d. energy baseline assessment - erie international airport
TRANSCRIPT
Master Plan Update
Appendix D D-1
D. Energy Baseline Assessment
D.1. INTRODUCTION
Erie International Airport is a publicly owned, primary commercial service airport that serves the aviation needs of Erie County, PA and its surrounding areas. As part of the Master Plan Update, McFarland Johnson performed an Energy Baseline assessment of the existing Passenger Terminal Building, the U.S. Customs and Border Control Building, the Airfield Maintenance and Fire Station Building and the Electrical Vault.
The passenger terminal building is the primary transition point from surface to air transportation for the airport. The original building was constructed circa 1956 and there have been several additions and renovation projects since. At its current configuration the terminal building occupies approximately 47,600 ft2. It is a steel frame, concrete block and face brick construction building with primarily double pane windows and skylights and a flat EPDM, gravel ballast roof.
The U.S. Customs and Border Control Building is an approximately 2,200 ft2 masonry / face brick construction building, with double pane windows and a flat EPDM roof. It was constructed in 1991.
The Airfield Maintenance and Fire Station Building is a 16,500 ft2 building. The building is a steel structure and concrete block with a brick facade and a flat built-up roof construction. The original portion was constructed at the same time that the passenger terminal building was built, in 1956, and has since had two additions added to it. A three-vehicle bay addition was constructed in 1988 on the south end of the building to accommodate the Airport’s ARFF vehicles, and two vehicle bays were constructed on the north end of the building for housing maintenance equipment.
The Airport is currently supplied water by the City of Erie Water Authority. A six-inch diameter water line serves the terminal complex from a water main running along West 12th Street. The passenger terminal complex is served by a six-inch diameter sanitary sewer line connected to the city’s trunk line. Natural gas is supplied to the terminal building by National Fuel Gas; a natural gas line runs from West 12th Street to the meter room on the basement floor of the terminal. GPU supplies electric power to the airport via above-ground power lines running from West 12th Street to Grant Avenue, then underground to the weather bureau, terminal building, and the remaining areas on the Airport.
D.2. PASSENGER TERMINAL BUILDING
D.2.1. Electrical Systems Description
Most of the lighting within the terminal has been upgraded to energy efficient T8 and compact fluorescent. There are still some incandescent lamps installed in downlights (café) and T12 linear
Master Plan Update
Appendix D D-2
fluorescent lamps being used in some areas in the front and back-of-house spaces (kitchen, baggage handling, airline supply spaces, offices, stairwells, cove lights behind ticketing, linear fixtures above the drop ceiling outside passenger screening). T5 fixtures have been installed in the ceiling in the area after passenger screening.
The basement lighting is a mix of T12 and T8 lamp linear fixtures (4’ and 8’ lengths) and ceramic light bases with compact fluorescent and LED bulbs installed in them. Second floor lighting is a mix of T8 and T12 recessed troffers with acrylic lenses. All lighting is controlled with manual switching except for the two restrooms in the secure side of the terminal. These lights are controlled with motion sensors w/timers. Exterior lighting is accomplished with a mix of metal halide downlights, surface mounted metal halide, and pole mounted metal halide and high pressure sodium. There are no exterior LED light fixtures.
Exit signage throughout the terminal is LED. Some of the fixtures have halogen emergency light heads installed on them, some have LED heads. Not all exit signs have emergency lighting installed. Battery tests indicated that not all of the exit signs have batteries that will operate during a power outage. Not all exit signs have battery back-up. Emergency lighting is accomplished with stand-alone emergency units and emergency ballasts installed in recessed fixtures. Emergency lighting and exit signage is powered from a Life Safety power panel which is fed from a back-up generator.
D.2.2. Mechanical Systems Description
The basement level of the terminal houses the terminal’s HVAC controls, telephone, and electrical equipment. The heat for the passenger terminal building is provided by a combination of low pressure steam boiler (Weil-McLain Model 88) and one hot water boiler (Weil-McLain Model Ultra 310). Both boilers use natural gas as the primary energy source. An third, older boiler (Weil-McLain Model LGB-9) has been abandoned in place.
