plant commissioning start up procedure

Upload: adityapathak

Post on 16-Oct-2015

590 views

Category:

Documents


45 download

DESCRIPTION

Standard Procedure for Industrial Plant Commissioning and Start-Up

TRANSCRIPT

  • 5/26/2018 Plant Commissioning Start Up Procedure

    1/100

    Slide 1

    Plant commissioning & start upPlant commissioning & start up

    procedureprocedure

  • 5/26/2018 Plant Commissioning Start Up Procedure

    2/100

    Slide 2

    The Commissioning ProcessThe Commissioning Process

    Key StagesKey StagesPreparation and planning

    Mechanical Completion

    and Integrity checking

    Performance and

    Acceptance testing

    Start Up & Initial

    Operation

    Post Commissioning

    Pre-commissioning &

    Operational Testing

  • 5/26/2018 Plant Commissioning Start Up Procedure

    3/100

    Slide 3

    The Commissioning Process DetailThe Commissioning Process Detail -- 11Preparation and planning

    Mechanical Completion

    and Integrity checking

    Performance and

    Acceptance testing

    Start Up & Initial

    Operation

    Pre-commissioning &

    Operational Testing

    Appointment of CommissioningAppointment of Commissioning

    Manager or Lead CommissioningManager or Lead Commissioning

    Engineer;Engineer;

    Appointment of Commissioning TeamAppointment of Commissioning Team

    Members and Support Staff;Members and Support Staff;

    Training;Training;

    Information Compilation;Information Compilation;

    Safety and Risk Assessment;Safety and Risk Assessment;

    Commi ssioning StrategyCommi ssioning StrategyDevelopment;Development;

    Procedures and Checkl i stProcedures and Checkl i st

    Development;Development;

    Detailed Plan and Budget Preparation;Detailed Plan and Budget Preparation;Post Commissioning

  • 5/26/2018 Plant Commissioning Start Up Procedure

    4/100

    Slide 4

    Commissioning StrategyCommissioning Strategy

    Equipment LevelActivities

    System

    Level Activities

    Facility/Plant

    Level Activities

    Commissioning

    StrategyCommissioning Master Plan

    Individual item commissioning

    plans, procedures and checklists

  • 5/26/2018 Plant Commissioning Start Up Procedure

    5/100

    Slide 5

    Facility Commissioning IssuesFacility Commissioning Issues

    Time phasing construction and commissioning activitiesTime phasing construction and commissioning activities

    Time phasing the commissioning of the various parts of theTime phasing the commissioning of the various parts of the

    plant relative to each other;plant relative to each other;

    Relationships and timings determining when various systemsRelationships and timings determining when various systemsneed to be available:need to be available:

    Electrical, Steam, Water, InstrumentationElectrical, Steam, Water, Instrumentation

    Sequencing of the overall plant startup and shutdown toSequencing of the overall plant startup and shutdown to

    ensure we do not create unsafe conditions;ensure we do not create unsafe conditions;

    Initial start up;Initial start up;

    Process Control and Shutdown;Process Control and Shutdown;

    Performance testing;Performance testing;

  • 5/26/2018 Plant Commissioning Start Up Procedure

    6/100

    Slide 6

    Developing Startup ProceduresDeveloping Startup Procedures

    Engineering and construction companies generally follow aEngineering and construction companies generally follow a

    systematic procedure where by their startup engineerssystematic procedure where by their startup engineers

    review the process design several times as it is developed;review the process design several times as it is developed;

    After the first review, a preliminary startAfter the first review, a preliminary start--up and operationsup and operations

    procedure is written;procedure is written;

    Decide what must be added to the design to make theDecide what must be added to the design to make the

    process capable of being started up and operated;process capable of being started up and operated;

    By the time the final engineering flowBy the time the final engineering flow--sheets have beensheets have beenreleased a complete startup and operating instructionsreleased a complete startup and operating instructions

    manual should have been completed.manual should have been completed.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    7/100

    Slide 7

    Issues consideredIssues considered Are various part of the process too depend on oneAre various part of the process too depend on one

    another;another;

    Is there enough surge capacity;Is there enough surge capacity;

    Are there provisions to prevent abnormalAre there provisions to prevent abnormal

    pressures, temperatures and rates of reaction;pressures, temperatures and rates of reaction;

    Where are additional valves and bypass linesWhere are additional valves and bypass lines

    needed;needed; Special lines to allow equipment to be started upSpecial lines to allow equipment to be started up

    and rerun product/raw materials.and rerun product/raw materials.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    8/100

    Slide 8

    System Level ActivitiesSystem Level Activities

    Utilities systemsUtilities systems -- steam, instrument air, processsteam, instrument air, process

    water, fire water, drainage, condensate return;water, fire water, drainage, condensate return;

    Electrical systems;Electrical systems;

    Instrumentation and instrumentation systems;Instrumentation and instrumentation systems;

    Cleaning and flushing;Cleaning and flushing;

    Purging;Purging; Initial start up and shutdowns;Initial start up and shutdowns;

    Performance testing;Performance testing;

  • 5/26/2018 Plant Commissioning Start Up Procedure

    9/100

    Slide 9

    Equipment Level ActivitiesEquipment Level Activities

    Pressure testing & mechanical integrity testing ofPressure testing & mechanical integrity testing of

    vessel, columns and pipe work;vessel, columns and pipe work;

    Heat Exchangers, condensers, coolers etc.Heat Exchangers, condensers, coolers etc. Mechanical equipment and machinery;Mechanical equipment and machinery;

    Control Systems and Instrumentation;Control Systems and Instrumentation;

    Operational testing;Operational testing;

    Proof testing and acceptance.Proof testing and acceptance.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    10/100

    Slide 10

    What can be done before mechanicalWhat can be done before mechanical

    completioncompletion

    Utilities commissioning

    Lube and Seal-Oil Systems Cleaned

    Instrumentation and Control Loops Proven

    Piping, Towers and Vessels Cleaned

    Boil-Out, Dry-Out and Acid Cleaning

    Turbine, Motor and Pump Run-Ins Nitrogen Purge and Tightness Testing

  • 5/26/2018 Plant Commissioning Start Up Procedure

    11/100

    Slide 11

    BuildingBuilding OrganisationalOrganisational LearningLearning

    Corporate

    Knowledge Base

    Best Practice

    Benchmarking

    IndustryStandards

    Legislation

    Process Design

    Specific

    Machinery &

    Equipment

    Procedures and

    Check sheets

    Improvement

    Processes

    Experience

    Incidents and

    Near Misses

  • 5/26/2018 Plant Commissioning Start Up Procedure

    12/100

    Slide 12

    ProceduresProcedures Procedures are written routines/instructions thatProcedures are written routines/instructions that

    describe the logical sequence of activities required todescribe the logical sequence of activities required to

    perform a work process and the specific actionsperform a work process and the specific actions

    required to perform each activity;required to perform each activity; If there are no written procedures, there is no basis forIf there are no written procedures, there is no basis for

    monitoring performance, focus for improvement ormonitoring performance, focus for improvement or

    mechanism by which to capture learning;mechanism by which to capture learning;

    The establishment of procedures and routines allowThe establishment of procedures and routines allow

    more time and mental energy to deal with themore time and mental energy to deal with the

    unexpected, which always happen duringunexpected, which always happen during

    commissioning.commissioning.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    13/100

