converting vessels to run on lng as a marine fuel

25
Converting vessels to run on LNG as a marine fuel 8 March 2021 • 09:00-09:45 GMT #marinefuels Marine Fuels Webinar Week Part of 8-12 March 2021 Panellist documents Page 2: Guus van der Bles, Conoship International Page 11: Stephan Vetter, KfW IPEX Bank Page 18: Björn Munko, TGE Marine Gas Engineering

Upload: others

Post on 18-Dec-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Converting vessels to run on LNG as a marine fuel8 March 2021 • 09:00-09:45 GMT

#marinefuels

Marine FuelsWebinar Week

Part of

8-12 March 2021

Panellist documents

Page 2: Guus van der Bles, Conoship InternationalPage 11: Stephan Vetter, KfW IPEX BankPage 18: Björn Munko, TGE Marine Gas Engineering

CO2 CAPTURING ON BOARDLNG-FUELED VESSELS

TURNING EMISSION TO FEEDSTOCK FORSYNTHETIC E-FUELS

BY GUUS VAN DER BLES

08-03-2021 CO2 Capturing on board LNG Fueled vessels 1

INTRODUCTION CONOSHIP INTERNATIONAL

CO2 Capturing on board LNG Fueled vessels08-03-2021 2

Conoship Int. , Groningen, Netherlands• Ship Design office started 1952• > 2000 vessels built of our design• Focus R&D: eCONOmy & eCOlogy

▪ Reduction of fuel & emissions▪ Propulsion on LNG/MeOH/H2▪ Wind Assisted Ship Propulsion▪ CO2 capturing on boardPractical applicable innovations

08-03-2021 CO2 Capturing on board LNG Fueled vessels 3

Capturing CO2: • proven technology• land-based plants: • size/weight/roll&pitch-effects?

Storing CO2 on board:• Liquid: -20 C @ 20 bar in tank(/-

containers)• Energy for cooling? => cool CO2

with LNG

CHALLENGES: CAPTURING & STORING CO2 ON BOARD

08-03-2021 CO2 Capturing on board LNG Fueled vessels 4

HOW DOES CARBON CAPTURE WORK

08-03-2021 CO2 Capturing on board LNG Fueled vessels 5

CO2 CAPTURE ON LNG VESSEL + LIQUIFY CO2 WITH LNG

Combining carbon capture

with LNG:

• Exhaust gases from LNG

contain little contaminants

(SOx, NOx, particulate matter)

=> less complicated capture

• CO2 needs cooling to be

stored: LNG is a cold source

- 163 C -> -20 C @ 20 bar

or -50 C @ 8 bar

08-03-2021 CO2 Capturing on board LNG Fueled vessels 6

CAPTURING INSTALLATION IN SHIP

08-03-2021 CO2 Capturing on board LNG Fueled vessels 7

2019~2021 FEASIBILITY STUDIES ON-BOARD APPLICATION

Fossile LNG => ~ 85% Methane = CH4

CH4 in LNG-engine: => CO2 + H20Capture CO2 on board + liquify +

store in CO2 tank (-containers)Unload & store in empty offshore gasfields f.e. NorhternLightsFulfil UN SDG 13 ‘Climate Action’!

Future: sell tankcontainers CO2…

LNG-FUELED VESSELS & CO2-CAPTURING~ CLOSED CARBON LOOP

08-03-2021 CO2 Capturing on board LNG Fueled vessels 8

Future: tankcontainers liquid CO2 => feedstockfor ‘synthetic E-Fuels’Windenergy -> clean E-power -> ‘green’H2 H2 + CO2 -> CH4 + H2O (Sabatier proces)Example E-Fuel CH4 = synthetic Methane=> liquifying => LSM ready to fuel LNG-vessel

Actual LNG fueled vessels can be CO2-neutralin future with Ship Based Carbon Capture

TURN CO2 EMISSIONS TO FEEDSTOCK FOR E-FUELS

08-03-2021 CO2 Capturing on board LNG Fueled vessels 9

Financing Alternatives for LNG Retrofits

Marine Fuels Webinar Week

04.03.2021

Financing Alternatives for LNG Retrofits, 08.03.2021, Marine Fuels Webinar Week 2

Challenges

LNG Retrofit Financing

Second lien financing

is difficult and expensive.

High investments

for LNG retrofitsneeded.

There are fewbanks

that finance vessel retrofits.

Usually existingship finance

mortgage on thevessel to be

intended for a retrofit.

LNG Retrofit Financing

?