The energy management system consists of a combination of electric controls (FAA offices) and pneumatic controls. The air compressor for the pneumatic controls as well as the electric controls terminal are located in the basement mechanical room. There is a wide assortment of thermostats throughout the facility characteristic of the era that they were installed, ranging from programmable thermostats to temperature sensors and traditional mercury type thermostats.
The main floor of the terminal building is served by a number of roof mounted units and is supplemented in select areas by unit heaters, cabinet unit heaters, air curtains, low intensity gas fired infrared heaters, unit ventilators and thru the window packaged air conditioning units.
The roof top units (RTU) serving the original 1956 portion of the building are providing heat by means of steam coils. Several roof top units have been added as part of addition/renovation projects. Heat from these units is provided either through hot water heating coils or natural gas furnaces. All roof top units provide cooling via packed direct expansion cooling coils. Most of the RTUs have far exceeded their useful life expectancy and should be scheduled for replacement with newer more efficient units.
Master Plan Update
Appendix D D-3
There are several, natural gas fired, domestic water heaters spread out throughout the terminal building to serve the facility’s domestic hot water needs. Public bathrooms have sensor type faucets on the lavatories and sensor flush valves on toilets and urinals.
General exhaust is provided through a number of roof exhaust fans. The Control Tower staircase is pressurized by multiple fans which are part of the smoke control system and are activated through the fire alarm panel.
The restaurant kitchen is served by a commercial range hood. There are several air curtains at the passenger departure/arrival gates intended to reduce energy loss through the open doors during these times that passengers are boarding or exiting the aircrafts. All of the air curtains are either out of order or have been disabled for various reasons.
The boiler and natural gas meters are both located on the basement level of the complex. The fire pump room and associated fire sprinkler risers and air compressor are also located in the basement in their own separate fire pump/sprinkler riser room adjacent to the mechanical room.
Refer to Table D-1 for a more detailed listing of the HVAC equipment in the Passenger Terminal Building as well as the U.S. Customs and Border and Maintenance Buildings.
Table D-1: Passenger Terminal Building HVAC Equipment List Equip.
No. Area Served
Manufacturer
Model No. Serial No. Condition Capacity
Notes
HVAC 01
ERAA - Restaurant Carrier 38AE-016-500 2394F00015 Fair/Poor 170,000 BTU/HR*
HVAC 02
ERAA - Main Lobby
Carrier 48PMMM16BR-
5-S8 0610G50019 Good
205,000 BTU/HR Failing duct insulation
HVAC 03
ERAA - South Carrier 48TJE005-
501GA 1694G01497 Poor
92,000 BTU/HR Failing duct insulation
HVAC 04
ERAA - Finance Area
Carrier 48SS030-080-
311 3394G10180 Fair 40,000 BTU/HR
HVAC 05
ERAA - Car Rental Hall
Carrier 48TJE007-501 1994G20107 Fair/Poor 92,000 BTU/HR
HVAC 06
ERAA - Baggage Claim HVAC
York D2CG180N3202
5E NFHM082611 Fair 320,000 BTU/HR
HVAC 07
ERAA - Center Boarding
Carrier 48TJE024-
510QA 3494F10261 Fair 216,000 BTU/HR
HVAC 08
ERAA - West Boarding
Carrier 48DRO014-
520AA Y797037 Fair/Poor
216,000 BTU/HR Rusted exposed
duct
HVAC 09
ERAA - West Ticketing
Carrier 48TJE012-
501GA 2494G30235 Fair/Poor 144,000 BTU/HR
HVAC 10
ERAA - East Ticketing
Carrier 48TJE012-
501GA 3194G30656 Fair/Poor 144,000 BTU/HR
HVAC 11
ERAA - Main FAA Unit
Carrier 50AK-