    Slide 13

    Commissioning/Startup LogicCommissioning/Startup Logic A Critical Path Network (Plan) with written procedures withA Critical Path Network (Plan) with written procedures with

    related documents are required. These should define for therelated documents are required. These should define for the

    facility, each plant system:facility, each plant system:

    The order in which the systems will be started up;The order in which the systems will be started up; Individual activities at each stage;Individual activities at each stage;

    Operation testing requirements;Operation testing requirements;

    Durations, waiting times, cooling times;Durations, waiting times, cooling times;

    Total duration for starting up each system;Total duration for starting up each system; Resources requiredResources required -- labourlabour, materials, equipment,, materials, equipment,

    services;services;

    Temperatures, pressures, fluid flows used.Temperatures, pressures, fluid flows used.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    14/100

    Slide 14

    Commissioning/Startup and Shutdown IssuesCommissioning/Startup and Shutdown Issues

    At the facility, system and equipment level, weAt the facility, system and equipment level, we

    want to avoid:want to avoid:

    Creation/existence of explosive mixtures, usuallyCreation/existence of explosive mixtures, usually

    because of the presence of air;because of the presence of air;

    Water hammer and water based explosionWater hammer and water based explosion

    effects, due to contact between water and hoteffects, due to contact between water and hot

    substances (steam, oil, etc.);substances (steam, oil, etc.);

    In particular, during commissioning hot fluids andIn particular, during commissioning hot fluids andgases will be coming into contact with coldgases will be coming into contact with cold

    surfaces in places that would be hot under normalsurfaces in places that would be hot under normal

    operations.operations.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    15/100

    Slide 15

    Mechanical Completion and IntegrityMechanical Completion and Integrity

    CheckingChecking

  • 5/26/2018 Plant Commissioning Start Up Procedure

    16/100

    Slide 16

    Mechanical Completion and IntegrityMechanical Completion and Integrity

    InspectionInspectionPreparation and planning

    Mechanical Completion

    and Integrity checking

    Performance and

    Acceptance testing

    Start Up & Initial

    Operation

    Pre-commissioning &

    Operational Testing

    InspectionInspection

    Pressure testingPressure testing

    Cleaning and FlushingCleaning and Flushing

    Machinery checkoutMachinery checkout

    Post Commissioning

  • 5/26/2018 Plant Commissioning Start Up Procedure

    17/100

    Slide 17

    Categories of Process EquipmentCategories of Process Equipment Distillation Towers/Fractionation TowersDistillation Towers/Fractionation Towers

    ReboilersReboilers & Other Shell & Tube Heat Exchangers& Other Shell & Tube Heat Exchangers

    Boilers and Fired HeatersBoilers and Fired Heaters

    Pressure Vessels and PipePressure Vessels and Pipe--workwork

    FinFin--Fan CoolersFan Coolers

    CondensersCondensers

    Machinery/Rotating EquipmentMachinery/Rotating Equipment

    ValvesValves

    InstrumentationInstrumentation

    Electrical EquipmentElectrical Equipment

  • 5/26/2018 Plant Commissioning Start Up Procedure

    18/100

    Slide 18

    Machinery/ Rotating EquipmentMachinery/ Rotating Equipment

    PumpsPumps

    Steam TurbinesSteam Turbines

    Gas TurbinesGas Turbines CompressorsCompressors

    Gas EnginesGas Engines

    Electric MotorsElectric Motors

  • 5/26/2018 Plant Commissioning Start Up Procedure

    19/100

    Slide 19

    Mechanical Completion and IntegrityMechanical Completion and Integrity

    InspectionInspection

    Involves checking that everything has been built and itInvolves checking that everything has been built and it

    there as per specification. Refer:there as per specification. Refer:

    Piping Plan Drawings;Piping Plan Drawings;

    Layout and construction drawings;Layout and construction drawings;

    P & IDP & IDss

    Electrical systems, Instrumentation and control systemsElectrical systems, Instrumentation and control systems

    checkout down by appropriately qualified personnelcheckout down by appropriately qualified personnel

    (Electricians and Instrumentation technicians).(Electricians and Instrumentation technicians). General commissioning engineers generally do not getGeneral commissioning engineers generally do not get

    involved in this in a handsinvolved in this in a hands--on manner.on manner.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    20/100

    Slide 20

    Mechanical Completion and IntegrityMechanical Completion and Integrity

    Inspection ProcedureInspection Procedure

    Divide plant into manageable areas;Divide plant into manageable areas;

    In a large plant, assign individuals or teams toIn a large plant, assign individuals or teams to

    specific areas;specific areas; Establish a master set of piping plan drawings andEstablish a master set of piping plan drawings and

    P&IDP&IDs, mark up areas:s, mark up areas:

    Individual commissioning engineers or teams walkIndividual commissioning engineers or teams walk

    every line and mark up every item that can beevery line and mark up every item that can beconfirmed as present on master set of drawings;confirmed as present on master set of drawings;

    Use differentUse different colouredcoloured highlighterhighlighterpens topens to

    indicate different services.indicate different services.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    21/100

    Slide 21

    Mechanical Completion and Integrity InspectionMechanical Completion and Integrity Inspection

    Every line must be walked! Physically sight everything!Every line must be walked! Physically sight everything!

  • 5/26/2018 Plant Commissioning Start Up Procedure

    22/100

    Slide 22

    Mechanical Completion and IntegrityMechanical Completion and Integrity

    Inspection ProcedureInspection Procedure -- Hints/TipsHints/Tips

    Ensure pipes, vessels, valves etc. are all in the rightEnsure pipes, vessels, valves etc. are all in the right

    place;place;

    Valves are correct typeValves are correct type -- globe, gate, control;globe, gate, control; Vents, drains, steam traps etc.Vents, drains, steam traps etc.

    Flanges, bolts, types of bolts;Flanges, bolts, types of bolts;

    Blind flanges andBlind flanges and swingableswingableblinds in place,blinds in place,

    correct rating;correct rating;

    Check all tag numbers;Check all tag numbers;

    PunchlistPunchlist any nonany non--conformances.conformances.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    23/100

    Slide 23

    New PlantPiping Tie-ins!

  • 5/26/2018 Plant Commissioning Start Up Procedure

    24/100

    Slide 24

    Pipe StressingPipe Stressing

    Piping should provide adequately for expansion andPiping should provide adequately for expansion and

    contraction due to temperature changes, withoutcontraction due to temperature changes, without

    placing excessive stresses on equipment;placing excessive stresses on equipment;

    Misalignment between matching flanges on pipeMisalignment between matching flanges on pipe--workwork --particular where there are changes inparticular where there are changes in

    direction (elbows) can cause stressing;direction (elbows) can cause stressing;

    Misalignments where pipeMisalignments where pipe--work connects towork connects to

    machinery, vessels and other process equipment;machinery, vessels and other process equipment;

    Can often be seen visually, or checked with gaugesCan often be seen visually, or checked with gauges

    using the same procedures we use to align rotatingusing the same procedures we use to align rotating

    equipment.equipment.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    25/100

    Slide 25

    Piping and Equipment SupportsPiping and Equipment Supports

  • 5/26/2018 Plant Commissioning Start Up Procedure

    26/100

    Slide 26

    Piping and equipment supportsPiping and equipment supports

    Mobile supports permit and guide the thermalMobile supports permit and guide the thermal

    growth of equipment undergoing temperaturegrowth of equipment undergoing temperature

    change;change; If they do not function correctly, vessels,If they do not function correctly, vessels,

    equipment, pipe work, nozzles heat exchangersequipment, pipe work, nozzles heat exchangers

    etc. may be damaged.etc. may be damaged.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    27/100

