2

CRM – New Verification Requirements

Key Issue: How should producers of CRM-modified asphalt products verify the quantity of CRM in their products?

Important for Caltrans – AB338 (2005) & PRC Sec. 42703 require annual reporting by Caltrans

Important for Industry – Desire for a uniform approach.

Page 3: Crumb Rubber Modifier in CA: New Verification Requirements

CRM – New Verification Requirements

3

Page 4: Crumb Rubber Modifier in CA: New Verification Requirements

CRM – New Verification Requirements

March 2014 Caltrans/Industry began work on Scoping Document

July 2014 first meeting of the CRM Verification Subtask Group under RPC

An RPC “Expedited Issue” “Verification” got expanded!

4

Page 5: Crumb Rubber Modifier in CA: New Verification Requirements

CRM – New Verification Requirements

March 2015 Caltrans/Industry finalized CRM Verification Protocols

Three Parts:1. CRM Source Verification2. Weights & Measures Protocol3. Independent Verification

5

Page 6: Crumb Rubber Modifier in CA: New Verification Requirements

6

CRM – New Verification Requirements

• CRM Source Verification• A Chain of Custody Protocol• Verify that CRM is from USA• Caltrans maintains a Qualified Products List (QPL)• CRM suppliers under CalRecycle automatically meet requirements Out-of-state CRM suppliers must have equivalent documentation• CRM suppliers provide certification to CRM users

Page 7: Crumb Rubber Modifier in CA: New Verification Requirements

CRM – New Verification Requirements

7

Page 8: Crumb Rubber Modifier in CA: New Verification Requirements

8

CRM – New Verification Requirements

• Weights and Measures Protocol• Applies to all Caltrans CRM binders

except Asphalt Rubber• Specifies equipment & procedures for blending CRM in asphalt• Solids measured by weight (load cells) Liquids measured by mass flow meters Requires plant process controller to meet certain specifications

Page 9: Crumb Rubber Modifier in CA: New Verification Requirements

9

CRM – New Verification Requirements

• Independent Verification• CRM binder plant operator must be a licensed weighmaster• Must produce a weighmaster’s certification for each batch• Caltrans may visit CRM binder production unannounced Caltrans must be notified prior to CRM binder production Contractor completes CRM Usage Report

Page 10: Crumb Rubber Modifier in CA: New Verification Requirements

CRM – New Verification Requirements

Implementation Status:

METS has docs necessary to add Approved CRM Suppliers to Authorized Materials List

CRM Weights & Measures Protocol is added as “errata” section to the MPQP document http://www.dot.ca.gov/hq/construc/hma/MPQP.pdf

CT Construction Div. is finalizing the “proof copy” of the CRM Usage Report Form (CEM-4410)

10

Page 11: Crumb Rubber Modifier in CA: New Verification Requirements

CRM – New Verification Requirements

Implementation Status:

[email protected] – email site for the deliverance of the CRM Usage Report Form is operable.

Spec changes for Sections 37, 39, 92 are ready for submittal to OE as RSS to 2015 Std. Specifications

Full implemented is required by July 1, 2016