plant commissioning start up procedure
DESCRIPTION
Standard Procedure for Industrial Plant Commissioning and Start-UpTRANSCRIPT
-
5/26/2018 Plant Commissioning Start Up Procedure
1/100
Slide 1
Plant commissioning & start upPlant commissioning & start up
procedureprocedure
-
5/26/2018 Plant Commissioning Start Up Procedure
2/100
Slide 2
The Commissioning ProcessThe Commissioning Process
Key StagesKey StagesPreparation and planning
Mechanical Completion
and Integrity checking
Performance and
Acceptance testing
Start Up & Initial
Operation
Post Commissioning
Pre-commissioning &
Operational Testing
-
5/26/2018 Plant Commissioning Start Up Procedure
3/100
Slide 3
The Commissioning Process DetailThe Commissioning Process Detail -- 11Preparation and planning
Mechanical Completion
and Integrity checking
Performance and
Acceptance testing
Start Up & Initial
Operation
Pre-commissioning &
Operational Testing
Appointment of CommissioningAppointment of Commissioning
Manager or Lead CommissioningManager or Lead Commissioning
Engineer;Engineer;
Appointment of Commissioning TeamAppointment of Commissioning Team
Members and Support Staff;Members and Support Staff;
Training;Training;
Information Compilation;Information Compilation;
Safety and Risk Assessment;Safety and Risk Assessment;
Commi ssioning StrategyCommi ssioning StrategyDevelopment;Development;
Procedures and Checkl i stProcedures and Checkl i st
Development;Development;
Detailed Plan and Budget Preparation;Detailed Plan and Budget Preparation;Post Commissioning
-
5/26/2018 Plant Commissioning Start Up Procedure
4/100
Slide 4
Commissioning StrategyCommissioning Strategy
Equipment LevelActivities
System
Level Activities
Facility/Plant
Level Activities
Commissioning
StrategyCommissioning Master Plan
Individual item commissioning
plans, procedures and checklists
-
5/26/2018 Plant Commissioning Start Up Procedure
5/100
Slide 5
Facility Commissioning IssuesFacility Commissioning Issues
Time phasing construction and commissioning activitiesTime phasing construction and commissioning activities
Time phasing the commissioning of the various parts of theTime phasing the commissioning of the various parts of the
plant relative to each other;plant relative to each other;
Relationships and timings determining when various systemsRelationships and timings determining when various systemsneed to be available:need to be available:
Electrical, Steam, Water, InstrumentationElectrical, Steam, Water, Instrumentation
Sequencing of the overall plant startup and shutdown toSequencing of the overall plant startup and shutdown to
ensure we do not create unsafe conditions;ensure we do not create unsafe conditions;
Initial start up;Initial start up;
Process Control and Shutdown;Process Control and Shutdown;
Performance testing;Performance testing;
-
5/26/2018 Plant Commissioning Start Up Procedure
6/100
Slide 6
Developing Startup ProceduresDeveloping Startup Procedures
Engineering and construction companies generally follow aEngineering and construction companies generally follow a
systematic procedure where by their startup engineerssystematic procedure where by their startup engineers
review the process design several times as it is developed;review the process design several times as it is developed;
After the first review, a preliminary startAfter the first review, a preliminary start--up and operationsup and operations
procedure is written;procedure is written;
Decide what must be added to the design to make theDecide what must be added to the design to make the
process capable of being started up and operated;process capable of being started up and operated;
By the time the final engineering flowBy the time the final engineering flow--sheets have beensheets have beenreleased a complete startup and operating instructionsreleased a complete startup and operating instructions
manual should have been completed.manual should have been completed.
-
5/26/2018 Plant Commissioning Start Up Procedure
7/100
Slide 7
Issues consideredIssues considered Are various part of the process too depend on oneAre various part of the process too depend on one
another;another;
Is there enough surge capacity;Is there enough surge capacity;
Are there provisions to prevent abnormalAre there provisions to prevent abnormal
pressures, temperatures and rates of reaction;pressures, temperatures and rates of reaction;
Where are additional valves and bypass linesWhere are additional valves and bypass lines
needed;needed; Special lines to allow equipment to be started upSpecial lines to allow equipment to be started up
and rerun product/raw materials.and rerun product/raw materials.
-
5/26/2018 Plant Commissioning Start Up Procedure
8/100
Slide 8
System Level ActivitiesSystem Level Activities
Utilities systemsUtilities systems -- steam, instrument air, processsteam, instrument air, process
water, fire water, drainage, condensate return;water, fire water, drainage, condensate return;
Electrical systems;Electrical systems;
Instrumentation and instrumentation systems;Instrumentation and instrumentation systems;
Cleaning and flushing;Cleaning and flushing;
Purging;Purging; Initial start up and shutdowns;Initial start up and shutdowns;
Performance testing;Performance testing;
-
5/26/2018 Plant Commissioning Start Up Procedure
9/100
Slide 9
Equipment Level ActivitiesEquipment Level Activities
Pressure testing & mechanical integrity testing ofPressure testing & mechanical integrity testing of
vessel, columns and pipe work;vessel, columns and pipe work;
Heat Exchangers, condensers, coolers etc.Heat Exchangers, condensers, coolers etc. Mechanical equipment and machinery;Mechanical equipment and machinery;
Control Systems and Instrumentation;Control Systems and Instrumentation;
Operational testing;Operational testing;
Proof testing and acceptance.Proof testing and acceptance.
-
5/26/2018 Plant Commissioning Start Up Procedure
10/100
Slide 10
What can be done before mechanicalWhat can be done before mechanical
completioncompletion
Utilities commissioning
Lube and Seal-Oil Systems Cleaned
Instrumentation and Control Loops Proven
Piping, Towers and Vessels Cleaned
Boil-Out, Dry-Out and Acid Cleaning
Turbine, Motor and Pump Run-Ins Nitrogen Purge and Tightness Testing
-
5/26/2018 Plant Commissioning Start Up Procedure
11/100
Slide 11
BuildingBuilding OrganisationalOrganisational LearningLearning
Corporate
Knowledge Base
Best Practice
Benchmarking
IndustryStandards
Legislation
Process Design
Specific
Machinery &
Equipment
Procedures and
Check sheets
Improvement
Processes
Experience
Incidents and
Near Misses
-
5/26/2018 Plant Commissioning Start Up Procedure
12/100
Slide 12
ProceduresProcedures Procedures are written routines/instructions thatProcedures are written routines/instructions that
describe the logical sequence of activities required todescribe the logical sequence of activities required to
perform a work process and the specific actionsperform a work process and the specific actions
required to perform each activity;required to perform each activity; If there are no written procedures, there is no basis forIf there are no written procedures, there is no basis for
monitoring performance, focus for improvement ormonitoring performance, focus for improvement or
mechanism by which to capture learning;mechanism by which to capture learning;
The establishment of procedures and routines allowThe establishment of procedures and routines allow
more time and mental energy to deal with themore time and mental energy to deal with the
unexpected, which always happen duringunexpected, which always happen during
commissioning.commissioning.
-
5/26/2018 Plant Commissioning Start Up Procedure
13/100
Slide 13
Commissioning/Startup LogicCommissioning/Startup Logic A Critical Path Network (Plan) with written procedures withA Critical Path Network (Plan) with written procedures with
related documents are required. These should define for therelated documents are required. These should define for the
facility, each plant system:facility, each plant system:
The order in which the systems will be started up;The order in which the systems will be started up; Individual activities at each stage;Individual activities at each stage;
Operation testing requirements;Operation testing requirements;
Durations, waiting times, cooling times;Durations, waiting times, cooling times;
Total duration for starting up each system;Total duration for starting up each system; Resources requiredResources required -- labourlabour, materials, equipment,, materials, equipment,
services;services;
Temperatures, pressures, fluid flows used.Temperatures, pressures, fluid flows used.