    Slide 27

    Typical piping support methodsTypical piping support methods

  • 5/26/2018 Plant Commissioning Start Up Procedure

    28/100

    Slide 28

    Piping and equipment supportsPiping and equipment supports

    Inspection prior to start up:Inspection prior to start up:

    Check that installed according to specification and not jammed;Check that installed according to specification and not jammed;

    Inspection during warm up:Inspection during warm up:

    Check thermal growth is occurring and supports are respondingCheck thermal growth is occurring and supports are respondingas per design;as per design;

    Check that there is no surface buckling or crimpingCheck that there is no surface buckling or crimping -- this needsthis needs

    to be corrected;to be corrected;

    Check expansion joints;Check expansion joints; Check long straight runs of piping for bowing or support shoesCheck long straight runs of piping for bowing or support shoes

    that may have slipped;that may have slipped;

    Rule of thumbRule of thumb -- bowing is excessive if you can see it.bowing is excessive if you can see it.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    29/100

    Slide 29

    Piping and equipment supportsPiping and equipment supports

    Inspection after coolInspection after cool--down:down:

    Check that sliding supports have returned toCheck that sliding supports have returned to

    original positions;original positions;

    Establish that equipment can expand andEstablish that equipment can expand and

    contract as required.contract as required.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    30/100

    Slide 30

    Inspection of spring supportsInspection of spring supports

    Before hydroBefore hydro--testing:testing:

    Check that spring stops are installed. (If not, theCheck that spring stops are installed. (If not, the

    weight of water in pipe will deform the spring).weight of water in pipe will deform the spring). After hydroAfter hydro--testing but before heating:testing but before heating:

    Check that stops are removed;Check that stops are removed;

    Check that spring pointer is positioned to coldCheck that spring pointer is positioned to coldsetting;setting;

  • 5/26/2018 Plant Commissioning Start Up Procedure

    31/100

    Slide 31

    Inspection of spring supportsInspection of spring supports

    During and at end of heating:During and at end of heating:

    Check pointer has not exceeded hot setting;Check pointer has not exceeded hot setting;

    After cool down:After cool down:

    check to establish piping can expand andcheck to establish piping can expand and

    contract as required;contract as required;

    establish that springs can absorb loads.establish that springs can absorb loads.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    32/100

    Slide 32

    Vessels and ColumnsVessels and Columns

  • 5/26/2018 Plant Commissioning Start Up Procedure

    33/100

    Slide 33

    Inspection of Vessels and ColumnsInspection of Vessels and Columns

    The inspection of vessels, columns and reactorsThe inspection of vessels, columns and reactors

    should be scheduled to be completed beforeshould be scheduled to be completed before

    construction has closed them up;construction has closed them up;

    Other inspectionsOther inspections -- e.g. for completeness or piping,e.g. for completeness or piping,

    insulation, safety etc. can be scheduled later;insulation, safety etc. can be scheduled later;

    If a vessel has been sealed up by construction, it isIf a vessel has been sealed up by construction, it is

    your duty to inspect it, even it construction resist.your duty to inspect it, even it construction resist.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    34/100

    Slide 34

    Inspection of Vessels and ColumnsInspection of Vessels and Columns

    Check that distributors have been installedCheck that distributors have been installed

    correctly;correctly;

    DeDe--misters installed correctly and of correctmisters installed correctly and of correctmaterials, design, type;materials, design, type;

    Vortex breakers in place;Vortex breakers in place;

    TraysTrays --packed orpacked or bubblebubble--capcap are correct:are correct:

    Bubble caps not jammed or damaged, downBubble caps not jammed or damaged, downcomers clear, supports all OK.comers clear, supports all OK.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    35/100

    Slide 35

    Pressure TestingPressure Testing

  • 5/26/2018 Plant Commissioning Start Up Procedure

    36/100

    Slide 36

    Pressure TestingPressure Testing -- ObjectivesObjectives

    The objective of pressure testing is to confirm theThe objective of pressure testing is to confirm the

    mechanical integrity of the plant;mechanical integrity of the plant;

    Verifying capability of containing the pressures it hasVerifying capability of containing the pressures it has

    been designed to hold;been designed to hold;

    Ensure there are no leaks and verify that the plant canEnsure there are no leaks and verify that the plant can

    be reliably made leak free;be reliably made leak free;

    Identify any vulnerabilities well before the plant isIdentify any vulnerabilities well before the plant isplaced into service;placed into service;

    Meet the requirements of legislation, local,Meet the requirements of legislation, local,

    international and industry standards.international and industry standards.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    37/100

    Slide 37

    Pressure TestingPressure Testing -- responsibilitiesresponsibilities

    Pressure tests of tanks, reactors and piping forPressure tests of tanks, reactors and piping for

    mechanical strength and tightness of joints ismechanical strength and tightness of joints is

    usually done by the construction team;usually done by the construction team; Commissioning team representatives shouldCommissioning team representatives should

    witness and certify the tests;witness and certify the tests;

    Need to verify that all necessary safety precautionsNeed to verify that all necessary safety precautions

    have been taken;have been taken;

  • 5/26/2018 Plant Commissioning Start Up Procedure

    38/100

    Slide 38

    Pressure TestingPressure Testing --proceduresprocedures

    Water for testing and flushing should contain a rustWater for testing and flushing should contain a rust

    inhibitorinhibitor -- one low in chloride content for stainlessone low in chloride content for stainless

    steel lines;steel lines;

    After testing, water should be drained completelyAfter testing, water should be drained completelyfrom all lines that do not normally carry water,from all lines that do not normally carry water,

    steam or steam condensate;steam or steam condensate;

    All low points should be checked for presence ofAll low points should be checked for presence of

    water;water; Lines should be dried by blowing hot air, dry inertLines should be dried by blowing hot air, dry inert

    gas or instrument air.gas or instrument air.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    39/100

    Slide 39

    Pressure TestingPressure Testing -- Vacuum SystemsVacuum Systems

    Final checks of vacuum systems are bestFinal checks of vacuum systems are best

    performed by pulling a vacuum and observing theperformed by pulling a vacuum and observing the

    rate of pressure rise in the blocked in system;rate of pressure rise in the blocked in system;

    Excessive leaks can then be located by applying aExcessive leaks can then be located by applying amild positive pressure and testing each flange withmild positive pressure and testing each flange with

    bubble solution.bubble solution.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    40/100

    Slide 40

    Pressure TestingPressure Testing -- Procedures 2Procedures 2

    Isometric drawings of all systems to be tested should beIsometric drawings of all systems to be tested should be

    displayed on a board and marked up as each section isdisplayed on a board and marked up as each section is

    tested;tested;

    HydrotestingHydrotesting of piping and equipment according to codeof piping and equipment according to code

    requirements to confirm mechanical strength should berequirements to confirm mechanical strength should be

    carried out on groups of equipment naturally suggested bycarried out on groups of equipment naturally suggested by

    design pressure and function;design pressure and function;

    All water, steam, condensate, oil, gas and process steamAll water, steam, condensate, oil, gas and process steam

    piping should be hydrotested;piping should be hydrotested; Major equipment that has already been tested as part ofMajor equipment that has already been tested as part of

    manufacturing may be isolated by blanks.manufacturing may be isolated by blanks.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    41/100

    Slide 41

    Cleaning and FlushingCleaning and Flushing

  • 5/26/2018 Plant Commissioning Start Up Procedure

    42/100

    Slide 42

    Cleaning and FlushingCleaning and Flushing

    Need to ensure no construction debris is left inNeed to ensure no construction debris is left in

    pipes of vesselspipes of vessels -- welding rods, bolts, gloves, ragswelding rods, bolts, gloves, rags

    etc.etc.