020QAQ611HQ 3307U2551 Fair AC unit
HVAC ERAA - Radar Carrier 48TEF008-A- 4007G50496 Good 92,000 BTU/HR
Master Plan Update
Appendix D D-4
12 Equipment Room Backup
511HQ
HVAC 13
ERAA - West FAA Wing
Carrier UNKNOWN UNKNOWN Poor 40,000 BTU/HR (not confirmed)
HVAC 15
ERAA - Delta Ops Carrier 48DJE006520 1290G38939 Poor 32,000 BTU/HR (not confirmed)
HVAC 16
ERAA - Third Floor Break Room
Carrier 48TJE005-
501GA 1694G10488 Poor 92,000 BTU/HR
HVAC 17
ERAA - Tower Cab Carrier 48TJE007-501 5193G01399 Poor 74,000 BTU/HR
HVAC 18
ERAA - Third Floor Equipment Room
Carrier 48TJE007-
501GA 1994G20111 Fair 92,000 BTU/HR
HVAC 19
ERAA - Police Office
Carrier 48SS-024060311 3294G11237 Fair 33,300 BTU/HR
HVAC 20
ERAA - US Airways Ops
Carrier 38CK042-341 389E06862 -- 15,000 BTU/HR
HVAC 21
ERAA - Steam Boiler
Weil McLain
988R n/a Fair 2,000,000 BTU/HR
HVAC 22
US Customs and Borders Building
Trane YCD048A3L0AB F04142202D -- 74,000 BTU/HR (not confirmed)
HVAC 23
US Customs and Borders Building
Trane YCD04ASL0AB F34142201D -- 74,000 BUT/HR (not confirmed)
HVAC 24
ERAA - FAA HW Boiler
Weil-McLain
ULTRA 310 CP5591984 Fair 300,000 BTU/HR
HVAC 25
Sidewalk Heaters Roberts Gordon
Vantage II CTH2-80 n/a Good
60,000 BTU/HR each
HVAC 26
ERAA - East Commuter Walkway
York D6CG060N0992
5C NKEM11525Y Fair
92,000 BTU/HR (not confirmed)
HVAC 27
ERAA - West Commuter Walkway
York DC6GO60N0992
5C NKE11254 Fair
92,000 BTU/HR (not confirmed)
HVAC 28
ERAA - Continental Express Ops
Lennox CG29M-21/26-
1P 5595M37560 Fair
33,300 BTU/HR (not confirmed)
HVAC 29
ERAA - Control Room
Liebert MMD36EPHED0 451136240 -- AC unit
HVAC 30
Restaurant Manager
Liebert PFC037A-YLO 0043N35277 -- AC unit
HVAC 31
ERAA - Hot Water Boiler
Weil-McLain
LGB-9 n/a Poor 1,040,000 BTU/HR
NOT IN SERVICE
HVAC 32
West Jetway PC Air
n/a n/a n/a -- Electric
HVAC 33
Center Jetway PC Air
n/a n/a n/a -- Electric
HVAC 34
East Jetway PC Air n/a n/a n/a -- Electric
HVAC 35
TSA Job Trailer HVAC-1 North
n/a MAC36A-A15B 058N890627889 -- Electric
Master Plan Update
Appendix D D-5
HVAC 36
TSA Job Trailer HVAC-2 South
n/a MAC36AA15B14
010 58N890627889 -- Electric
HVAC 37
Fire Bay Overhead Tube Heaters (Typ. 4)
n/a n/a n/a -- 60,000 BTU/HR
each
HVAC 38
Airfield OPS Work Area (Installed 2014)
LENNOX KGA048S4Ds 5614P08333 -- 65,000 BTU/HR
HVAC 39
Airfield Equipment Bay Tube Heaters (Typ. 4)
n/a n/a n/a Fair 60,000 BTU/HR
each
HVAC 40
Airfield Storage Bays Tube Heaters (5)
n/a n/a n/a Fair 60,000 BTU/HR
each
HVAC 41
Sand Salt Storage Tube Heaters (Typ. 2)
n/a n/a n/a Fair 60,000 BTU/HR
each
HVAC 42
Baggage claim tube heaters (Typ. 2)
n/a n/a n/a Good 60,000 BTU/HR
each
MISC 1 Terminal Domestic Hot Water
Bradford White
Defender MI40T6FBN GL14165959 Fair
40,000 BTU/HR Input
40 Gallon Tank
MISC 2 Restaurant Hot Water Tanks 2 (80 Gallon)
n/a n/a n/a --
MISC 3 US Customs Hot Water Tank 40 Gallon
Bradford White
MI40T6FBN KH18718973 Good 40,000 BTU/HR
Input 40 Gallon Tank
MISC 4 Airfield Hot Water Tank (40 Gallon)
n/a n/a n/a -- 40,000 BTU/HR
Input 40 Gallon Tank
MISC 5 Maintenance Building Tank (40 Gallon)
Whirlpool M40T91-403 11497452304 Fair 40,000 BTU/HR
Input 40 Gallon Tank
Source: Chief Ian A. Bogle, Erie Regional Airport Authority * Capacity information from manufacturer’s catalog
D.2.3. Recommendations
In order to conserve energy, it is recommended that all light fixtures utilizing incandescent, T-12, and T-8 lamps be replaced with energy efficient LED light fixtures. LED lighting utilizes approximately 20% the energy of the existing light fixtures and will provide noticeable savings to the airport. Exterior lighting on the apron and in the parking lot can also be changed out to LED light fixtures to provide additional savings.
