control, energy management and protection for …control, energy management and protection for...
TRANSCRIPT
Prof. TRAN Q. Tuan
CEA-INES
Control, Energy Management and Protection for Microgrids:
Co-Simulation and Tests
5 – 8 Sept. 2017Montreal, Quebec, Canada
Page 2TRAN Q. Tuan – CEA-INES
PV systems integration into grids
Page 3TRAN Q. Tuan – CEA-INES
Micro Grid at CEA-INES - Platform PRISMES
Page 4TRAN Q. Tuan – CEA-INES
Micro Grid at CEA-INES - Platform PRISMES
Page 5TRAN Q. Tuan – CEA-INES
Challenges for Microgrids Control & Energy Management
Page 6TRAN Q. Tuan – CEA-INES
Strategies of distributed control and management
• Rational use of components and infrastructure• Manage large number of components• Rational use of resources with cooperation
between components• More flexible system
CENTRALISED DISTRIBUTED
to
Objectives for Microgrids Control & Energy Management
Page 7TRAN Q. Tuan – CEA-INES
Control & Management of Multi-level of grid
• Strategies of control and management forMicrogrid
• Strategies of control and management forMulti-Microgrids
• Strategies of control and management fordistribution grid
µgrid
µgrid
µgrid
Multi-µgrids Distribution grid
Multi-Agent system
Solutions for Microgrids Control & Energy Management
Page 8TRAN Q. Tuan – CEA-INES
Distributed control in microgrid
Macsimjx Interface
Communication between agents
2 3 4 5 6 7 8 9 10 1149
49.5
50
50.5
51
Time(s)
Fre
quency(H
z)
System frequency
2 3 4 5 6 7 8 9 10 110
1
2
3
x 104
Time(s)
Active P
ow
er(
W)
Gen2 output
Gen4 output
Generator power
T.L Nguyen PhD Thesis
Page 9TRAN Q. Tuan – CEA-INES
Agent Based Distributed Control of Islanded Microgrid– Real-Time Cyber-Physical Implementation
DG1 DG4
DG3
DG2
DG5
Load1
Load2
Agent1
Agent3
Agent2
Agent4
Agent5
Power
Control
Controller 1 Controller 4
Controller 3
Controller 5
Controller 2
Microgrid test case
DG controller diagram
Layer control structure
Page 10TRAN Q. Tuan – CEA-INES
Agent Based Distributed Control of Islanded Microgrid– Real-Time Cyber-Physical Implementation
Loads
Hardware Agent
Source and
Controller
Source and
Controller
Source and
Controller
Source and
Controller
Hardware Agent
Hardware Agent
Hardware Agent
Hardware Agent
Source and
Controller
Communication network
Real time simulator
Hardware system
The testing setup
Web server interface
Aiomas_Agent 1
Aiomas_Agent 2
Aiomas_Agent 3
Aiomas_Agent 4
Hardware controllers and communication network
Data from web server sent to RPI clusterData from opal-rt sent to
web server
Optimal result from RPIsOptimal result
Aiomas_Agent 5
RPI4 RPI3
RPI5
RPI2
RPI1
Consensus processing
Page 11TRAN Q. Tuan – CEA-INES
Agent Based Distributed Control of Islanded Microgrid– Real-Time Cyber-Physical Implementation
The transmission time in network
The consensus processing time The overall operation of MG
Page 12TRAN Q. Tuan – CEA-INES
FMI Compliant Approach to Investigate the Impact of Communication to Islanded Microgrid Secondary Control
FMI (Function Mockup Interface): is a standard designed to provide an unified model execution interface for dynamic system models between modeling tools and simulation tools.
FMI compliant co-simulation approach to investigate the impact of communication system
General elements of a communication FMU
Pilot Support Package (PSP)
FMU block
An agent in Matlab/Simulink
Page 13TRAN Q. Tuan – CEA-INES
FMI Compliant Approach to Investigate the Impact of Communication to Islanded Microgrid Secondary Control
DG4
DG3
DG5
Load1
Load2
Communication
Power
Control
Controller 1 Controller 4
Controller 3
Controller 5
Microgrid central controller
Controller 2
DG2
DG1
Centralized control
DG1
DG2
DG5
Load1
Load2
Agent1
Agent3
Agent2
Agent4
Agent5
Controller 1 Controller 4
Controller 3
Controller 5
Controller 2
Distributed control
Three communication test case from MGCC to LCs
The inter-agent latency time in the three test cases
Page 14TRAN Q. Tuan – CEA-INES
Context and objectives:
A lot of different technologies for oceanenergy conversion are being developed.