    Large debris (lumber, cable, packaging) shouldLarge debris (lumber, cable, packaging) should

    have been removed during mechanical integrityhave been removed during mechanical integrity

    inspections;inspections;

    Small debris (rags, nuts, dirt) must be flushed outSmall debris (rags, nuts, dirt) must be flushed out

    of all pipe and vessels;of all pipe and vessels;

    Where oil coatings must be removed, chemicalWhere oil coatings must be removed, chemical

    cleaning is necessary.cleaning is necessary.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    43/100

    Slide 43

    Cleaning and FlushingCleaning and Flushing

    Before flushing is started, check the processBefore flushing is started, check the process

    thoroughly to ensure:thoroughly to ensure:

    Screens have been installed in front of pumpScreens have been installed in front of pumpsuctions;suctions;

    Blinds in front of equipment such asBlinds in front of equipment such as

    compressors and turbines;compressors and turbines;

    JumperJumper spool pieces to allow for continuity ofspool pieces to allow for continuity offlow.flow.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    44/100

    Slide 44

    FlushingFlushing

    Can be handled by geographic plant area;Can be handled by geographic plant area;

    Sections too large for water flushing:Sections too large for water flushing:

    Pipes greater than 30 in diameter (0.75 m), orPipes greater than 30 in diameter (0.75 m), or

    Pipes that should not be touched with water;Pipes that should not be touched with water;

    Should all be blown out with air or inert gas.Should all be blown out with air or inert gas.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    45/100

    Slide 45

    FlushingFlushing

    Regardless of whether pipes are cleaned withRegardless of whether pipes are cleaned with

    water, steam, air or nitrogen, flow velocitieswater, steam, air or nitrogen, flow velocities

    should be high enough to ensure that pipes willshould be high enough to ensure that pipes will

    be suitably scoured;be suitably scoured; Need to ensure that the debris from one piece ofNeed to ensure that the debris from one piece of

    equipment will not simply be flushed intoequipment will not simply be flushed into

    another;another;

    Water velocities should be at least 12 ft/secWater velocities should be at least 12 ft/sec(approx. 3.75 m/sec);(approx. 3.75 m/sec);

    Air velocities a minimum of 200 ft/sec (approx.Air velocities a minimum of 200 ft/sec (approx.

    65 m/sec);65 m/sec);

  • 5/26/2018 Plant Commissioning Start Up Procedure

    46/100

    Slide 46

    PrePre--commissioning and Operationalcommissioning and Operational

    TestingTesting

  • 5/26/2018 Plant Commissioning Start Up Procedure

    47/100

    Slide 47

    The Commissioning Process DetailThe Commissioning Process Detail -- 33

    Preparation and planning

    Performance and

    Acceptance testing

    Start Up & Initial

    Operation

    Steam and other utilitiesSteam and other utilitiescommissioned and introduced;commissioned and introduced;

    Dry running trials;Dry running trials;

    Hot running trials;Hot running trials;

    SafeSafe--fluid dynamic testing;fluid dynamic testing;

    Solvent dynamic testing;Solvent dynamic testing;

    Process fluid tests.Process fluid tests.

    Mechanical Completion

    and Integrity checking

    Pre-commissioning &

    Operational Testing

    Post Commissioning

  • 5/26/2018 Plant Commissioning Start Up Procedure

    48/100

    Slide 48

    Commissioning UtilitiesCommissioning Utilities

  • 5/26/2018 Plant Commissioning Start Up Procedure

    49/100

    Slide 49

    Commissioning UtilitiesCommissioning Utilities

    Utilities commissioning usually represents the firstUtilities commissioning usually represents the first

    phase of commissioning, as these usually need tophase of commissioning, as these usually need to

    operational first, before the rest of the plant can beoperational first, before the rest of the plant can be

    commissioned;commissioned;

    The steps for commissioning each utility should beThe steps for commissioning each utility should be

    planned in detail;planned in detail;

    Provides planning practice for planning the startupProvides planning practice for planning the startupof the main plant.of the main plant.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    50/100

    Slide 50

    Commissioning UtilitiesCommissioning Utilities -- Broad GuidelinesBroad Guidelines

    Check supply pressures of all servicesCheck supply pressures of all services -- steam, cooling water,steam, cooling water,

    instrument air, nitrogen etc.instrument air, nitrogen etc.

    At the most distant points, open drains, vent valves or pipeAt the most distant points, open drains, vent valves or pipe

    flanges and purge until fluids come out clean and rust free;flanges and purge until fluids come out clean and rust free;

    Purge/blow out lines to each piece of equipment;Purge/blow out lines to each piece of equipment;

    Check that instrument air is clean and dry, and at correctCheck that instrument air is clean and dry, and at correct

    pressure;pressure;

    Circulate water to waste water system until water lines clear anCirculate water to waste water system until water lines clear andd

    clean;clean;

    Flush waste water and drain systems to ensure no blockages;Flush waste water and drain systems to ensure no blockages;

    Check operation of steam traps;Check operation of steam traps;

    Drain condensate to waste water until is is clean.Drain condensate to waste water until is is clean.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    51/100

    Slide 51

    Commissioning UtilitiesCommissioning Utilities

    Introducing SteamIntroducing Steam Steam usually represents the firstSteam usually represents the first hazardoushazardous fluidfluid

    introduced into theintroduced into the newnew system;system;

    Admit steam slowly into the distribution system withAdmit steam slowly into the distribution system with

    atmospheric bleeds open:atmospheric bleeds open: Cold pipes will condense steam in places where itCold pipes will condense steam in places where it

    would not under normal operation;would not under normal operation;

    Can lead toCan lead to water hammerwater hammer -- can distort and rupturecan distort and rupture

    lines;lines;

    After system has been warmed, slowly raise pressure andAfter system has been warmed, slowly raise pressure and

    blow down the system with traps bypassed, until clean;blow down the system with traps bypassed, until clean;

    Then place steam traps into service and check operation.Then place steam traps into service and check operation.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    52/100

    Slide 52

    High Pressure Steam SystemsHigh Pressure Steam Systems

    Specific IssuesSpecific Issues The cleanliness and purity of high pressure steam systemsThe cleanliness and purity of high pressure steam systems --

    particularly where the steam is used to drive a steam turbineparticularly where the steam is used to drive a steam turbine

    should be checked by use of ashould be checked by use of a targettarget;;

    For new boilers, or new sections added to steam systemFor new boilers, or new sections added to steam system --blow down at full pressure;blow down at full pressure;

    When steam appears clean, fit a target with aWhen steam appears clean, fit a target with a mirroredmirrored

    surface (surface (ieie. Small steel plate which has been polished, so that. Small steel plate which has been polished, so that

    it is in the steam blow down stream;it is in the steam blow down stream;

    Blow down the boiler or system so that the target is impingedBlow down the boiler or system so that the target is impingedupon for a few minutes;upon for a few minutes;

    Check targetCheck target -- ensure there are no smallensure there are no small pock markspock marks left onleft on

    the target. If pock markedthe target. If pock marked -- repeat process.repeat process.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    53/100

    Slide 53

    Electrical SystemsElectrical Systems

  • 5/26/2018 Plant Commissioning Start Up Procedure

    54/100

    Slide 54

    Commissioning Electrical SystemsCommissioning Electrical Systems

    The following checks are typical of what is requiredThe following checks are typical of what is required Open circuit breakers and switches;Open circuit breakers and switches;

    Check that all busCheck that all bus--bars are free of dirt and foreign matter;bars are free of dirt and foreign matter;

    Check grounding systems for continuity and resistance.Check grounding systems for continuity and resistance.