-
5/26/2018 Plant Commissioning Start Up Procedure
14/100
Slide 14
Commissioning/Startup and Shutdown IssuesCommissioning/Startup and Shutdown Issues
At the facility, system and equipment level, weAt the facility, system and equipment level, we
want to avoid:want to avoid:
Creation/existence of explosive mixtures, usuallyCreation/existence of explosive mixtures, usually
because of the presence of air;because of the presence of air;
Water hammer and water based explosionWater hammer and water based explosion
effects, due to contact between water and hoteffects, due to contact between water and hot
substances (steam, oil, etc.);substances (steam, oil, etc.);
In particular, during commissioning hot fluids andIn particular, during commissioning hot fluids andgases will be coming into contact with coldgases will be coming into contact with cold
surfaces in places that would be hot under normalsurfaces in places that would be hot under normal
operations.operations.
-
5/26/2018 Plant Commissioning Start Up Procedure
15/100
Slide 15
Mechanical Completion and IntegrityMechanical Completion and Integrity
CheckingChecking
-
5/26/2018 Plant Commissioning Start Up Procedure
16/100
Slide 16
Mechanical Completion and IntegrityMechanical Completion and Integrity
InspectionInspectionPreparation and planning
Mechanical Completion
and Integrity checking
Performance and
Acceptance testing
Start Up & Initial
Operation
Pre-commissioning &
Operational Testing
InspectionInspection
Pressure testingPressure testing
Cleaning and FlushingCleaning and Flushing
Machinery checkoutMachinery checkout
Post Commissioning
-
5/26/2018 Plant Commissioning Start Up Procedure
17/100
Slide 17
Categories of Process EquipmentCategories of Process Equipment Distillation Towers/Fractionation TowersDistillation Towers/Fractionation Towers
ReboilersReboilers & Other Shell & Tube Heat Exchangers& Other Shell & Tube Heat Exchangers
Boilers and Fired HeatersBoilers and Fired Heaters
Pressure Vessels and PipePressure Vessels and Pipe--workwork
FinFin--Fan CoolersFan Coolers
CondensersCondensers
Machinery/Rotating EquipmentMachinery/Rotating Equipment
ValvesValves
InstrumentationInstrumentation
Electrical EquipmentElectrical Equipment
-
5/26/2018 Plant Commissioning Start Up Procedure
18/100
Slide 18
Machinery/ Rotating EquipmentMachinery/ Rotating Equipment
PumpsPumps
Steam TurbinesSteam Turbines
Gas TurbinesGas Turbines CompressorsCompressors
Gas EnginesGas Engines
Electric MotorsElectric Motors
-
5/26/2018 Plant Commissioning Start Up Procedure
19/100
Slide 19
Mechanical Completion and IntegrityMechanical Completion and Integrity
InspectionInspection
Involves checking that everything has been built and itInvolves checking that everything has been built and it
there as per specification. Refer:there as per specification. Refer:
Piping Plan Drawings;Piping Plan Drawings;
Layout and construction drawings;Layout and construction drawings;
P & IDP & IDss
Electrical systems, Instrumentation and control systemsElectrical systems, Instrumentation and control systems
checkout down by appropriately qualified personnelcheckout down by appropriately qualified personnel
(Electricians and Instrumentation technicians).(Electricians and Instrumentation technicians). General commissioning engineers generally do not getGeneral commissioning engineers generally do not get
involved in this in a handsinvolved in this in a hands--on manner.on manner.
-
5/26/2018 Plant Commissioning Start Up Procedure
20/100
Slide 20
Mechanical Completion and IntegrityMechanical Completion and Integrity
Inspection ProcedureInspection Procedure
Divide plant into manageable areas;Divide plant into manageable areas;
In a large plant, assign individuals or teams toIn a large plant, assign individuals or teams to
specific areas;specific areas; Establish a master set of piping plan drawings andEstablish a master set of piping plan drawings and
P&IDP&IDs, mark up areas:s, mark up areas:
Individual commissioning engineers or teams walkIndividual commissioning engineers or teams walk
every line and mark up every item that can beevery line and mark up every item that can beconfirmed as present on master set of drawings;confirmed as present on master set of drawings;
Use differentUse different colouredcoloured highlighterhighlighterpens topens to
indicate different services.indicate different services.
-
5/26/2018 Plant Commissioning Start Up Procedure
21/100
Slide 21
Mechanical Completion and Integrity InspectionMechanical Completion and Integrity Inspection
Every line must be walked! Physically sight everything!Every line must be walked! Physically sight everything!
-
5/26/2018 Plant Commissioning Start Up Procedure
22/100
Slide 22
Mechanical Completion and IntegrityMechanical Completion and Integrity
Inspection ProcedureInspection Procedure -- Hints/TipsHints/Tips
Ensure pipes, vessels, valves etc. are all in the rightEnsure pipes, vessels, valves etc. are all in the right
place;place;
Valves are correct typeValves are correct type -- globe, gate, control;globe, gate, control; Vents, drains, steam traps etc.Vents, drains, steam traps etc.
Flanges, bolts, types of bolts;Flanges, bolts, types of bolts;
Blind flanges andBlind flanges and swingableswingableblinds in place,blinds in place,
correct rating;correct rating;
Check all tag numbers;Check all tag numbers;
PunchlistPunchlist any nonany non--conformances.conformances.
-
5/26/2018 Plant Commissioning Start Up Procedure
23/100
Slide 23
New PlantPiping Tie-ins!
-
5/26/2018 Plant Commissioning Start Up Procedure
24/100
Slide 24
Pipe StressingPipe Stressing
Piping should provide adequately for expansion andPiping should provide adequately for expansion and
contraction due to temperature changes, withoutcontraction due to temperature changes, without
placing excessive stresses on equipment;placing excessive stresses on equipment;
Misalignment between matching flanges on pipeMisalignment between matching flanges on pipe--workwork --particular where there are changes inparticular where there are changes in
direction (elbows) can cause stressing;direction (elbows) can cause stressing;
Misalignments where pipeMisalignments where pipe--work connects towork connects to
machinery, vessels and other process equipment;machinery, vessels and other process equipment;
Can often be seen visually, or checked with gaugesCan often be seen visually, or checked with gauges
using the same procedures we use to align rotatingusing the same procedures we use to align rotating
equipment.equipment.
-
5/26/2018 Plant Commissioning Start Up Procedure
25/100
Slide 25
Piping and Equipment SupportsPiping and Equipment Supports
-
5/26/2018 Plant Commissioning Start Up Procedure
26/100
Slide 26
Piping and equipment supportsPiping and equipment supports
Mobile supports permit and guide the thermalMobile supports permit and guide the thermal
growth of equipment undergoing temperaturegrowth of equipment undergoing temperature
change;change; If they do not function correctly, vessels,If they do not function correctly, vessels,
equipment, pipe work, nozzles heat exchangersequipment, pipe work, nozzles heat exchangers
etc. may be damaged.etc. may be damaged.