Necessity to test the technologies on site (at sea), creation of marine test sites for demonstration and validation of Marine Renewable Energy Converters
Integration of these sites to the electric network: two major issues
Systems big enough to be connected to the grid.Intermittence and variability of the output powerprofile can cause damages to the grid
Example of a simulated output power profile over a year for a wave energy converter
Systems too small to be connected to theelectric grid via the offshore cable butoperationaldissipation and storage of the energyproduced
Experimental autonomous maritime platform for the study of marine energies and their integration into grid
H. Clemot PhD Thesis
Page 15TRAN Q. Tuan – CEA-INES
Onshore prototype of a marine storage unit on a floating platform (Real Time Simulation platform)
Objectives:• Definition of the hardware architecture
for the platform• Development of the algorithms for
control• Study of power smoothing and energy
storage strategies for marine renewableenergy converters
• Determine the behavior of electric gridduring interactions with marinerenewable energy sources.
• Marine generator simulation• Grid simulation• Storage simulation or real system
storage
floating autonomous experimentation platform including power supply, dissipation system and grid simulator.
Experimental autonomous maritime platform for the study of marine energies and their integration into grid
Power modules and ESSsupercapacitors
Test the power electronics interface and their control system Evaluate power quality at the point of conexion to the electrical grid Test different control and energy management strategies without or with energy storage systems
Page 16TRAN Q. Tuan – CEA-INES
Experimental autonomous maritime platform for the study of marine energies and their integration into grid
1 MW 5 MW
Page 17TRAN Q. Tuan – CEA-INES
Experimental autonomous maritime platform for the study of marine energies and their integration into grid
With storage
Page 18TRAN Q. Tuan – CEA-INES
Real-time evaluation of Energy Management for a grid-connected Microgrid
BATTERY 1
BATTERY 2
BATTERY 3ESS
INVERTER
PV
INVERTER
EMSSERVER1
PVAS CONTROL PC
Ethernet
Modbus TCP/IP
SERVER2AC Electrical Grid
DC Electrical Grid
Modbus TCP/IP Communication Grid
Ethernet Communication Grid
E. Amicarelli PhD Thesis
Page 19TRAN Q. Tuan – CEA-INES
Real-time evaluation of Energy Management for a grid-connected Microgrid: High Forecasted PV Power
without intra-day optimization
with intra-day optimization
Profiles of photovoltaic, battery, consumption and grid exchange
Page 20TRAN Q. Tuan – CEA-INES
Microgrid of PRISMES platform (CEA/INES)
Load125 kVA
Load0 à 11 kW
Power
Communication
PC local control
PC remonte control
PV simulator
Inverter
Diesel Genset44 kVA
AC Bus
XtenderInverter
18 kW
Battery420 Ah/ 48V
Senarios:
PV system: 10 kWc
Max load: 17 kW
Min Load: 2.2 kW
P_Diesel: 20 kW
E_bat: 18 kWh
P_bat (charge): 6 kW
P_Bat (Dis.): -6 kW
Test time : 2h
Real time evaluation of Energy Management (EMS) for an Island Microgrid
G. Coukoi PhD Thesis
Page 21TRAN Q. Tuan – CEA-INES
Power variation (Testing)Power variation (Simulation with dynamic programming)
Battery
Bidirectional
inverter
AC Bus
Load
Diesel generator PV array
inverter
˜=
EMS
800 1600 2400 3200 4000 4800 5600 6400 7200-5
0
5
10
15
20
Time [s]
Po
wer
[kW
]
PLOAD forecast
