Walden Athletic Complex320 Irwin Street, NE, Atlanta, GA 30312
Construction ManagerPre-Proposal BriefingAtlanta Public Schools Facilities Service Center
March 25, 2010
Facilities Services Department
February 28, 2017
Project Overview
• Abatement and demolition of the existing 3 level, +/- 88,000 sf building• Drainage and storm water management systems• Site utilities, sewer, water, gas, electric, etc. • Grading and retaining structures• Sidewalk, ramps, steps, etc.• Parking and drives• Fencing, netting and gates• Drinking water to the fields • Irrigation to natural turf • Competition athletic lighting • Score boards and control systems• Public Address System • Synthetic turf football and multi-sport field with GHSA competition game markings• Natural turf baseball / softball field convertible by season with GHSA competition
game markings • Field markers, goals, bases, dugouts, backstops, benches and support equipment• Concrete pads and bleachers
Project Overview (continued)
• Construction of a Field House (full program TBD) Likely include the following items: male and female, lockers, restrooms, showers and dressing areas, public restrooms, concessions, field storage, mechanical, offices for athletics operations and security, etc.
• Safe and efficient bus, car and pedestrian access and flow.• Comprehensive ADA accessibility• Attention to security through environmental design• Security lighting • Low Voltage systems, data, voice, video, security, etc. • Monument signage, exterior and interior signage and landscaping• All facilities, structures, fields, etc. to meet Georgia High School Association
requirements for athletic competition and practice.
Site Plan
Existing Site Plan
Project Location
Aerial View of Existing Site
Project Photo
Southeast View from Street
Project Photo
View of Existing Field
Project Photo
Southwest View from Street
Concept Plan
Conceptual Site Plan
Project Timeline (Tentative)
• Engineers RFP Issued Oct 18, 2016
• Engineers Pre-Proposal Briefing Nov 01, 2016
• Site Inspection Nov 04, 2016
• Engineers Proposals Due Nov 17, 2016
• Select Engineer Jan 04, 2017
• Request for Proposal out to CMs Feb 21, 2017
• CMs Pre-Proposal Briefing Feb 28, 2017
• Site Inspection Mar 02, 2017
• CM Proposals Due Mar 23, 2017
• Draft Design Narrative TBD
• Project Committee Meeting TBD
• Select CM TBD
• Recommend CM to Board TBD
• Construction Documents Complete Jul 1, 2017
• Project Start Oct 2017
• Project Completion Jul 2018
Site Inspection Date and Time
10:00 amThursday, March 02, 2016
at the Walden Middle School Site
If you have any questions contact the Project Manager.
Proposal Due Date and Time
2:00 pmThursday, March 23, 2017
at APS Facilities Service Center
Questions & Answers
During Construction progress reports for the Walden Athletic Complex can be accessed at:
http://www.atlanta.k12.ga.us