    Make sure all electrical equipment, vessels, structures areMake sure all electrical equipment, vessels, structures areconnected to the grounding system in accordance withconnected to the grounding system in accordance with

    drawings and specifications;drawings and specifications;

    Check that all sealed fittings are filled with proper sealants,Check that all sealed fittings are filled with proper sealants,

    all explosion proof,all explosion proof, vapourvapour--tight, dusttight, dust--tight and weathertight and weather

    tight enclosures are properly closed and secured;tight enclosures are properly closed and secured;

    Check motor control and power circuitry for correctCheck motor control and power circuitry for correct

    hookup.hookup.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    55/100

    Slide 55

    Commissioning Electrical SystemsCommissioning Electrical Systems -- 22

    The following checks are typical of what is requiredThe following checks are typical of what is required Check all nameplates and panel directories to ensure thatCheck all nameplates and panel directories to ensure that

    each circuit breaker and switch does control the propereach circuit breaker and switch does control the proper

    circuit. Label all switches even though their applicationcircuit. Label all switches even though their application

    may seem obvious;may seem obvious;

    Close main transformer primary disconnect switch andClose main transformer primary disconnect switch and

    switchswitch--gear main circuit breaker;gear main circuit breaker;

    Check voltmeter at switchCheck voltmeter at switch--gear for proper voltage;gear for proper voltage;

    Close first switchClose first switch--gear circuit breaker, second, third etc.gear circuit breaker, second, third etc.

    Close first motor control centre main circuit breaker, thenClose first motor control centre main circuit breaker, then

    each motor starter circuit breaker. Repeat for each MCC.each motor starter circuit breaker. Repeat for each MCC.

    Check overload breakers and heaters to ensure that theCheck overload breakers and heaters to ensure that the

    correct capacity units have been installed.correct capacity units have been installed.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    56/100

    Slide 56

    Commissioning Electrical SystemsCommissioning Electrical Systems -- 33

    The following checks are typical of what is requiredThe following checks are typical of what is required Check that all lighting and power circuits are functioningCheck that all lighting and power circuits are functioning

    correctly;correctly;

    Check motor bearings for proper lubrication;Check motor bearings for proper lubrication;

    Remove motor power fuses and check main contractor,Remove motor power fuses and check main contractor,interlock and sequencing devices;interlock and sequencing devices;

    Uncouple each motor, replace fuses and check direction ofUncouple each motor, replace fuses and check direction of

    rotation by momentarily pressing the start button, then stop;rotation by momentarily pressing the start button, then stop;

    Check manual, then automatic operation.Check manual, then automatic operation.

    Replace all couplings, check drive belts and make sureReplace all couplings, check drive belts and make sure

    guards are installed.guards are installed.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    57/100

    Slide 57

    Electric motor driven pumpsElectric motor driven pumps

  • 5/26/2018 Plant Commissioning Start Up Procedure

    58/100

    Slide 58

    Operational TestingOperational Testing

  • 5/26/2018 Plant Commissioning Start Up Procedure

    59/100

    Slide 59

    Operational TestingOperational Testing

    Progresses through several stages;Progresses through several stages;

    Dry runs of individual items of equipmentDry runs of individual items of equipment

    Hot testing of individual items of equipment andHot testing of individual items of equipment andsystems;systems;

    Several stages of Dynamic Testing of:Several stages of Dynamic Testing of:

    Individual items of equipment;Individual items of equipment;

    Individual Systems/processes in isolation;Individual Systems/processes in isolation;

    The whole new process plant installation.The whole new process plant installation.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    60/100

    Slide 60

    Dry runs and Hot TestsDry runs and Hot Tests

    Check that motors are connected correctly and turnCheck that motors are connected correctly and turn

    in the right direction;in the right direction;

    Shafts and impellers move freely;Shafts and impellers move freely; Equipment that is to be operated at temperature,Equipment that is to be operated at temperature,

    raise to temperature and check;raise to temperature and check;

    These tests should be performed by theThese tests should be performed by the

    manufacturermanufacturers representative but witnessed bys representative but witnessed bymembers of the clientmembers of the clients operating/commissionings operating/commissioning

    personnel.personnel.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    61/100

    Slide 61

    Hot testing equipmentHot testing equipment

    Applies to equipment whose leakApplies to equipment whose leak--tightness must be tested attightness must be tested at

    operating temperatures and after temperature reversals;operating temperatures and after temperature reversals;

    FixedFixed--bed catalytic reactors that in normal conditions arebed catalytic reactors that in normal conditions are

    heated by heat transfer fluids where leakage wouldheated by heat transfer fluids where leakage wouldcontaminate the catalyst;contaminate the catalyst;

    Critical exchangers whose steam or cooling water is at aCritical exchangers whose steam or cooling water is at a

    high pressure than the process fluid;high pressure than the process fluid;

    Any equipment having complicated seals through whichAny equipment having complicated seals through which

    leakage could occur;leakage could occur;

    Rotating machinery which must be able to rotate freely atRotating machinery which must be able to rotate freely at

    temperaturetemperature egeg. Steam turbines, etc.. Steam turbines, etc.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    62/100

    Slide 62

    Hot testing proceduresHot testing procedures

    The thermal shock tolerance of equipment must beThe thermal shock tolerance of equipment must be

    determined beforehand;determined beforehand;

    To avoid thermal shock, the temperature of theTo avoid thermal shock, the temperature of the

    heating medium may have to be raised gradually;heating medium may have to be raised gradually;

    Time required for a hot test must be established inTime required for a hot test must be established in

    advance;advance;

    Establish a uniform temperature in all parts ofEstablish a uniform temperature in all parts of

    equipment that are supposed to be uniformly hotequipment that are supposed to be uniformly hot

    during operation to avoid setting up stresses;during operation to avoid setting up stresses;

  • 5/26/2018 Plant Commissioning Start Up Procedure

    63/100

    Slide 63

    Dynamic TestingDynamic Testing

  • 5/26/2018 Plant Commissioning Start Up Procedure

    64/100

    Slide 64

    Dynamic TestingDynamic Testing

    Involves operating the equipment, before introducingInvolves operating the equipment, before introducing

    liveliveprocess fluid;process fluid;

    During dynamic testing, we progress through:During dynamic testing, we progress through:

    SafeSafe--fluid dynamic testing;fluid dynamic testing;

    Dynamic testing with solvent;Dynamic testing with solvent;

    Closed loop testing with process fluid.Closed loop testing with process fluid.

    Once process fluid is introduced, normal plant safetyOnce process fluid is introduced, normal plant safetyprocedures must come into effect as if it were a liveprocedures must come into effect as if it were a live

    operating plant.operating plant.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    65/100

    Slide 65

    SafeSafe--Fluid Dynamic TestingFluid Dynamic Testing

    Closed loop dynamic testing with safe fluids consists ofClosed loop dynamic testing with safe fluids consists of

    operating equipment systems with air, water, inert gasesoperating equipment systems with air, water, inert gases

    etc.etc.