PPV forecast
PINV optimal
PDiesel optimal
PBatt optimal
800 1600 2400 3200 4000 4800 5600 6400 7200-10
-5
0
5
10
15
20
Time [s]
Po
wer
[kW
]
PLOAD measured
PPV measured
PINV measured
PDiesel measured
PBatt measured
It shows that test results are accorded with the simulation results
Real time evaluation of Energy Management (EMS) for an Island Microgrid
Page 22TRAN Q. Tuan – CEA-INES
800 1600 2400 3200 4000 4800 5600 6400 7200226
227
228
229
230
231
232
233
234
235
Time [s]
Vo
ltag
e[V
]
V1 measured
V2 measured
V3 measured
800 1600 2400 3200 4000 4800 5600 6400 720049
49.5
50
50.5
51
Time [s]
Fre
qu
en
cy[H
z]
Frequency measured
After these tests, proposed
strategies are tranfered to
Brkina Faso
Frequency and voltages are maintained in limits
Real time evaluation of Energy Management (EMS) for an Island Microgrid
Page 23TRAN Q. Tuan – CEA-INES
Objective:
CH12 – Vond
CH11 – IVP
CH10 – VVP
CH3 – Courant de commande de la source DC
VReseau
- Study behaviors of PV inverters face to faults in microgrid
- Validate the proposed solutions for protection
Test Bench
Scenarios: different faults on microgrid
Real time evaluation of microgrid protection
Page 24TRAN Q. Tuan – CEA-INES
Fusible
FD1N2N3
N4 N5 N6 N7
10m 20m 20m 20m 10m
N8 N9 N10 N11 N12
20m 20m 20m 20m 10m
10m
10m
15m
5m
N13 N14 N15 N16
20m 20m 20m
N17 N18 N19 N20
20m 20m 20m20m20m
N21
N22
N23
N24
1
c
b
a
20/0.4
400kVA aaa
a a a
b b b b
b
bb
ccc
c c c
Fusible
FD2
PV
Fusible
FD1N2N3
N4 N5 N6 N7
10m 20m 20m 20m 10m
N8 N9 N10 N11 N12
20m 20m 20m 20m 10m
10m
10m
15m
5m
N13 N14 N15 N16
20m 20m 20m
N17 N18 N19 N20
20m 20m 20m20m20m
N21
N22
N23
N24
1
c
b
a
20/0.4
400kVA aaa
a a a
b b b b
b
bb
ccc
c c c
Fusible
FD2
PV
288.9 288.95 289 289.05 289.1 289.15 289.2-15
-10
-5
0
5
10
Temps (s)
Cou
rant
(A)
Instance of SC
disconnection
288.5 288.6 288.7 288.8 288.9 289 289.1 289.2 289.3 289.4 289.5
1000
2000
3000
4000
5000
6000
7000
Temps (s)
Cou
rant
(A)
Fuse current FD1
Instance of SC
Fuse FD1 activated
321.3 321.35 321.4 321.45 321.5 321.55 321.6
-10
-5
0
5
10
15
Temps (s)
Cou
rant
(A)
SC 1 (feeder with PV system) SC 2 (without PV system)
Validation par essai
Inverter current
PV Inverters are very sensitive face to faults
SC on the adjacent feeder can provide a non desirable disconnection
Inverter current
Real time evaluation of microgrid protection
Page 25TRAN Q. Tuan – CEA-INES
with the proposed solution
=> Non-desired disconnection is avoided
Solution: Using FRT characteristic (Fault Ride Through)
0.2 0.4 0.6 0.8 1 1.2 1.40
0.2
0.4
0.6
0.8
1
1.2
1.4
Time(s)
Vo
ltag
e(p
u)
Voltage-time Characteristic
Vpv without using the proposed solution
Vpv with using the proposed solution
Moment
de CC
Temporisation
du FD2
FD2 fond
Tens
ion
(pu)
Temps (s)
Gabarit de tension
Vpv sans utilisation du gabarit
Vpv avec utilisation du gabarit
0.2 0.4 0.6 0.8 1 1.2 1.40
0.2
0.4
0.6
0.8
1
1.2
1.4
Time(s)
Vo
ltag
e(p
u)
Voltage-time Characteristic
Vpv without using the proposed solution
Vpv with using the proposed solution
Moment
de CC
Temporisation
du FD2
FD2 fond
Tens
ion
(pu)
Temps (s)
Gabarit de tension
Vpv sans utilisation du gabarit
Vpv avec utilisation du gabarit
0.2 0.4 0.6 0.8 1 1.2 1.40
0.2
0.4
0.6
0.8
1
1.2
1.4
Time(s)
Vo
ltag
e(p
u)
Voltage-time Characteristic
Vpv without using the proposed solution
Vpv with using the proposed solution
Moment
de CC
Temporisation
du FD2
FD2 fond
Tens
ion
(pu)
Temps (s)
