Transcript
Page 1: Southwick, MA Trail Culvert

Farmington Canal Heritage Trail

• New Haven to Northhampton

• 84-miles when complete

• Over 50% done

• ECG overlays ~47 miles

Page 2: Southwick, MA Trail Culvert

Farmington Canal Heritage Trail

• Simsbury, CT to Mass. Line opened up in May

• Phase 1 in Southwick, MA under construction

Southwick, MA

Page 3: Southwick, MA Trail Culvert

Southwick, MAPoint Grove Road Underpass

• High Pressure Gas Line buried in Corridor

• Trail installed by town after pipeline is buried.

Page 4: Southwick, MA Trail Culvert

April, 2009

Page 5: Southwick, MA Trail Culvert

Site Plan -- Point Grove Road Culvert

Page 6: Southwick, MA Trail Culvert

•Sheet Piling

•Box Culvert on North Side

•Traffic Flow with 1-lane automatic lights

•Traffic never stopped

•Estimated cost $170 K

Page 7: Southwick, MA Trail Culvert

Standing on top of culvert looking East on

Point Grove Road.

July 2009

Page 8: Southwick, MA Trail Culvert

Looking South Towards Connecticut from the top of the Culvert

Page 9: Southwick, MA Trail Culvert

Looking north thru Culvert -- July 2009

Page 10: Southwick, MA Trail Culvert

Looking North Towards Northhampton -- July 2009

Page 11: Southwick, MA Trail Culvert

Point Grove Road Culvert from south

July

2009


Top Related