    This permits flow testing of equipment;This permits flow testing of equipment; Gives first indication of how control loops work;Gives first indication of how control loops work;

    Establishes performance while there is still time to modifyEstablishes performance while there is still time to modify

    the plant;the plant;

    FamiliarisesFamiliarises operators with the operation of the equipmentoperators with the operation of the equipmentbefore hazardous materials are introduced;before hazardous materials are introduced;

    Gets rid of a lot of dirt which would be more difficult toGets rid of a lot of dirt which would be more difficult to

    clear once the process fluid has been introduced.clear once the process fluid has been introduced.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    66/100

    Slide 66

    General Principles for TestingGeneral Principles for Testing

    For most plants, a period of 2For most plants, a period of 2--3 weeks is usually sufficient3 weeks is usually sufficient

    for operational testing, after the mechanical dry running offor operational testing, after the mechanical dry running of

    individual pieces of equipment and hot testing complete;individual pieces of equipment and hot testing complete;

    Air and water tests should be set up in a closed loop withAir and water tests should be set up in a closed loop withfluids continuously recycled, with loops as large asfluids continuously recycled, with loops as large as

    possible;possible;

    The loop should ideally be the same loop that will beThe loop should ideally be the same loop that will be

    subject to solvent testing;subject to solvent testing;

    Tests should continue for several days in order to give allTests should continue for several days in order to give allshifts a chance to conduct the same tests;shifts a chance to conduct the same tests;

    All shifts should be given the opportunity to start up andAll shifts should be given the opportunity to start up and

    shutdown each closed loop test.shutdown each closed loop test.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    67/100

    Slide 67

    General Principles for TestingGeneral Principles for Testing

    A rough flowA rough flow--sheet should be developed for airsheet should be developed for air

    and water tests, predicting all information thatand water tests, predicting all information that

    normally appears on a process flow sheetnormally appears on a process flow sheet -- flow,flow,

    temperature, pressure, heat transfer, power etc.temperature, pressure, heat transfer, power etc. will assist in alerting commissioning team towill assist in alerting commissioning team to

    risks from overrisks from over--pressuring, overloading,pressuring, overloading,

    temperaturetemperature--shocking and stressing equipment;shocking and stressing equipment;

  • 5/26/2018 Plant Commissioning Start Up Procedure

    68/100

    Slide 68

    Cautions during TestingCautions during Testing

    Dynamic testing may lead to:

    Unusual or unforeseen differential expansions;Unusual or unforeseen differential expansions;

    Corrosion;Corrosion;

    Excessive weight of liquid into parts of theExcessive weight of liquid into parts of the

    system;system;

    Care must be taken not to collapse or burstCare must be taken not to collapse or burst

    pressure vessels and tanks:pressure vessels and tanks: ensure there is always adequate venting;ensure there is always adequate venting;

    avoid pulling a vacuum.avoid pulling a vacuum.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    69/100

    Slide 69

    Dynamic TestingDynamic Testing -- Simulated OperationsSimulated Operations

    Safe Fluid TestingSafe Fluid Testing

    Auxiliary services must be brought into operationAuxiliary services must be brought into operation

    first:first:

    water cooling, inert gas generators, boilerwater cooling, inert gas generators, boilerfeedwaterfeedwater, firewater, steam production, etc., firewater, steam production, etc.

    Water is pumped through the process (exceptWater is pumped through the process (except

    where special conditions do not permit it) andwhere special conditions do not permit it) and

    boiled up in columns;boiled up in columns; Compressors and blowers should be operated onCompressors and blowers should be operated on

    air or inert gas.air or inert gas.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    70/100

    Slide 70

    The Value of Dynamic TestingThe Value of Dynamic Testing --

    Simulated OperationsSimulated Operations Value of simulated operations will be to allow operator toValue of simulated operations will be to allow operator to

    become familiar with the operation of the process, beforebecome familiar with the operation of the process, before

    hazardous fluids are introduced;hazardous fluids are introduced;

    Equipment deficiencies can become apparent duringEquipment deficiencies can become apparent duringdynamic testing;dynamic testing;

    Failures and problems more easily corrected with safeFailures and problems more easily corrected with safe

    fluids presentfluids present

    Leaks should be found and tightened;Leaks should be found and tightened;

    Instruments can be placed into serviceInstruments can be placed into service -- although selectionalthough selection

    of setof set--points will have to be deferred;points will have to be deferred;

    Inspect the plant for evidence of design and constructionInspect the plant for evidence of design and construction

    errors.errors.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    71/100

    Slide 71

    Dynamic TestingDynamic Testing -- Simulated OperationsSimulated Operations

    At the end of the simulation, water should beAt the end of the simulation, water should be

    draineddrained -- equipment dried and purged;equipment dried and purged;

    Depending on the processDepending on the process -- drying may not bedrying may not benecessarynecessary --but purging will always be required;but purging will always be required;

  • 5/26/2018 Plant Commissioning Start Up Procedure

    72/100

    Slide 72

    Dynamic testing with a solventDynamic testing with a solvent

    After safe fluid testing and subsequent repairs andAfter safe fluid testing and subsequent repairs and

    modifications, we are ready for dynamic closedmodifications, we are ready for dynamic closed

    loop testing with a solvent;loop testing with a solvent;

    TheThe solventsolvent is a relatively safe fluid whoseis a relatively safe fluid whose

    properties are close to that of the process fluid, orproperties are close to that of the process fluid, or

    the process fluid itself;the process fluid itself;

    In order to allow for continuous reIn order to allow for continuous re--circulation ofcirculation ofthe solvent and the use of different solvents inthe solvent and the use of different solvents in

    different parts of the plant, temporary lines willdifferent parts of the plant, temporary lines will

    need to be installed.need to be installed.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    73/100

    Slide 73

    Dynamic Testing with Process SolventDynamic Testing with Process Solvent

    Introduce the process solvent. (if there is more thanIntroduce the process solvent. (if there is more than

    one, introduce only one at this stage);one, introduce only one at this stage);

    The dynamic testing procedure used for the safeThe dynamic testing procedure used for the safe

    fluid test is repeated for the process solvent dynamicfluid test is repeated for the process solvent dynamictesting;testing;

    After operations with the first solvent have beenAfter operations with the first solvent have been

    brought completely under control, should the secondbrought completely under control, should the second

    solvent be introduced (if there is one).solvent be introduced (if there is one).

  • 5/26/2018 Plant Commissioning Start Up Procedure

    74/100

    Slide 74

    Dynamic testing with a solventDynamic testing with a solvent

    The purpose of dynamic testing with a solvent is toThe purpose of dynamic testing with a solvent is to

    check out equipment and instrument loops at, orcheck out equipment and instrument loops at, or

    near design conditions prior to the introduction ofnear design conditions prior to the introduction of

    more hazardous process fluid;more hazardous process fluid; No reactions should be allowed to occur duringNo reactions should be allowed to occur during

    these tests, so as to ensure that test fluids remainthese tests, so as to ensure that test fluids remain

    predictable in composition and properties;predictable in composition and properties;

    Guidelines used for safeGuidelines used for safe--testing apply;testing apply;

    Need to plan how solvent will be fed into theNeed to plan how solvent will be fed into the

    system and later removed.system and later removed.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    75/100

    Slide 75

    Stages of dynamic testing with aStages of dynamic testing with a solventsolvent

    Drain safe fluid and purge air used in the previous test fromDrain safe fluid and purge air used in the previous test from

    the system;the system;

    Dry out equipment where safe fluid was water. Check flowDry out equipment where safe fluid was water. Check flow

    sheets for where water is likely to accumulate.sheets for where water is likely to accumulate.