-
5/26/2018 Plant Commissioning Start Up Procedure
27/100
Slide 27
Typical piping support methodsTypical piping support methods
-
5/26/2018 Plant Commissioning Start Up Procedure
28/100
Slide 28
Piping and equipment supportsPiping and equipment supports
Inspection prior to start up:Inspection prior to start up:
Check that installed according to specification and not jammed;Check that installed according to specification and not jammed;
Inspection during warm up:Inspection during warm up:
Check thermal growth is occurring and supports are respondingCheck thermal growth is occurring and supports are respondingas per design;as per design;
Check that there is no surface buckling or crimpingCheck that there is no surface buckling or crimping -- this needsthis needs
to be corrected;to be corrected;
Check expansion joints;Check expansion joints; Check long straight runs of piping for bowing or support shoesCheck long straight runs of piping for bowing or support shoes
that may have slipped;that may have slipped;
Rule of thumbRule of thumb -- bowing is excessive if you can see it.bowing is excessive if you can see it.
-
5/26/2018 Plant Commissioning Start Up Procedure
29/100
Slide 29
Piping and equipment supportsPiping and equipment supports
Inspection after coolInspection after cool--down:down:
Check that sliding supports have returned toCheck that sliding supports have returned to
original positions;original positions;
Establish that equipment can expand andEstablish that equipment can expand and
contract as required.contract as required.
-
5/26/2018 Plant Commissioning Start Up Procedure
30/100
Slide 30
Inspection of spring supportsInspection of spring supports
Before hydroBefore hydro--testing:testing:
Check that spring stops are installed. (If not, theCheck that spring stops are installed. (If not, the
weight of water in pipe will deform the spring).weight of water in pipe will deform the spring). After hydroAfter hydro--testing but before heating:testing but before heating:
Check that stops are removed;Check that stops are removed;
Check that spring pointer is positioned to coldCheck that spring pointer is positioned to coldsetting;setting;
-
5/26/2018 Plant Commissioning Start Up Procedure
31/100
Slide 31
Inspection of spring supportsInspection of spring supports
During and at end of heating:During and at end of heating:
Check pointer has not exceeded hot setting;Check pointer has not exceeded hot setting;
After cool down:After cool down:
check to establish piping can expand andcheck to establish piping can expand and
contract as required;contract as required;
establish that springs can absorb loads.establish that springs can absorb loads.
-
5/26/2018 Plant Commissioning Start Up Procedure
32/100
Slide 32
Vessels and ColumnsVessels and Columns
-
5/26/2018 Plant Commissioning Start Up Procedure
33/100
Slide 33
Inspection of Vessels and ColumnsInspection of Vessels and Columns
The inspection of vessels, columns and reactorsThe inspection of vessels, columns and reactors
should be scheduled to be completed beforeshould be scheduled to be completed before
construction has closed them up;construction has closed them up;
Other inspectionsOther inspections -- e.g. for completeness or piping,e.g. for completeness or piping,
insulation, safety etc. can be scheduled later;insulation, safety etc. can be scheduled later;
If a vessel has been sealed up by construction, it isIf a vessel has been sealed up by construction, it is
your duty to inspect it, even it construction resist.your duty to inspect it, even it construction resist.
-
5/26/2018 Plant Commissioning Start Up Procedure
34/100
Slide 34
Inspection of Vessels and ColumnsInspection of Vessels and Columns
Check that distributors have been installedCheck that distributors have been installed
correctly;correctly;
DeDe--misters installed correctly and of correctmisters installed correctly and of correctmaterials, design, type;materials, design, type;
Vortex breakers in place;Vortex breakers in place;
TraysTrays --packed orpacked or bubblebubble--capcap are correct:are correct:
Bubble caps not jammed or damaged, downBubble caps not jammed or damaged, downcomers clear, supports all OK.comers clear, supports all OK.
-
5/26/2018 Plant Commissioning Start Up Procedure
35/100
Slide 35
Pressure TestingPressure Testing
-
5/26/2018 Plant Commissioning Start Up Procedure
36/100
Slide 36
Pressure TestingPressure Testing -- ObjectivesObjectives
The objective of pressure testing is to confirm theThe objective of pressure testing is to confirm the
mechanical integrity of the plant;mechanical integrity of the plant;
Verifying capability of containing the pressures it hasVerifying capability of containing the pressures it has
been designed to hold;been designed to hold;
Ensure there are no leaks and verify that the plant canEnsure there are no leaks and verify that the plant can
be reliably made leak free;be reliably made leak free;
Identify any vulnerabilities well before the plant isIdentify any vulnerabilities well before the plant isplaced into service;placed into service;
Meet the requirements of legislation, local,Meet the requirements of legislation, local,
international and industry standards.international and industry standards.
-
5/26/2018 Plant Commissioning Start Up Procedure
37/100
Slide 37
Pressure TestingPressure Testing -- responsibilitiesresponsibilities
Pressure tests of tanks, reactors and piping forPressure tests of tanks, reactors and piping for
mechanical strength and tightness of joints ismechanical strength and tightness of joints is
usually done by the construction team;usually done by the construction team; Commissioning team representatives shouldCommissioning team representatives should
witness and certify the tests;witness and certify the tests;
Need to verify that all necessary safety precautionsNeed to verify that all necessary safety precautions
have been taken;have been taken;
-
5/26/2018 Plant Commissioning Start Up Procedure
38/100
Slide 38
Pressure TestingPressure Testing --proceduresprocedures
Water for testing and flushing should contain a rustWater for testing and flushing should contain a rust
inhibitorinhibitor -- one low in chloride content for stainlessone low in chloride content for stainless
steel lines;steel lines;
After testing, water should be drained completelyAfter testing, water should be drained completelyfrom all lines that do not normally carry water,from all lines that do not normally carry water,
steam or steam condensate;steam or steam condensate;
All low points should be checked for presence ofAll low points should be checked for presence of
water;water; Lines should be dried by blowing hot air, dry inertLines should be dried by blowing hot air, dry inert
gas or instrument air.gas or instrument air.
-
5/26/2018 Plant Commissioning Start Up Procedure
39/100
Slide 39
Pressure TestingPressure Testing -- Vacuum SystemsVacuum Systems
Final checks of vacuum systems are bestFinal checks of vacuum systems are best
performed by pulling a vacuum and observing theperformed by pulling a vacuum and observing the
rate of pressure rise in the blocked in system;rate of pressure rise in the blocked in system;
Excessive leaks can then be located by applying aExcessive leaks can then be located by applying amild positive pressure and testing each flange withmild positive pressure and testing each flange with
bubble solution.bubble solution.
-
5/26/2018 Plant Commissioning Start Up Procedure
40/100
Slide 40
Pressure TestingPressure Testing -- Procedures 2Procedures 2
Isometric drawings of all systems to be tested should beIsometric drawings of all systems to be tested should be
displayed on a board and marked up as each section isdisplayed on a board and marked up as each section is
tested;tested;
HydrotestingHydrotesting of piping and equipment according to codeof piping and equipment according to code
requirements to confirm mechanical strength should berequirements to confirm mechanical strength should be
carried out on groups of equipment naturally suggested bycarried out on groups of equipment naturally suggested by
design pressure and function;design pressure and function;
All water, steam, condensate, oil, gas and process steamAll water, steam, condensate, oil, gas and process steam
piping should be hydrotested;piping should be hydrotested; Major equipment that has already been tested as part ofMajor equipment that has already been tested as part of
manufacturing may be isolated by blanks.manufacturing may be isolated by blanks.