Install low flow aerators on all lavatory faucets. A faucet aerator can be simply screwed onto the faucet head. Because the aerator limits the water flow through the faucet, water use is reduced by an average of 50% as compared to a faucet without an aerator.
Master Plan Update
Appendix D D-6
In interviewing facility personnel, it was discovered that due to maintenance issues a number of steam traps get stuck either in the open or the closed position. This results in either condensate backing up when the trap is stuck closed, therefore inhibiting the transfer of latent heat, or steam blowing through the trap when it's stuck open, leading to heating issues and waste of energy. A stuck or failed open steam trap can also cause issues with the remainder of the steam traps in the system as it may pressurize the condensate return line, therefore preventing condensate from the other traps from draining properly. Facility personnel also mentioned that whenever any major maintenance is needed the work is contracted to an outside firm or contractor. Regular equipment maintenance has a significant effect on both life expectancy and maintaining peak efficiency of equipment. It is suggested that a regular maintenance schedule is implemented and that maintenance personnel is trained in the required maintenance tasks.
The building automation system (BAS) consists of multiple iterations of various manufacturers, some parts of it original to the building. As a result, the airport is far from realizing the full potential energy savings that a properly implemented control system would offer the capability for. A complete replacement of the energy management system could prove very costly. Factoring in the age of most of the air handling equipment, that would also need to be replaced or upgraded, this type of upgrade could only be viable as part of a capital project.
D.3. U.S. CUSTOMS AND BORDER CONTROL BUILDING
D.3.1. Electrical Systems Description
The Custom’s building light fixtures are T12, recessed light fixtures (2x4 and 2x2), T-12 surface wraparound (bathrooms), with a few metal halide recessed downlights. Light fixtures are all manual control with single pole light switches.
Exit signs are old lamp style fixtures with no battery back-up. Emergency lighting is accomplished with stand-alone lighting units and battery tests indicate that these fixtures will operate during a power outage.
D.3.2. Mechanical Systems Description
The building is conditioned by a pair of gas fired RTUs and miscellaneous electric terminal units, and through the window AS units. The two RTUs are controlled by programmable wall mounted thermostats.
Domestic hot water is generated by a Bradford White Model MI40T6FBN, 40 gallon, 40,000 btu/hr natural gas fired water heater. There are manual flush valves for toilets and urinals. The lavatory faucets are in fair shape and do not appear to be the low flow type.
On the building exterior it was observed that the west and south exposure window caulking has disintegrated. There are also signs of water leakage within exterior block walls, possibly from water pooling on the roof.
Master Plan Update
Appendix D D-7
D.3.3. Recommendations
The existing RTUs are past their useful life expectancy. It is recommended that funds are appropriated for the replacement of the units. Though operations and maintenance costs will be reduced, there is not a significant payback from energy savings to justify the replacement of the units before they are rendered inoperable. Replacement decision should be based on facility importance and the potential of having no heat in the building during the cold winter months if the units fail.
Replace existing lavatory faucets and shower heads with low flow fixtures to conserve water and energy. Typical payback for this type of replacement is less than a year, depending on use time of the plumbing fixtures. This is a relatively low cost measure that can be easily implemented.
