structure outside the vessel to ensure easy

    access/egress Vessel should be closed after inspection to prevent

    unauthorized entry

  • 8/12/2019 Plant Commissioning and Startup

    24/31

    Plant InspectionEquipment Check

    Heat Exchangers:

    -Sliding supports check to ensure free operation

    -Shipping stops and supports removed from expansions

    bellows

    -Check heads of large exchangers are clean-Inspect tube sheet and tubes if possible

  • 8/12/2019 Plant Commissioning and Startup

    25/31

    Plant InspectionEquipment Check

    Pumps:-

    -Aligned correctly and rotational direction correct

    -Seal and lubrication systems installed, clean and working

    -Pump suctions flushed clean prior to initial operation

    -Switch pumps regularly during initial operation and cleanthe suction filter

  • 8/12/2019 Plant Commissioning and Startup

    26/31

    Plant InspectionEquipment Check

    Compressors:-Seal and lubricant systems checked against P&IDs, installed

    and working correctly

    -Oil flushing is completed to compressor vendor satisfaction

    -Follow vendor instrument for operation, start-up, pre-comm., commissioning and maintenance

  • 8/12/2019 Plant Commissioning and Startup

    27/31

  • 8/12/2019 Plant Commissioning and Startup

    28/31

    Plant InspectionElectrical Check

    Electrical Pre-comm. ChecksMostly in Switch Room

    -Main switches labeled

    -Overload cut-outs set to protect motors from overheating

    Electrical Checks During Construction:

    -Testing cable continuity-Current leak testing

    -Direction of motor rotation

    -Electrical earthing of machinery, piping, etc.

  • 8/12/2019 Plant Commissioning and Startup

    29/31

    Plant InspectionElectrical Check

    All such checks are the responsibility of theConstruction/Plant Electrical Engineer

    Commissioning/Operating personnel required to be familiar

    with layout and function of electrical equipment.

    Suitable training to be organized on site.

  • 8/12/2019 Plant Commissioning and Startup

    30/31

    Plant InspectionLaboratory Check

    Lab equipment fully in place and operational Lab staff suitably trained and familiar with equipment

    operation

    Pre-comm. checks will be carried out by the commissioning

    chemist Exercise tests on all analytical procedures errors free

    results

    Plant sample point location check installation and

    identification