Upsizing of Existing Facility

+ Can be done by existing

lenders

- Banks reluctant due to

higher LTV

Secured Loan

+ Typical ship finance

structure (mortgages from

other vessels)

- Provision of mortgage

Unsecured Loan

+ No provision of security

- Expensive

- Only acceptable for top

notch ship owners

- Normally 2-3 years tenor

ECA Covered Loan

+ Longer tenors possible

+ Potentially no provision of

mortgages needed

+ Bigger bank appetite

- Slightly longer execution

period

Financing Alternatives for LNG Retrofits, 08.03.2021, Marine Fuels Webinar Week 3

Financing Alternatives

Excerpt of our recent deals

Several retrofit financings in the last three years

Finance Partner for all kinds of maritime retrofits

Strong structuring expertise in retrofit financings

Access to market leading specialized suppliers for the relevant retrofit equipment

Financing Alternatives for LNG Retrofits, 08.03.2021, Marine Fuels Webinar Week 4

Retrofit Experience

KfW IPEX-Bank´s major maritime financing criteria

European link

− Ship owners and operators

− Shipyards

− Charterer

− Vessel / retrofit equipment

Strong counterparties

− Market leaders

− Sustainable business model

− Robust P&L and balance sheet

Min. ticket size

− EUR [15,000,000]

− Depending on complexity

Sustainable elements

− Green Loans

− Sustainability-Linked Loans

− CO2 efficient vessels / projects

− Environmental-friendly retrofits

Financing Alternatives for LNG Retrofits, 08.03.2021, Marine Fuels Webinar Week 5

Stephan Vetter

Vice President - Maritime Industries

Phone: +49 (0)69 7431-3355

Mobil: +49 (0)173-1457606

Mail: [email protected]

Palmengartenstraße 5‒960325 Frankfurt am Main, Germany

www.kfw-ipex-bank.de

www.linkedin.com/company/kfw-ipex-bank

KfW IPEX-Bank GmbH

Green Steel - Vargas Holding | Structuring and Arranging Proposal | November 2020 strictly private and confidential 7

08 Mar. 2021

Webinar –Converting vessels to run on LNG as a marine fuel

Björn Munko

Company Introduction

Convertiong Vessels to LNG Fuel | 08 Mar 20212 |

• TGE Marine Gas Engineering GmbH

• 40 years of experience with liquefied gas

• More than 200 gas carrier and fuel gas systems contracted

• Fuel gas systems for 4-stroke, 2-stroke engines

• Market leader as independent fuel gas supplier

• EPCS Contractor – Fuel Gas Systems / Fuel Gas Tanks

• Shareholder: Mitsui Engineering & Shipbuilding Co., Ltd. (MES)

260,000 m³ LNG carrier (conversion):• Owner: Nakilat, Qatar• Yard: N-KOM, Qatar• Classification: ABS

• Completion: 2015• Scope: pre-fabricated high pressure LNG fuel gas

system for 2-stroke dual fuel MAN ME-GI main engine• Contract: MAN Diesel & Turbo (MDT)

Convertiong Vessels to LNG Fuel | 08 Mar 2021

LNG Conversions – Gas Carriers

6,500 m³ LNG/LEG carrier:• Owner: Anthony Veder, The Netherlands• Yard: AVIC Dingheng, China• Classification: BV• Completion: 2012• Conversion: 2014 LNG as fuel• Scope: Ship design, complete gas handling and fuel

supply system, complete tanks

3

Conversion of 3,750 dwt Product Tanker:• Owner: Bergen Tankers, Norway• Yard: Noryards, Norway• Classification: BV• Completion: 2015 (for conversion to gas

propulsion)• Scope: LNG fuel tanks (vacuum insulated)

and fuel gas system• Rolls Royce gas engines, 4s/Otto

LNG Conversion - Product Tanker

Convertiong Vessels to LNG Fuel | 08 Mar 20214 |

LNG Conversion - Container Feeder ‚Wes Amelie‘

Conversion2017 at German Dry Docks

TGE Marine scope of supply:LNG Fuel Gas System

LNG Tank with a capacity of 500 m³

Engineering, Supervision & Commissioning

Funding by German Government:Funding program for LNG as marine fuel

Up to 60% of cost for conversion are eligible

Max. funding amount 7 M€ per project

Funding program was extended until end of 2021

Convertiong Vessels to LNG Fuel | 08 Mar 20215 |

LNG fuel gas systems – basic components

Convertiong Vessels to LNG Fuel | 08 Mar 2021

Primary auxiliary systems:

• Water-glycol heating system

• Inert gas system

• Valve remote operation

• Safety systems

• Automation & control

Secondary auxiliary systems:

• Vent / ventilation

• Valve remote operation

• Instrument air

Supply toengines

Master gasfuel valve

Fuel Gas System Battery Limits

BunkeringStation

LNG Containment System (Tank)

Fuel Gas conditioning(pump, vaporizer…)

6 |

Trilobe Tank for 15.000 TEU Container vessel

7 |

Tank type TrilobeTank Dimensions Ø 10.8 x B 18.6 x 43.7 m

Tank Volume (geometric) 7,600 m³

Tank Volume (usable) 6,900 m³

BOR ~ 0.25 %/day (~ 320 kg/h)

Weight ~ 960 t

Convertiong Vessels to LNG Fuel | 08 Mar 2021