It is recommended that the existing fluorescent and metal halide light fixtures be replaced with energy efficient LED fixtures. It is also recommended that automatic lighting controls be added to the offices and bathrooms. The existing exit signage shall also be replaced with LED type exit signage with battery backup.
D.4. AIRFIELD MAINTENANCE AND FIRE STATION BUILDING
D.4.1. Electrical Systems Description
The Airfield Maintenance and Fire Station Building has T8 recessed troffers in the office area and T12 linear fixtures (4’ and 8’ lengths) in the truck and maintenance bays. The old salt storage area, which is now used as a two-bay truck area has 400W metal halide light fixtures. 250W and 400W high pressure sodium fixtures are installed on the exterior of the building. Interior lighting is controlled with manual switches. Exterior lighting is controlled by photocell.
Exit signage throughout the AARF/Maintenance Garage is LED with battery back-up. Battery tests indicate that these fixtures will operate during a power outage. Emergency lighting is accomplished with standalone emergency fixtures with a mix of halogen and LED lamping. Battery testing indicated that some of these fixtures will not operate during a power outage. A 400kw generator was installed in 2008 to supply power for life safety.
D.4.2. Mechanical Systems Description
The Airfield Maintenance and Fire Station Building is primarily served by multiple low intensity, gas-fired infrared heaters which are typical for this type of building use. The office area and employee is served by a packaged gas-fired RTU. The RTU and infrared heaters are controlled by programmable wall mounted thermostats.
There is a partial sprinkler system serving the mezzanine area in the building but there were no alarm devices observed, which is inconsistent with NFPA standards and International Fire Code.
There is an air compressor for used for maintenance on the stored vehicles and an emergency generator.
Master Plan Update
Appendix D D-8
The vehicle storage bays are also served by multiple exhaust fans controlled by wall mounted switches. The fans are intended to exhaust heat in the warm summer months. No carbon monoxide (CO) or nitrogen oxides (NOx) sensors were observed which are typically utilized for exhausting vehicle storage bays when potentially hazardous concentrations of CO and/or NOx are detected.
A 40 gallon, 40,000 btu/hr, natural gas fired water heater (Whirlpool Model M40T91-403) provides the domestic hot water for the facility.
D.4.3. Recommendations
It is recommended that the existing T12 and T8 light fixtures be replaced with energy efficient LED fixtures. It is also recommended that the existing metal halide and high pressure sodium light fixtures be replaced with LED type fixtures. Automatic lighting control should be added to bathrooms and break rooms to turn lighting off when the rooms are not occupied.
Emergency lighting throughout the building should be verified to be operational and non-working units should be replaced to ensure operation during times of need.
It is recommended that a CO / NOx detection system is provided for the facility and tied to the existing exhaust fans. The existing exhaust fan capacity should be reviewed for adequacy of exhaust volume capabilities.
D.5. ELECTRICAL VAULT
D.5.1. Electrical Systems Description
The vault houses all of the constant current regulators (CCR’s) for the airfield lighting. Airfield lighting has been upgraded in certain areas and is original in other areas. Runway 6/24 has all new incandescent lighting, new cable, new conduit, and new transformers and cans. Runway 2/20 is all original equipment. Taxiway ‘A’ edge lighting is LED for the extended part of the taxiway. This was done in 2012-2013. The balance of taxiway A’s lighting is original (transformers, cans, cable, conduit). Taxiway ‘C’ lighting between Taxiway ‘A’ and Runway 2/20 is new LED and transformer utilizing original cable and cans. Taxiway ‘D’ lighting between Runway 6/24 and Runway 2/20 is new LED and transformer utilizing original cable and cans. Signage on the airside is currently being changed out to LED. Twenty-three of the existing signs have yet to be changed out to LED. Existing cabling is being utilized except those signs associated with the runway. The cable feeding these signs was changed out during the runway extension project. The light fixtures in the vault building utilize T8 lamps.