-
5/26/2018 Plant Commissioning Start Up Procedure
41/100
Slide 41
Cleaning and FlushingCleaning and Flushing
-
5/26/2018 Plant Commissioning Start Up Procedure
42/100
Slide 42
Cleaning and FlushingCleaning and Flushing
Need to ensure no construction debris is left inNeed to ensure no construction debris is left in
pipes of vesselspipes of vessels -- welding rods, bolts, gloves, ragswelding rods, bolts, gloves, rags
etc.etc.
Large debris (lumber, cable, packaging) shouldLarge debris (lumber, cable, packaging) should
have been removed during mechanical integrityhave been removed during mechanical integrity
inspections;inspections;
Small debris (rags, nuts, dirt) must be flushed outSmall debris (rags, nuts, dirt) must be flushed out
of all pipe and vessels;of all pipe and vessels;
Where oil coatings must be removed, chemicalWhere oil coatings must be removed, chemical
cleaning is necessary.cleaning is necessary.
-
5/26/2018 Plant Commissioning Start Up Procedure
43/100
Slide 43
Cleaning and FlushingCleaning and Flushing
Before flushing is started, check the processBefore flushing is started, check the process
thoroughly to ensure:thoroughly to ensure:
Screens have been installed in front of pumpScreens have been installed in front of pumpsuctions;suctions;
Blinds in front of equipment such asBlinds in front of equipment such as
compressors and turbines;compressors and turbines;
JumperJumper spool pieces to allow for continuity ofspool pieces to allow for continuity offlow.flow.
-
5/26/2018 Plant Commissioning Start Up Procedure
44/100
Slide 44
FlushingFlushing
Can be handled by geographic plant area;Can be handled by geographic plant area;
Sections too large for water flushing:Sections too large for water flushing:
Pipes greater than 30 in diameter (0.75 m), orPipes greater than 30 in diameter (0.75 m), or
Pipes that should not be touched with water;Pipes that should not be touched with water;
Should all be blown out with air or inert gas.Should all be blown out with air or inert gas.
-
5/26/2018 Plant Commissioning Start Up Procedure
45/100
Slide 45
FlushingFlushing
Regardless of whether pipes are cleaned withRegardless of whether pipes are cleaned with
water, steam, air or nitrogen, flow velocitieswater, steam, air or nitrogen, flow velocities
should be high enough to ensure that pipes willshould be high enough to ensure that pipes will
be suitably scoured;be suitably scoured; Need to ensure that the debris from one piece ofNeed to ensure that the debris from one piece of
equipment will not simply be flushed intoequipment will not simply be flushed into
another;another;
Water velocities should be at least 12 ft/secWater velocities should be at least 12 ft/sec(approx. 3.75 m/sec);(approx. 3.75 m/sec);
Air velocities a minimum of 200 ft/sec (approx.Air velocities a minimum of 200 ft/sec (approx.
65 m/sec);65 m/sec);
-
5/26/2018 Plant Commissioning Start Up Procedure
46/100
Slide 46
PrePre--commissioning and Operationalcommissioning and Operational
TestingTesting
-
5/26/2018 Plant Commissioning Start Up Procedure
47/100
Slide 47
The Commissioning Process DetailThe Commissioning Process Detail -- 33
Preparation and planning
Performance and
Acceptance testing
Start Up & Initial
Operation
Steam and other utilitiesSteam and other utilitiescommissioned and introduced;commissioned and introduced;
Dry running trials;Dry running trials;
Hot running trials;Hot running trials;
SafeSafe--fluid dynamic testing;fluid dynamic testing;
Solvent dynamic testing;Solvent dynamic testing;
Process fluid tests.Process fluid tests.
Mechanical Completion
and Integrity checking
Pre-commissioning &
Operational Testing
Post Commissioning
-
5/26/2018 Plant Commissioning Start Up Procedure
48/100
Slide 48
Commissioning UtilitiesCommissioning Utilities
-
5/26/2018 Plant Commissioning Start Up Procedure
49/100
Slide 49
Commissioning UtilitiesCommissioning Utilities
Utilities commissioning usually represents the firstUtilities commissioning usually represents the first
phase of commissioning, as these usually need tophase of commissioning, as these usually need to
operational first, before the rest of the plant can beoperational first, before the rest of the plant can be
commissioned;commissioned;
The steps for commissioning each utility should beThe steps for commissioning each utility should be
planned in detail;planned in detail;
Provides planning practice for planning the startupProvides planning practice for planning the startupof the main plant.of the main plant.
-
5/26/2018 Plant Commissioning Start Up Procedure
50/100
Slide 50
Commissioning UtilitiesCommissioning Utilities -- Broad GuidelinesBroad Guidelines
Check supply pressures of all servicesCheck supply pressures of all services -- steam, cooling water,steam, cooling water,
instrument air, nitrogen etc.instrument air, nitrogen etc.
At the most distant points, open drains, vent valves or pipeAt the most distant points, open drains, vent valves or pipe
flanges and purge until fluids come out clean and rust free;flanges and purge until fluids come out clean and rust free;
Purge/blow out lines to each piece of equipment;Purge/blow out lines to each piece of equipment;
Check that instrument air is clean and dry, and at correctCheck that instrument air is clean and dry, and at correct
pressure;pressure;
Circulate water to waste water system until water lines clear anCirculate water to waste water system until water lines clear andd
clean;clean;
Flush waste water and drain systems to ensure no blockages;Flush waste water and drain systems to ensure no blockages;
Check operation of steam traps;Check operation of steam traps;
Drain condensate to waste water until is is clean.Drain condensate to waste water until is is clean.
-
5/26/2018 Plant Commissioning Start Up Procedure
51/100
Slide 51
Commissioning UtilitiesCommissioning Utilities
Introducing SteamIntroducing Steam Steam usually represents the firstSteam usually represents the first hazardoushazardous fluidfluid
introduced into theintroduced into the newnew system;system;
Admit steam slowly into the distribution system withAdmit steam slowly into the distribution system with
atmospheric bleeds open:atmospheric bleeds open: Cold pipes will condense steam in places where itCold pipes will condense steam in places where it
would not under normal operation;would not under normal operation;
Can lead toCan lead to water hammerwater hammer -- can distort and rupturecan distort and rupture
lines;lines;
After system has been warmed, slowly raise pressure andAfter system has been warmed, slowly raise pressure and
blow down the system with traps bypassed, until clean;blow down the system with traps bypassed, until clean;
Then place steam traps into service and check operation.Then place steam traps into service and check operation.
-
5/26/2018 Plant Commissioning Start Up Procedure
52/100
Slide 52
High Pressure Steam SystemsHigh Pressure Steam Systems
Specific IssuesSpecific Issues The cleanliness and purity of high pressure steam systemsThe cleanliness and purity of high pressure steam systems --
particularly where the steam is used to drive a steam turbineparticularly where the steam is used to drive a steam turbine
should be checked by use of ashould be checked by use of a targettarget;;
For new boilers, or new sections added to steam systemFor new boilers, or new sections added to steam system --blow down at full pressure;blow down at full pressure;
When steam appears clean, fit a target with aWhen steam appears clean, fit a target with a mirroredmirrored
surface (surface (ieie. Small steel plate which has been polished, so that. Small steel plate which has been polished, so that
it is in the steam blow down stream;it is in the steam blow down stream;
Blow down the boiler or system so that the target is impingedBlow down the boiler or system so that the target is impingedupon for a few minutes;upon for a few minutes;
Check targetCheck target -- ensure there are no smallensure there are no small pock markspock marks left onleft on
the target. If pock markedthe target. If pock marked -- repeat process.repeat process.