    Fill systems with the solvent. Ensure provisions made forFill systems with the solvent. Ensure provisions made for

    venting and drains closed;venting and drains closed;

    When adequate levels established, place pumps andWhen adequate levels established, place pumps and

    compressors online to complete filling;compressors online to complete filling;

    Start closed loop circulation;Start closed loop circulation;

    Heat up the systems to simulate operating conditions byHeat up the systems to simulate operating conditions by

    placing reflux,placing reflux, reboilerreboilerand condensation systems intoand condensation systems into

    operationoperation

  • 5/26/2018 Plant Commissioning Start Up Procedure

    76/100

    Slide 76

    Stages of dynamic testing with aStages of dynamic testing with a solventsolvent

    Systematically check out instrumentation and control loops;Systematically check out instrumentation and control loops;

    After instruments have checked out, place as many asAfter instruments have checked out, place as many as

    possible on automatic control;possible on automatic control;

    All shifts should go through starting and stoppingAll shifts should go through starting and stoppingequipment, heating and cooling closed loop systems;equipment, heating and cooling closed loop systems;

    DynamicDynamic solventsolvent testing offers the best opportunity fortesting offers the best opportunity for

    operator training before theoperator training before the real thingreal thing;;

    Operate equipment as near as possible to design capacities;Operate equipment as near as possible to design capacities;

    Reliability of emergency shutdown systems and alarmsReliability of emergency shutdown systems and alarms

    must be proven;must be proven;

    Critical instruments must be calibrated over their full range.Critical instruments must be calibrated over their full range.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    77/100

    Slide 77

    Stages of dynamic testing with aStages of dynamic testing with a solventsolvent

    Deliberately operate equipment near its limits:Deliberately operate equipment near its limits:

    Flood columns;Flood columns;

    Ease compressors into mild surges and plot surge curves;Ease compressors into mild surges and plot surge curves;

    Overload condensers;Overload condensers; Do not fear blowing a relief valve or two!Do not fear blowing a relief valve or two!

    After tests have been completed, plant should be ready forAfter tests have been completed, plant should be ready for

    initial operation.initial operation.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    78/100

    Slide 78

    Closed Loop Dynamic Testing withClosed Loop Dynamic Testing with

    Process FluidProcess Fluid Finally, introduce process fluid;Finally, introduce process fluid;

    During this step, instruments should be calibratedDuring this step, instruments should be calibrated

    to cover their full range of flow, temperature andto cover their full range of flow, temperature and

    pressure;pressure;

    Ensure that instruments, processEnsure that instruments, process analysersanalysers andand

    safety devices are kept work properly during thesesafety devices are kept work properly during these

    processes;processes;

    After operations with process fluid are broughtAfter operations with process fluid are brought

    completely under control should the final stage ofcompletely under control should the final stage of

    startstart--up be attempted.up be attempted.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    79/100

    Slide 79

    Preparing to introduce process fluidsPreparing to introduce process fluids

    Before introducing hazardous liquids into theBefore introducing hazardous liquids into the

    plant, we complete additional pressure testing andplant, we complete additional pressure testing and

    purging;purging;

    Need to check that the stresses and strains ofNeed to check that the stresses and strains of

    dynamic testing has not caused any leaksdynamic testing has not caused any leaks -- thesethese

    must be found and fixed;must be found and fixed;

  • 5/26/2018 Plant Commissioning Start Up Procedure

    80/100

    Slide 80

    Pressure testing and purgingPressure testing and purging

    Consists of pressuring and deConsists of pressuring and de--pressuring withpressuring with

    nitrogen several times, until at least

  • 5/26/2018 Plant Commissioning Start Up Procedure

    81/100

    Slide 81

    Dehydrating by CirculationDehydrating by Circulation

    It is usually not possible to waterIt is usually not possible to water--free equipmentfree equipment

    simply by draining;simply by draining;

    Only positive method to waterOnly positive method to water--free processfree process

    equipment is oil circulation followed by repeatedequipment is oil circulation followed by repeateddraining of low points;draining of low points;

    Ensure sufficient low point drains are provided onEnsure sufficient low point drains are provided on

    piping, control valve loops, vessels and processpiping, control valve loops, vessels and process

    machinery;machinery; Startup linesStartup lines -- deliver oil to upper part (trays) ofdeliver oil to upper part (trays) of

    distillation towers (size for 20% of net distillatedistillation towers (size for 20% of net distillate

    product rate);product rate);

  • 5/26/2018 Plant Commissioning Start Up Procedure

    82/100

    Slide 82

    Start Up and Initial OperationStart Up and Initial Operation

  • 5/26/2018 Plant Commissioning Start Up Procedure

    83/100

    Slide 83

    Start Up and Initial OperationStart Up and Initial Operation

    Preparation and planning

    Performance and

    Acceptance testing

    Post Commissioning

    Introduction of process fluidIntroduction of process fluid

    StartStart--up and initial operationup and initial operation TroubleTrouble--shooting andshooting and

    problem correction.problem correction.

    Plant taken to full operations.Plant taken to full operations.

    Mechanical Completion

    and Integrity checking

    Pre-commissioning &

    Operational Testing

    Start Up & Initial

    Operation

  • 5/26/2018 Plant Commissioning Start Up Procedure

    84/100

    Slide 84

    Starting Up the PlantStarting Up the Plant

    Productrefining

    RecoveryReactionFeedPreparation

    Most plants in petrochemical/chemical industryMost plants in petrochemical/chemical industry

    have the followinghave the following generalgeneral form.form.

    Start Up from theStart Up from the

    End of the ProcessEnd of the Process

    and Work backand Work back

  • 5/26/2018 Plant Commissioning Start Up Procedure

    85/100

    Slide 85

    Start Up LogicStart Up Logic

    It is common practice to buy in product and startIt is common practice to buy in product and start

    up the last past of the process first and workup the last past of the process first and work

    backwards to the front. E.g.backwards to the front. E.g.