Gabarit de tension
Vpv sans utilisation du gabarit
Vpv avec utilisation du gabarit
0.2 0.4 0.6 0.8 1 1.2 1.40
0.2
0.4
0.6
0.8
1
1.2
1.4
Time(s)
Vo
ltag
e(p
u)
Voltage-time Characteristic
Vpv without using the proposed solution
Vpv with using the proposed solution
Moment
de CC
Temporisation
du FD2
FD2 fond
Tens
ion
(pu)
Temps (s)
Gabarit de tension
Vpv sans utilisation du gabarit
Vpv avec utilisation du gabarit
0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.80
0.2
0.4
0.6
0.8
1
1.2
1.4
Time (s)
Vo
ltag
e (p
u)
PV voltage
Classic Voltage/time Characteristique
New Voltage/time Characteristic
0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.80
0.2
0.4
0.6
0.8
1
1.2
1.4
Time (s)
Vo
ltag
e (p
u)
PV voltage
Classic Voltage/time Characteristique
New Voltage/time Characteristic
Temps (s)
Tens
ion
(pu)
Tension du PV
Gabarit classique de tension
Nouveau gabarit de tension
Real time evaluation of microgrid protection
Page 26TRAN Q. Tuan – CEA-INES
The proposed co-simulation structure
Relays
Simulated network
MCR
Measurement
Control signal
Simulated microgrid
OpenIEC61850
Virtual Machine
Page 27TRAN Q. Tuan – CEA-INES
Project: PV 50.2 Realized at CEA-INES in collaboration with RTE Context: for 200000 to 300000 PV inverters < 250 kW in France
What is their behavior face to degraded frequency? Is there the massive disconnection at 50.2 Hz (called "common mode“)? Do disconnections present a risk to the stability of the electrical network?
Objectives: Evaluate PV inverters behaviors in grid perturbations(frequency and voltage) by real time tests (OPAL-RT)
Works carried out: Developing methodologies for real time testing and creating the different scenarios by tacking into account
frequency/voltage uncertainty Real time testing for different PV inverters (Types of inverters: # manufac., size, mono or three phase…)
- Measure of the disconnection and reconnection threshold (frequency/voltage) of each inverter- Measure the disconnection and reconnection time of each inverter- Test the sensitivity of the inverters (operating power, rate of change of the frequency…)
Evaluate PV inverters behaviors in grid perturbations
Page 28TRAN Q. Tuan – CEA-INES
Inverter
under test
=
~
PV
simulator
A
V
A
V
A
V
Generator of
I(V) curve
IMPP
VMPP I
AC
1
IAC
2
IAC
3
VA
C1
VA
C2
VAC
3
Network
model
Real time
simulater
OPAL-RT
Recording and
analyse
Measure and acquisition
+
-
L
1L
2L
3N
Simulation for different
power (irradiation)
Variation: frequency,
voltage, impedance…
VA
C1
VA
C2
VAC
3
IAC
1
f
5 Agilent 34410A: Measure
Description of the test bench
Page 29TRAN Q. Tuan – CEA-INES
PV Simulator PV2 x 12 kWc900 V max
2 x 32A DC max
Controlable load125 kVA
Inverterunder test
AC bus5 DMM HP344101 Frequency1 Iac3 VacSwitch of Ethernet com.
3 Amplifies- 5kVA / +15 kVA
Real time simulatorOPAL-RT
Description of the test bench
Page 30TRAN Q. Tuan – CEA-INES
Over-Frequency: Some tested inverters do not respect standards.
Under-Frequency: All tested inverters respect standards
Voltage: Some tested inverters do not respect standards.
No impact of the rate of change in frequency (verified with tests with different speed ramp) on the
disconnect frequency value
No impact of the operation power on disconnection / reconnection.
From disconnections based on frequency / voltage criterion of these PV inverters
=> RISK FOR NETWORK STABILITY!
Remarks
31
THANK YOU