-
5/26/2018 Plant Commissioning Start Up Procedure
53/100
Slide 53
Electrical SystemsElectrical Systems
-
5/26/2018 Plant Commissioning Start Up Procedure
54/100
Slide 54
Commissioning Electrical SystemsCommissioning Electrical Systems
The following checks are typical of what is requiredThe following checks are typical of what is required Open circuit breakers and switches;Open circuit breakers and switches;
Check that all busCheck that all bus--bars are free of dirt and foreign matter;bars are free of dirt and foreign matter;
Check grounding systems for continuity and resistance.Check grounding systems for continuity and resistance.
Make sure all electrical equipment, vessels, structures areMake sure all electrical equipment, vessels, structures areconnected to the grounding system in accordance withconnected to the grounding system in accordance with
drawings and specifications;drawings and specifications;
Check that all sealed fittings are filled with proper sealants,Check that all sealed fittings are filled with proper sealants,
all explosion proof,all explosion proof, vapourvapour--tight, dusttight, dust--tight and weathertight and weather
tight enclosures are properly closed and secured;tight enclosures are properly closed and secured;
Check motor control and power circuitry for correctCheck motor control and power circuitry for correct
hookup.hookup.
-
5/26/2018 Plant Commissioning Start Up Procedure
55/100
Slide 55
Commissioning Electrical SystemsCommissioning Electrical Systems -- 22
The following checks are typical of what is requiredThe following checks are typical of what is required Check all nameplates and panel directories to ensure thatCheck all nameplates and panel directories to ensure that
each circuit breaker and switch does control the propereach circuit breaker and switch does control the proper
circuit. Label all switches even though their applicationcircuit. Label all switches even though their application
may seem obvious;may seem obvious;
Close main transformer primary disconnect switch andClose main transformer primary disconnect switch and
switchswitch--gear main circuit breaker;gear main circuit breaker;
Check voltmeter at switchCheck voltmeter at switch--gear for proper voltage;gear for proper voltage;
Close first switchClose first switch--gear circuit breaker, second, third etc.gear circuit breaker, second, third etc.
Close first motor control centre main circuit breaker, thenClose first motor control centre main circuit breaker, then
each motor starter circuit breaker. Repeat for each MCC.each motor starter circuit breaker. Repeat for each MCC.
Check overload breakers and heaters to ensure that theCheck overload breakers and heaters to ensure that the
correct capacity units have been installed.correct capacity units have been installed.
-
5/26/2018 Plant Commissioning Start Up Procedure
56/100
Slide 56
Commissioning Electrical SystemsCommissioning Electrical Systems -- 33
The following checks are typical of what is requiredThe following checks are typical of what is required Check that all lighting and power circuits are functioningCheck that all lighting and power circuits are functioning
correctly;correctly;
Check motor bearings for proper lubrication;Check motor bearings for proper lubrication;
Remove motor power fuses and check main contractor,Remove motor power fuses and check main contractor,interlock and sequencing devices;interlock and sequencing devices;
Uncouple each motor, replace fuses and check direction ofUncouple each motor, replace fuses and check direction of
rotation by momentarily pressing the start button, then stop;rotation by momentarily pressing the start button, then stop;
Check manual, then automatic operation.Check manual, then automatic operation.
Replace all couplings, check drive belts and make sureReplace all couplings, check drive belts and make sure
guards are installed.guards are installed.
-
5/26/2018 Plant Commissioning Start Up Procedure
57/100
Slide 57
Electric motor driven pumpsElectric motor driven pumps
-
5/26/2018 Plant Commissioning Start Up Procedure
58/100
Slide 58
Operational TestingOperational Testing
-
5/26/2018 Plant Commissioning Start Up Procedure
59/100
Slide 59
Operational TestingOperational Testing
Progresses through several stages;Progresses through several stages;
Dry runs of individual items of equipmentDry runs of individual items of equipment
Hot testing of individual items of equipment andHot testing of individual items of equipment andsystems;systems;
Several stages of Dynamic Testing of:Several stages of Dynamic Testing of:
Individual items of equipment;Individual items of equipment;
Individual Systems/processes in isolation;Individual Systems/processes in isolation;
The whole new process plant installation.The whole new process plant installation.
-
5/26/2018 Plant Commissioning Start Up Procedure
60/100
Slide 60
Dry runs and Hot TestsDry runs and Hot Tests
Check that motors are connected correctly and turnCheck that motors are connected correctly and turn
in the right direction;in the right direction;
Shafts and impellers move freely;Shafts and impellers move freely; Equipment that is to be operated at temperature,Equipment that is to be operated at temperature,
raise to temperature and check;raise to temperature and check;
These tests should be performed by theThese tests should be performed by the
manufacturermanufacturers representative but witnessed bys representative but witnessed bymembers of the clientmembers of the clients operating/commissionings operating/commissioning
personnel.personnel.
-
5/26/2018 Plant Commissioning Start Up Procedure
61/100
Slide 61
Hot testing equipmentHot testing equipment
Applies to equipment whose leakApplies to equipment whose leak--tightness must be tested attightness must be tested at
operating temperatures and after temperature reversals;operating temperatures and after temperature reversals;
FixedFixed--bed catalytic reactors that in normal conditions arebed catalytic reactors that in normal conditions are
heated by heat transfer fluids where leakage wouldheated by heat transfer fluids where leakage wouldcontaminate the catalyst;contaminate the catalyst;
Critical exchangers whose steam or cooling water is at aCritical exchangers whose steam or cooling water is at a
high pressure than the process fluid;high pressure than the process fluid;
Any equipment having complicated seals through whichAny equipment having complicated seals through which
leakage could occur;leakage could occur;
Rotating machinery which must be able to rotate freely atRotating machinery which must be able to rotate freely at
temperaturetemperature egeg. Steam turbines, etc.. Steam turbines, etc.
-
5/26/2018 Plant Commissioning Start Up Procedure
62/100
Slide 62
Hot testing proceduresHot testing procedures
The thermal shock tolerance of equipment must beThe thermal shock tolerance of equipment must be
determined beforehand;determined beforehand;
To avoid thermal shock, the temperature of theTo avoid thermal shock, the temperature of the
heating medium may have to be raised gradually;heating medium may have to be raised gradually;
Time required for a hot test must be established inTime required for a hot test must be established in
advance;advance;
Establish a uniform temperature in all parts ofEstablish a uniform temperature in all parts of
equipment that are supposed to be uniformly hotequipment that are supposed to be uniformly hot
during operation to avoid setting up stresses;during operation to avoid setting up stresses;
-
5/26/2018 Plant Commissioning Start Up Procedure
63/100
Slide 63
Dynamic TestingDynamic Testing
-
5/26/2018 Plant Commissioning Start Up Procedure
64/100
Slide 64
Dynamic TestingDynamic Testing
Involves operating the equipment, before introducingInvolves operating the equipment, before introducing
liveliveprocess fluid;process fluid;
During dynamic testing, we progress through:During dynamic testing, we progress through:
SafeSafe--fluid dynamic testing;fluid dynamic testing;
Dynamic testing with solvent;Dynamic testing with solvent;
Closed loop testing with process fluid.Closed loop testing with process fluid.
Once process fluid is introduced, normal plant safetyOnce process fluid is introduced, normal plant safetyprocedures must come into effect as if it were a liveprocedures must come into effect as if it were a live
operating plant.operating plant.