D.5.2. Mechanical Systems Description
N/A
D.5.3. Recommendations
The airport is currently undertaking the replacement of some of the signage light fixtures to energy efficient LED type fixtures. It is recommended that the airport continue to replace
Master Plan Update
Appendix D D-9
signage fixtures with LED type to conserve energy. It is also recommended that old taxiway lighting be replaced with LED fixtures to match the new LED lighting along the edge of some of the taxiways.
D.6. CURRENT AIRPORT ENERGY AND WATER USE
D.6.1. Natural Gas Consumption
The natural gas bills provided by Erie Airport were compiled into Table D-2, Figure D-1, and Figure D-2.
Table D-2: Natural Gas Consumption (DTH)
Meter No. Month 3256518 5233292 6840261 TOTAL USAGE (DTH) Cost ($)
Dec-14 1441.9 193 43.5 1678.4 7,848
Jan-15 1880.4 384.1 53.1 2317.6 9,685
Feb-15 1901.1 156.1 57.9 2115.1 9,034
Mar-15 1383.3 180 46.7 1610 7,268
Apr-15 685 89.3 24.1 798.4 3,442
May-15 219.9 10.8 7.6 238.3 915
Jun-15 85.6 0.2 2 87.8 388
Jul-15 78.5 1.7 0.9 81.1 348
Aug-15 65.6 2 0.5 68.1 340
Sep-15 61.2 4.2 1.8 67.2 514
Oct-15 258.4 17.2 19 294.6 1,865
Nov-15 619.4 51.7 14.3 685.4 4,328
Dec-15 984.8 77.7 23.9 1086.4 6,060
Source: National Fuel Resources Inc. energy Bills
Master Plan Update
Appendix D D-10
$7,849
$9,686 $9,034
$7,268
$3,442
$916 $388 $348 $341 $515
$1,866
$4,328
$6,060
$-
$2,000
$4,000
$6,000
$8,000
$10,000
$12,000
Co
st (
$)
Figure D-1: Total Natural Gas Consumption
Source: Utility bills.
Figure D-2: Natural Gas Cost
Source: Utility bills.
0
2000
4000
6000
8000
10000
12000
Co
st (
$)
Master Plan Update
Appendix D D-11
D.6.2. Electric Consumption
The electric bills provided by Erie Airport were compiled into Table D-3, Figure D-3, and Figure D-4.
Table D-3: Electric Consumption (KWH) Month
Meter#
Dec- 14
Jan- 15
Feb-15
Mar-15
Apr-15 May-
15 Jun- 15
Jul- 15
Aug-15
Sep-15
Oct-15 Nov-15
TOTAL USAGE (KWH)
100 004 925 630
100 100 100 100 100 100 100 100 100 100 100 100 1,200
100 071 525 974
0 0 0 0 0 0 0 0 0 0 0 0 0
100 005 025 885
12 8 11 13 9 18 2 26 1 30 13 24 167
100 006 723 421
324 279 261 54 56 23 22 21 24 246 74 297 1,681
100 005 513 401
313 315 281 277 215 200 197 191 237 233 310 280 3,049
100 040 377 507
907 522 582 462 447 362 379 359 372 374 474 445 5,685
100 040 377 473
4,009 3,209 5,576 3,937 3,758 2,645 2,509 2,192 2,384 2,590 3,104 3,719 39,632
100 088 938 327
15,522 16,040 6,565 6,143 6,646 5,754 6,368 3,004 5,517 6,167 7,983 7,916 93,625
100 040 377 481
351 245 1,648 1,566 1,671 293 271 271 265 340 375 -317 6,979
100 084 426 798
938 747 6469 568 1,844 2,000 3,487 3,746 3,654 2,801 1,940 1,697 29,891
100 040 377 499
395 392 435 365 355 314 313 277 274 287 375 434 4,216
100 004 925 465
162,800
157,200
174,400
143,600
146,000
136,000
178,000
151,600
160,000
142,000
150,000
131,600
1,833,200
100 004 377 515
2,322 1,276 2,074 1,343 979 712 374 310 311 354 558 905 11,518
100 004 924 906
423 275 334 269 291 232 252 217 245 246 348 322 3,454
100 004 167 605
314 323 323 342 256 243 188 251 263 192 292 321 3,308
100 105 974 825
31 204 88 97 28 122 65 93 20 174 116 162 1,200
Total Usage (KWH)
30,786 28,451 30,233 19,580 20,500 15,758 15,421 13,233 14,900 15,574 17,876 18,751 242,063
Cost ($) 14,327 14,279 17,597 12,439 13,327 12,895 15,915 13,687 14,092 12,917 13,364 12,346 167,184
Source: Penelec Electricity Bills
Master Plan Update
Appendix D D-12
Figure D-3: Electric Consumption
Source: Utility bills.
