In 2008-09, a box culvert 'tunnel' was constructed under the Point Grove Road in Southwick, MA. The culvert accommodates a high-pressure gas pipeline and a bike/ped trail. This project was accomplished without stopping traffic on the road for a cost estimated at ~$250 K.TRANSCRIPT
Farmington Canal Heritage Trail
• New Haven to Northhampton
• 84-miles when complete
• Over 50% done
• ECG overlays ~47 miles
Farmington Canal Heritage Trail
• Simsbury, CT to Mass. Line opened up in May
• Phase 1 in Southwick, MA under construction
Southwick, MA
Southwick, MAPoint Grove Road Underpass
• High Pressure Gas Line buried in Corridor
• Trail installed by town after pipeline is buried.
April, 2009
Site Plan -- Point Grove Road Culvert
•Sheet Piling
•Box Culvert on North Side
•Traffic Flow with 1-lane automatic lights
•Traffic never stopped
•Estimated cost $170 K
Standing on top of culvert looking East on
Point Grove Road.
July 2009
Looking South Towards Connecticut from the top of the Culvert
Looking north thru Culvert -- July 2009
Looking North Towards Northhampton -- July 2009
Point Grove Road Culvert from south
July
2009