-
5/26/2018 Plant Commissioning Start Up Procedure
65/100
Slide 65
SafeSafe--Fluid Dynamic TestingFluid Dynamic Testing
Closed loop dynamic testing with safe fluids consists ofClosed loop dynamic testing with safe fluids consists of
operating equipment systems with air, water, inert gasesoperating equipment systems with air, water, inert gases
etc.etc.
This permits flow testing of equipment;This permits flow testing of equipment; Gives first indication of how control loops work;Gives first indication of how control loops work;
Establishes performance while there is still time to modifyEstablishes performance while there is still time to modify
the plant;the plant;
FamiliarisesFamiliarises operators with the operation of the equipmentoperators with the operation of the equipmentbefore hazardous materials are introduced;before hazardous materials are introduced;
Gets rid of a lot of dirt which would be more difficult toGets rid of a lot of dirt which would be more difficult to
clear once the process fluid has been introduced.clear once the process fluid has been introduced.
-
5/26/2018 Plant Commissioning Start Up Procedure
66/100
Slide 66
General Principles for TestingGeneral Principles for Testing
For most plants, a period of 2For most plants, a period of 2--3 weeks is usually sufficient3 weeks is usually sufficient
for operational testing, after the mechanical dry running offor operational testing, after the mechanical dry running of
individual pieces of equipment and hot testing complete;individual pieces of equipment and hot testing complete;
Air and water tests should be set up in a closed loop withAir and water tests should be set up in a closed loop withfluids continuously recycled, with loops as large asfluids continuously recycled, with loops as large as
possible;possible;
The loop should ideally be the same loop that will beThe loop should ideally be the same loop that will be
subject to solvent testing;subject to solvent testing;
Tests should continue for several days in order to give allTests should continue for several days in order to give allshifts a chance to conduct the same tests;shifts a chance to conduct the same tests;
All shifts should be given the opportunity to start up andAll shifts should be given the opportunity to start up and
shutdown each closed loop test.shutdown each closed loop test.
-
5/26/2018 Plant Commissioning Start Up Procedure
67/100
Slide 67
General Principles for TestingGeneral Principles for Testing
A rough flowA rough flow--sheet should be developed for airsheet should be developed for air
and water tests, predicting all information thatand water tests, predicting all information that
normally appears on a process flow sheetnormally appears on a process flow sheet -- flow,flow,
temperature, pressure, heat transfer, power etc.temperature, pressure, heat transfer, power etc. will assist in alerting commissioning team towill assist in alerting commissioning team to
risks from overrisks from over--pressuring, overloading,pressuring, overloading,
temperaturetemperature--shocking and stressing equipment;shocking and stressing equipment;
-
5/26/2018 Plant Commissioning Start Up Procedure
68/100
Slide 68
Cautions during TestingCautions during Testing
Dynamic testing may lead to:
Unusual or unforeseen differential expansions;Unusual or unforeseen differential expansions;
Corrosion;Corrosion;
Excessive weight of liquid into parts of theExcessive weight of liquid into parts of the
system;system;
Care must be taken not to collapse or burstCare must be taken not to collapse or burst
pressure vessels and tanks:pressure vessels and tanks: ensure there is always adequate venting;ensure there is always adequate venting;
avoid pulling a vacuum.avoid pulling a vacuum.
-
5/26/2018 Plant Commissioning Start Up Procedure
69/100
Slide 69
Dynamic TestingDynamic Testing -- Simulated OperationsSimulated Operations
Safe Fluid TestingSafe Fluid Testing
Auxiliary services must be brought into operationAuxiliary services must be brought into operation
first:first:
water cooling, inert gas generators, boilerwater cooling, inert gas generators, boilerfeedwaterfeedwater, firewater, steam production, etc., firewater, steam production, etc.
Water is pumped through the process (exceptWater is pumped through the process (except
where special conditions do not permit it) andwhere special conditions do not permit it) and
boiled up in columns;boiled up in columns; Compressors and blowers should be operated onCompressors and blowers should be operated on
air or inert gas.air or inert gas.
-
5/26/2018 Plant Commissioning Start Up Procedure
70/100
Slide 70
The Value of Dynamic TestingThe Value of Dynamic Testing --
Simulated OperationsSimulated Operations Value of simulated operations will be to allow operator toValue of simulated operations will be to allow operator to
become familiar with the operation of the process, beforebecome familiar with the operation of the process, before
hazardous fluids are introduced;hazardous fluids are introduced;
Equipment deficiencies can become apparent duringEquipment deficiencies can become apparent duringdynamic testing;dynamic testing;
Failures and problems more easily corrected with safeFailures and problems more easily corrected with safe
fluids presentfluids present
Leaks should be found and tightened;Leaks should be found and tightened;
Instruments can be placed into serviceInstruments can be placed into service -- although selectionalthough selection
of setof set--points will have to be deferred;points will have to be deferred;
Inspect the plant for evidence of design and constructionInspect the plant for evidence of design and construction
errors.errors.
-
5/26/2018 Plant Commissioning Start Up Procedure
71/100
Slide 71
Dynamic TestingDynamic Testing -- Simulated OperationsSimulated Operations
At the end of the simulation, water should beAt the end of the simulation, water should be
draineddrained -- equipment dried and purged;equipment dried and purged;
Depending on the processDepending on the process -- drying may not bedrying may not benecessarynecessary --but purging will always be required;but purging will always be required;
-
5/26/2018 Plant Commissioning Start Up Procedure
72/100
Slide 72
Dynamic testing with a solventDynamic testing with a solvent
After safe fluid testing and subsequent repairs andAfter safe fluid testing and subsequent repairs and
modifications, we are ready for dynamic closedmodifications, we are ready for dynamic closed
loop testing with a solvent;loop testing with a solvent;
TheThe solventsolvent is a relatively safe fluid whoseis a relatively safe fluid whose
properties are close to that of the process fluid, orproperties are close to that of the process fluid, or
the process fluid itself;the process fluid itself;
In order to allow for continuous reIn order to allow for continuous re--circulation ofcirculation ofthe solvent and the use of different solvents inthe solvent and the use of different solvents in
different parts of the plant, temporary lines willdifferent parts of the plant, temporary lines will
need to be installed.need to be installed.
-
5/26/2018 Plant Commissioning Start Up Procedure
73/100
Slide 73
Dynamic Testing with Process SolventDynamic Testing with Process Solvent
Introduce the process solvent. (if there is more thanIntroduce the process solvent. (if there is more than
one, introduce only one at this stage);one, introduce only one at this stage);
The dynamic testing procedure used for the safeThe dynamic testing procedure used for the safe
fluid test is repeated for the process solvent dynamicfluid test is repeated for the process solvent dynamictesting;testing;
After operations with the first solvent have beenAfter operations with the first solvent have been
brought completely under control, should the secondbrought completely under control, should the second
solvent be introduced (if there is one).solvent be introduced (if there is one).
-
5/26/2018 Plant Commissioning Start Up Procedure
74/100
Slide 74
Dynamic testing with a solventDynamic testing with a solvent
The purpose of dynamic testing with a solvent is toThe purpose of dynamic testing with a solvent is to
check out equipment and instrument loops at, orcheck out equipment and instrument loops at, or
near design conditions prior to the introduction ofnear design conditions prior to the introduction of
more hazardous process fluid;more hazardous process fluid; No reactions should be allowed to occur duringNo reactions should be allowed to occur during
these tests, so as to ensure that test fluids remainthese tests, so as to ensure that test fluids remain
predictable in composition and properties;predictable in composition and properties;
Guidelines used for safeGuidelines used for safe--testing apply;testing apply;
Need to plan how solvent will be fed into theNeed to plan how solvent will be fed into the
system and later removed.system and later removed.