Figure D-4: Electricity Cost
Source: Utility bills.
188,761 181,135
199,147
159,136 162,655
149,018
192,527
162,658 173,667
156,134 166,062
147,905
-
50,000
100,000
150,000
200,000
250,000El
ect
rici
ty U
se (
KW
H)
$14,327 $14,279
$17,597
$12,439 $13,327
$12,895
$15,915
$13,687 $14,092
$12,917 $13,364
$12,346
$-
$2,000
$4,000
$6,000
$8,000
$10,000
$12,000
$14,000
$16,000
$18,000
$20,000
CO
ST
Master Plan Update
Appendix D D-13
D.6.3. Water Consumption
The Water consumption bills provided by Erie Airport were compiled into Table D-4 and Figure D-5.
Table D-4: Water Consumption (cu. ft.)
Meter # Month 70098745 Car Wash
60848337 FAA-SSC
52084828 Fire Pump
31955792 Main
51706496 Quonset Hut
49673744 Restaurant
TOTAL
Jan-15 22 136 9 167
Feb-15 30 129 9 168
Mar-15 25 5 8 138 3 10 189
Apr-15 20 104 10 134
May-15 25 168 10 203
Jun-15 22 5 18 217 10 9 281
Jul-15 25 131 12 168
Aug-15 24 112 10 146
Sep-15 22 6 7 72 2 11 120
Oct-15 20 74 10 104
Nov-15 18 65 9 92
Dec-15 18 5 6 78 1 10 118
TOTAL 271 21 39 1424 16 119 1890
Source: Erie Waterworks Bills Figure D-5: Water Consumption
Source: Erie Waterworks Bills
Master Plan Update
Appendix D D-14
D.6.4. Metrics Comparison
The compiled energy metrics from all the natural gas, electric and water usage were input into US EPA’s online energy tracking tool, the Portfolio Manager. Table D-5 below is a summary of the energy use of Erie Airport compared to other facilities of similar size and function.
Table D-5: Metrics Comparison
Metric Median Property ERAA
Source EUI (kBtu/ft2) 85.1 488.5
Site EUI (kBtu/ft2) 44.7 256.4
Source Energy Use (kBtu) 5,642,641 13,137,485
Site Energy Use (kBtu) 2,961,536 10,867,918
Total GHG Emissions (Metric Tons CO2e) 255.2 1,464.6
Source: Energy Star, Portfolio Manager (portfoliomanager.energystar.gov)
Figure D-6: Airport Energy Use by Calendar Month
Source: Energy Star, Portfolio Manager (portfoliomanager.energystar.gov)
D.6.5. International Trade Center
In addition to the buildings and facilities mentioned in the paragraphs above Erie Municipal Airport Authority occupies office space at the International Trade Center (ITC). The ITC also functions as a warehouse and houses commercial leases. Even though this building was not part of energy assessment its energy consumption is outlined in the following tables.
Master Plan Update
Appendix D D-15
Table D-6: ITC Electric Consumption
Month Meter#
Dec- 14
Jan- 15
Feb-15
Mar-15
Apr-15
May-15
Jun- 15
Jul- 15
Aug-15
Sep-15
Oct-15
Nov-15
TOTAL USAGE (KWH)
100 032 942 706
41 43 43 41 45 34 36 30 31 29 37 36 446
100 032 942 680
4,477 4,180 5,107 3,744 3,535 2,466 1,513 1,866 902 1156 1,502 2,181 32,629
Total Usage (KWH)
4,518 4,223 5,150 3,785 3,580 2,500 1,549 1,896 933 1,185 1,539 2,217 33,075
Source: Utility bills