    Start up refining, get this working and inStart up refining, get this working and in

    control;control;

    Then possibly start up reaction and recovery;Then possibly start up reaction and recovery;

    Finally, feed preparation.Finally, feed preparation.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    86/100

    Slide 86

    Into the initial operationInto the initial operation

    Once raw materials are fed into the plantOnce raw materials are fed into the plant -- usuallyusually

    at reduced rate until reaction conditions have beenat reduced rate until reaction conditions have been

    established;established;

    As each section is started up, establish as quicklyAs each section is started up, establish as quicklyas possible that process conditions are as expected;as possible that process conditions are as expected;

    If potentially serious problems develop, thereIf potentially serious problems develop, there

    should be no hesitation on going into anshould be no hesitation on going into an

    emergency shutdown.emergency shutdown.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    87/100

    Slide 87

    Ramping up the plantRamping up the plant

    Plant is brought slowly to design feedPlant is brought slowly to design feed--rates andrates and

    operating conditions;operating conditions;

    Usually done in steps with operating dataUsually done in steps with operating data

    evaluated and verified as OK at each step;evaluated and verified as OK at each step;

    Plant and laboratory data are now being collectedPlant and laboratory data are now being collected

    and should be being evaluated promptly;and should be being evaluated promptly;

  • 5/26/2018 Plant Commissioning Start Up Procedure

    88/100

    Slide 88

    Coordination and Supervision duringCoordination and Supervision during

    start upstart up Additional personnel, both supervisory andAdditional personnel, both supervisory and onon--

    thethe--groundground are required at this stage;are required at this stage;

    Cooperation between startup personnel and plantCooperation between startup personnel and plantsupervisory personnel is critical at this stage:supervisory personnel is critical at this stage:

    Need a daily meeting at least;Need a daily meeting at least;

    Often, a briefing each shift.Often, a briefing each shift.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    89/100

    Slide 89

    Trouble ShootingTrouble Shooting

    At this stage, many problem with equipment of theAt this stage, many problem with equipment of the

    process itself may become apparent;process itself may become apparent;

    The commissioning process goes through what isThe commissioning process goes through what isoften an intense (and hopefully short) period ofoften an intense (and hopefully short) period of

    problem trouble shooting, problem solving,problem trouble shooting, problem solving,

    engineering correction and plant modification;engineering correction and plant modification;

  • 5/26/2018 Plant Commissioning Start Up Procedure

    90/100

    Slide 90

    Performance and Acceptance TrailsPerformance and Acceptance Trails

  • 5/26/2018 Plant Commissioning Start Up Procedure

    91/100

    Slide 91

    Performance and Acceptance TestingPerformance and Acceptance Testing

    Preparation and planning

    Performance and

    Acceptance testing

    Post Commissioning

    Performance trails;Performance trails;

    Formal Acceptance testFormal Acceptance test

    Mechanical Completion

    and Integrity checking

    Pre-commissioning &

    Operational Testing

    Start Up & Initial

    Operation

  • 5/26/2018 Plant Commissioning Start Up Procedure

    92/100

    Slide 92

    The Performance TrailsThe Performance Trails

    Once the plant is fully operational, the finalOnce the plant is fully operational, the final

    proving trailproving trail or performance run is performed inor performance run is performed in

    order to prove the plant can do what it is supposedorder to prove the plant can do what it is supposed

    to do;to do; The values or range of values for each independentThe values or range of values for each independent

    variablevariable -- flow, temperature, pressure, level,flow, temperature, pressure, level,

    concentrations, etc. to which the plant must beconcentrations, etc. to which the plant must be

    operated to are determined;operated to are determined; The plant is brought up to those conditions and theThe plant is brought up to those conditions and the

    prepre--agreed trial period begins.agreed trial period begins.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    93/100

    Slide 93

    Before the trail or performance run needBefore the trail or performance run need

    to ensure thatto ensure that Control of plant operating conditions has beenControl of plant operating conditions has been

    achieved. I.e. temperature, pressures, levels andachieved. I.e. temperature, pressures, levels and

    analyses are reasonably constant or in the case of aanalyses are reasonably constant or in the case of a

    batch process, there is repeatability;batch process, there is repeatability;

    Daily material and energy balanced can beDaily material and energy balanced can be

    performed and that these agree withperformed and that these agree with officialofficial

    production figures;production figures;

    Product specifications are being achievedProduct specifications are being achieved

    consistently.consistently.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    94/100

    Slide 94

    Need to verifyNeed to verify ..

    Physical operation, capability and capacity of plantPhysical operation, capability and capacity of plant

    and equipment;and equipment;

    Energy and mass balance;Energy and mass balance; Process chemistry;Process chemistry;

    Efficiencies, yields and quality;Efficiencies, yields and quality;

    All to specification.All to specification.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    95/100

    Slide 95

    AcceptanceAcceptance

    When the plant has met the Performance andWhen the plant has met the Performance and

    Acceptance test requirements designed by theAcceptance test requirements designed by the

    commissioning team there is usually a formalcommissioning team there is usually a formal

    acceptance process involving signing of acceptanceacceptance process involving signing of acceptance

    certificates;certificates;

    Once the plant is accepted it is officially part of theOnce the plant is accepted it is officially part of the

    normal operationsnormal operations -- the responsibility of operationsthe responsibility of operations

    and maintenance;and maintenance;

    Commissioning is officially over;Commissioning is officially over;

    The may still be outstandingThe may still be outstandingpunchlistpunchlist itemsitems

  • 5/26/2018 Plant Commissioning Start Up Procedure

    96/100

    Slide 96

    Acceptance TestingAcceptance Testing

    It is common practice to prove performanceIt is common practice to prove performance

    repeatability and plant integrity as part of therepeatability and plant integrity as part of the

    performance test. That is:performance test. That is:

    Shutdown and Start Up the plant on severalShutdown and Start Up the plant on severaloccasions and bring it up to test conditions tooccasions and bring it up to test conditions to

    prove repeatability. Also ramp down and ramp upprove repeatability. Also ramp down and ramp up

    while online;while online;

    ReRe--inspection of critical process equipmentinspection of critical process equipment --particularly columns to ensure they have not beenparticularly columns to ensure they have not been

    damaged by the performance run.damaged by the performance run.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    97/100

    Slide 97

    Commercial Significant of AcceptanceCommercial Significant of Acceptance

    Formal Acceptance represents formal acknowledgmentFormal Acceptance represents formal acknowledgment

    that thethat the

    Contractor has fullContractor has full--filled their contractualfilled their contractual

    obligations;obligations;

    Commissioning team have fullCommissioning team have full--filled theirfilled their

    obligations;obligations;

    Completion of the Capital Project and transfer toCompletion of the Capital Project and transfer to

    Operations;Operations;

    Expenses and costs from acceptance onwards are nowExpenses and costs from acceptance onwards are now

    operating expenses not capital project costs;operating expenses not capital project costs;

    All subject to agreed punchAll subject to agreed punch--list items.list items.

  • 5/26/2018 Plant Commissioning Start Up Procedure

    98/100

    Slide 98

    PostPost--CommissioningCommissioning

  • 5/26/2018 Plant Commissioning Start Up Procedure

    99/100

    Slide 99

    Post CommissioningPost Commissioning

    Preparation and planning

    Mechanical Completion

    and Integrity checking

    Pre-commissioning &

    Operational Testing

    Start Up & Initial

    Operation

    Performance and

    Acceptance testing

    Post Commissioning

    From plant onFrom plant on--stream to settledstream to settled

    down and in regular production;down and in regular production;

    Adjustments, modifications andAdjustments, modifications andfault correction;fault correction;

    Completion of outstandingCompletion of outstanding

    punchlistpunchlist itemsitems

  • 5/26/2018 Plant Commissioning Start Up Procedure

    100/100

    Post CommissioningPost Commissioning

    Covers the period immediately after Acceptance;Covers the period immediately after Acceptance;

    Outstanding punchOutstanding punch--list items are completed;list items are completed;

    The first routine maintenance checks are performed,The first routine maintenance checks are performed,

    findings evaluated and reported;findings evaluated and reported;

    Process equipment and items covered by warrantyProcess equipment and items covered by warranty

    are scrutinized for signs of premature wearare scrutinized for signs of premature wear--out orout or

    problems;problems;

    Operating data is collected and evaluated to ensureOperating data is collected and evaluated to ensure

    consistent plant operations are maintained andconsistent plant operations are maintained and

    sustainable.sustainable.