-
5/26/2018 Plant Commissioning Start Up Procedure
75/100
Slide 75
Stages of dynamic testing with aStages of dynamic testing with a solventsolvent
Drain safe fluid and purge air used in the previous test fromDrain safe fluid and purge air used in the previous test from
the system;the system;
Dry out equipment where safe fluid was water. Check flowDry out equipment where safe fluid was water. Check flow
sheets for where water is likely to accumulate.sheets for where water is likely to accumulate.
Fill systems with the solvent. Ensure provisions made forFill systems with the solvent. Ensure provisions made for
venting and drains closed;venting and drains closed;
When adequate levels established, place pumps andWhen adequate levels established, place pumps and
compressors online to complete filling;compressors online to complete filling;
Start closed loop circulation;Start closed loop circulation;
Heat up the systems to simulate operating conditions byHeat up the systems to simulate operating conditions by
placing reflux,placing reflux, reboilerreboilerand condensation systems intoand condensation systems into
operationoperation
-
5/26/2018 Plant Commissioning Start Up Procedure
76/100
Slide 76
Stages of dynamic testing with aStages of dynamic testing with a solventsolvent
Systematically check out instrumentation and control loops;Systematically check out instrumentation and control loops;
After instruments have checked out, place as many asAfter instruments have checked out, place as many as
possible on automatic control;possible on automatic control;
All shifts should go through starting and stoppingAll shifts should go through starting and stoppingequipment, heating and cooling closed loop systems;equipment, heating and cooling closed loop systems;
DynamicDynamic solventsolvent testing offers the best opportunity fortesting offers the best opportunity for
operator training before theoperator training before the real thingreal thing;;
Operate equipment as near as possible to design capacities;Operate equipment as near as possible to design capacities;
Reliability of emergency shutdown systems and alarmsReliability of emergency shutdown systems and alarms
must be proven;must be proven;
Critical instruments must be calibrated over their full range.Critical instruments must be calibrated over their full range.
-
5/26/2018 Plant Commissioning Start Up Procedure
77/100
Slide 77
Stages of dynamic testing with aStages of dynamic testing with a solventsolvent
Deliberately operate equipment near its limits:Deliberately operate equipment near its limits:
Flood columns;Flood columns;
Ease compressors into mild surges and plot surge curves;Ease compressors into mild surges and plot surge curves;
Overload condensers;Overload condensers; Do not fear blowing a relief valve or two!Do not fear blowing a relief valve or two!
After tests have been completed, plant should be ready forAfter tests have been completed, plant should be ready for
initial operation.initial operation.
-
5/26/2018 Plant Commissioning Start Up Procedure
78/100
Slide 78
Closed Loop Dynamic Testing withClosed Loop Dynamic Testing with
Process FluidProcess Fluid Finally, introduce process fluid;Finally, introduce process fluid;
During this step, instruments should be calibratedDuring this step, instruments should be calibrated
to cover their full range of flow, temperature andto cover their full range of flow, temperature and
pressure;pressure;
Ensure that instruments, processEnsure that instruments, process analysersanalysers andand
safety devices are kept work properly during thesesafety devices are kept work properly during these
processes;processes;
After operations with process fluid are broughtAfter operations with process fluid are brought
completely under control should the final stage ofcompletely under control should the final stage of
startstart--up be attempted.up be attempted.
-
5/26/2018 Plant Commissioning Start Up Procedure
79/100
Slide 79
Preparing to introduce process fluidsPreparing to introduce process fluids
Before introducing hazardous liquids into theBefore introducing hazardous liquids into the
plant, we complete additional pressure testing andplant, we complete additional pressure testing and
purging;purging;
Need to check that the stresses and strains ofNeed to check that the stresses and strains of
dynamic testing has not caused any leaksdynamic testing has not caused any leaks -- thesethese
must be found and fixed;must be found and fixed;
-
5/26/2018 Plant Commissioning Start Up Procedure
80/100
Slide 80
Pressure testing and purgingPressure testing and purging
Consists of pressuring and deConsists of pressuring and de--pressuring withpressuring with
nitrogen several times, until at least
-
5/26/2018 Plant Commissioning Start Up Procedure
81/100
Slide 81
Dehydrating by CirculationDehydrating by Circulation
It is usually not possible to waterIt is usually not possible to water--free equipmentfree equipment
simply by draining;simply by draining;
Only positive method to waterOnly positive method to water--free processfree process
equipment is oil circulation followed by repeatedequipment is oil circulation followed by repeateddraining of low points;draining of low points;
Ensure sufficient low point drains are provided onEnsure sufficient low point drains are provided on
piping, control valve loops, vessels and processpiping, control valve loops, vessels and process
machinery;machinery; Startup linesStartup lines -- deliver oil to upper part (trays) ofdeliver oil to upper part (trays) of
distillation towers (size for 20% of net distillatedistillation towers (size for 20% of net distillate
product rate);product rate);
-
5/26/2018 Plant Commissioning Start Up Procedure
82/100
Slide 82
Start Up and Initial OperationStart Up and Initial Operation
-
5/26/2018 Plant Commissioning Start Up Procedure
83/100
Slide 83
Start Up and Initial OperationStart Up and Initial Operation
Preparation and planning
Performance and
Acceptance testing
Post Commissioning
Introduction of process fluidIntroduction of process fluid
StartStart--up and initial operationup and initial operation TroubleTrouble--shooting andshooting and
problem correction.problem correction.
Plant taken to full operations.Plant taken to full operations.
Mechanical Completion
and Integrity checking
Pre-commissioning &
Operational Testing
Start Up & Initial
Operation
-
5/26/2018 Plant Commissioning Start Up Procedure
84/100
Slide 84
Starting Up the PlantStarting Up the Plant
Productrefining
RecoveryReactionFeedPreparation
Most plants in petrochemical/chemical industryMost plants in petrochemical/chemical industry
have the followinghave the following generalgeneral form.form.
Start Up from theStart Up from the
End of the ProcessEnd of the Process
and Work backand Work back
-
5/26/2018 Plant Commissioning Start Up Procedure
85/100
Slide 85
Start Up LogicStart Up Logic
It is common practice to buy in product and startIt is common practice to buy in product and start
up the last past of the process first and workup the last past of the process first and work
backwards to the front. E.g.backwards to the front. E.g.
Start up refining, get this working and inStart up refining, get this working and in
control;control;
Then possibly start up reaction and recovery;Then possibly start up reaction and recovery;
Finally, feed preparation.Finally, feed preparation.
-
5/26/2018 Plant Commissioning Start Up Procedure
86/100
Slide 86
Into the initial operationInto the initial operation
Once raw materials are fed into the plantOnce raw materials are fed into the plant -- usuallyusually
at reduced rate until reaction conditions have beenat reduced rate until reaction conditions have been
established;established;
As each section is started up, establish as quicklyAs each section is started up, establish as quicklyas possible that process conditions are as expected;as possible that process conditions are as expected;
If potentially serious problems develop, thereIf potentially serious problems develop, there
should be no hesitation on going into anshould be no hesitation on going into an
emergency shutdown.emergency shutdown.
-
5/26/2018 Plant Commissioning Start Up Procedure
87/100
Slide 87
Ramping up the plantRamping up the plant
Plant is brought slowly to design feedPlant is brought slowly to design feed--rates andrates and
operating conditions;operating conditions;
Usually done in steps with operating dataUsually done in steps with operating data
evaluated and verified as OK at each step;evaluated and verified as OK at each step;
Plant and laboratory data are now being collectedPlant and laboratory data are now being collected
and should be being evaluated promptly;and should be being evaluated promptly;
-
5/26/2018 Plant Commissioning Start Up Procedure
88/100
Slide 88
Coordination and Supervision duringCoordination and Supervision during
start upstart up Additional personnel, both supervisory andAdditional personnel, both supervisory and onon--
thethe--groundground are required at this stage;are required at this stage;
Cooperation between startup personnel and plantCooperation between startup personnel and plantsupervisory personnel is critical at this stage:supervisory personnel is critical at this stage:
Need a daily meeting at least;Need a daily meeting at least;
Often, a briefing each shift.Often, a briefing each shift.
-
5/26/2018 Plant Commissioning Start Up Procedure
89/100
Slide 89
Trouble ShootingTrouble Shooting
At this stage, many problem with equipment of theAt this stage, many problem with equipment of the
process itself may become apparent;process itself may become apparent;
The commissioning process goes through what isThe commissioning process goes through what isoften an intense (and hopefully short) period ofoften an intense (and hopefully short) period of
problem trouble shooting, problem solving,problem trouble shooting, problem solving,
engineering correction and plant modification;engineering correction and plant modification;
-
5/26/2018 Plant Commissioning Start Up Procedure
90/100
Slide 90
Performance and Acceptance TrailsPerformance and Acceptance Trails
-
5/26/2018 Plant Commissioning Start Up Procedure
91/100
Slide 91
Performance and Acceptance TestingPerformance and Acceptance Testing
Preparation and planning
Performance and
Acceptance testing
Post Commissioning
Performance trails;Performance trails;
Formal Acceptance testFormal Acceptance test
Mechanical Completion
and Integrity checking
Pre-commissioning &
Operational Testing
Start Up & Initial
Operation
-
5/26/2018 Plant Commissioning Start Up Procedure
92/100
Slide 92
The Performance TrailsThe Performance Trails
Once the plant is fully operational, the finalOnce the plant is fully operational, the final
proving trailproving trail or performance run is performed inor performance run is performed in
order to prove the plant can do what it is supposedorder to prove the plant can do what it is supposed
to do;to do; The values or range of values for each independentThe values or range of values for each independent
variablevariable -- flow, temperature, pressure, level,flow, temperature, pressure, level,
concentrations, etc. to which the plant must beconcentrations, etc. to which the plant must be
operated to are determined;operated to are determined; The plant is brought up to those conditions and theThe plant is brought up to those conditions and the
prepre--agreed trial period begins.agreed trial period begins.
-
5/26/2018 Plant Commissioning Start Up Procedure
93/100
Slide 93
Before the trail or performance run needBefore the trail or performance run need
to ensure thatto ensure that Control of plant operating conditions has beenControl of plant operating conditions has been
achieved. I.e. temperature, pressures, levels andachieved. I.e. temperature, pressures, levels and
analyses are reasonably constant or in the case of aanalyses are reasonably constant or in the case of a
batch process, there is repeatability;batch process, there is repeatability;
Daily material and energy balanced can beDaily material and energy balanced can be
performed and that these agree withperformed and that these agree with officialofficial
production figures;production figures;
Product specifications are being achievedProduct specifications are being achieved
consistently.consistently.
-
5/26/2018 Plant Commissioning Start Up Procedure
94/100
Slide 94
Need to verifyNeed to verify ..
Physical operation, capability and capacity of plantPhysical operation, capability and capacity of plant
and equipment;and equipment;
Energy and mass balance;Energy and mass balance; Process chemistry;Process chemistry;
Efficiencies, yields and quality;Efficiencies, yields and quality;
All to specification.All to specification.
-
5/26/2018 Plant Commissioning Start Up Procedure
95/100
Slide 95
AcceptanceAcceptance
When the plant has met the Performance andWhen the plant has met the Performance and
Acceptance test requirements designed by theAcceptance test requirements designed by the
commissioning team there is usually a formalcommissioning team there is usually a formal
acceptance process involving signing of acceptanceacceptance process involving signing of acceptance
certificates;certificates;
Once the plant is accepted it is officially part of theOnce the plant is accepted it is officially part of the
normal operationsnormal operations -- the responsibility of operationsthe responsibility of operations
and maintenance;and maintenance;
Commissioning is officially over;Commissioning is officially over;
The may still be outstandingThe may still be outstandingpunchlistpunchlist itemsitems
-
5/26/2018 Plant Commissioning Start Up Procedure
96/100
Slide 96
Acceptance TestingAcceptance Testing
It is common practice to prove performanceIt is common practice to prove performance
repeatability and plant integrity as part of therepeatability and plant integrity as part of the
performance test. That is:performance test. That is:
Shutdown and Start Up the plant on severalShutdown and Start Up the plant on severaloccasions and bring it up to test conditions tooccasions and bring it up to test conditions to
prove repeatability. Also ramp down and ramp upprove repeatability. Also ramp down and ramp up
while online;while online;
ReRe--inspection of critical process equipmentinspection of critical process equipment --particularly columns to ensure they have not beenparticularly columns to ensure they have not been
damaged by the performance run.damaged by the performance run.
-
5/26/2018 Plant Commissioning Start Up Procedure
97/100
Slide 97
Commercial Significant of AcceptanceCommercial Significant of Acceptance
Formal Acceptance represents formal acknowledgmentFormal Acceptance represents formal acknowledgment
that thethat the
Contractor has fullContractor has full--filled their contractualfilled their contractual
obligations;obligations;
Commissioning team have fullCommissioning team have full--filled theirfilled their
obligations;obligations;
Completion of the Capital Project and transfer toCompletion of the Capital Project and transfer to
Operations;Operations;
Expenses and costs from acceptance onwards are nowExpenses and costs from acceptance onwards are now
operating expenses not capital project costs;operating expenses not capital project costs;
All subject to agreed punchAll subject to agreed punch--list items.list items.
-
5/26/2018 Plant Commissioning Start Up Procedure
98/100
Slide 98
PostPost--CommissioningCommissioning
-
5/26/2018 Plant Commissioning Start Up Procedure
99/100
Slide 99
Post CommissioningPost Commissioning
Preparation and planning
Mechanical Completion
and Integrity checking
Pre-commissioning &
Operational Testing
Start Up & Initial
Operation
Performance and
Acceptance testing
Post Commissioning
From plant onFrom plant on--stream to settledstream to settled
down and in regular production;down and in regular production;
Adjustments, modifications andAdjustments, modifications andfault correction;fault correction;
Completion of outstandingCompletion of outstanding
punchlistpunchlist itemsitems
-
5/26/2018 Plant Commissioning Start Up Procedure
100/100
Post CommissioningPost Commissioning
Covers the period immediately after Acceptance;Covers the period immediately after Acceptance;
Outstanding punchOutstanding punch--list items are completed;list items are completed;
The first routine maintenance checks are performed,The first routine maintenance checks are performed,
findings evaluated and reported;findings evaluated and reported;
Process equipment and items covered by warrantyProcess equipment and items covered by warranty
are scrutinized for signs of premature wearare scrutinized for signs of premature wear--out orout or
problems;problems;
Operating data is collected and evaluated to ensureOperating data is collected and evaluated to ensure
consistent plant operations are maintained andconsistent plant operations are maintained and
sustainable.sustainable.